Description
IGF::OT::IGF P00016 (SA-14), SOD AT BIO RETENTION
Base award description: IGF::OT::IGF DEMOLITION OF UTILITY PLANT, VAMC ST. LOUIS, MO
Modification chain · 17 transactions
Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.
- Base2015-03-27+$1,374,000= $1,374,000
- Mod P000012015-09-10+$4,695= $1,378,695
- Mod P000022015-09-15+$9,534= $1,388,229
- Mod P000032015-09-21+$1,300= $1,389,529
- Mod P000042015-09-21+$774= $1,390,303
- Mod P000072015-10-15+$30,000= $1,420,303
- Mod P000052015-10-21+$17,637= $1,437,940
- Mod P000062015-10-21+$3,698= $1,441,638
- Mod P000082015-11-19+$0= $1,441,638
- Mod P000092015-11-19+$5,186= $1,446,824
- Mod P000102016-01-12+$0= $1,446,824
- Mod P000112016-02-01+$6,093= $1,452,917
- Mod P000122016-02-08+$50,000= $1,502,917
- Mod P000132016-03-18+$0= $1,502,917
- Mod P000142016-04-21+$378,079= $1,880,996
- Mod P000152016-07-28+$8,000= $1,888,996
- Mod P000162017-01-20+$7,960= $1,896,956
| Transaction | Action date | This action (delta) | Running total | Description on this transaction |
|---|---|---|---|---|
| Base | 2015-03-27 | +$1,374,000 | $1,374,000 | IGF::OT::IGF DEMOLITION OF UTILITY PLANT, VAMC ST. LOUIS, MO |
| Mod P00001· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2015-09-10 | +$4,695 | $1,378,695 | IGF::OT::IGF P00001 (SA-01) EMPLOY TRENCH BOX FOR UNDERGROUND STEAM LINE ABATEMENT |
| Mod P00002· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2015-09-15 | +$9,534 | $1,388,229 | IGF::OT::IGF P00002 (SA-02) CUT AND CAP STEAM TRENCH |
| Mod P00003· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2015-09-21 | +$1,300 | $1,389,529 | IGF::OT::IGF P00003 (SA-03) WATER DISCONNECT |
| Mod P00004· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2015-09-21 | +$774 | $1,390,303 | IGF::OT::IGF P00004 (SA-04), ABATE TRANSITE PANELS IN CHILLER CONTROL ROOM, BUILDING 70A |
| Mod P00007· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2015-10-15 | +$30,000 | $1,420,303 | IGF::OT::IGF P00007 (CO-01), IMMEDIATE CONTAINMENT AND ABATEMENT OF EXPOSED ASBESTOS. |
| Mod P00005· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2015-10-21 | +$17,637 | $1,437,940 | IGF::OT::IGF P00006 (SA-006) ELECTRIC DISCONNECT. |
| Mod P00006· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2015-10-21 | +$3,698 | $1,441,638 | IGF::OT::IGF P00006 (SA-06), ELECTRIC DISCONNECT |
| Mod P00008· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2015-11-19 | +$0 | $1,441,638 | IGF::OT::IGF P00008 (SA-007) TIME EXTENSION FOR SUBMITTAL DELAYS. |
| Mod P00009· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2015-11-19 | +$5,186 | $1,446,824 | IGF::OT::IGF P00009 (SA-08) DEBRIS REMOVAL. |
| Mod P00010· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2016-01-12 | +$0 | $1,446,824 | IGF::OT::IGF P00010 (SA-09), ABATE FLUE BREECHING ASSEMBLY |
| Mod P00011· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2016-02-01 | +$6,093 | $1,452,917 | IGF::OT::IGF P00011 (SA-10) CONTAMINATED FUEL DISPOSAL |
| Mod P00012· CHANGE ORDER | 2016-02-08 | +$50,000 | $1,502,917 | IGF::OT::IGF P00010 (SA-09), REMOVE AND CONTAIN CONTAMINATED SOIL |
| Mod P00013· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2016-03-18 | +$0 | $1,502,917 | IGF::OT::IGF P00010 (SA-09), REMOVE AND CONTAIN CONTAMINATED SOIL |
| Mod P00014· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2016-04-21 | +$378,079 | $1,880,996 | IGF::OT::IGF P00010 (SA-09), REMOVE AND CONTAIN CONTAMINATED SOIL |
| Mod P00015· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2016-07-28 | +$8,000 | $1,888,996 | IGF::OT::IGF P00015 (SA-13), CLAY PIPE REMOVAL |
| Mod P00016· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2017-01-20 | +$7,960 | $1,896,956 | IGF::OT::IGF P00016 (SA-14), SOD AT BIO RETENTION |
Related awards · 5
Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.
Other recipients under Y1PZ from OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F) (most recent first)
| Award | Recipient | Office | Net obligations | FY |
|---|---|---|---|---|
| 36C10F22C0002 | VETERAN DESIGN & CONSTRUCTION INC | OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F) | $28,956,154 | FY2022 |
| 36C10F21C0002 | CARIBE TECNO CRL | OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F) | $35,935,734 | FY2021 |
| 36C10F20C0011 | SGC SERVICES, LLC | OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F) | $1,295,194 | FY2020 |
| 36C10F20C0004 | MGC SERVICES A JOINT VENTURE LLC | OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F) | $0 | FY2020 |
| 36C10F19N0024 | CMP COMMERCIAL CONSTRUCTION INC | OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F) | $1,382,571 | FY2019 |
Cite as: Glassbox VA record view · VA contract (USAspending / FPDS) · CONT_AWD_VA101F15C0014_3600_-NONE-_-NONE- · retrieved 2026-09-26.