Description
CONSTRUCTION OF PIKES PEAK NATIONAL CEMETERY
Base award description: IGF::OT::IGF CONSTRUCTION OF PIKES PEAK NATIONAL CEMETERY
Modification chain · 58 transactions
Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.
- Base2017-09-20+$31,843,000= $31,843,000
- Mod P000012017-12-08+$100,000= $31,943,000
- Mod P000022018-03-09+$100,000= $32,043,000
- Mod P000032018-04-27+$166,000= $32,209,000
- Mod P000042018-08-27+$22,121= $32,231,121
- Mod P000052018-08-31+$75,000= $32,306,121
- Mod P000062018-08-31+$16,640= $32,322,761
- Mod P000082018-09-27+$0= $32,322,761
- Mod P000072018-10-02+$0= $32,322,761
- Mod P000102018-10-05+$27,186= $32,349,947
- Mod P000112018-10-05+$62,285= $32,412,232
- Mod P000092018-10-08+$11,958= $32,424,190
- Mod P000122018-10-12+$22,349= $32,446,539
- Mod P000132018-10-12+$66,461= $32,513,000
- Mod P000142018-11-06+$3,355= $32,516,355
- Mod P000152018-11-06+$7,304= $32,523,659
- Mod P000162018-11-07+$7,007= $32,530,666
- Mod P000172018-11-07+$23,516= $32,554,182
- Mod P000182019-08-27+$0= $32,554,182
- Mod P000212019-10-10+$274,368= $32,828,550
- Mod P000192019-10-17+$0= $32,828,550
- Mod P000202019-10-30+$43,046= $32,871,596
- Mod P000232019-11-12+$186,571= $33,058,167
- Mod P000242020-01-21+$0= $33,058,167
- Mod P000252020-02-20+$0= $33,058,167
- Mod P000272020-03-19+$0= $33,058,167
- Mod P000262020-03-20+$0= $33,058,167
- Mod P000292020-04-10+$0= $33,058,167
- Mod P000282020-04-13+$9,690= $33,067,857
- Mod P000302020-04-22+$300,116= $33,367,973
- Mod P000312020-04-28+$19,919= $33,387,892
- Mod P000222020-05-04+$6,804= $33,394,696
- Mod P000322020-05-06+$9,125= $33,403,821
- Mod P000342020-05-21+$263,739= $33,667,560
- Mod P000332020-06-25+$7,838= $33,675,398
- Mod P000362020-06-25-$41,147= $33,634,251
- Mod P000352020-06-30+$85,467= $33,719,718
- Mod P000392020-08-12+$107,231= $33,826,949
- Mod P000382020-08-19+$46,551= $33,873,500
- Mod P000402020-08-20+$123,418= $33,996,918
- Mod P000372020-11-09+$133,427= $34,130,345
- Mod P000422020-12-07+$79,794= $34,210,139
- Mod P000412020-12-10+$16,201= $34,226,340
- Mod P000432021-01-07+$19,541= $34,245,881
- Mod P000442021-01-29+$57,136= $34,303,017
- Mod P000452021-02-11+$16,201= $34,319,218
- Mod P000462021-03-11+$0= $34,319,218
- Mod P000472021-03-19+$0= $34,319,218
- Mod P000482021-03-31+$11,968= $34,331,186
- Mod P000492021-05-03+$113,463= $34,444,649
- Mod P000502021-05-14+$0= $34,444,649
- Mod P000512021-06-30+$0= $34,444,649
- Mod P000522021-07-10+$0= $34,444,649
- Mod P000532021-08-31+$0= $34,444,649
- Mod P000542021-09-10+$0= $34,444,649
- Mod P000552021-09-20+$0= $34,444,649
- Mod P000562021-09-29+$26,016= $34,470,665
- Mod P000572021-10-10+$0= $34,470,665
| Transaction | Action date | This action (delta) | Running total | Description on this transaction |
|---|---|---|---|---|
| Base | 2017-09-20 | +$31,843,000 | $31,843,000 | IGF::OT::IGF CONSTRUCTION OF PIKES PEAK NATIONAL CEMETERY |
| Mod P00001· CHANGE ORDER | 2017-12-08 | +$100,000 | $31,943,000 | IGF::OT::IGF CONSTRUCTION OF PIKES PEAK NATIONAL CEMETERY |
| Mod P00002· CHANGE ORDER | 2018-03-09 | +$100,000 | $32,043,000 | IGF::OT::IGF CONSTRUCTION OF PIKES PEAK NATIONAL CEMETERY |
| Mod P00003· CHANGE ORDER | 2018-04-27 | +$166,000 | $32,209,000 | IGF::OT::IGF CONSTRUCTION OF PIKES PEAK NATIONAL CEMETERY |
| Mod P00004· CHANGE ORDER | 2018-08-27 | +$22,121 | $32,231,121 | IGF::OT::IGF CONSTRUCTION OF PIKES PEAK NATIONAL CEMETERY |
| Mod P00005· CHANGE ORDER | 2018-08-31 | +$75,000 | $32,306,121 | IGF::OT::IGF CONSTRUCTION OF PIKES PEAK NATIONAL CEMETERY |
| Mod P00006· CHANGE ORDER | 2018-08-31 | +$16,640 | $32,322,761 | IGF::OT::IGF CONSTRUCTION OF PIKES PEAK NATIONAL CEMETERY |
| Mod P00008· CHANGE ORDER | 2018-09-27 | +$0 | $32,322,761 | IGF::OT::IGF CONSTRUCTION OF PIKES PEAK NATIONAL CEMETERY |
| Mod P00007· CHANGE ORDER | 2018-10-02 | +$0 | $32,322,761 | IGF::OT::IGF CONSTRUCTION OF PIKES PEAK NATIONAL CEMETERY |
| Mod P00010· CHANGE ORDER | 2018-10-05 | +$27,186 | $32,349,947 | CONSTRUCTION OF PIKES PEAK NATIONAL CEMETERY |
| Mod P00011· CHANGE ORDER | 2018-10-05 | +$62,285 | $32,412,232 | CONSTRUCTION OF PIKES PEAK NATIONAL CEMETERY |
| Mod P00009· CHANGE ORDER | 2018-10-08 | +$11,958 | $32,424,190 | CONSTRUCTION OF PIKES PEAK NATIONAL CEMETERY |
| Mod P00012· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2018-10-12 | +$22,349 | $32,446,539 | CONSTRUCTION OF PIKES PEAK NATIONAL CEMETERY |
| Mod P00013· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2018-10-12 | +$66,461 | $32,513,000 | CONSTRUCTION OF PIKES PEAK NATIONAL CEMETERY |
| Mod P00014· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2018-11-06 | +$3,355 | $32,516,355 | CONSTRUCTION OF PIKES PEAK NATIONAL CEMETERY |
| Mod P00015· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2018-11-06 | +$7,304 | $32,523,659 | CONSTRUCTION OF PIKES PEAK NATIONAL CEMETERY |
| Mod P00016· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2018-11-07 | +$7,007 | $32,530,666 | CONSTRUCTION OF PIKES PEAK NATIONAL CEMETERY |
| Mod P00017· CHANGE ORDER | 2018-11-07 | +$23,516 | $32,554,182 | CONSTRUCTION OF PIKES PEAK NATIONAL CEMETERY |
| Mod P00018· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2019-08-27 | +$0 | $32,554,182 | CONSTRUCTION OF PIKES PEAK NATIONAL CEMETERY |
| Mod P00021· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2019-10-10 | +$274,368 | $32,828,550 | CONSTRUCTION OF PIKES PEAK NATIONAL CEMETERY |
| Mod P00019· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2019-10-17 | +$0 | $32,828,550 | CONSTRUCTION OF PIKES PEAK NATIONAL CEMETERY |
| Mod P00020· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2019-10-30 | +$43,046 | $32,871,596 | CONSTRUCTION OF PIKES PEAK NATIONAL CEMETERY |
| Mod P00023· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2019-11-12 | +$186,571 | $33,058,167 | CONSTRUCTION OF PIKES PEAK NATIONAL CEMETERY |
| Mod P00024· CHANGE ORDER | 2020-01-21 | +$0 | $33,058,167 | CONSTRUCTION OF PIKES PEAK NATIONAL CEMETERY |
| Mod P00025· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2020-02-20 | +$0 | $33,058,167 | CONSTRUCTION OF PIKES PEAK NATIONAL CEMETERY |
| Mod P00027· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2020-03-19 | +$0 | $33,058,167 | CONSTRUCTION OF PIKES PEAK NATIONAL CEMETERY |
| Mod P00026· OTHER ADMINISTRATIVE ACTION | 2020-03-20 | +$0 | $33,058,167 | CONSTRUCTION OF PIKES PEAK NATIONAL CEMETERY |
| Mod P00029· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2020-04-10 | +$0 | $33,058,167 | CONSTRUCTION OF PIKES PEAK NATIONAL CEMETERY |
| Mod P00028· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2020-04-13 | +$9,690 | $33,067,857 | CONSTRUCTION OF PIKES PEAK NATIONAL CEMETERY |
| Mod P00030· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2020-04-22 | +$300,116 | $33,367,973 | CONSTRUCTION OF PIKES PEAK NATIONAL CEMETERY |
| Mod P00031· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2020-04-28 | +$19,919 | $33,387,892 | CONSTRUCTION OF PIKES PEAK NATIONAL CEMETERY |
| Mod P00022· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2020-05-04 | +$6,804 | $33,394,696 | CONSTRUCTION OF PIKES PEAK NATIONAL CEMETERY |
| Mod P00032· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2020-05-06 | +$9,125 | $33,403,821 | CONSTRUCTION OF PIKES PEAK NATIONAL CEMETERY |
| Mod P00034· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2020-05-21 | +$263,739 | $33,667,560 | CONSTRUCTION OF PIKES PEAK NATIONAL CEMETERY |
| Mod P00033· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2020-06-25 | +$7,838 | $33,675,398 | CONSTRUCTION OF PIKES PEAK NATIONAL CEMETERY |
| Mod P00036· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2020-06-25 | −$41,147 | $33,634,251 | CONSTRUCTION OF PIKES PEAK NATIONAL CEMETERY |
| Mod P00035· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2020-06-30 | +$85,467 | $33,719,718 | CONSTRUCTION OF PIKES PEAK NATIONAL CEMETERY |
| Mod P00039· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2020-08-12 | +$107,231 | $33,826,949 | CONSTRUCTION OF PIKES PEAK NATIONAL CEMETERY |
| Mod P00038· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2020-08-19 | +$46,551 | $33,873,500 | CONSTRUCTION OF PIKES PEAK NATIONAL CEMETERY |
| Mod P00040· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2020-08-20 | +$123,418 | $33,996,918 | CONSTRUCTION OF PIKES PEAK NATIONAL CEMETERY |
| Mod P00037· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2020-11-09 | +$133,427 | $34,130,345 | CONSTRUCTION OF PIKES PEAK NATIONAL CEMETERY |
| Mod P00042· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2020-12-07 | +$79,794 | $34,210,139 | CONSTRUCTION OF PIKES PEAK NATIONAL CEMETERY |
| Mod P00041· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2020-12-10 | +$16,201 | $34,226,340 | CONSTRUCTION OF PIKES PEAK NATIONAL CEMETERY |
| Mod P00043· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2021-01-07 | +$19,541 | $34,245,881 | CONSTRUCTION OF PIKES PEAK NATIONAL CEMETERY |
| Mod P00044· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2021-01-29 | +$57,136 | $34,303,017 | CONSTRUCTION OF PIKES PEAK NATIONAL CEMETERY |
| Mod P00045· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2021-02-11 | +$16,201 | $34,319,218 | CONSTRUCTION OF PIKES PEAK NATIONAL CEMETERY |
| Mod P00046· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2021-03-11 | +$0 | $34,319,218 | CONSTRUCTION OF PIKES PEAK NATIONAL CEMETERY |
| Mod P00047· CHANGE ORDER | 2021-03-19 | +$0 | $34,319,218 | CONSTRUCTION OF PIKES PEAK NATIONAL CEMETERY |
| Mod P00048· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2021-03-31 | +$11,968 | $34,331,186 | CONSTRUCTION OF PIKES PEAK NATIONAL CEMETERY |
| Mod P00049· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2021-05-03 | +$113,463 | $34,444,649 | CONSTRUCTION OF PIKES PEAK NATIONAL CEMETERY |
| Mod P00050· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2021-05-14 | +$0 | $34,444,649 | CONSTRUCTION OF PIKES PEAK NATIONAL CEMETERY |
| Mod P00051· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2021-06-30 | +$0 | $34,444,649 | CONSTRUCTION OF PIKES PEAK NATIONAL CEMETERY |
| Mod P00052· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2021-07-10 | +$0 | $34,444,649 | CONSTRUCTION OF PIKES PEAK NATIONAL CEMETERY |
| Mod P00053· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2021-08-31 | +$0 | $34,444,649 | CONSTRUCTION OF PIKES PEAK NATIONAL CEMETERY |
| Mod P00054· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2021-09-10 | +$0 | $34,444,649 | CONSTRUCTION OF PIKES PEAK NATIONAL CEMETERY |
| Mod P00055· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2021-09-20 | +$0 | $34,444,649 | CONSTRUCTION OF PIKES PEAK NATIONAL CEMETERY |
| Mod P00056· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2021-09-29 | +$26,016 | $34,470,665 | CONSTRUCTION OF PIKES PEAK NATIONAL CEMETERY |
| Mod P00057· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2021-10-10 | +$0 | $34,470,665 | CONSTRUCTION OF PIKES PEAK NATIONAL CEMETERY |
Related awards · 11
Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.
Other VA awards to the same recipient (UEI CFZ1ZEPL22N9)
| Award | Office · PSC / listing | Net obligations | FY |
|---|---|---|---|
| 36C78621P0137 | NATIONAL CEMETERY ADMIN (36C786) · H224 · EQUIPMENT AND MATERIALS TESTING- TRACTORS | $1,965 | FY2021 |
| 36C78621P0075 | NATIONAL CEMETERY ADMIN (36C786) · Y1AZ · CONSTRUCTION OF OTHER ADMINISTRATIVE FACILITIES AND SERVICE BUILDINGS | $530 | FY2021 |
| 36C78621P0063 | NATIONAL CEMETERY ADMIN (36C786) · Y1AZ · CONSTRUCTION OF OTHER ADMINISTRATIVE FACILITIES AND SERVICE BUILDINGS | $1,965 | FY2021 |
| 36C10F18C3383 | OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F) · Y1AZ · CONSTRUCTION OF OTHER ADMINISTRATIVE FACILITIES AND SERVICE BUILDINGS | $24,343,213 | FY2018 |
| 36C10F18C3386 | OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F) · Y1PZ · CONSTRUCTION OF OTHER NON-BUILDING FACILITIES | $28,968,604 | FY2018 |
| 36C78618N0186 | NATIONAL CEMETERY ADMIN (36C786) · S208 · HOUSEKEEPING- LANDSCAPING/GROUNDSKEEPING | $86,400 | FY2018 |
Other recipients under Y1AZ from OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F) (most recent first)
| Award | Recipient | Office | Net obligations | FY |
|---|---|---|---|---|
| 36C10F26C0002 | SANDOW CONSTRUCTION INC | OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F) | $783,108 | FY2026 |
| 36C10F24C0002 | RICHARD GROUP LLC | OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F) | $42,737,190 | FY2024 |
| 36C10F22C0007 | RANDY KINDER EXCAVATING INC | OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F) | $1,663,765 | FY2022 |
| 36C10F21C0001 | SPEES-HERNANDEZ JV LLC | OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F) | $19,726,379 | FY2021 |
| 36C10F21F0004 | HAMILTON PACIFIC CHAMBERLAIN LLC | OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F) | $406,155 | FY2021 |