Description
EXTENSION TO PERIOD OF PERFORMANCE.
Base award description: CONSTRUCTION OF PHASE 5 PARKING GARAGE VAMC SAN JUAN, PR
Modification chain · 36 transactions
Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.
- Base2021-06-24+$29,671,053= $29,671,053
- Mod A000012022-01-21+$109,913= $29,780,966
- Mod A000072022-07-27+$11,028= $29,791,994
- Mod A000122022-11-18+$2,057= $29,794,051
- Mod A000112022-12-13+$0= $29,794,051
- Mod A000132022-12-22+$28,409= $29,822,460
- Mod A000142023-01-23+$0= $29,822,460
- Mod P000102023-02-01+$435,944= $30,258,404
- Mod A000172023-03-10+$33,000= $30,291,404
- Mod A000022023-05-17+$0= $30,291,404
- Mod A000042023-05-18+$1,400= $30,292,804
- Mod A000052023-05-18+$1,500= $30,294,304
- Mod A000062023-06-05+$800= $30,295,104
- Mod A000162023-06-05+$119,310= $30,414,414
- Mod P000182023-08-31+$1,514,012= $31,928,426
- Mod A000202023-09-08+$20,000= $31,948,426
- Mod A000092023-10-16+$57,942= $32,006,368
- Mod A000222023-10-16+$0= $32,006,368
- Mod A000252023-12-11+$41,000= $32,047,368
- Mod A000232024-01-12+$4,355= $32,051,723
- Mod A000242024-01-12+$11,916= $32,063,639
- Mod A000262024-03-21+$30,844= $32,094,483
- Mod A000272024-05-14+$80,000= $32,174,483
- Mod A000282024-05-16+$101,519= $32,276,002
- Mod A000292024-07-19-$76,000= $32,200,002
- Mod A000312024-09-27+$150,000= $32,350,002
- Mod P000322024-11-01+$686,980= $33,036,982
- Mod A000302025-02-19+$0= $33,036,982
- Mod P000342025-03-03+$618,667= $33,655,649
- Mod A000352025-06-03+$11,637= $33,667,286
- Mod A000362025-12-16+$9,412= $33,676,697
- Mod A000372025-12-22+$33,933= $33,710,630
- Mod A000382026-01-07+$4,944= $33,715,575
- Mod P000332026-01-12+$73,385= $33,788,960
- Mod P000352026-02-26+$2,146,774= $35,935,734
- Mod P000362026-08-06+$0= $35,935,734
| Transaction | Action date | This action (delta) | Running total | Description on this transaction |
|---|---|---|---|---|
| Base | 2021-06-24 | +$29,671,053 | $29,671,053 | CONSTRUCTION OF PHASE 5 PARKING GARAGE VAMC SAN JUAN, PR |
| Mod A00001· CHANGE ORDER | 2022-01-21 | +$109,913 | $29,780,966 | CONSTRUCTION OF PHASE 5 PARKING GARAGE VAMC SAN JUAN, PR |
| Mod A00007· CHANGE ORDER | 2022-07-27 | +$11,028 | $29,791,994 | CONSTRUCTION OF PHASE 5 PARKING GARAGE VAMC SAN JUAN, PR ADMINISTRATIVE MODIFICATION |
| Mod A00012· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2022-11-18 | +$2,057 | $29,794,051 | CONSTRUCTION OF PHASE 5 PARKING GARAGE VAMC SAN JUAN, PR ADMINISTRATIVE MODIFICATION |
| Mod A00011· DEFINITIZE CHANGE ORDER | 2022-12-13 | +$0 | $29,794,051 | CONSTRUCTION OF PHASE 5 PARKING GARAGE VAMC SAN JUAN, PR |
| Mod A00013· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2022-12-22 | +$28,409 | $29,822,460 | CONSTRUCTION OF PHASE 5 PARKING GARAGE VAMC SAN JUAN, PR ADMINISTRATIVE MODIFICATION |
| Mod A00014· DEFINITIZE CHANGE ORDER | 2023-01-23 | +$0 | $29,822,460 | CONSTRUCTION OF PHASE 5 PARKING GARAGE VAMC SAN JUAN, PR |
| Mod P00010· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2023-02-01 | +$435,944 | $30,258,404 | CONSTRUCTION OF PHASE 5 PARKING GARAGE VAMC SAN JUAN, PR |
| Mod A00017· CHANGE ORDER | 2023-03-10 | +$33,000 | $30,291,404 | CONSTRUCTION OF PHASE 5 PARKING GARAGE VAMC SAN JUAN, PR ADMINISTRATIVE MODIFICATION |
| Mod A00002· CHANGE ORDER | 2023-05-17 | +$0 | $30,291,404 | CONSTRUCTION OF PHASE 5 PARKING GARAGE VAMC SAN JUAN, PR |
| Mod A00004· CHANGE ORDER | 2023-05-18 | +$1,400 | $30,292,804 | CONSTRUCTION OF PHASE 5 PARKING GARAGE VAMC SAN JUAN, PR |
| Mod A00005· CHANGE ORDER | 2023-05-18 | +$1,500 | $30,294,304 | CONSTRUCTION OF PHASE 5 PARKING GARAGE VAMC SAN JUAN, PR |
| Mod A00006· CHANGE ORDER | 2023-06-05 | +$800 | $30,295,104 | CONSTRUCTION OF PHASE 5 PARKING GARAGE VAMC SAN JUAN, PR ADMINISTRATIVE MODIFICATION |
| Mod A00016· CHANGE ORDER | 2023-06-05 | +$119,310 | $30,414,414 | CONSTRUCTION OF PHASE 5 PARKING GARAGE VAMC SAN JUAN, PR |
| Mod P00018· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2023-08-31 | +$1,514,012 | $31,928,426 | CONSTRUCTION OF PHASE 5 PARKING GARAGE VAMC SAN JUAN, PR |
| Mod A00020· CHANGE ORDER | 2023-09-08 | +$20,000 | $31,948,426 | CONSTRUCTION OF PHASE 5 PARKING GARAGE VAMC SAN JUAN, PR ADMINISTRATIVE MODIFICATION |
| Mod A00009· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2023-10-16 | +$57,942 | $32,006,368 | CONSTRUCTION OF PHASE 5 PARKING GARAGE VAMC SAN JUAN, PR ADMINISTRATIVE MODIFICATION |
| Mod A00022· DEFINITIZE CHANGE ORDER | 2023-10-16 | +$0 | $32,006,368 | CONSTRUCTION OF PHASE 5 PARKING GARAGE VAMC SAN JUAN, PR ADMINISTRATIVE MODIFICATION |
| Mod A00025· CHANGE ORDER | 2023-12-11 | +$41,000 | $32,047,368 | CONSTRUCTION OF PHASE 5 PARKING GARAGE VAMC SAN JUAN, PR ADMINISTRATIVE MODIFICATION |
| Mod A00023· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2024-01-12 | +$4,355 | $32,051,723 | CONSTRUCTION OF PHASE 5 PARKING GARAGE VAMC SAN JUAN, PR ADMINISTRATIVE MODIFICATION |
| Mod A00024· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2024-01-12 | +$11,916 | $32,063,639 | CONSTRUCTION OF PHASE 5 PARKING GARAGE VAMC SAN JUAN, PR ADMINISTRATIVE MODIFICATION |
| Mod A00026· CHANGE ORDER | 2024-03-21 | +$30,844 | $32,094,483 | CONSTRUCTION OF PHASE 5 PARKING GARAGE VAMC SAN JUAN, PR ADMINISTRATIVE MODIFICATION |
| Mod A00027· CHANGE ORDER | 2024-05-14 | +$80,000 | $32,174,483 | CONSTRUCTION OF PHASE 5 PARKING GARAGE VAMC SAN JUAN, PR ADMINISTRATIVE MODIFICATION |
| Mod A00028· CHANGE ORDER | 2024-05-16 | +$101,519 | $32,276,002 | CONSTRUCTION OF PHASE 5 PARKING GARAGE VAMC SAN JUAN, PR ADMINISTRATIVE MODIFICATION |
| Mod A00029· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2024-07-19 | −$76,000 | $32,200,002 | CONSTRUCTION OF PHASE 5 PARKING GARAGE VAMC SAN JUAN, PR ADMINISTRATIVE MODIFICATION |
| Mod A00031· CHANGE ORDER | 2024-09-27 | +$150,000 | $32,350,002 | CONSTRUCTION OF PHASE 5 PARKING GARAGE VAMC SAN JUAN, PR ADMINISTRATIVE MODIFICATION |
| Mod P00032· DEFINITIZE CHANGE ORDER | 2024-11-01 | +$686,980 | $33,036,982 | CONSTRUCTION OF PHASE 5 PARKING GARAGE VAMC SAN JUAN, PR ADMINISTRATIVE MODIFICATION |
| Mod A00030· CHANGE ORDER | 2025-02-19 | +$0 | $33,036,982 | CONSTRUCTION OF PHASE 5 PARKING GARAGE VAMC SAN JUAN, PR ADMINISTRATIVE MODIFICATION |
| Mod P00034· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2025-03-03 | +$618,667 | $33,655,649 | CONSTRUCTION OF PHASE 5 PARKING GARAGE VAMC SAN JUAN, PR ADMINISTRATIVE MODIFICATION |
| Mod A00035· CHANGE ORDER | 2025-06-03 | +$11,637 | $33,667,286 | CONSTRUCTION OF PHASE 5 PARKING GARAGE VAMC SAN JUAN, PR ADMINISTRATIVE MODIFICATION |
| Mod A00036· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2025-12-16 | +$9,412 | $33,676,697 | CONSTRUCTION OF PHASE 5 PARKING GARAGE VAMC SAN JUAN, PR ADMINISTRATIVE MODIFICATION SA FOR RFP 007 |
| Mod A00037· DEFINITIZE CHANGE ORDER | 2025-12-22 | +$33,933 | $33,710,630 | CONSTRUCTION OF PHASE 5 PARKING GARAGE VAMC SAN JUAN, PR ADMINISTRATIVE MODIFICATION SA FOR RFP 007 |
| Mod A00038· CHANGE ORDER | 2026-01-07 | +$4,944 | $33,715,575 | CONSTRUCTION OF PHASE 5 PARKING GARAGE VAMC SAN JUAN, PR ADMINISTRATIVE MODIFICATION SA FOR RFP 007 |
| Mod P00033· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2026-01-12 | +$73,385 | $33,788,960 | CONSTRUCTION OF PHASE 5 PARKING GARAGE VAMC SAN JUAN, PR ADMINISTRATIVE MODIFICATION |
| Mod P00035· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2026-02-26 | +$2,146,774 | $35,935,734 | CONSTRUCTION OF PHASE 5 PARKING GARAGE VAMC SAN JUAN, PR UST REA COR 43 |
| Mod P00036· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2026-08-06 | +$0 | $35,935,734 | EXTENSION TO PERIOD OF PERFORMANCE. |
Related awards · 5
Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.
Other recipients under Y1PZ from OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F) (most recent first)
| Award | Recipient | Office | Net obligations | FY |
|---|---|---|---|---|
| 36C10F22C0002 | VETERAN DESIGN & CONSTRUCTION INC | OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F) | $28,956,154 | FY2022 |
| 36C10F20C0011 | SGC SERVICES, LLC | OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F) | $1,295,194 | FY2020 |
| 36C10F20C0004 | MGC SERVICES A JOINT VENTURE LLC | OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F) | $0 | FY2020 |
| 36C10F19N0024 | CMP COMMERCIAL CONSTRUCTION INC | OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F) | $1,382,571 | FY2019 |
| 36C10F18C3394 | SUN EAGLE, CORPORATION | OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F) | $33,947,688 | FY2018 |