Award recordCONTRACT

GC&P FAB-CON LLC

PIID VA101CFMC0054· VA Staff Offices· OFFICE OF CONSTRUCTION & FACILITIES MANAGEMENT· Y299 · CONTRUCT/ALL OTHER NON-BLDG FACS· FY2009· $33,817,702 net obligations· UEI HKDMN65VKN89· NJ

Description

PROVIDE CENTRAL STATION MONITORING

Base award description: CALVERTON NATIONAL CEMETERY - GRAVESITE EXPANSION

First action · last action
2009-09-03 · 2012-09-18
Transactions
71
First transaction's obligation
$32,191,900
Base + all options value (sum of deltas)
$33,817,882
Extent competed
FULL AND OPEN COMPETITION
Other than full & open authority
—
Set-aside
NO SET ASIDE USED.
Offers received
9
SDVOSB flag on record
Yes (self-representation)
NAICS
237990 · OTHER HEAVY AND CIVIL ENGINEERING CONSTRUCTION

Modification chain · 71 transactions

Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.

$33,817,702$0Base award · 2009-09-03 · this action $32,191,900 · running total $32,191,900Modification SA001 · 2009-11-16 · this action $9,936 · running total $32,201,836Modification SA002 · 2009-11-25 · this action $11,779 · running total $32,213,615Modification SA004 · 2010-04-23 · this action -$92,767 · running total $32,120,849Modification SA005 · 2010-04-29 · this action $3,258 · running total $32,124,107Modification CO01A · 2010-05-05 · this action $3,500 · running total $32,127,607Modification SA006 · 2010-05-10 · this action $7,920 · running total $32,135,527Modification SA008 · 2010-06-17 · this action $175 · running total $32,135,702Modification SA009 · 2010-06-17 · this action $14,664 · running total $32,150,366Modification SA010 · 2010-06-29 · this action $2,800 · running total $32,153,166Modification SA003 · 2010-07-06 · this action $2,143 · running total $32,155,309Modification CO01B · 2010-08-19 · this action $34,685 · running total $32,189,994Modification CO01C · 2010-08-23 · this action -$13,350 · running total $32,176,644Modification SA012 · 2010-08-23 · this action $2,120 · running total $32,178,764Modification SA007 · 2010-08-24 · this action $6,500 · running total $32,185,264Modification SA013 · 2010-08-24 · this action -$8,320 · running total $32,176,944Modification SA011 · 2010-09-01 · this action $122,500 · running total $32,299,444Modification SA015 · 2010-09-17 · this action $0 · running total $32,299,444Modification SA016 · 2010-09-17 · this action $67,000 · running total $32,366,444Modification SA014 · 2010-09-22 · this action $335,000 · running total $32,701,444Modification SA017 · 2010-09-22 · this action -$3,930 · running total $32,697,514Modification SA018 · 2010-12-20 · this action $20,300 · running total $32,717,814Modification SA019 · 2010-12-20 · this action $0 · running total $32,717,814Modification SA020 · 2010-12-20 · this action $38,000 · running total $32,755,814Modification 26 · 2010-12-21 · this action -$65,397 · running total $32,690,417Modification SA021 · 2010-12-27 · this action $9,000 · running total $32,699,417Modification SA022 · 2010-12-27 · this action $27,000 · running total $32,726,417Modification SA025 · 2010-12-27 · this action $50,534 · running total $32,776,951Modification SA023 · 2010-12-28 · this action $7,216 · running total $32,784,167Modification SA028 · 2011-01-06 · this action -$65,397 · running total $32,718,770Modification SA027 · 2011-01-11 · this action $0 · running total $32,718,770Modification SA029 · 2011-01-18 · this action $5,800 · running total $32,724,570Modification SA030 · 2011-01-18 · this action $2,265 · running total $32,726,835Modification SA031 · 2011-01-18 · this action $910 · running total $32,727,745Modification TE001 · 2011-01-19 · this action $0 · running total $32,727,745Modification SA024 · 2011-01-24 · this action -$50,534 · running total $32,677,211Modification SA034 · 2011-03-15 · this action $0 · running total $32,677,211Modification CO01D · 2011-04-13 · this action $2,145 · running total $32,679,356Modification CO01E · 2011-04-13 · this action $6,175 · running total $32,685,531Modification SA035 · 2011-04-19 · this action $38,000 · running total $32,723,531Modification SA036 · 2011-04-19 · this action $2,245 · running total $32,725,776Modification SA032 · 2011-04-25 · this action $35,250 · running total $32,761,026Modification SA033 · 2011-04-25 · this action $97,500 · running total $32,858,526Modification TE002 · 2011-04-25 · this action $0 · running total $32,858,526Modification SA037 · 2011-05-11 · this action $79,550 · running total $32,938,076Modification SA038 · 2011-05-13 · this action $75,000 · running total $33,013,076Modification SA039 · 2011-06-30 · this action $855 · running total $33,013,931Modification SA040 · 2011-06-30 · this action $655 · running total $33,014,586Modification SA041 · 2011-07-19 · this action -$4,250 · running total $33,010,336Modification SA042 · 2011-08-18 · this action $17,000 · running total $33,027,336Modification SA043 · 2011-08-18 · this action $32,000 · running total $33,059,336Modification SA044 · 2011-08-18 · this action $13,465 · running total $33,072,801Modification SA045 · 2011-08-18 · this action -$4,325 · running total $33,068,476Modification CO01F · 2011-09-01 · this action $13,000 · running total $33,081,476Modification CO01G · 2011-09-02 · this action $49,000 · running total $33,130,476Modification TE003 · 2011-09-26 · this action $0 · running total $33,130,476Modification SA046 · 2011-10-18 · this action -$8,441 · running total $33,122,035Modification SA048 · 2011-10-21 · this action $44,000 · running total $33,166,035Modification SA049 · 2011-10-21 · this action $13,236 · running total $33,179,271Modification SA050 · 2011-10-28 · this action $95,771 · running total $33,275,042Modification SA051 · 2011-10-28 · this action $7,092 · running total $33,282,134Modification TE004 · 2011-10-28 · this action $0 · running total $33,282,134Modification SA052 · 2011-11-04 · this action -$2,174 · running total $33,279,960Modification CO01H · 2011-11-10 · this action $16,000 · running total $33,295,960Modification SA053 · 2011-12-07 · this action $0 · running total $33,295,960Modification SA054 · 2011-12-08 · this action $17,573 · running total $33,313,533Modification SA055 · 2011-12-09 · this action $7,370 · running total $33,320,903Modification SA047 · 2012-01-20 · this action $475,000 · running total $33,795,903Modification SA056 · 2012-06-26 · this action $9,690 · running total $33,805,592Modification SA057 · 2012-06-28 · this action $10,493 · running total $33,816,086Modification SA058 · 2012-09-18 · this action $1,616 · running total $33,817,702
  • Base2009-09-03+$32,191,900= $32,191,900
  • Mod SA0012009-11-16+$9,936= $32,201,836
  • Mod SA0022009-11-25+$11,779= $32,213,615
  • Mod SA0042010-04-23-$92,767= $32,120,849
  • Mod SA0052010-04-29+$3,258= $32,124,107
  • Mod CO01A2010-05-05+$3,500= $32,127,607
  • Mod SA0062010-05-10+$7,920= $32,135,527
  • Mod SA0082010-06-17+$175= $32,135,702
  • Mod SA0092010-06-17+$14,664= $32,150,366
  • Mod SA0102010-06-29+$2,800= $32,153,166
  • Mod SA0032010-07-06+$2,143= $32,155,309
  • Mod CO01B2010-08-19+$34,685= $32,189,994
  • Mod CO01C2010-08-23-$13,350= $32,176,644
  • Mod SA0122010-08-23+$2,120= $32,178,764
  • Mod SA0072010-08-24+$6,500= $32,185,264
  • Mod SA0132010-08-24-$8,320= $32,176,944
  • Mod SA0112010-09-01+$122,500= $32,299,444
  • Mod SA0152010-09-17+$0= $32,299,444
  • Mod SA0162010-09-17+$67,000= $32,366,444
  • Mod SA0142010-09-22+$335,000= $32,701,444
  • Mod SA0172010-09-22-$3,930= $32,697,514
  • Mod SA0182010-12-20+$20,300= $32,717,814
  • Mod SA0192010-12-20+$0= $32,717,814
  • Mod SA0202010-12-20+$38,000= $32,755,814
  • Mod 262010-12-21-$65,397= $32,690,417
  • Mod SA0212010-12-27+$9,000= $32,699,417
  • Mod SA0222010-12-27+$27,000= $32,726,417
  • Mod SA0252010-12-27+$50,534= $32,776,951
  • Mod SA0232010-12-28+$7,216= $32,784,167
  • Mod SA0282011-01-06-$65,397= $32,718,770
  • Mod SA0272011-01-11+$0= $32,718,770
  • Mod SA0292011-01-18+$5,800= $32,724,570
  • Mod SA0302011-01-18+$2,265= $32,726,835
  • Mod SA0312011-01-18+$910= $32,727,745
  • Mod TE0012011-01-19+$0= $32,727,745
  • Mod SA0242011-01-24-$50,534= $32,677,211
  • Mod SA0342011-03-15+$0= $32,677,211
  • Mod CO01D2011-04-13+$2,145= $32,679,356
  • Mod CO01E2011-04-13+$6,175= $32,685,531
  • Mod SA0352011-04-19+$38,000= $32,723,531
  • Mod SA0362011-04-19+$2,245= $32,725,776
  • Mod SA0322011-04-25+$35,250= $32,761,026
  • Mod SA0332011-04-25+$97,500= $32,858,526
  • Mod TE0022011-04-25+$0= $32,858,526
  • Mod SA0372011-05-11+$79,550= $32,938,076
  • Mod SA0382011-05-13+$75,000= $33,013,076
  • Mod SA0392011-06-30+$855= $33,013,931
  • Mod SA0402011-06-30+$655= $33,014,586
  • Mod SA0412011-07-19-$4,250= $33,010,336
  • Mod SA0422011-08-18+$17,000= $33,027,336
  • Mod SA0432011-08-18+$32,000= $33,059,336
  • Mod SA0442011-08-18+$13,465= $33,072,801
  • Mod SA0452011-08-18-$4,325= $33,068,476
  • Mod CO01F2011-09-01+$13,000= $33,081,476
  • Mod CO01G2011-09-02+$49,000= $33,130,476
  • Mod TE0032011-09-26+$0= $33,130,476
  • Mod SA0462011-10-18-$8,441= $33,122,035
  • Mod SA0482011-10-21+$44,000= $33,166,035
  • Mod SA0492011-10-21+$13,236= $33,179,271
  • Mod SA0502011-10-28+$95,771= $33,275,042
  • Mod SA0512011-10-28+$7,092= $33,282,134
  • Mod TE0042011-10-28+$0= $33,282,134
  • Mod SA0522011-11-04-$2,174= $33,279,960
  • Mod CO01H2011-11-10+$16,000= $33,295,960
  • Mod SA0532011-12-07+$0= $33,295,960
  • Mod SA0542011-12-08+$17,573= $33,313,533
  • Mod SA0552011-12-09+$7,370= $33,320,903
  • Mod SA0472012-01-20+$475,000= $33,795,903
  • Mod SA0562012-06-26+$9,690= $33,805,592
  • Mod SA0572012-06-28+$10,493= $33,816,086
  • Mod SA0582012-09-18+$1,616= $33,817,702
TransactionAction dateThis action (delta)Running totalDescription on this transaction
Base2009-09-03+$32,191,900$32,191,900CALVERTON NATIONAL CEMETERY - GRAVESITE EXPANSION
Mod SA001· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2009-11-16+$9,936$32,201,836GRAVESITE EXP. & SITE IMPROVEMENTS, CALVERTON, NY SA-001 ISSUED TO REMOVE AND RELOCATE TREES, CUT AND CAP AN E…
Mod SA002· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2009-11-25+$11,779$32,213,615GRAVESITE EXP. & SITE IMPROVEMENTS, CALVERTON, NY SA-0002 ISSUED TO PROVIDE COPY FOR RE OFFICE.
Mod SA004· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-04-23−$92,767$32,120,849CALVERTON NATIONAL CEMETERY - GRAVESITE EXPANSION
Mod SA005· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-04-29+$3,258$32,124,107GRAVESITE EXP. & SITE IMPROVEMENTS, CALVERTON, NY SA-005 ISSUED FOR PARTNERING SESSION.
Mod CO01A· CHANGE ORDER2010-05-05+$3,500$32,127,607CALVERTON NATIONAL CEMETERY - GRAVESITE EXPANSION
Mod SA006· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-05-10+$7,920$32,135,527GRAVESITE EXP. & SITE IMPROVEMENTS, CALVERTON, NY SA-006 ISSUED FOR MONTHLY AERIAL PHOTOGRAPHS.
Mod SA008· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-06-17+$175$32,135,702GRAVESITE EXP. & SITE IMPROVEMENTS, CALVERTON, NY SA-008 ISSUED TO REMOVE AND REPAIR WALLBOARD.
Mod SA009· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-06-17+$14,664$32,150,366GRAVESITE EXP. & SITE IMPROVEMENTS, CALVERTON, NY SA-009 ISSUED TO RECONNECT IRRIGATION CONTROL WIRES.
Mod SA010· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-06-29+$2,800$32,153,166GRAVESITE EXP. & SITE IMPROVEMENTS, CALVERTON, NY, SA-010
Mod SA003· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-07-06+$2,143$32,155,309GRAVESITE EXP. & SITE IMPROVEMENTS, CALVERTON, NY
Mod CO01B· CHANGE ORDER2010-08-19+$34,685$32,189,994GRAVESITE EXP. & SITE IMPROVEMENTS, CALVERTON, NY CO-01B - ADDITIONAL ROAD RECONSTRUCTION
Mod CO01C· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-08-23−$13,350$32,176,644GRAVESITE EXP. & SITE IMPROVEMENTS, CALVERTON, NY CO-01C
Mod SA012· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-08-23+$2,120$32,178,764GRAVESITE EXP. & SITE IMPROVEMENTS, CALVERTON, NY SA-012 ISSUED FOR RE OFFICE SECURITY SYSTEM.
Mod SA007· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-08-24+$6,500$32,185,264GRAVESITE EXP. & SITE IMPROVEMENTS, CALVERTON, NY, SA-007
Mod SA013· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-08-24−$8,320$32,176,944GRAVESITE EXP. & SITE IMPROVEMENTS, CALVERTON, NY
Mod SA011· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-09-01+$122,500$32,299,444GRAVESITE EXP. & SITE IMPROVEMENTS, CALVERTON, NY SA-011
Mod SA015· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-09-17+$0$32,299,444GRAVESITE EXP. & SITE IMPROVEMENTS, CALVERTON, NY SA-015
Mod SA016· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-09-17+$67,000$32,366,444GRAVESITE EXP. & SITE IMPROVEMENTS, CALVERTON, NY SA-016
Mod SA014· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-09-22+$335,000$32,701,444GRAVESITE EXP. & SITE IMPROVEMENTS, CALVERTON, NY
Mod SA017· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-09-22−$3,930$32,697,514GRAVESITE EXP. & SITE IMPROVEMENTS, CALVERTON, NY SA-017 ISSUED TO DEFINITIZE CO-01B ADDITIONAL ROAD RECONSTRU…
Mod SA018· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-12-20+$20,300$32,717,814GRAVESITE EXP.&SITE IMPROVEMENTS, CALVERTON, NY SA-018
Mod SA019· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-12-20+$0$32,717,814GRAVESITE EXP.&SITE IMPROVEMENTS, CALVERTON, NY SA-019
Mod SA020· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-12-20+$38,000$32,755,814GRAVESITE EXP.&SITE IMPROVEMENTS, CALVERTON, NY SA-020
Mod 26· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-12-21−$65,397$32,690,417ASPHALT SEAL COATING CNC CALVERTON, NY
Mod SA021· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-12-27+$9,000$32,699,417GRAVESITE EXP.&SITE IMPROVEMENTS, CALVERTON, NY SA-021
Mod SA022· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-12-27+$27,000$32,726,417GRAVESITE EXP.&SITE IMPROVEMENTS, CALVERTON, NY SA-022
Mod SA025· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-12-27+$50,534$32,776,951GRAVESITE EXP.&SITE IMPROVEMENTS, CALVERTON, NY SA-025
Mod SA023· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-12-28+$7,216$32,784,167GRAVESITE EXP.&SITE IMPROVEMENTS, CALVERTON, NY SA-023
Mod SA028· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-01-06−$65,397$32,718,770GRAVESITE EXP.&SITE IMPROVEMENTS, CALVERTON, NY SA-026
Mod SA027· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-01-11+$0$32,718,770PROVIDE CONCEALED GRID PAN TYPE CEILINGS IN LIEU OF REVEALED GRID PANEL CEILINGS AT THE ADMIN BLDG ENTRANCE CA…
Mod SA029· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-01-18+$5,800$32,724,570PROVIDE KARNACK #220AF IN LIEU OF HENRY AIR BLOC 21 VAPOR BARRIER CNC CALVERTON, NY
Mod SA030· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-01-18+$2,265$32,726,835PROVIDE ADDITIONAL SIGNAGE PER SHEET SK-15 CNC CALVERTON, NY
Mod SA031· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-01-18+$910$32,727,745REVISED IRRIGATION LATERAL PIPING PER SHEET I-17 REVISED 12/1/2010 CNC CALVERTON, NY
Mod TE001· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-01-19+$0$32,727,745GRAVESITE EXP.&SITE IMPROVEMENTS, CALVERTON, NY TE-001
Mod SA024· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-01-24−$50,534$32,677,211GRAVESITE EXP.&SITE IMPROVEMENTS, CALVERTON, NY SA-024
Mod SA034· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-03-15+$0$32,677,211PROVIDE LANDSCAPE PLANTING AT ALL COMMITTAL SHELTERS PER DRAWING SK-7 AND ELIMINATE SITE PLANTINGS AS SHOWN ON…
Mod CO01D· CHANGE ORDER2011-04-13+$2,145$32,679,356ADDING 8" SILENT WAFER CHECK VALVES GRAVESITE EXP.&SITE IMPROVEMENTS, CALVERTON, NY CO-01C
Mod CO01E· CHANGE ORDER2011-04-13+$6,175$32,685,531ADDITIONAL ROOF DRAIN GRAVESITE EXP.&SITE IMPROVEMENTS, CALVERTON, NY CO-01C
Mod SA035· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-04-19+$38,000$32,723,531MAINTENANCE YARD DRAINAGE CNC CALVERTON, NY
Mod SA036· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-04-19+$2,245$32,725,7762011 PARTNERING SESSION CNC CALVERTON, NY
Mod SA032· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-04-25+$35,250$32,761,026HVAC REPAIRS AT MAINT. BUILDING CNC CALVERTON, NY
Mod SA033· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-04-25+$97,500$32,858,526ADDITIONAL HYDRANT STATIONS CNC CALVERTON, NY
Mod TE002· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-04-25+$0$32,858,526WEATHER DELAYS - 11 CALENDAR DAYS GRAVESITE EXP.&SITE IMPROVEMENTS, CALVERTON, NY TE-002
Mod SA037· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-05-11+$79,550$32,938,076RECONSTRUCT ALEXANDER HAMILTON DRIVE FROM THE INTERSECTION OF MOHICAN WAY TO CALVERTON DRIVE.
Mod SA038· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-05-13+$75,000$33,013,076REMOVE AND REPLACE THE EXISTING BARBED WIRE TOPPED FENCE AND GATES AT THE MAINTENANCE COMPLEX.
Mod SA039· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-06-30+$855$33,013,931INSTALL SILENT WAFER VALVE IN PUMP HOUSE 8 AND 9 PER DRAWING SK-20 PREPARED BY CVDA DATED 3/25/11. THIS SA WIL…
Mod SA040· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-06-30+$655$33,014,586INSTALL ADDITIONAL ROOF DRAINS AT THE ADMINISTRATION BUILDING
Mod SA041· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-07-19−$4,250$33,010,336PROVIDE 166 VIBURNUM PRUNIFOLIUM 'GUARDIAN' 5/6' HT IN LIEU OF 166 CORNUS RACEMOSA 'CUYZAM' 6/8' HT.
Mod SA042· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-08-18+$17,000$33,027,336RE-GRADE CATCHMENT AREAS TO PROVIDE POSITIVE DRAINAGE PREVENTING STANDING WATER CALVERTON NATIONAL CEMETERY -…
Mod SA043· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-08-18+$32,000$33,059,336ADDITIONAL CONCRETE FENCE PANELS AT THE COMMITTAL SHELTER SERVICES AREA CALVERTON NATIONAL CEMETERY - GRAVESIT…
Mod SA044· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-08-18+$13,465$33,072,801RE-CONSTRUCT ENTRY PER RFI-10 AND DRAWINGS CALVERTON NATIONAL CEMETERY - GRAVESITE EXPANSION CALVERTON, NEW YO…
Mod SA045· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-08-18−$4,325$33,068,476DELETE PLANTINGS ADD STONE AND TREES CALVERTON NATIONAL CEMETERY - GRAVESITE EXPANSION CALVERTON, NEW YORK
Mod CO01F· CHANGE ORDER2011-09-01+$13,000$33,081,476PROVIDE IRRIGATION CONTROL WIRE CONDUIT AT THE NEW COLUMBARIUM.
Mod CO01G· CHANGE ORDER2011-09-02+$49,000$33,130,476POSITIVE DRAINAGE
Mod TE003· OTHER ADMINISTRATIVE ACTION2011-09-26+$0$33,130,476SEVERE WEATHER DELAY
Mod SA046· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-10-18−$8,441$33,122,035THIS SA DEFINITIZES CO-01G WHICH INCLUDED THE FOLLOWING: PROVIDE POSITIVE DRAINAGE FOR CATCHMENT AREAS, INSTA…
Mod SA048· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-10-21+$44,000$33,166,035THIS SA DEFINITIZES CO-01G WHICH INCLUDED THE FOLLOWING: PROVIDE POSITIVE DRAINAGE FOR CATCHMENT AREAS, INSTA…
Mod SA049· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-10-21+$13,236$33,179,271THIS SA DEFINITIZES CO-01G WHICH INCLUDED THE FOLLOWING: PROVIDE POSITIVE DRAINAGE FOR CATCHMENT AREAS, INSTA…
Mod SA050· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-10-28+$95,771$33,275,042THIS SA DEFINITIZES CO-01G WHICH INCLUDED THE FOLLOWING: PROVIDE POSITIVE DRAINAGE FOR CATCHMENT AREAS, INSTA…
Mod SA051· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-10-28+$7,092$33,282,134THIS SA DEFINITIZES CO-01G WHICH INCLUDED THE FOLLOWING: PROVIDE POSITIVE DRAINAGE FOR CATCHMENT AREAS, INSTA…
Mod TE004· OTHER ADMINISTRATIVE ACTION2011-10-28+$0$33,282,134SEVERE WEATHER DELAY
Mod SA052· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-11-04−$2,174$33,279,960THIS SA DEFINITIZES CO-01G WHICH INCLUDED THE FOLLOWING: PROVIDE POSITIVE DRAINAGE FOR CATCHMENT AREAS, INSTA…
Mod CO01H· CHANGE ORDER2011-11-10+$16,000$33,295,960POSITIVE DRAINAGE
Mod SA053· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-12-07+$0$33,295,960THIS SA DEFINITIZES CO-01G WHICH INCLUDED THE FOLLOWING: PROVIDE POSITIVE DRAINAGE FOR CATCHMENT AREAS, INSTA…
Mod SA054· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-12-08+$17,573$33,313,533THIS SA DEFINITIZES CO-01G WHICH INCLUDED THE FOLLOWING: PROVIDE POSITIVE DRAINAGE FOR CATCHMENT AREAS, INSTA…
Mod SA055· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-12-09+$7,370$33,320,903THIS SA DEFINITIZES CO-01G WHICH INCLUDED THE FOLLOWING: PROVIDE POSITIVE DRAINAGE FOR CATCHMENT AREAS, INSTA…
Mod SA047· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2012-01-20+$475,000$33,795,903INSTALL FIRE DETECTION AND SECURITY SYSTEMS ACCORDING TO PLANS AND SPECIFICATIONS LISTED IN RFP D-1 0039, PREP…
Mod SA056· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2012-06-26+$9,690$33,805,592PROVIDE INTERNALLY BRACED DOUBLE SIDED ALUMINUM INFORMATIONAL SIGNS IN LIEU OFCONTRACT REQUIRED STEELL BACKED…
Mod SA057· DEFINITIZE CHANGE ORDER2012-06-28+$10,493$33,816,086REMOVE UNSTABLE SOIL FROM SITE, INSTALL SUB DRAINAGE AND REPAIR ROOF DRAIN.
Mod SA058· DEFINITIZE CHANGE ORDER2012-09-18+$1,616$33,817,702PROVIDE CENTRAL STATION MONITORING

Related awards · 5

Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.

Other recipients under Y299 from OFFICE OF CONSTRUCTION & FACILITIES MANAGEMENT (most recent first)

AwardRecipientOfficeNet obligationsFY
VA101CFMP0254INTERNATIONAL PUBLIC WORKS, LLCOFFICE OF CONSTRUCTION & FACILITIES MANAGEMENT$176,885FY2011
VA101CFMC0143SPANISH SPRINGS CONSTRUCTION INCOFFICE OF CONSTRUCTION & FACILITIES MANAGEMENT$17,403,315FY2011
VA101CFMC0074KEVCON-TTP, JVOFFICE OF CONSTRUCTION & FACILITIES MANAGEMENT$25,303,657FY2010
VA101CFMC0087US BUILDERS GROUP INC.OFFICE OF CONSTRUCTION & FACILITIES MANAGEMENT$13,860,444FY2010