Award recordCONTRACT

ROY ANDERSON CORP

PIID VA101F14C0021· VA Staff Offices· OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F)· Y1DZ · CONSTRUCTION OF OTHER HOSPITAL BUILDINGS· FY2014· $44,067,533 net obligations· UEI WMX2JXNH41J8· MS

Description

BOND ADJUSTMENT

Base award description: IGF::OT::IGF - RENOVATION OF BUILDINGS 1&2 AT VAMC BILOXI MS

First action · last action
2014-06-27 · 2026-02-05
Transactions
82
First transaction's obligation
$31,134,000
Base + all options value (sum of deltas)
$44,067,533
Extent competed
FULL AND OPEN COMPETITION
Other than full & open authority
—
Set-aside
NO SET ASIDE USED.
Offers received
11
SDVOSB flag on record
No
NAICS
236220 · COMMERCIAL AND INSTITUTIONAL BUILDING CONSTRUCTION

Modification chain · 82 transactions

Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.

$49,916,335$0Base award · 2014-06-27 · this action $31,134,000 · running total $31,134,000Modification P00001 · 2014-08-07 · this action $3,619 · running total $31,137,619Modification P00002 · 2014-12-03 · this action $250,020 · running total $31,387,639Modification P00003 · 2015-01-05 · this action $10,712 · running total $31,398,351Modification P00004 · 2015-03-18 · this action $6,049 · running total $31,404,400Modification P00005 · 2015-05-05 · this action $197,048 · running total $31,601,448Modification P00006 · 2015-06-12 · this action $8,633 · running total $31,610,081Modification P00007 · 2015-07-08 · this action $43,554 · running total $31,653,635Modification P00008 · 2015-07-14 · this action $11,116 · running total $31,664,751Modification P00011 · 2015-08-06 · this action $95,000 · running total $31,759,751Modification P00010 · 2015-08-10 · this action $18,268 · running total $31,778,019Modification P00012 · 2015-09-23 · this action $90,000 · running total $31,868,019Modification P00013 · 2015-10-20 · this action $883 · running total $31,868,902Modification P00014 · 2015-10-27 · this action $45,619 · running total $31,914,521Modification P00015 · 2015-11-04 · this action $0 · running total $31,914,521Modification P00016 · 2016-04-25 · this action $193,626 · running total $32,108,147Modification P00017 · 2016-07-13 · this action $52,057 · running total $32,160,204Modification P00018 · 2016-08-24 · this action $525,729 · running total $32,685,933Modification P00019 · 2016-08-25 · this action $36,156 · running total $32,722,089Modification P00020 · 2016-10-27 · this action $657,000 · running total $33,379,089Modification P00021 · 2016-12-19 · this action $0 · running total $33,379,089Modification P00022 · 2017-04-10 · this action $70,000 · running total $33,449,089Modification P00023 · 2017-05-08 · this action $2,869,000 · running total $36,318,089Modification P00024 · 2017-05-22 · this action $29,392 · running total $36,347,482Modification P00025 · 2017-05-23 · this action $121,066 · running total $36,468,548Modification P00026 · 2017-05-23 · this action $119,986 · running total $36,588,534Modification P00028 · 2017-06-28 · this action $1,495,325 · running total $38,083,859Modification P00030 · 2017-07-07 · this action $28,434 · running total $38,112,293Modification P00031 · 2017-07-11 · this action $72,564 · running total $38,184,857Modification P00027 · 2017-07-24 · this action $75,082 · running total $38,259,939Modification P00029 · 2017-08-01 · this action $114,404 · running total $38,374,343Modification P00039 · 2017-08-01 · this action $320,010 · running total $38,694,353Modification P00040 · 2017-08-09 · this action $38,027 · running total $38,732,380Modification P00043 · 2017-11-14 · this action $59,050 · running total $38,791,430Modification P00042 · 2017-11-15 · this action $31,776 · running total $38,823,206Modification P00036 · 2017-12-15 · this action $6,900,000 · running total $45,723,206Modification P00046 · 2018-06-20 · this action $0 · running total $45,723,206Modification P00047 · 2018-09-18 · this action $6,041 · running total $45,729,247Modification P00050 · 2018-11-09 · this action $46,000 · running total $45,775,247Modification P00048 · 2018-11-28 · this action $0 · running total $45,775,247Modification P00051 · 2019-02-27 · this action $20,792 · running total $45,796,039Modification P00052 · 2019-03-25 · this action $0 · running total $45,796,039Modification P00054 · 2019-03-26 · this action $0 · running total $45,796,039Modification P00053 · 2019-05-13 · this action -$9,466 · running total $45,786,573Modification P00055 · 2019-09-06 · this action $3,351 · running total $45,789,924Modification P00056 · 2019-10-09 · this action $85,000 · running total $45,874,924Modification P00057 · 2019-10-09 · this action $15,000 · running total $45,889,924Modification P00058 · 2019-10-28 · this action $6,036 · running total $45,895,960Modification P00060 · 2020-01-15 · this action $17,379 · running total $45,913,339Modification P00063 · 2020-02-11 · this action $1,943 · running total $45,915,282Modification P00064 · 2020-02-14 · this action $15,112 · running total $45,930,394Modification P00059 · 2020-02-25 · this action $2,953,421 · running total $48,883,816Modification P00061 · 2020-02-25 · this action $534,732 · running total $49,418,548Modification P00062 · 2020-02-25 · this action $483,315 · running total $49,901,863Modification P00068 · 2020-05-12 · this action $14,472 · running total $49,916,335Modification P00066 · 2020-05-13 · this action -$9,718,481 · running total $40,197,854Modification P00067 · 2020-05-13 · this action $9,737 · running total $40,207,591Modification P00071 · 2020-05-15 · this action $153,661 · running total $40,361,252Modification P00070 · 2020-05-18 · this action $9,694 · running total $40,370,946Modification P00069 · 2020-06-02 · this action $14,516 · running total $40,385,462Modification P00072 · 2020-06-17 · this action $9,291 · running total $40,394,753Modification P00073 · 2020-06-23 · this action $2,561 · running total $40,397,315Modification P00076 · 2020-08-25 · this action -$1,062 · running total $40,396,253Modification P00077 · 2020-09-03 · this action $0 · running total $40,396,253Modification P00078 · 2020-09-23 · this action $393,938 · running total $40,790,191Modification P00065 · 2020-11-03 · this action $7,077 · running total $40,797,268Modification P00079 · 2020-11-03 · this action $22,284 · running total $40,819,552Modification P00080 · 2020-11-04 · this action $540 · running total $40,820,092Modification P00081 · 2020-12-14 · this action $10,494 · running total $40,830,586Modification P00082 · 2020-12-15 · this action $0 · running total $40,830,586Modification P00083 · 2021-03-10 · this action $1,339 · running total $40,831,925Modification P00084 · 2021-03-17 · this action -$1,575 · running total $40,830,350Modification P00085 · 2021-03-24 · this action -$12,501 · running total $40,817,849Modification P00086 · 2021-06-23 · this action $0 · running total $40,817,849Modification P00087 · 2021-11-18 · this action $350,000 · running total $41,167,849Modification P00088 · 2022-09-16 · this action $6,405 · running total $41,174,254Modification P00089 · 2025-04-21 · this action $198,377 · running total $41,372,632Modification P00090 · 2025-04-24 · this action -$198,377 · running total $41,174,254Modification P00091 · 2025-05-21 · this action $198,377 · running total $41,372,632Modification P00092 · 2025-10-10 · this action -$198,377 · running total $41,174,254Modification P00093 · 2025-12-16 · this action $2,850,000 · running total $44,024,254Modification P00094 · 2026-02-05 · this action $43,279 · running total $44,067,533
  • Base2014-06-27+$31,134,000= $31,134,000
  • Mod P000012014-08-07+$3,619= $31,137,619
  • Mod P000022014-12-03+$250,020= $31,387,639
  • Mod P000032015-01-05+$10,712= $31,398,351
  • Mod P000042015-03-18+$6,049= $31,404,400
  • Mod P000052015-05-05+$197,048= $31,601,448
  • Mod P000062015-06-12+$8,633= $31,610,081
  • Mod P000072015-07-08+$43,554= $31,653,635
  • Mod P000082015-07-14+$11,116= $31,664,751
  • Mod P000112015-08-06+$95,000= $31,759,751
  • Mod P000102015-08-10+$18,268= $31,778,019
  • Mod P000122015-09-23+$90,000= $31,868,019
  • Mod P000132015-10-20+$883= $31,868,902
  • Mod P000142015-10-27+$45,619= $31,914,521
  • Mod P000152015-11-04+$0= $31,914,521
  • Mod P000162016-04-25+$193,626= $32,108,147
  • Mod P000172016-07-13+$52,057= $32,160,204
  • Mod P000182016-08-24+$525,729= $32,685,933
  • Mod P000192016-08-25+$36,156= $32,722,089
  • Mod P000202016-10-27+$657,000= $33,379,089
  • Mod P000212016-12-19+$0= $33,379,089
  • Mod P000222017-04-10+$70,000= $33,449,089
  • Mod P000232017-05-08+$2,869,000= $36,318,089
  • Mod P000242017-05-22+$29,392= $36,347,482
  • Mod P000252017-05-23+$121,066= $36,468,548
  • Mod P000262017-05-23+$119,986= $36,588,534
  • Mod P000282017-06-28+$1,495,325= $38,083,859
  • Mod P000302017-07-07+$28,434= $38,112,293
  • Mod P000312017-07-11+$72,564= $38,184,857
  • Mod P000272017-07-24+$75,082= $38,259,939
  • Mod P000292017-08-01+$114,404= $38,374,343
  • Mod P000392017-08-01+$320,010= $38,694,353
  • Mod P000402017-08-09+$38,027= $38,732,380
  • Mod P000432017-11-14+$59,050= $38,791,430
  • Mod P000422017-11-15+$31,776= $38,823,206
  • Mod P000362017-12-15+$6,900,000= $45,723,206
  • Mod P000462018-06-20+$0= $45,723,206
  • Mod P000472018-09-18+$6,041= $45,729,247
  • Mod P000502018-11-09+$46,000= $45,775,247
  • Mod P000482018-11-28+$0= $45,775,247
  • Mod P000512019-02-27+$20,792= $45,796,039
  • Mod P000522019-03-25+$0= $45,796,039
  • Mod P000542019-03-26+$0= $45,796,039
  • Mod P000532019-05-13-$9,466= $45,786,573
  • Mod P000552019-09-06+$3,351= $45,789,924
  • Mod P000562019-10-09+$85,000= $45,874,924
  • Mod P000572019-10-09+$15,000= $45,889,924
  • Mod P000582019-10-28+$6,036= $45,895,960
  • Mod P000602020-01-15+$17,379= $45,913,339
  • Mod P000632020-02-11+$1,943= $45,915,282
  • Mod P000642020-02-14+$15,112= $45,930,394
  • Mod P000592020-02-25+$2,953,421= $48,883,816
  • Mod P000612020-02-25+$534,732= $49,418,548
  • Mod P000622020-02-25+$483,315= $49,901,863
  • Mod P000682020-05-12+$14,472= $49,916,335
  • Mod P000662020-05-13-$9,718,481= $40,197,854
  • Mod P000672020-05-13+$9,737= $40,207,591
  • Mod P000712020-05-15+$153,661= $40,361,252
  • Mod P000702020-05-18+$9,694= $40,370,946
  • Mod P000692020-06-02+$14,516= $40,385,462
  • Mod P000722020-06-17+$9,291= $40,394,753
  • Mod P000732020-06-23+$2,561= $40,397,315
  • Mod P000762020-08-25-$1,062= $40,396,253
  • Mod P000772020-09-03+$0= $40,396,253
  • Mod P000782020-09-23+$393,938= $40,790,191
  • Mod P000652020-11-03+$7,077= $40,797,268
  • Mod P000792020-11-03+$22,284= $40,819,552
  • Mod P000802020-11-04+$540= $40,820,092
  • Mod P000812020-12-14+$10,494= $40,830,586
  • Mod P000822020-12-15+$0= $40,830,586
  • Mod P000832021-03-10+$1,339= $40,831,925
  • Mod P000842021-03-17-$1,575= $40,830,350
  • Mod P000852021-03-24-$12,501= $40,817,849
  • Mod P000862021-06-23+$0= $40,817,849
  • Mod P000872021-11-18+$350,000= $41,167,849
  • Mod P000882022-09-16+$6,405= $41,174,254
  • Mod P000892025-04-21+$198,377= $41,372,632
  • Mod P000902025-04-24-$198,377= $41,174,254
  • Mod P000912025-05-21+$198,377= $41,372,632
  • Mod P000922025-10-10-$198,377= $41,174,254
  • Mod P000932025-12-16+$2,850,000= $44,024,254
  • Mod P000942026-02-05+$43,279= $44,067,533
TransactionAction dateThis action (delta)Running totalDescription on this transaction
Base2014-06-27+$31,134,000$31,134,000IGF::OT::IGF - RENOVATION OF BUILDINGS 1&2 AT VAMC BILOXI MS
Mod P00001· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2014-08-07+$3,619$31,137,619IGF::OT::IGF - TO CONDUCT AN ASBESTOS/HAZARDOUS MATERIAL SURVEY TO THE DETERMINE THE EXTENT AND LOCATIONS OF S…
Mod P00002· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2014-12-03+$250,020$31,387,639IGF::OT::IGF - REMOVE AN ADDITIONAL 93,500 SF OF ASBESTOS CONTAINING MATERIAL SURVEY AT BUILDINGS 1&2, VAMC BI…
Mod P00003· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2015-01-05+$10,712$31,398,351IGF::OT::IGF - TO REROUTE S SIDEWALK THATH CURRENTLY GOES THROUGH THE CONTRACTOR'S LAYDOWN AREA.
Mod P00004· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2015-03-18+$6,049$31,404,400IGF::OT::IGF - TO INSTALL AN ANTEROOM ON THE 5TH FLOOR OF BUILDING 1 AT THE REQUEST OF THE MEDICAL CENTER TO A…
Mod P00005· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2015-05-05+$197,048$31,601,448IGF::OT::IGF - TO REPLACE BLACKOUT PANELS IN 183 WINDOWS IN BUILDING 2 FOR LEED SILVER CERTIFICATION POINTS, V…
Mod P00006· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2015-06-12+$8,633$31,610,081IGF::OT::IGF - TOA BATE THE ASBESTOS MASTIC MATERIAL UNDER THE CERAMIC TILE IN BUILDING 2 THAT WAS NOT INDICAT…
Mod P00007· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2015-07-08+$43,554$31,653,635IGF::OT::IGF - TO PROVIDE ADDITIONAL DESIGN REQUIREMENTS BASED ON VA FIT THE FOOTPRINT, OMB MEMO M-12-12.
Mod P00008· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2015-07-14+$11,116$31,664,751IGF::OT::IGF - TO PROVIDE A PROTECTIVE WALL AROUND THE EXISTING MEDICAL GAS EQUIPMENT LOCATED IN THE ATTIC OF…
Mod P00011· CHANGE ORDER2015-08-06+$95,000$31,759,751IGF::OT::IGF - TO GET THE CONTRACTOR STARTED ON INVESTIGATING THE MOLD AND WATER INTRUSION ISSUES IN BUILDINGS…
Mod P00010· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2015-08-10+$18,268$31,778,019IGF::OT::IGF - TO ABATE THE ACM UNDER THE CERAMIC TILE IN BUILDING 1 THAT WAS NOT INDICATED ON THE DRAWINGS OR…
Mod P00012· CHANGE ORDER2015-09-23+$90,000$31,868,019IGF::OT::IGF - MAJOR DESIGN CHANGES FROM APPROVED CONCEPT.
Mod P00013· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2015-10-20+$883$31,868,902IGF::OT::IGF - TO DEMOLISH THE SAMPLE WALL THAT WAS USED FOR ALL THE PROJECTS AND IS NO LONGER NEEDED.
Mod P00014· CHANGE ORDER2015-10-27+$45,619$31,914,521IGF::OT::IGF - MAJOR DESIGN CHANGES FROM APPROVED CONCEPT.
Mod P00015· CHANGE ORDER2015-11-04+$0$31,914,521IGF::OT::IGF - ADMINISTRATIVE MODIFICATION TO CORRECT THE LINE OF ACCOUNTING FROM MODIFICATION P00014 FOR BLDG…
Mod P00016· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2016-04-25+$193,626$32,108,147IGF::OT::IGF - SUPPLEMENTAL AGREEMENT TO DEFINITIZE P00012 FOR THE RE-DESIGN EFFORT FOR BLDGS 1&2 RENOVATION P…
Mod P00017· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2016-07-13+$52,057$32,160,204IGF::OT::IGF - SUPPLEMENTAL AGREEMENT TO TEST THE EXISTING SOIL CAPACITIES AND PILES IN BUILDING 1.
Mod P00018· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2016-08-24+$525,729$32,685,933IGF::OT::IGF - SUPPLEMENTAL AGREEMENT TO DESIGN FOR THE WATER INTRUSION FIX.
Mod P00019· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2016-08-25+$36,156$32,722,089IGF::OT::IGF - SUPPLEMENTAL AGREEMENT FOR ADDITIONAL CONCRETE TESTING AS REQUIRED BY THE VACO STRUCTURAL ENGIN…
Mod P00020· CHANGE ORDER2016-10-27+$657,000$33,379,089IGF::OT::IGF - VAMC BILOXI BUILDINGS 1&2 RENOVATION, PROJECT 520-371, CHANGE ORDER FOR FIBER REINFORCED POLYME…
Mod P00021· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2016-12-19+$0$33,379,089IGF::OT::IGF - SUPPLEMENTAL AGREEMENT FOR COMPENSABLE AND CONCURRENT TIME DELAYS.
Mod P00022· CHANGE ORDER2017-04-10+$70,000$33,449,089IGF::OT::IGF - CO TO PROVIDE A TEST PILE TO SIMULATE AND TEST THE STRENGTH OF THE EXISTING PILES IN BUILDINGS…
Mod P00023· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2017-05-08+$2,869,000$36,318,089IGF::OT::IGF - DEFINITIZES MODIFICATION P00020 FOR THE FRP REPAIRS AT VAMC BILOXI, MS.
Mod P00024· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2017-05-22+$29,392$36,347,482IGF::OT::IGF - DEFINITIZES MODIFICATION P00022 FOR THE INSTALLATION OF A TEST PILE AT BUILDING 1.
Mod P00025· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2017-05-23+$121,066$36,468,548IGF::OT::IGF - DEFINITIZES MODIFICATION P00020 FOR THE FRP REPAIRS AT VAMC BILOXI, MS.
Mod P00026· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2017-05-23+$119,986$36,588,534IGF::OT::IGF - DEFINITIZES MODIFICATION P00020 FOR THE FRP REPAIRS AT VAMC BILOXI, MS.
Mod P00028· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2017-06-28+$1,495,325$38,083,859IGF::OT::IGF - DEFINITIZES MODIFICATION P00021 FOR THE COMPENSABLE TIME DELAY AT VAMC BILOXI, MS.
Mod P00030· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2017-07-07+$28,434$38,112,293IGF::OT::IGF - TO INSTALL THE TEST PILE AT BUILDING 2 TO THE DEPTH OF THE ORIGINAL PILES; AN ADDITIONAL 17 FEE…
Mod P00031· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2017-07-11+$72,564$38,184,857IGF::OT::IGF - TO DEMOLISH THE INTERIOR WALL OF THE EXISTING CHIMNEY, TO INCREASE THE DIMENSIONS OF THE CHASE…
Mod P00027· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2017-07-24+$75,082$38,259,939IGF::OT::IGF - TO REMOVE THE EXTERIOR WRAP ON 8 COLUMNS IN ORDER TO INSTALL FRP STRUCTURAL DEFICIENCY MITIGATI…
Mod P00029· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2017-08-01+$114,404$38,374,343IGF::OT::IGF - HVAC REPAIRS AT BUILDINGS 1&2 VAMC BILOXI, MS.
Mod P00039· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2017-08-01+$320,010$38,694,353IGF::OT::IGF - REMOVE/REPLACE FIREPROOFING&INVESTIGATE
Mod P00040· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2017-08-09+$38,027$38,732,380IGF::OT::IGF - TO PROVIDE A DEAD LOAD TEST ON THE PILES AT BUILDING 1 BECAUSE THERE IS NOT ENOUGH ROOM TO DO A…
Mod P00043· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2017-11-14+$59,050$38,791,430IGF::OT::IGF - TO ANALYZE THE DATA PRODUCED BY THE PILE TESTING IN AN EFFORT TO REDUCE OF ELIMINATE THE NUMBER…
Mod P00042· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2017-11-15+$31,776$38,823,206IGF::OT::IGF - TO REPAIR 14" CHILLED WATER LINE A T BUILDING 1 THAT WAS DAMAGED DURING THE INSTALLATION OF PIL…
Mod P00036· CHANGE ORDER2017-12-15+$6,900,000$45,723,206IGF::OT::IGF - BLDG 2 WATER INTRUSION REPAIRS AND BUILDING 1 WINDOW MATERIAL COSTS CHANGE ORDER
Mod P00046· FUNDING ONLY ACTION2018-06-20+$0$45,723,206IGF::OT::IGF - MODIFICATION TO CORRECT LINE OF ACCOUNTING
Mod P00047· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2018-09-18+$6,041$45,729,247IGF::OT::IGF - MODIFICATION TO PROVIDE LABOR AND MATERIAL TO INVESTIGATE AND DESIGN REPAIRS FOR DAMAGED CONCRE…
Mod P00050· CHANGE ORDER2018-11-09+$46,000$45,775,247IGF::OT::IGF - TO REPAIR DETERIORATED CONCRETE AT BEAMS AND COLUMNS ON NORTH, EAST, AND SOUTH ELEVATIONS OF BU…
Mod P00048· CHANGE ORDER2018-11-28+$0$45,775,247IGF::OT::IGF - MODIFICATION TO EXTEND CONTRACT COMPLETION DATE.
Mod P00051· CHANGE ORDER2019-02-27+$20,792$45,796,039IGF::OT::IGF - MODIFICATION TO REPLACE THE EXISTING DEFECTIVE LINTELS IN THE PUNCHED WINDOW OPENINGS ON THE 2N…
Mod P00052· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2019-03-25+$0$45,796,039IGF::OT::IGF - MODIFICATION FOR ABNORMAL WEATHER DAYS. EXTENSION TO DECEMBER 24, 2020.
Mod P00054· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2019-03-26+$0$45,796,039IGF::OT::IGF - MODIFICATION FOR ABNORMAL WEATHER DAYS. CONTRACT EXTENSION TO JANUARY 6, 2021.
Mod P00053· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2019-05-13−$9,466$45,786,573IGF::OT::IGF - MODIFICATION TO DEFINITIZE P00050, CONCRETE REPAIRS
Mod P00055· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2019-09-06+$3,351$45,789,924MODIFICATION TO REPLACE THE BIN TYPE ICE MAKER SPECIFIED WITH A FREE STANDING, INDIVIDUAL SERVING TYPE AS REQU…
Mod P00056· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLIES)2019-10-09+$85,000$45,874,924MODIFICATION TO REPAIR CONCRETE BEAMS THAT DEVELOPED CRACKS WHEN THE HVAC EQUIPMENT WAS MOVED INTO AND INSTALL…
Mod P00057· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLIES)2019-10-09+$15,000$45,889,924MODIFICATION TO INSTALL FLOOR TO DECK WALLS IN THE COMM ROOMS AND SECURITY ROOMS
Mod P00058· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLIES)2019-10-28+$6,036$45,895,960MODIFICATION TO INSTALL AND FINISH DRYWALL OVER THE EXISTING PLASTER AT WINDOW WALLS IN THE STAIRWELLS OF BUIL…
Mod P00060· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2020-01-15+$17,379$45,913,339MODIFICATION TO PROVIDE COMPENSATION TO THE CONTRACTOR FOR SHOP DRAWINGS FOR THE WINDOWS IN BUILDING 1. THIS W…
Mod P00063· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2020-02-11+$1,943$45,915,282MODIFICATION TO PROVIDE COMPENSATION FOR THE LABOR TO INSTALL NEW LIGHT FIXTURES THAT WERE FURNISHED BY THE ME…
Mod P00064· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2020-02-14+$15,112$45,930,394TO CHANGE THE SPECIFIED TOILET PARTITIONS FROM PLASTIC TO HDPE FLOOR MOUNTED PARTITIONS BECAUSE THE PLASTIC ON…
Mod P00059· CHANGE ORDER2020-02-25+$2,953,421$48,883,816MODIFICATION TO COMPENSATE FOR THE TIA BASED ON THE AUDIT REPORT.
Mod P00061· CHANGE ORDER2020-02-25+$534,732$49,418,548MODIFICATION TO PROVIDE COMPENSATION BASED ON THE AUDIT REPORT
Mod P00062· CHANGE ORDER2020-02-25+$483,315$49,901,863MODIFICATION TO PROVIDE COMPENSATION TO THE CONTRACTOR BASED ON AUDIT REPORT.
Mod P00068· ADDITIONAL WORK (NEW AGREEMENT, JUSTIFICATION REQUIRED)2020-05-12+$14,472$49,916,335MODIFICATION TO REPAIR LINTELS ABOVE WINDOWS ON THE 2ND FLOOR DURING DEMOLITION OF THE EXISTING WINDOWS.
Mod P00066· TERMINATE FOR CONVENIENCE (COMPLETE OR PARTIAL)2020-05-13−$9,718,481$40,197,854MODIFICATION TO DEOBLIGATE THE BUILDING 1 PARTIALLY TERMINATED PORTION OF THE CONTRACT.
Mod P00067· ADDITIONAL WORK (NEW AGREEMENT, JUSTIFICATION REQUIRED)2020-05-13+$9,737$40,207,591MODIFICATION TO REPAIR THE CONCRETE AT THE SLAB EDGES UNDER THE WINDOWS ON THE 2ND FLOOR FOUND DURING THEE DEM…
Mod P00071· TERMINATE FOR CONVENIENCE (COMPLETE OR PARTIAL)2020-05-15+$153,661$40,361,252MODIFICATION TO PROVIDE COMPENSATION TO THE CONTRACTOR BASED ON POST AUDIT REPORT.
Mod P00070· ADDITIONAL WORK (NEW AGREEMENT, JUSTIFICATION REQUIRED)2020-05-18+$9,694$40,370,946MODIFICATION TO ENLARGE THE REST ROOMS ON THE WEST END TO MITIGATE A SAFETY ISSUE. THE STALLS WERE SO NARROW…
Mod P00069· ADDITIONAL WORK (NEW AGREEMENT, JUSTIFICATION REQUIRED)2020-06-02+$14,516$40,385,462MODIFICATION TO RELOCATE AND/OR ADD OUTLETS FOR MODULAR FURNITURE AND AUDIOVISUAL EQUIPMENT.
Mod P00072· ADDITIONAL WORK (NEW AGREEMENT, JUSTIFICATION REQUIRED)2020-06-17+$9,291$40,394,753MODIFICATION TO SUPPLY AND INSTALL STEEL SUPPORTS FOR THE LINTELS ON THE NEW WINDOWS AT THE GABLE WALL ON THE…
Mod P00073· ADDITIONAL WORK (NEW AGREEMENT, JUSTIFICATION REQUIRED)2020-06-23+$2,561$40,397,315MODIFICATION TO SUPPLY AND INSTALL MOP PLATES AND KICK PLATES TO ALL DOORS EXCEPT THOSE THAT ARE EXEMPT PER TH…
Mod P00076· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2020-08-25−$1,062$40,396,253CREDIT TO DELETE THE ROUGH IN REQUIREMENT FOR ICE MAKERS THAT WILL NOT BE PURCHASED OR INSTALLED ON THIS PROJE…
Mod P00077· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2020-09-03+$0$40,396,253MODIFICATION TO CORRECT MODIFICATION P00059.
Mod P00078· DEFINITIZE CHANGE ORDER2020-09-23+$393,938$40,790,191MODIFICATION TO DEFINITIZE MODIFICATION P00036.
Mod P00065· ADDITIONAL WORK (NEW AGREEMENT, JUSTIFICATION REQUIRED)2020-11-03+$7,077$40,797,268MODIFICATION TO PROVIDE COMPENSATION FOR REPAIRING THE MANUAL HANDLE ON THE ATS AND TESTING TO DETERMINE IF TH…
Mod P00079· ADDITIONAL WORK (NEW AGREEMENT, JUSTIFICATION REQUIRED)2020-11-03+$22,284$40,819,552MODIFICATION REPAIR CRACKED COLUMN AND REPLACE BRICK AROUND THE REPAIRED COLUMN.
Mod P00080· OTHER ADMINISTRATIVE ACTION2020-11-04+$540$40,820,092MODIFICATION TO CORRECT THE AMOUNT OF P00079 ENTERED INCORRECTLY FROM $22,284.00 TO $22,824.00.
Mod P00081· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2020-12-14+$10,494$40,830,586MODIFICATION TO PAY THE CONTRACTOR FOR WORK DONE TO REPAIR THE LS-ATS THAT WAS DAMAGED DURING POWER OUTAGE WHE…
Mod P00082· OTHER ADMINISTRATIVE ACTION2020-12-15+$0$40,830,586ADMINISTRATIVE CHANGE ORDER TO CORRECT THE ACCOUNTING DATA (STRING) ON P00079 AND P00080 TO (36 X 0110 520HS23…
Mod P00083· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2021-03-10+$1,339$40,831,925ADMINISTRATIVE CHANGE ORDER TO COMPENSATE THE CONTRACTOR FOR RETESTING THE ATS BECAUSE THE ORIGINAL TEST WAS T…
Mod P00084· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2021-03-17−$1,575$40,830,350TO PROVIDE A CREDIT TO THE CONTRACT FOR THE MEDICAL CENTER FURNISHING 3 TYPE 6B IN LIEU OF BEING PU7RHCASE AND…
Mod P00085· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2021-03-24−$12,501$40,817,849TO PROVIDE A CREDIT TO THE CONTRACT FOR DELETING THE REQUIREMENT FOR CAE EQUIPMENT, LABOR, AND TRAINING.
Mod P00086· OTHER ADMINISTRATIVE ACTION2021-06-23+$0$40,817,849ADMINISTRATIVE MODIFICATION TO CHANGE THE BOC CODE
Mod P00087· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2021-11-18+$350,000$41,167,849MODIFICATION TO SOLIDIFY CBCA6802 SETTLEMENT
Mod P00088· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2022-09-16+$6,405$41,174,254TO PROVIDE ADDITIONAL ATS TRAINING
Mod P00089· FUNDING ONLY ACTION2025-04-21+$198,377$41,372,632TO PROVIDE ADDITIONAL FUNDING BASED ON POST AUDIT RESULTS
Mod P00090· FUNDING ONLY ACTION2025-04-24−$198,377$41,174,254TO PROVIDE ADDITIONAL FUNDING BASED ON POST AUDIT RESULTS. TO CHANGE THE LINE OF ACCOUNTING ON P00089.
Mod P00091· FUNDING ONLY ACTION2025-05-21+$198,377$41,372,632TO PROVIDE ADDITIONAL FUNDING BASED ON POST AUDIT RESULTS.
Mod P00092· FUNDING ONLY ACTION2025-10-10−$198,377$41,174,254DEOBLIGATE MONEY AS THIS IS A PART OF A CBCA SETTLEMENT AND WILL BE ISSUED ON ANOTHER MODIFICATION.
Mod P00093· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2025-12-16+$2,850,000$44,024,254INCORPORATE CBCA7095-7099 SETTLEMENT AGREEMENT
Mod P00094· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2026-02-05+$43,279$44,067,533BOND ADJUSTMENT

Related awards · 7

Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.

Other VA awards to the same recipient (UEI WMX2JXNH41J8)

AwardOffice · PSC / listingNet obligationsFY
VA101F13C0016OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F) · Y1DA · CONSTRUCTION OF HOSPITALS AND INFIRMARIES$42,845,047FY2013
VA101CFMC0070OFFICE OF CONSTRUCTION & FACILITIES MANAGEMENT · Y111 · CONSTRUCTION OF OFFICE BUILDINGS$38,245,927FY2008

Other recipients under Y1DZ from OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F) (most recent first)

AwardRecipientOfficeNet obligationsFY
36C10F26P0007S. J. AMOROSO CONSTRUCTION CO., LLCOFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F)$10,000FY2026
36C10F26P0006KORTE CONSTRUCTION COMPANYOFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F)$10,000FY2026
36C10F25C0001S. J. AMOROSO CONSTRUCTION CO., LLCOFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F)$69,636,302FY2025
36C10F25C50000ESA SOUTH, INC.OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F)$81,146,200FY2025
36C10F23F0025ANDERSON ENGINEERING OF MINNESOTA, LLCOFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F)$147,012FY2023