Award recordCONTRACT

C & C CONTRACTORS LLC

PIID VA101CFMC0048· VA Staff Offices· OFFICE OF CONSTRUCTION & FACILITIES MANAGEMENT· Y299 · CONTRUCT/ALL OTHER NON-BLDG FACS· FY2009· $12,831,309 net obligations· UEI Z6ZVR3MXC9L4· AL

Description

THIS SA IS TO COMPENSATE THE CONTRACTOR FOR INCREASED COSTS IN PERFORMANCE BOND PREMIUM AND FINAL REPAIRS AND CORRECTIONS TO THE CONTRACT DUE TO DESIGN ERRORS OR CONFLICT WITH EXISTING CONDITIONS.

Base award description: ALABAMA NATIONAL CEMETERY, PHASE 1B

First action · last action
2009-07-31 · 2011-05-13
Transactions
44
First transaction's obligation
$11,056,000
Base + all options value (sum of deltas)
$12,831,309
Extent competed
FULL AND OPEN COMPETITION AFTER EXCLUSION OF SOURCES
Other than full & open authority
—
Set-aside
SERVICE DISABLED VETERAN OWNED SMALL BUSINESS SET-ASIDE
Offers received
12
SDVOSB flag on record
Yes (self-representation)
NAICS
237990 · OTHER HEAVY AND CIVIL ENGINEERING CONSTRUCTION

Modification chain · 44 transactions

Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.

$12,831,309$0Base award · 2009-07-31 · this action $11,056,000 · running total $11,056,000Modification 1 · 2009-09-08 · this action $4,900 · running total $11,060,900Modification 2 · 2009-09-25 · this action $1,874 · running total $11,062,774Modification SA004 · 2009-10-30 · this action $98,444 · running total $11,161,219Modification SA005 · 2009-11-17 · this action $86,839 · running total $11,248,058Modification TE001 · 2009-11-19 · this action $0 · running total $11,248,058Modification TE002 · 2009-12-03 · this action $0 · running total $11,248,058Modification 10 · 2010-03-08 · this action $28,861 · running total $11,276,919Modification 11 · 2010-03-08 · this action $3,096 · running total $11,280,015Modification 7 · 2010-03-08 · this action $55,599 · running total $11,335,614Modification 8 · 2010-03-08 · this action $55,767 · running total $11,391,381Modification 12 · 2010-03-23 · this action $98,458 · running total $11,489,839Modification SA009 · 2010-03-29 · this action $161,505 · running total $11,651,344Modification SA018 · 2010-05-10 · this action $32,112 · running total $11,683,456Modification SA020 · 2010-05-10 · this action $89,923 · running total $11,773,380Modification SA017 · 2010-05-14 · this action $0 · running total $11,773,380Modification TE003 · 2010-05-14 · this action $0 · running total $11,773,380Modification SA019 · 2010-05-30 · this action -$168,939 · running total $11,604,441Modification SA026 · 2010-07-06 · this action $97,968 · running total $11,702,409Modification SA003 · 2010-08-13 · this action $31,678 · running total $11,734,086Modification SA013 · 2010-08-13 · this action $77,011 · running total $11,811,097Modification SA015 · 2010-08-13 · this action $68,085 · running total $11,879,182Modification SA016 · 2010-08-13 · this action $40,910 · running total $11,920,092Modification SA021 · 2010-08-13 · this action $47,762 · running total $11,967,853Modification SA006 · 2010-09-18 · this action $10,898 · running total $11,978,751Modification SA022 · 2010-09-18 · this action $87,951 · running total $12,066,702Modification SA023 · 2010-09-18 · this action $41,704 · running total $12,108,406Modification SA024 · 2010-09-18 · this action $74,285 · running total $12,182,691Modification SA025 · 2010-09-18 · this action $63,696 · running total $12,246,387Modification SA014 · 2010-09-22 · this action $262,320 · running total $12,508,707Modification SA029 · 2010-10-19 · this action $24,703 · running total $12,533,410Modification SA030 · 2010-11-30 · this action $3,632 · running total $12,537,042Modification SA031 · 2010-12-13 · this action $12,257 · running total $12,549,299Modification SA027 · 2010-12-29 · this action $70,689 · running total $12,619,988Modification SA028 · 2010-12-29 · this action $18,460 · running total $12,638,449Modification CO01A · 2011-01-21 · this action $24,781 · running total $12,663,230Modification CO01B · 2011-02-08 · this action $33,000 · running total $12,696,230Modification TE004 · 2011-02-17 · this action $0 · running total $12,696,230Modification SA032 · 2011-02-28 · this action $38,147 · running total $12,734,376Modification SA033 · 2011-04-19 · this action $40,870 · running total $12,775,246Modification TE005 · 2011-04-19 · this action $0 · running total $12,775,246Modification SA034 · 2011-05-13 · this action $8,325 · running total $12,783,571Modification SA035 · 2011-05-13 · this action $7,995 · running total $12,791,566Modification SA036 · 2011-05-13 · this action $39,743 · running total $12,831,309
  • Base2009-07-31+$11,056,000= $11,056,000
  • Mod 12009-09-08+$4,900= $11,060,900
  • Mod 22009-09-25+$1,874= $11,062,774
  • Mod SA0042009-10-30+$98,444= $11,161,219
  • Mod SA0052009-11-17+$86,839= $11,248,058
  • Mod TE0012009-11-19+$0= $11,248,058
  • Mod TE0022009-12-03+$0= $11,248,058
  • Mod 102010-03-08+$28,861= $11,276,919
  • Mod 112010-03-08+$3,096= $11,280,015
  • Mod 72010-03-08+$55,599= $11,335,614
  • Mod 82010-03-08+$55,767= $11,391,381
  • Mod 122010-03-23+$98,458= $11,489,839
  • Mod SA0092010-03-29+$161,505= $11,651,344
  • Mod SA0182010-05-10+$32,112= $11,683,456
  • Mod SA0202010-05-10+$89,923= $11,773,380
  • Mod SA0172010-05-14+$0= $11,773,380
  • Mod TE0032010-05-14+$0= $11,773,380
  • Mod SA0192010-05-30-$168,939= $11,604,441
  • Mod SA0262010-07-06+$97,968= $11,702,409
  • Mod SA0032010-08-13+$31,678= $11,734,086
  • Mod SA0132010-08-13+$77,011= $11,811,097
  • Mod SA0152010-08-13+$68,085= $11,879,182
  • Mod SA0162010-08-13+$40,910= $11,920,092
  • Mod SA0212010-08-13+$47,762= $11,967,853
  • Mod SA0062010-09-18+$10,898= $11,978,751
  • Mod SA0222010-09-18+$87,951= $12,066,702
  • Mod SA0232010-09-18+$41,704= $12,108,406
  • Mod SA0242010-09-18+$74,285= $12,182,691
  • Mod SA0252010-09-18+$63,696= $12,246,387
  • Mod SA0142010-09-22+$262,320= $12,508,707
  • Mod SA0292010-10-19+$24,703= $12,533,410
  • Mod SA0302010-11-30+$3,632= $12,537,042
  • Mod SA0312010-12-13+$12,257= $12,549,299
  • Mod SA0272010-12-29+$70,689= $12,619,988
  • Mod SA0282010-12-29+$18,460= $12,638,449
  • Mod CO01A2011-01-21+$24,781= $12,663,230
  • Mod CO01B2011-02-08+$33,000= $12,696,230
  • Mod TE0042011-02-17+$0= $12,696,230
  • Mod SA0322011-02-28+$38,147= $12,734,376
  • Mod SA0332011-04-19+$40,870= $12,775,246
  • Mod TE0052011-04-19+$0= $12,775,246
  • Mod SA0342011-05-13+$8,325= $12,783,571
  • Mod SA0352011-05-13+$7,995= $12,791,566
  • Mod SA0362011-05-13+$39,743= $12,831,309
TransactionAction dateThis action (delta)Running totalDescription on this transaction
Base2009-07-31+$11,056,000$11,056,000ALABAMA NATIONAL CEMETERY, PHASE 1B
Mod 1· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2009-09-08+$4,900$11,060,900A. ALABAMA NATIONAL CEMETERY B. TOTAL CONTRACT PRICE INCREASED $4,900.00 AND 0 DAY(S) ADDITIONAL CONTRACT TIME…
Mod 2· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2009-09-25+$1,874$11,062,774A. ALABAMA NATIONAL CEMETERY B. TOTAL CONTRACT PRICE INCREASED $1,874.41 AND 0 DAY(S) ADDITIONAL CONTRACT TIME…
Mod SA004· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2009-10-30+$98,444$11,161,219ALABAMA NATIONAL CEMETERY PHASE 1B; SA-004 ISSUED FOR ADDITIONAL TESTING REQUIREMENTS.
Mod SA005· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2009-11-17+$86,839$11,248,058ALABAMA NATIONAL CEMETERY PHASE 1B; SA-005;
Mod TE001· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2009-11-19+$0$11,248,058ALABAMA NATIONAL CEMETERY PHASE 1B TE-001 WEATHER DELAY (AUG-SEPT 2009)
Mod TE002· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2009-12-03+$0$11,248,058ALABAMA NATIONAL CEMETERY PHASE 1B TE-002 WEATHER DELAY FOR (OCT 2009)
Mod 10· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-03-08+$28,861$11,276,919ALABAMA NATIONAL CEMETERY PHASE 1B EXCAVATION AND REMOVAL OF UNSUITABLE MATERIALS UNDER THE COLUMBARIA AND REP…
Mod 11· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-03-08+$3,096$11,280,015ALABAMA NATIONAL CEMETERY PHASE 1B PHASE 1A IRRIGATION WORK, REMOVE 3 IRRIGATION HEADS, DISCONNECT AND PLUG LA…
Mod 7· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-03-08+$55,599$11,335,614ALABAMA NATIONAL CEMETERY PHASE 1B PROVIDE LIMESTONE WATERTABLE AT PIC/ADMIN, CONTRACTOR SHALL SUBSTITUTE PVC…
Mod 8· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-03-08+$55,767$11,391,381ALABAMA NATIONAL CEMETERY PHASE 1B SUBSTITUTION OF BRICK VENEER FOR STEEL SIDING ON THE MAINTENANCE OFFICE BUI…
Mod 12· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-03-23+$98,458$11,489,839ALABAMA NATIONAL CEMETERY PHASE 1B CLEARING AND GRUBBING, EROSION CONTROL AND STORM SEWER
Mod SA009· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-03-29+$161,505$11,651,344ALABAMA NATIONAL CEMETERY PHASE 1B; SA-005;
Mod SA018· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-05-10+$32,112$11,683,456ALABAMA NATIONAL CEMETERY PHASE 1B; SA-018 ISSUED FOR IRRIGATION SYSTEM.
Mod SA020· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-05-10+$89,923$11,773,380ALABAMA NATIONAL CEMETERY PHASE 1B; SA-020 PUMP STATION INTAKE STRUCTURE
Mod SA017· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-05-14+$0$11,773,380ALABAMA NATIONAL CEMETERY PHASE 1B; SA-005;
Mod TE003· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-05-14+$0$11,773,380ALABAMA NATIONAL CEMETERY, PHASE 1B
Mod SA019· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-05-30−$168,939$11,604,441ALABAMA NATIONAL CEMETERY PHASE 1B; SA-019 DELETE PAYMENT
Mod SA026· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-07-06+$97,968$11,702,409ALABAMA NATIONAL CEMETERY PHASE 1B; SA-026;
Mod SA003· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-08-13+$31,678$11,734,086ALABAMA NATIONAL CEMETERY PHASE 1B; SA-003;
Mod SA013· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-08-13+$77,011$11,811,097ALABAMA NATIONAL CEMETERY PHASE 1B; SA-013;
Mod SA015· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-08-13+$68,085$11,879,182ALABAMA NATIONAL CEMETERY PHASE 1B; SA-015;
Mod SA016· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-08-13+$40,910$11,920,092ALABAMA NATIONAL CEMETERY PHASE 1B; SA-016;
Mod SA021· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-08-13+$47,762$11,967,853ALABAMA NATIONAL CEMETERY PHASE 1B; SA-021;
Mod SA006· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-09-18+$10,898$11,978,751SA-006
Mod SA022· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-09-18+$87,951$12,066,702ALABAMA NATIONAL CEMETERY PHASE 1B; SA-022;
Mod SA023· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-09-18+$41,704$12,108,406ALABAMA NATIONAL CEMETERY PHASE 1B;
Mod SA024· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-09-18+$74,285$12,182,691ALABAMA NATIONAL CEMETERY PHASE 1B;
Mod SA025· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-09-18+$63,696$12,246,387ALABAMA NATIONAL CEMETERY PHASE 1B; SA-005;
Mod SA014· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-09-22+$262,320$12,508,707ALABAMA NATIONAL CEMETERY PHASE 1B SA-014 PRIMARY DUCT BANK, GENERATORS, UNDERGROUND SERVICE
Mod SA029· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-10-19+$24,703$12,533,410INSTALL TWO 14' WIDE CATTLE GATES WITH 12' OF CATTLE FENCE ON EACH SIDE; F&I CURB AND GUTTER; CHANGES FOR SWB…
Mod SA030· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-11-30+$3,632$12,537,0421) INSTALL 9 HIGHBAY LIGHT. THE ORIGINAL DESIGN FOR THE MAINTENANCE GARAGE REQUIRED TH INSTALLATION OF STAND…
Mod SA031· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-12-13+$12,257$12,549,299THE ORIGINAL CONTRACT REQUIRED THE INSTALLATION OF CEILING HUNG COMPRESSED PLASTIC TOILET PARTITIONS. THE SHO…
Mod SA027· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-12-29+$70,689$12,619,988ALABAMA NATIONAL CEMETERY PHASE 1B; SA-027;
Mod SA028· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-12-29+$18,460$12,638,449ALABAMA NATIONAL CEMETERY PHASE 1B; SA-028;
Mod CO01A· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-01-21+$24,781$12,663,230MEMORIAL WALL CORRECTIONS ALL LABOR, MATERIALS, EQUIPMENT AND SUPERVISION ANC MONTEVALLO, AL
Mod CO01B· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-02-08+$33,000$12,696,230ADDITIONAL TESTING SERVICES ANC MONTEVALLO, AL
Mod TE004· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-02-17+$0$12,696,230STEEL DOORS; CONTRACT COMPLETION EXTENDED TO APRIL 15, 2011 ANC MONTEVALLO, AL
Mod SA032· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-02-28+$38,147$12,734,376GATE, PLANTING, PIC SIDEWALK, RIP RAP ANC MONTEVALLO, AL
Mod SA033· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-04-19+$40,870$12,775,246MISCELLANEOUS CLOSEOUT WORK ANC MONTEVALLO, AL
Mod TE005· OTHER ADMINISTRATIVE ACTION2011-04-19+$0$12,775,246GOVERNMENT CAUSED DELAY IN MOVING T1 LINE; CONTRACT COMPLETION EXTENDED TO APRIL 25, 2011 ANC MONTEVALLO, AL
Mod SA034· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-05-13+$8,325$12,783,571THIS SA DEFINITIZES CO-01B FOR ADDITIONAL TESTING AND QA/QC SERVICES REQUIRED TO PROTECT THE INTEREST OF THE G…
Mod SA035· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-05-13+$7,995$12,791,566THIS SA DEFINITIZES CO-01A FOR COSTS ASSOCIATED WITH ADDITIONAL WORK REQUIRED FOR COMPLETION OF THE MEMORIAL W…
Mod SA036· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-05-13+$39,743$12,831,309THIS SA IS TO COMPENSATE THE CONTRACTOR FOR INCREASED COSTS IN PERFORMANCE BOND PREMIUM AND FINAL REPAIRS AND…

Related awards · 11

Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.

Other VA awards to the same recipient (UEI Z6ZVR3MXC9L4)

AwardOffice · PSC / listingNet obligationsFY
36C78626C0020NATIONAL CEMETERY ADMIN (36C786) · Y1AZ · CONSTRUCTION OF OTHER ADMINISTRATIVE FACILITIES AND SERVICE BUILDINGS$31,145,450FY2026
36C24726C0055247-NETWORK CONTRACT OFFICE 7 (36C247) · Z1DA · MAINTENANCE OF HOSPITALS AND INFIRMARIES$9,079,864FY2026
36C78626N0338NATIONAL CEMETERY ADMIN (36C786) · Y1AZ · CONSTRUCTION OF OTHER ADMINISTRATIVE FACILITIES AND SERVICE BUILDINGS$122,570FY2026
36C78626N0342NATIONAL CEMETERY ADMIN (36C786) · Z2JZ · REPAIR OR ALTERATION OF MISCELLANEOUS BUILDINGS$361,151FY2026
36C78625C0042NATIONAL CEMETERY ADMIN (36C786) · Y1JZ · CONSTRUCTION OF MISCELLANEOUS BUILDINGS$24,203,981FY2025
36C78625N0565NATIONAL CEMETERY ADMIN (36C786) · Y1AZ · CONSTRUCTION OF OTHER ADMINISTRATIVE FACILITIES AND SERVICE BUILDINGS$281,750FY2025

Other recipients under Y299 from OFFICE OF CONSTRUCTION & FACILITIES MANAGEMENT (most recent first)

AwardRecipientOfficeNet obligationsFY
VA101CFMP0254INTERNATIONAL PUBLIC WORKS, LLCOFFICE OF CONSTRUCTION & FACILITIES MANAGEMENT$176,885FY2011
VA101CFMC0143SPANISH SPRINGS CONSTRUCTION INCOFFICE OF CONSTRUCTION & FACILITIES MANAGEMENT$17,403,315FY2011
VA101CFMC0074KEVCON-TTP, JVOFFICE OF CONSTRUCTION & FACILITIES MANAGEMENT$25,303,657FY2010
VA101CFMC0087US BUILDERS GROUP INC.OFFICE OF CONSTRUCTION & FACILITIES MANAGEMENT$13,860,444FY2010
VA101CFMC0082G&C FAB-CON, LLCOFFICE OF CONSTRUCTION & FACILITIES MANAGEMENT$21,354,503FY2010

Cite as: Glassbox VA record view · VA contract (USAspending / FPDS) · CONT_AWD_VA101CFMC0048_3600_-NONE-_-NONE- · retrieved 2026-09-26.