Description
DE-OBLIGATING $72,490.00 FROM CONTRACT IN PREPARATION FOR CLOSING OUT THE CONTRACT.
Base award description: CONSTRUCTION AT ABRAHAM LINCOLN NATIONAL CEMETERY
Modification chain · 65 transactions
Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.
- Base2010-08-04+$22,978,000= $22,978,000
- Mod 12011-01-05+$2,925= $22,980,925
- Mod 22011-01-18+$63,997= $23,044,922
- Mod 32011-01-31+$7,405= $23,052,327
- Mod SA0042011-03-10+$17,885= $23,070,212
- Mod SA052011-03-11+$709= $23,070,921
- Mod SA0062011-04-20+$36,183= $23,107,104
- Mod SA0072011-04-21+$0= $23,107,104
- Mod SA0082011-06-09+$24,138= $23,131,242
- Mod SA0092011-06-16+$86,987= $23,218,229
- Mod SA0112011-07-01+$82,587= $23,300,816
- Mod SA0122011-07-01+$0= $23,300,816
- Mod SA0132011-07-01+$0= $23,300,816
- Mod SA0142011-07-01+$3,405= $23,304,220
- Mod SA0102011-07-18+$18,920= $23,323,140
- Mod CO01A2011-07-25+$13,200= $23,336,340
- Mod SA0162011-08-02+$1,772= $23,338,112
- Mod SA0152011-08-16+$44,987= $23,383,099
- Mod CO01B2011-09-22+$75,000= $23,458,099
- Mod SA0172011-10-13-$9,832= $23,448,267
- Mod SA0182011-10-13+$2,056= $23,450,323
- Mod SA0192011-10-13+$3,180= $23,453,503
- Mod SA0202011-11-01-$9,844= $23,443,659
- Mod SA0212011-11-07+$73,935= $23,517,594
- Mod SA0222011-11-16+$9,376= $23,526,970
- Mod SA0232011-11-16+$0= $23,526,970
- Mod SA0242011-11-18+$5,407= $23,532,377
- Mod SA0252011-11-28+$6,544= $23,538,921
- Mod SA0262011-11-28+$17,633= $23,556,554
- Mod SA0272011-12-08+$10,790= $23,567,344
- Mod SA0282011-12-19+$69,489= $23,636,833
- Mod SA0292012-01-05+$4,316= $23,641,149
- Mod SA0302012-01-05-$1,783= $23,639,366
- Mod SA0312012-01-19+$1,440= $23,640,806
- Mod SA0322012-01-24+$2,035= $23,642,841
- Mod SA0352012-02-27+$3,363= $23,646,204
- Mod SA0362012-02-27-$2,510= $23,643,694
- Mod SA0372012-03-20+$8,804= $23,652,498
- Mod SA0382012-04-13+$34,571= $23,687,069
- Mod SA0392012-05-02+$800= $23,687,869
- Mod CO01C2012-05-09+$24,509= $23,712,378
- Mod SA0332012-06-04+$4,333= $23,716,711
- Mod SA0402012-07-27+$2,018= $23,718,729
- Mod SA0412012-07-27+$419= $23,719,148
- Mod SA0422012-07-27+$954= $23,720,102
- Mod SA0432012-07-27+$2,435= $23,722,537
- Mod SA0442012-07-27+$5,716= $23,728,253
- Mod SA0342012-07-30+$129,058= $23,857,312
- Mod CO01D2012-08-02+$15,852= $23,873,164
- Mod SA0482012-08-07+$0= $23,873,164
- Mod SA0452012-08-08+$2,489= $23,875,653
- Mod SA0462012-08-08+$15,005= $23,890,658
- Mod SA0492012-08-09+$3,337= $23,893,995
- Mod SA0502012-08-14+$4,921= $23,898,916
- Mod CO01E2012-08-23-$3,907= $23,895,009
- Mod SA0472012-08-24+$11,067= $23,906,076
- Mod SA0512012-08-24+$2,996= $23,909,072
- Mod SA0532012-08-29+$8,721= $23,917,793
- Mod SA0542012-09-07+$10,717= $23,928,510
- Mod CO01F2012-09-10+$47,250= $23,975,760
- Mod SA0552012-09-14+$1,959= $23,977,719
- Mod SA0562012-09-24+$34,711= $24,012,430
- Mod CO01G2012-10-11+$6,273= $24,018,702
- Mod P000022013-08-01+$0= $24,018,702
- Mod P000102017-05-30-$72,490= $23,946,212
| Transaction | Action date | This action (delta) | Running total | Description on this transaction |
|---|---|---|---|---|
| Base | 2010-08-04 | +$22,978,000 | $22,978,000 | CONSTRUCTION AT ABRAHAM LINCOLN NATIONAL CEMETERY |
| Mod 1· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-01-05 | +$2,925 | $22,980,925 | PARTNERING SESSION FACILITATED BY FMI ALNC ELWOOD, IL |
| Mod 2· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-01-18 | +$63,997 | $23,044,922 | INSTALL ADDITIONAL FENCE; TO INSTALL APPROXIMATELY 2300LF OF ADDITIONAL BLACK (PVC) VINYL COATED FENCE ON THE… |
| Mod 3· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-01-31 | +$7,405 | $23,052,327 | VOICE, DATA AND INTERNET FOR RE OFFICE ALNC ELWOOD, IL |
| Mod SA004· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-03-10 | +$17,885 | $23,070,212 | NO PROVISION WAS MADE IN THE ORIGINAL CONTRACT SOLICITATION FOR RE VEHICLE. THE CONTRACTOR WAS ASKED TO PROPO… |
| Mod SA05· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-03-11 | +$709 | $23,070,921 | PAVING AND CURB CHANGES ALNC ELWOOD, IL |
| Mod SA006· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-04-20 | +$36,183 | $23,107,104 | ADDITIONAL ASBESTOS REMOVAL |
| Mod SA007· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-04-21 | +$0 | $23,107,104 | CONTRACTOR HAS OFFERED AN UNSOLICITED PROPOSAL TO REVISE THE AS BID PHASING PLAN IN AN EFFORT TO REDUCE DISRUP… |
| Mod SA008· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-06-09 | +$24,138 | $23,131,242 | NECESSARY ADDITION OF A STORM SEWER STRUCTURE TO ACCOMODATE THE DISCOVERY OF AN EXISTING FOUNDATION. THE ADDIT… |
| Mod SA009· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-06-16 | +$86,987 | $23,218,229 | GENERALLY, THAT COMPENSATORY FLOODPLAIN BE DEVELOPED AS MITIGATIVE MEASURE WITHIN THE BOUNDARY OF THE FLOOD PL… |
| Mod SA011· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-07-01 | +$82,587 | $23,300,816 | DURING REMOVAL OF THE PAVING BRICK AND STONES IN COLUMBARIUM #3 A 4" SLAB OF CONCRETE NOT PREVIOUSLY NOTED O… |
| Mod SA012· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-07-01 | +$0 | $23,300,816 | MODIFY THE LOCATION OF THE NEW ELECTRICAL SERVICE ENTRANCE TO THE ADMINISTRATION BULDING TO AVOID CONFLICT WIT… |
| Mod SA013· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-07-01 | +$0 | $23,300,816 | REMOVAL OF UNSUITABLE MATERIAL FROM THE BOTTOM OF CRYPT FEILD 16 AND WITHIN THE BASE OF VAN BUREN LANE. SUBSTI… |
| Mod SA014· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-07-01 | +$3,405 | $23,304,220 | DELETE THE REQUIREMENT TO RELOCATE THE PEARL HARBOR MONUMENT DUE TO THE DISCOVERY OF A CRACK IN THE BASE OF TH… |
| Mod SA010· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-07-18 | +$18,920 | $23,323,140 | PROVIDE A PROPOSAL TO INCLUDE LABOR, MATERIALS AND EQUIPMENT TO ADJUST THE COVER OVER THE NICOR GAS LINES IN T… |
| Mod CO01A· CHANGE ORDER | 2011-07-25 | +$13,200 | $23,336,340 | PORVIDE ADDITIONAL TREE REMOVAL AND UNDERSTORY CLEARING AT COLUMBARIUM 7 AREA AND HONOR GUARD PARKING LOT. |
| Mod SA016· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-08-02 | +$1,772 | $23,338,112 | THE SA WAS UNDERTAKEN TO CORRECT A DESIGN BUST IN THE ACTUAL/EXISTING GRADE ELEVATIONS WHERE THE MAINTENANCE… |
| Mod SA015· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-08-16 | +$44,987 | $23,383,099 | NECESSARY CHANGE TO PROVIDE FOR THE PROPER ABANDONMENT OF A WELL THAT IS ON PROPERTY AND CHANGE IN LAYOUT AND… |
| Mod CO01B· CHANGE ORDER | 2011-09-22 | +$75,000 | $23,458,099 | NECESSARY CHANGE TO ACCOMODATE AN ERROR IN DESIGN DATA PROVIDED FOR ROAD ELEVATIONS AT THE CORTEGE LANES. THIS… |
| Mod SA017· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-10-13 | −$9,832 | $23,448,267 | AFTER SOIL ANALYSIS WAS PERFORMED, IT WAS IDENTIFIED THAT THE USE OF ORGANIC COMPOST WOULD NOT BE ADEQUATE IN… |
| Mod SA018· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-10-13 | +$2,056 | $23,450,323 | SA-018 DEFINITIZES CO-01A. NECESSARY REMOVAL OF ADDITIONAL TREES THAT WERE FOUND TO BE DEAD OR STORM DAMAGED P… |
| Mod SA019· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-10-13 | +$3,180 | $23,453,503 | CONTRACT REQUIRED THE RE-LOCATION OF THE POW/MIA FLAG POLE. THE EXISTING FLAG POLE WAS ORIGINALLY INSTALLED IN… |
| Mod SA020· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-11-01 | −$9,844 | $23,443,659 | NECESSARY DELETION OF THE SIX (6) DOOR CANOPIES FOUND TO BE IN CONFLICT WITH MECHANICAL LOUVERS. ADDITIONALLY,… |
| Mod SA021· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-11-07 | +$73,935 | $23,517,594 | THE EXISTING DOMESTIC WATER SUPPLY IS MINIMALLY TREATED WELL WATER, HIGHLY UNPALATABLE AND UNRELIABLE. BID DE… |
| Mod SA022· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-11-16 | +$9,376 | $23,526,970 | A CONTRACT MODIFICATION IS NECESSARY TO DELIVER THE EQUIPMENT, MATERIAL, LABOR TO PROVIDE FOR THE REVISION OF… |
| Mod SA023· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-11-16 | +$0 | $23,526,970 | SUBSTITUTION NECESSITATED BY THE DIFFICULTIES ENCOUNTERED BY THE CONTRACTOR IN FINDING A QUALIFIED MANUFACTURE… |
| Mod SA024· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-11-18 | +$5,407 | $23,532,377 | NECESSARY REQUIREMENTS TO CONVEY PAYMENT FOR UNFORESEEN CONNECTION FEES TO THE LOCAL UTILITY PROVIDER. |
| Mod SA025· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-11-28 | +$6,544 | $23,538,921 | THE EXISTING CONCRETE SLAB UNDER THE BRICK PAVERS WAS FOUND TO BE AT THE WRONG ELEVATION TO ACCOMMODATE THE NE… |
| Mod SA026· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-11-28 | +$17,633 | $23,556,554 | BUILDING 3001 IN THE MAINTENANCE COMPLEX NEEDED TO BE INSULATED AND THE SCOPE WAS DROPPED IN THE DESIGN PERIOD… |
| Mod SA027· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-12-08 | +$10,790 | $23,567,344 | NECESSARY ALTERATION TO THE PLANNED FENCE ALIGNMENT TO CAPTURE THE PROPERTY CORNER THEREBY PREVENTING ENCROACH… |
| Mod SA028· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-12-19 | +$69,489 | $23,636,833 | PROVIDE FOR ADEQUATE BATHROOM AND HYDRATION FACILITIES FOR THE ALNC HONOR GUARD AND ADMIN BUILDING AND PROVIDE… |
| Mod SA029· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-01-05 | +$4,316 | $23,641,149 | IT WAS NECESSARY INVESTIGATIVE AND REPAIR WORK TO CORRECT DAMAGE TO AN EXISTING IRRIGATION VALVE AND QUICK COU… |
| Mod SA030· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-01-05 | −$1,783 | $23,639,366 | PROVIDE FOR THE INSTALLATION OF FLOWER WATERING HYDRANTS ALONG THE MEMORIAL WALK WAY THAT WERE REQUESTED BY TH… |
| Mod SA031· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-01-19 | +$1,440 | $23,640,806 | NECESSSARY ADDITION OF FEES TO COMPENSATE THE GC AFTER A PREVIOUSLY UNKNOWN DELIVERY FEE WAS IMPOSED ON THE VI… |
| Mod SA032· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-01-24 | +$2,035 | $23,642,841 | NECESSARY ADJUSTMENT TO DESIGN GRADING TO STOP POOLING OF RUN OFF AT THE HIGHLY VISIBLE ENTRY TO THE CEMETERY. |
| Mod SA035· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-02-27 | +$3,363 | $23,646,204 | NECESSARY DELETION OF MILLING REQUIREMENTS TO ACCOMODATE AN ELEVATIONAL BUST IN DESIGN DOCUMENTS. CHANGE WILL… |
| Mod SA036· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-02-27 | −$2,510 | $23,643,694 | NECESSARY CHANGE TO ACCOMMODATE AN ERROR IN DESIGN DATA PROVIDED FOR ROAD ELEVATIONS AT THE CORTEGE LANES. THI… |
| Mod SA037· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-03-20 | +$8,804 | $23,652,498 | NECESSARY ADDITION OF LABOR AND MATERIALS TO REMOVE AND RESET 39 MEMORIAL HEADSTONES THAT WERE NOT ACCOUNTED F… |
| Mod SA038· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-04-13 | +$34,571 | $23,687,069 | NECESSARY ADDITIONS AND DELETIONS TO THE STORM SEWER AND ASSOCIATED DISCIPLINES DESIGN AS DISCREPENCIES WERE… |
| Mod SA039· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-05-02 | +$800 | $23,687,869 | TO COMPLETE THE TREE REMOVAL/TRANSPLANTING PRPCESS AND TO CORRECT THE CONFILICTS BETWEEN SOME EXISTING TREES A… |
| Mod CO01C· CHANGE ORDER | 2012-05-09 | +$24,509 | $23,712,378 | ROAD GRADE AND PROFILE CHANGES ABRAHAM LINCOLN NATIONAL CEMETERY ELWOOD, ILLINOIS |
| Mod SA033· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-06-04 | +$4,333 | $23,716,711 | THE SEALER FOR THE LIMESTONE CAPS AND VENEER STONE IS TO BE DELETED. THIS WAS RECOMMENDED BY THE STONE SUPPLIE… |
| Mod SA040· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-07-27 | +$2,018 | $23,718,729 | PROVIDE PAYMENT OF FEES TO COMED, THE LOCAL UTILITY PROVIDER, TO PERFORM THE SERVICE DISCONNECT AND RE-CONNECT… |
| Mod SA041· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-07-27 | +$419 | $23,719,148 | PROVIDE SEAL OFF COUPLINGS TO THE SERVICE ENTRY CONDUITS LOCATED IN THE HONOR GUARD BUILDING TO MITIGATE GROUN… |
| Mod SA042· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-07-27 | +$954 | $23,720,102 | DUE TO THE CHANGE OF THE ELEVATIONS OF THE WALKWAYS AT COLUMBARIUM #7 TO MAKE THEM ADA COMPLIANT IT WAS REQUIR… |
| Mod SA043· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-07-27 | +$2,435 | $23,722,537 | UPON COMPLETION OF VARIOUS REPAIRS AND UP GRADES AT THE PIC IT WAS NOTED THAT REPAIRS TO THE ROOF DRAINS IN TH… |
| Mod SA044· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-07-27 | +$5,716 | $23,728,253 | THIS SA WAS NECESSARY DUE TO VARIOUS DESIGN GRADE DEFICIENCIES WHICH WILL REQUIRE ADDITIONAL GRADING AND A TRE… |
| Mod SA034· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-07-30 | +$129,058 | $23,857,312 | CONTRACT REQUIRES THAT THE CONTRACTOR WAS TO PROVIDE FOR ELECTRICAL POWER TO THE RE JOB TRAILER. THE SITE ELEC… |
| Mod CO01D· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-08-02 | +$15,852 | $23,873,164 | PROVIDE IRRIGATION AT COLUMBARIA 1 AND 2 IN ACCORDANCE WITH EXHIBIT A. THIS WORK SHALL ALSO INCLUDE THE INSTAL… |
| Mod SA048· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-08-07 | +$0 | $23,873,164 | THE EXISTING DRAIN TILE AROUND THE SIDES OF THE BUILDING WAS FOUND TO BE OPEN AND VIABLE WHICH MADE IT UNNECE… |
| Mod SA045· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-08-08 | +$2,489 | $23,875,653 | REPAIR THE 6" DIA. IRRIGATION LINE RUNNING ALONG THE NORTH EDGE OF HOFF ROAD AT THE LUNCH PAIL STATUE. THIS RE… |
| Mod SA046· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-08-08 | +$15,005 | $23,890,658 | PROVIDE AN AREA DRAIN AND PIPING TO EXISTING STRUCTURES AT THE LIMESTONE RETAINING WALL BY THE CORTEGE LANE EN… |
| Mod SA049· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-08-09 | +$3,337 | $23,893,995 | MAKE NECESSARY CHANGES IN THE DESIGN CONCEPT OF APRONS TO BE INSTALLED AT COMMITTAL SHELTER D AND REMOVE AND R… |
| Mod SA050· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-08-14 | +$4,921 | $23,898,916 | IT WAS NECESSARY CHANGE FROM THE EXISTING LOCATION TO THE PIC AND CHANGE TO "LANDSCAPE" ORIENTATION AND ADD NE… |
| Mod CO01E· CHANGE ORDER | 2012-08-23 | −$3,907 | $23,895,009 | PROVIDE FOR AN ALTERNATE ROUTING TO INSTALL NATURAL GAS LINE FROM THE METER TO THE GENERATOR AT THE ADMIN BUIL… |
| Mod SA047· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-08-24 | +$11,067 | $23,906,076 | PROVIDE NECESSARY REPAIRS TO THE FIBER OPTIC AND COMMUNICATIONS LINES SERVICING THE PIC BUILDING AS THE CONDIT… |
| Mod SA051· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-08-24 | +$2,996 | $23,909,072 | TO ELEVIATE THE CONSTANT PONDING AND OVER SATURATION OF THE GRASS AREA AT THE LOCATIONS INDICATED ON JACKSON L… |
| Mod SA053· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-08-29 | +$8,721 | $23,917,793 | NECESSARY ADDITION TO REQUIRED DEBRIS REMOVAL TO ACCOUNT FOR UNIDENTIFIED/CONCEALED MATERIALS WHEN GRADING AND… |
| Mod SA054· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-09-07 | +$10,717 | $23,928,510 | PROVIDE FOR THE CONTINUED LEASING OF THE RE GATORS PAST THE ORIGINAL CCD DATE OF 03/12. THE CONTINUED USE OF T… |
| Mod CO01F· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-09-10 | +$47,250 | $23,975,760 | MAKE NECESSARY GRADE ADJUSTMENTS TO THE CONVERGENCE OF HOFF ROAD AND LINCOLN THAT CREATES THE NEW ENTRY TO ALN… |
| Mod SA055· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-09-14 | +$1,959 | $23,977,719 | PROVIDE FOR THE CONTINUED LEASING OF THE RE GATORS PAST THE ORIGINAL CCD DATE OF 03/12. THE CONTINUED USE OF T… |
| Mod SA056· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-09-24 | +$34,711 | $24,012,430 | NECESSARY CHANGES TO ACCOMODATE SAFETY ISSUES IDENTIFIED ON STATION INSPECTIONS AND PROVIDE FOR OMMISSIONS IN… |
| Mod CO01G· CHANGE ORDER | 2012-10-11 | +$6,273 | $24,018,702 | MAKE NECESSARY GRADE ADJUSTMENTS TO THE CONVERGENCE OF HOFF ROAD AND LINCOLN THAT CREATES THE NEW ENTRY TO ALN… |
| Mod P00002· OTHER ADMINISTRATIVE ACTION | 2013-08-01 | +$0 | $24,018,702 | MAKE NECESSARY GRADE ADJUSTMENTS TO THE CONVERGENCE OF HOFF ROAD AND LINCOLN THAT CREATES THE NEW ENTRY TO ALN… |
| Mod P00010· CLOSE OUT | 2017-05-30 | −$72,490 | $23,946,212 | DE-OBLIGATING $72,490.00 FROM CONTRACT IN PREPARATION FOR CLOSING OUT THE CONTRACT. |
Related awards · 11
Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.
Other VA awards to the same recipient (UEI JKAHXUMJX5E3)
| Award | Office · PSC / listing | Net obligations | FY |
|---|---|---|---|
| VA24714P3210 | 508-ATLANTA · H343 · INSPECTION- PUMPS AND COMPRESSORS | $116,289 | FY2014 |
| VA24414P0550 | 693-WILKES-BARRE · 5925 · CIRCUIT BREAKERS | $45,334 | FY2014 |
| VA24413C0405 | 693-WILKES-BARRE · 6150 · MISCELLANEOUS ELECTRIC POWER AND DISTRIBUTION EQUIPMENT | $308,124 | FY2013 |
| VA25712P1420 | 257-NETWORK CONTRACT OFFICE 17 · H336 · INSPECTION- SPECIAL INDUSTRY MACHINERY | $100,000 | FY2012 |
| VA26312P1990 | 636-NEBRASKA WESTERN-IOWA · 7125 · CABINETS, LOCKERS, BINS, AND SHELVING | $17,433 | FY2012 |
| VA69DP0683 | 69D-NETWORK CONTRACT OFFICE 12 · R499 · OTHER PROFESSIONAL SERVICES | $11,900 | FY2011 |
Other recipients under Y299 from OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F) (most recent first)
| Award | Recipient | Office | Net obligations | FY |
|---|---|---|---|---|
| VA101CFMC0165 | G&C FAB-CON, LLC | OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F) | $18,626,889 | FY2011 |
| VA101CFMC0081 | WEST CONSTRUCTION, INC. | OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F) | $22,945,085 | FY2010 |
| VA101CFMP0021 | SMITHGROUPJJR, INC. | OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F) | $3,343,772 | FY2009 |
| VA101183B4C0046 | EMERSON CONSTRUCTION COMPANY, INC. | OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F) | $21,687,294 | FY2008 |
| VA101183B4C0047 | KEVCON, INC | OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F) | $16,297,324 | FY2008 |
Cite as: Glassbox VA record view · VA contract (USAspending / FPDS) · CONT_AWD_VA101CFMC0093_3600_-NONE-_-NONE- · retrieved 2026-09-26.