Description
INCORPORATE CLAUSE 52.222-90, ADDRESSING DEI DISCRIMINATION BY FEDERAL CONTRACTORS (EXECUTIVE ORDER 14398 / FAR 52.222-90 DEVIATION APR 2026) INTO THE CONTRACT.
Base award description: NEW BOILER PLANT AT THE VA MEDICAL CENTER, WEST LOS ANGELES, CA
Modification chain · 16 transactions
Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.
- Base2025-02-27+$68,877,000= $68,877,000
- Mod P000012025-02-28+$0= $68,877,000
- Mod P000022025-09-18+$24,780= $68,901,780
- Mod P000032025-09-18+$39,222= $68,941,002
- Mod P000042025-09-18+$32,015= $68,973,016
- Mod P000052025-09-18+$36,574= $69,009,590
- Mod P000062025-09-18+$3,074= $69,012,664
- Mod P000072025-09-18+$1,490= $69,014,154
- Mod P000082025-09-18+$37,463= $69,051,617
- Mod P000092026-01-07+$124,969= $69,176,586
- Mod P000102026-01-07+$23,803= $69,200,389
- Mod P000112026-04-17+$317,487= $69,517,876
- Mod P000122026-04-17+$2,409= $69,520,285
- Mod P000132026-04-17+$48,035= $69,568,320
- Mod P000142026-04-17+$67,982= $69,636,302
- Mod P000152026-06-04+$0= $69,636,302
| Transaction | Action date | This action (delta) | Running total | Description on this transaction |
|---|---|---|---|---|
| Base | 2025-02-27 | +$68,877,000 | $68,877,000 | NEW BOILER PLANT AT THE VA MEDICAL CENTER, WEST LOS ANGELES, CA |
| Mod P00001· OTHER ADMINISTRATIVE ACTION | 2025-02-28 | +$0 | $68,877,000 | THE PURPOSE OF THIS MODIFICATION IS TO CHANGE THE CONTRACT NUMBER FROM 36C10F24C0008 TO 36C10F25C0001. |
| Mod P00002· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2025-09-18 | +$24,780 | $68,901,780 | PERFORM ARCHAEOLOGICAL BURIED SITE TESTING (BST) AND PROVIDE A REPORT TO VA PRIOR TO MASS EXCAVATION AT THE BO… |
| Mod P00003· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2025-09-18 | +$39,222 | $68,941,002 | ABATEMENT, REMOVAL AND DISPOSAL OF APPROXIMATELY 150 LF OF ASBESTOS CONTAINING TRANSITE PIPE. |
| Mod P00004· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2025-09-18 | +$32,015 | $68,973,016 | INSTALL ADDITIONAL PROTECTION FOR SHORING BEAMS TO BE INSTALLED PER RFI #23 |
| Mod P00005· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2025-09-18 | +$36,574 | $69,009,590 | ABATEMENT AND REMOVAL OF ADDITIONAL TRANSITE PIPE REMOVAL OF PV DUCT BANK AND REMOVAL OF ASPHALT AND CONCRETE,… |
| Mod P00006· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2025-09-18 | +$3,074 | $69,012,664 | TO INSTALL A 4" 150# CHECK VALVE FOR LOW PRESSURE STEAM ON THE FLASH STEAM ECONOMIZER, PER PCO 0011 |
| Mod P00007· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2025-09-18 | +$1,490 | $69,014,154 | TO INSTALL AN ADDITIONAL HSS 4X2X1/4 POST, PER PCO 0014. |
| Mod P00008· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2025-09-18 | +$37,463 | $69,051,617 | TO PROVIDE A VAULT THAT SOUTHERN CALIFORNIA EDISON REQUIRES UNDER THE PME GEAR PER SCE DRAWING. |
| Mod P00009· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2026-01-07 | +$124,969 | $69,176,586 | TO PROVIDE A VAULT THAT SOUTHERN CALIFORNIA EDISON REQUIRES UNDER THE PME GEAR PER SCE DRAWING. |
| Mod P00010· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2026-01-07 | +$23,803 | $69,200,389 | TO REMOVE A SECTION OF A WATER LINE THAT IS WITHIN THE AREA OF MASS EXCAVATION FOR THE BUILDING PAD. |
| Mod P00011· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2026-04-17 | +$317,487 | $69,517,876 | CONTRACTOR SUBMITTED THREE TIA CAUSING 30 ADDITIONAL DAYS OF COMPENSATORY WORK. |
| Mod P00012· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2026-04-17 | +$2,409 | $69,520,285 | PROVIDE ALL MATERIAL, LABOR, EQUIPMENT, AND SUPERVISION REQUIRED FOR THE REROUTING OF THE CONDENSATE FOR FAN C… |
| Mod P00013· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2026-04-17 | +$48,035 | $69,568,320 | PROVIDE ALL MATERIAL, LABOR, EQUIPMENT, AND SUPERVISION REQUIRED TO ADDS AN ADDITIONAL MINI-PUMP TRAP AND ASSO… |
| Mod P00014· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2026-04-17 | +$67,982 | $69,636,302 | PROVIDE ALL MATERIAL, LABOR, EQUIPMENT, AND SUPERVISION REQUIRED TO INCORPORATE THE UPSIZE OF MINI POWER ZONE,… |
| Mod P00015· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2026-06-04 | +$0 | $69,636,302 | INCORPORATE CLAUSE 52.222-90, ADDRESSING DEI DISCRIMINATION BY FEDERAL CONTRACTORS (EXECUTIVE ORDER 14398 / FA… |
Related awards · 11
Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.
Other VA awards to the same recipient (UEI KU19CNLCK2K7)
| Award | Office · PSC / listing | Net obligations | FY |
|---|---|---|---|
| 36C10F26P0007 | OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F) · Y1DZ · CONSTRUCTION OF OTHER HOSPITAL BUILDINGS | $10,000 | FY2026 |
| 36C26122C0022 | 261-NETWORK CONTRACT OFFICE 21 (36C261) · Z1DA · MAINTENANCE OF HOSPITALS AND INFIRMARIES | $8,861,096 | FY2022 |
| VA101F16C2782 | OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F) · Y1DA · CONSTRUCTION OF HOSPITALS AND INFIRMARIES | $26,067,145 | FY2016 |
| VA101F16C2610 | OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F) · Y1DZ · CONSTRUCTION OF OTHER HOSPITAL BUILDINGS | $110,710,165 | FY2016 |
| VA101F14C0003 | OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F) · Y1DZ · CONSTRUCTION OF OTHER HOSPITAL BUILDINGS | $127,518,496 | FY2014 |
| VA101CFMC0005 | OFFICE OF CONSTRUCTION & FACILITIES MANAGEMENT · Y141 · CONSTRUCT/HOSPITALS & INFIRMARIES | $102,428,575 | FY2008 |
Other recipients under Y1DZ from OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F) (most recent first)
| Award | Recipient | Office | Net obligations | FY |
|---|---|---|---|---|
| 36C10F26P0006 | KORTE CONSTRUCTION COMPANY | OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F) | $10,000 | FY2026 |
| 36C10F25C50000 | ESA SOUTH, INC. | OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F) | $81,146,200 | FY2025 |
| 36C10F23F0025 | ANDERSON ENGINEERING OF MINNESOTA, LLC | OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F) | $147,012 | FY2023 |
| 36C10F23C0002 | VENERGY GROUP LLC | OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F) | $3,522,554 | FY2023 |
| 36C10F22C0017 | SHORE HERMAN JV | OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F) | $16,822,812 | FY2022 |
Cite as: Glassbox VA record view · VA contract (USAspending / FPDS) · CONT_AWD_36C10F25C0001_3600_-NONE-_-NONE- · retrieved 2026-09-26.