Description
REVISE RETAINING WALL ENGINEERING, ADD FENCE ON TOP OF RETAINING WALL FOR FALL PROTECTION, AND FINAL BOND ADJUSTMENT.
Base award description: CONTRACTOR SHALL FURNISH ALL LABPOR, EQUIPMENT, AND MATERIALS FOR PHASE 1A GRAVESITE EXPANSION AND CEMETERY DEVELOPMENTS AT THE JEFFERSON BARRACKS NATIONAL CEMETERY, ST. LOUIS, MO.
Modification chain · 14 transactions
Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.
- Base2010-05-28+$12,997,000= $12,997,000
- Mod CO01A2011-02-07+$22,680= $13,019,680
- Mod SA0012011-02-09+$171,642= $13,191,322
- Mod SA0022011-02-22+$59,003= $13,250,325
- Mod SA0032011-04-07+$3,511= $13,253,836
- Mod SA0042011-04-19+$35,611= $13,289,447
- Mod CO01B2011-04-25+$62,337= $13,351,784
- Mod SA0072011-06-13+$97,513= $13,449,297
- Mod SA0062011-07-11+$8,536= $13,457,833
- Mod TE0012011-07-18+$0= $13,457,833
- Mod SA0082011-08-11+$50,947= $13,508,780
- Mod SA0052011-10-14+$263,287= $13,772,067
- Mod SA0092012-01-19+$50,183= $13,822,250
- Mod SA0102012-07-05+$38,194= $13,860,444
| Transaction | Action date | This action (delta) | Running total | Description on this transaction |
|---|---|---|---|---|
| Base | 2010-05-28 | +$12,997,000 | $12,997,000 | CONTRACTOR SHALL FURNISH ALL LABPOR, EQUIPMENT, AND MATERIALS FOR PHASE 1A GRAVESITE EXPANSION AND CEMETERY DE… |
| Mod CO01A· CHANGE ORDER | 2011-02-07 | +$22,680 | $13,019,680 | ADD POWER POLE AND TWO PULL BOXES JBNC ST. LOUIS, MO |
| Mod SA001· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-02-09 | +$171,642 | $13,191,322 | MSD&SHPO REQUIRED CHANGES JBNC ST. LOUIS, MO |
| Mod SA002· DEFINITIZE CHANGE ORDER | 2011-02-22 | +$59,003 | $13,250,325 | DEFINITIZES CO-01A NEW POWER POLE AND PULL BOXES JBNC ST. LOUIS, MO |
| Mod SA003· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-04-07 | +$3,511 | $13,253,836 | REROUTE STORM LINES JBNC ST. LOUIS, MO |
| Mod SA004· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-04-19 | +$35,611 | $13,289,447 | ADD CAPS AT CRYPT LIFTING LUGS AS REQUESTED BY NCA |
| Mod CO01B· CHANGE ORDER | 2011-04-25 | +$62,337 | $13,351,784 | GENERATORS&FUEL FOR ELEC OUTAGE JBNC ST. LOUIS, MO |
| Mod SA007· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-06-13 | +$97,513 | $13,449,297 | MSN REQUEST. |
| Mod SA006· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-07-11 | +$8,536 | $13,457,833 | PROVIDE GENERATORS AND FUEL TO POWER VARIOUS BUILDINGS AT THE JEFFERSON BARRACKS HOSPITAL COMPLEX DURING THE E… |
| Mod TE001· OTHER ADMINISTRATIVE ACTION | 2011-07-18 | +$0 | $13,457,833 | TIME EXTENSION DUE TO UNUSUALLY SEVERE RAINFALL DURING THE MONTH OF JUNE 2011 |
| Mod SA008· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-08-11 | +$50,947 | $13,508,780 | NCA REQUEST - IMPROVE DRAINAGE IN SECTION L OF THE CEMETERY, THE AREA STAYS WET MAKING IT SOFT AND MUDDY AND M… |
| Mod SA005· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-10-14 | +$263,287 | $13,772,067 | NCA REQUEST - EXCAVATE AND CLEAN-UP DEBRIS FROM EXISTING FILL AT SECTION 1K TO ALLOW FOR CREMAIN BURIALS. |
| Mod SA009· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-01-19 | +$50,183 | $13,822,250 | NCA REQUEST - IMPROVE DRAINAGE IN SECTION F OF THE CEMETERY, THE AREA STAYS WET MAKING IT SOFT AND MUDDY AND M… |
| Mod SA010· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-07-05 | +$38,194 | $13,860,444 | REVISE RETAINING WALL ENGINEERING, ADD FENCE ON TOP OF RETAINING WALL FOR FALL PROTECTION, AND FINAL BOND ADJU… |
Related awards · 11
Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.
Other VA awards to the same recipient (UEI V9AXKY9KLVJ1)
| Award | Office · PSC / listing | Net obligations | FY |
|---|---|---|---|
| VA24514C0063 | 688-WASHINGTON DC · Y1DA · CONSTRUCTION OF HOSPITALS AND INFIRMARIES | $0 | FY2014 |
| VA24614C0013 | 246-NETWORK CONTRACTING OFFICE 6 · Z2DA · REPAIR OR ALTERATION OF HOSPITALS AND INFIRMARIES | $9,283 | FY2014 |
| VA24413C0103 | 540-CLARKSBURG · Z2DA · REPAIR OR ALTERATION OF HOSPITALS AND INFIRMARIES | $299,700 | FY2013 |
| VA101F12C0030 | OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F) · Y1PC · CONSTRUCTION OF UNIMPROVED REAL PROPERTY (LAND) | $20,246,738 | FY2012 |
| VA655C00257 | 655-SAGINAW · Z141 · MAINT-REP-ALT/HOSPITALS & INFIRMARY | $11,614 | FY2010 |
| VA786AC0382 | NATIONAL CEMETERY ADMINISTRATION · Y216 · CONSTRUCTION OF DREDGING | $3,547,804 | FY2010 |
Other recipients under Y299 from OFFICE OF CONSTRUCTION & FACILITIES MANAGEMENT (most recent first)
| Award | Recipient | Office | Net obligations | FY |
|---|---|---|---|---|
| VA101CFMP0254 | INTERNATIONAL PUBLIC WORKS, LLC | OFFICE OF CONSTRUCTION & FACILITIES MANAGEMENT | $176,885 | FY2011 |
| VA101CFMC0143 | SPANISH SPRINGS CONSTRUCTION INC | OFFICE OF CONSTRUCTION & FACILITIES MANAGEMENT | $17,403,315 | FY2011 |
| VA101CFMC0074 | KEVCON-TTP, JV | OFFICE OF CONSTRUCTION & FACILITIES MANAGEMENT | $25,303,657 | FY2010 |
| VA101CFMC0082 | G&C FAB-CON, LLC | OFFICE OF CONSTRUCTION & FACILITIES MANAGEMENT | $21,354,503 | FY2010 |
| VA101CFMC0062 | GLEN/MAR CONSTRUCTION, INC. | OFFICE OF CONSTRUCTION & FACILITIES MANAGEMENT | $16,301,436 | FY2010 |