Description
SOUTH FLORIDA DESIGN-BUILD CONSTRUCTION - OBLIGATION ERROR CORRECTION
Base award description: SOUTH FLORIDA DESIGN-BUILD CONSTRUCTION
Modification chain · 24 transactions
Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.
- Base2018-09-13+$24,840,000= $24,840,000
- Mod P000022021-06-30-$614,970= $24,225,030
- Mod P000042022-01-21+$40,730= $24,265,760
- Mod P000052022-02-08+$120,720= $24,386,480
- Mod P000012022-04-28+$413,616= $24,800,096
- Mod P000062022-05-17+$38,482= $24,838,578
- Mod P000072022-08-04+$53,942= $24,892,520
- Mod P000082022-08-19+$176,414= $25,068,934
- Mod P000092022-10-27+$98,284= $25,167,218
- Mod P000102022-12-08+$34,662= $25,201,880
- Mod P000112023-01-13+$270,461= $25,472,341
- Mod P000122023-02-10+$46,226= $25,518,567
- Mod P000132023-03-22+$4,506= $25,523,073
- Mod P000152023-04-05+$97,000= $25,620,073
- Mod P000142023-05-17+$149,000= $25,769,073
- Mod P000172023-08-22+$6,682= $25,775,755
- Mod P000182023-08-22+$2,112= $25,777,867
- Mod A000192023-08-30+$79,338= $25,857,205
- Mod P000212023-09-28+$102,584= $25,959,789
- Mod P000202023-09-29+$651,252= $26,611,041
- Mod P000222023-11-16+$2,132,607= $28,743,648
- Mod P000162024-01-16+$183,658= $28,927,307
- Mod P000232025-12-03+$40,873= $28,968,180
- Mod P000242026-07-06+$424= $28,968,604
| Transaction | Action date | This action (delta) | Running total | Description on this transaction |
|---|---|---|---|---|
| Base | 2018-09-13 | +$24,840,000 | $24,840,000 | SOUTH FLORIDA DESIGN-BUILD CONSTRUCTION |
| Mod P00002· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2021-06-30 | −$614,970 | $24,225,030 | SOUTH FLORIDA DESIGN-BUILD CONSTRUCTION |
| Mod P00004· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2022-01-21 | +$40,730 | $24,265,760 | SOUTH FLORIDA DESIGN-BUILD CONSTRUCTION |
| Mod P00005· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2022-02-08 | +$120,720 | $24,386,480 | SOUTH FLORIDA DESIGN-BUILD CONSTRUCTION |
| Mod P00001· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2022-04-28 | +$413,616 | $24,800,096 | SOUTH FLORIDA DESIGN-BUILD CONSTRUCTION |
| Mod P00006· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2022-05-17 | +$38,482 | $24,838,578 | SOUTH FLORIDA DESIGN-BUILD CONSTRUCTION |
| Mod P00007· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2022-08-04 | +$53,942 | $24,892,520 | SOUTH FLORIDA DESIGN-BUILD CONSTRUCTION |
| Mod P00008· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2022-08-19 | +$176,414 | $25,068,934 | SOUTH FLORIDA DESIGN-BUILD CONSTRUCTION |
| Mod P00009· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2022-10-27 | +$98,284 | $25,167,218 | SOUTH FLORIDA DESIGN-BUILD CONSTRUCTION |
| Mod P00010· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2022-12-08 | +$34,662 | $25,201,880 | SOUTH FLORIDA DESIGN-BUILD CONSTRUCTION |
| Mod P00011· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2023-01-13 | +$270,461 | $25,472,341 | SOUTH FLORIDA DESIGN-BUILD CONSTRUCTION |
| Mod P00012· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2023-02-10 | +$46,226 | $25,518,567 | SOUTH FLORIDA DESIGN-BUILD CONSTRUCTION |
| Mod P00013· CHANGE ORDER | 2023-03-22 | +$4,506 | $25,523,073 | SOUTH FLORIDA DESIGN-BUILD CONSTRUCTION |
| Mod P00015· CHANGE ORDER | 2023-04-05 | +$97,000 | $25,620,073 | CHANGE ORDER, ADD EARLY TURN OVER SECTION. CEMETERY DEPLETION FORECAST UPDATED, NEED SECTIONS TURNED OVER IN… |
| Mod P00014· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2023-05-17 | +$149,000 | $25,769,073 | SOUTH FLORIDA DESIGN-BUILD CONSTRUCTION |
| Mod P00017· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2023-08-22 | +$6,682 | $25,775,755 | REALIGNMENT OF CHAIN LINK FENCE SOUTH PROPERTY LINE |
| Mod P00018· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2023-08-22 | +$2,112 | $25,777,867 | REALIGNMENT OF THE ADMIN BUILDING SYSTEM FURNITURE |
| Mod A00019· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2023-08-30 | +$79,338 | $25,857,205 | DEFINITIZE P00015 ETO OF BURIAL SECTIONS IN PHASE 2 |
| Mod P00021· OTHER ADMINISTRATIVE ACTION | 2023-09-28 | +$102,584 | $25,959,789 | ADMINISTRATIVE MOD TO FIX ERRORS MADE ON P00002 |
| Mod P00020· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2023-09-29 | +$651,252 | $26,611,041 | P00020 - PHYSICAL SECURITY UPGRADES |
| Mod P00022· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2023-11-16 | +$2,132,607 | $28,743,648 | P00022 - IRRIGATION LOOP CLOSURE |
| Mod P00016· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2024-01-16 | +$183,658 | $28,927,307 | SOUTH FLORIDA DESIGN-BUILD CONSTRUCTION EX. MEM. WALL DEMO AND BLDG. PAINTING |
| Mod P00023· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2025-12-03 | +$40,873 | $28,968,180 | SOUTH FLORIDA DESIGN-BUILD CONSTRUCTION - BOND PREMIUM ADJUST |
| Mod P00024· FUNDING ONLY ACTION | 2026-07-06 | +$424 | $28,968,604 | SOUTH FLORIDA DESIGN-BUILD CONSTRUCTION - OBLIGATION ERROR CORRECTION |
Related awards · 11
Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.
Other VA awards to the same recipient (UEI CFZ1ZEPL22N9)
| Award | Office · PSC / listing | Net obligations | FY |
|---|---|---|---|
| 36C78621P0137 | NATIONAL CEMETERY ADMIN (36C786) · H224 · EQUIPMENT AND MATERIALS TESTING- TRACTORS | $1,965 | FY2021 |
| 36C78621P0075 | NATIONAL CEMETERY ADMIN (36C786) · Y1AZ · CONSTRUCTION OF OTHER ADMINISTRATIVE FACILITIES AND SERVICE BUILDINGS | $530 | FY2021 |
| 36C78621P0063 | NATIONAL CEMETERY ADMIN (36C786) · Y1AZ · CONSTRUCTION OF OTHER ADMINISTRATIVE FACILITIES AND SERVICE BUILDINGS | $1,965 | FY2021 |
| 36C10F18C3383 | OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F) · Y1AZ · CONSTRUCTION OF OTHER ADMINISTRATIVE FACILITIES AND SERVICE BUILDINGS | $24,343,213 | FY2018 |
| 36C78618N0186 | NATIONAL CEMETERY ADMIN (36C786) · S208 · HOUSEKEEPING- LANDSCAPING/GROUNDSKEEPING | $86,400 | FY2018 |
| VA101F17C3088 | OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F) · Y1AZ · CONSTRUCTION OF OTHER ADMINISTRATIVE FACILITIES AND SERVICE BUILDINGS | $34,470,665 | FY2017 |
Other recipients under Y1PZ from OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F) (most recent first)
| Award | Recipient | Office | Net obligations | FY |
|---|---|---|---|---|
| 36C10F22C0002 | VETERAN DESIGN & CONSTRUCTION INC | OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F) | $28,956,154 | FY2022 |
| 36C10F21C0002 | CARIBE TECNO CRL | OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F) | $35,935,734 | FY2021 |
| 36C10F20C0011 | SGC SERVICES, LLC | OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F) | $1,295,194 | FY2020 |
| 36C10F20C0004 | MGC SERVICES A JOINT VENTURE LLC | OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F) | $0 | FY2020 |
| 36C10F19N0024 | CMP COMMERCIAL CONSTRUCTION INC | OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F) | $1,382,571 | FY2019 |
Cite as: Glassbox VA record view · VA contract (USAspending / FPDS) · CONT_AWD_36C10F18C3386_3600_-NONE-_-NONE- · retrieved 2026-09-26.