Award recordCONTRACT

MGC SERVICES A JOINT VENTURE LLC

PIID 36C10F18C3390· VA Staff Offices· OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F)· Y1PZ · CONSTRUCTION OF OTHER NON-BUILDING FACILITIES· FY2018· $50,765,099 net obligations· UEI FKDAZLJM9YM3· FL

Description

SUPPLEMENT AGREEMENT FOR INSTALLING ADDITIONAL FLOWERING WATER STATIONS

Base award description: DESIGN-BUILD CONSTRUCTION

First action · last action
2018-09-25 · 2025-10-29
Transactions
64
First transaction's obligation
$40,854,000
Base + all options value (sum of deltas)
$50,765,318
Extent competed
FULL AND OPEN COMPETITION AFTER EXCLUSION OF SOURCES
Other than full & open authority
—
Set-aside
SERVICE DISABLED VETERAN OWNED SMALL BUSINESS SET-ASIDE
Offers received
1
SDVOSB flag on record
Yes (self-representation)
NAICS
237990 · OTHER HEAVY AND CIVIL ENGINEERING CONSTRUCTION

Modification chain · 64 transactions

Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.

$50,765,099$0Base award · 2018-09-25 · this action $40,854,000 · running total $40,854,000Modification P00003 · 2019-11-25 · this action $90,000 · running total $40,944,000Modification P00002 · 2019-12-03 · this action $5,500 · running total $40,949,500Modification P00004 · 2020-01-31 · this action $2,095 · running total $40,951,595Modification P00005 · 2020-02-12 · this action -$48,094 · running total $40,903,501Modification P00006 · 2020-04-30 · this action $172,428 · running total $41,075,929Modification P00007 · 2020-06-08 · this action $6,325 · running total $41,082,254Modification P00010 · 2020-07-24 · this action $4,127 · running total $41,086,381Modification P00008 · 2020-09-11 · this action $112,000 · running total $41,198,381Modification P00009 · 2020-09-28 · this action $172,198 · running total $41,370,578Modification A00011 · 2020-10-06 · this action $73,788 · running total $41,444,367Modification A00012 · 2020-12-16 · this action $96,929 · running total $41,541,296Modification A00013 · 2020-12-16 · this action $64,511 · running total $41,605,807Modification A00015 · 2021-02-23 · this action $88,884 · running total $41,694,691Modification A00014 · 2021-03-03 · this action $82,841 · running total $41,777,532Modification A00016 · 2021-03-09 · this action $106,611 · running total $41,884,143Modification P00011 · 2021-06-10 · this action $314,199 · running total $42,198,342Modification P00017 · 2021-08-12 · this action $320,957 · running total $42,519,299Modification A00018 · 2021-10-21 · this action $11,786 · running total $42,531,085Modification A00020 · 2021-10-21 · this action $37,065 · running total $42,568,149Modification A00021 · 2021-10-21 · this action $13,324 · running total $42,581,473Modification A00022 · 2021-10-21 · this action $3,646 · running total $42,585,119Modification A00023 · 2021-10-21 · this action $21,779 · running total $42,606,898Modification A00024 · 2021-10-21 · this action $31,418 · running total $42,638,316Modification A00025 · 2021-11-19 · this action $134,865 · running total $42,773,181Modification A00027 · 2021-11-22 · this action $22,849 · running total $42,796,030Modification A00028 · 2021-11-22 · this action $8,851 · running total $42,804,881Modification A00029 · 2021-11-22 · this action $13,627 · running total $42,818,508Modification A00030 · 2022-01-25 · this action $4,423 · running total $42,822,932Modification A00031 · 2022-01-25 · this action $15,931 · running total $42,838,863Modification A00026 · 2022-02-22 · this action $248,663 · running total $43,087,526Modification A00032 · 2022-02-22 · this action $123,220 · running total $43,210,746Modification A00033 · 2022-02-24 · this action $4,754 · running total $43,215,500Modification P00019 · 2022-02-28 · this action $2,055,330 · running total $45,270,829Modification A00034 · 2022-03-10 · this action $41,120 · running total $45,311,950Modification A00035 · 2022-03-15 · this action $14,199 · running total $45,326,149Modification A00037 · 2022-03-23 · this action $116,447 · running total $45,442,596Modification A00036 · 2022-03-30 · this action $102,888 · running total $45,545,484Modification A00038 · 2022-04-22 · this action $45,402 · running total $45,590,885Modification A00039 · 2022-06-10 · this action -$32,700 · running total $45,558,185Modification A00040 · 2022-06-10 · this action $4,758 · running total $45,562,943Modification A00041 · 2022-06-15 · this action $135,363 · running total $45,698,305Modification A00043 · 2022-07-08 · this action $103,420 · running total $45,801,725Modification A00042 · 2022-07-15 · this action $21,083 · running total $45,822,808Modification P00046 · 2022-12-02 · this action $971,182 · running total $46,793,989Modification A00049 · 2022-12-05 · this action $149,621 · running total $46,943,610Modification A00044 · 2023-02-21 · this action $2,456 · running total $46,946,066Modification A00045 · 2023-02-21 · this action $54,625 · running total $47,000,692Modification A00047 · 2023-02-21 · this action $32,797 · running total $47,033,489Modification A00048 · 2023-02-21 · this action $146,899 · running total $47,180,387Modification A00050 · 2023-02-22 · this action $249,695 · running total $47,430,082Modification A00051 · 2023-03-03 · this action $233,243 · running total $47,663,325Modification A00052 · 2023-03-28 · this action $100,000 · running total $47,763,325Modification A00053 · 2023-03-28 · this action $64,398 · running total $47,827,723Modification A00054 · 2023-03-30 · this action $40,593 · running total $47,868,316Modification A00055 · 2023-05-09 · this action $8,342 · running total $47,876,658Modification P00056 · 2023-05-22 · this action $280,609 · running total $48,157,267Modification A00058 · 2023-08-29 · this action -$149,621 · running total $48,007,646Modification A00059 · 2023-09-06 · this action $239,482 · running total $48,247,128Modification P00062 · 2024-09-03 · this action $112,329 · running total $48,359,457Modification P00063 · 2024-09-30 · this action $649,782 · running total $49,009,239Modification P00065 · 2025-04-16 · this action $850,509 · running total $49,859,748Modification P00066 · 2025-07-28 · this action $33,061 · running total $49,892,809Modification P00067 · 2025-10-29 · this action $872,290 · running total $50,765,099
  • Base2018-09-25+$40,854,000= $40,854,000
  • Mod P000032019-11-25+$90,000= $40,944,000
  • Mod P000022019-12-03+$5,500= $40,949,500
  • Mod P000042020-01-31+$2,095= $40,951,595
  • Mod P000052020-02-12-$48,094= $40,903,501
  • Mod P000062020-04-30+$172,428= $41,075,929
  • Mod P000072020-06-08+$6,325= $41,082,254
  • Mod P000102020-07-24+$4,127= $41,086,381
  • Mod P000082020-09-11+$112,000= $41,198,381
  • Mod P000092020-09-28+$172,198= $41,370,578
  • Mod A000112020-10-06+$73,788= $41,444,367
  • Mod A000122020-12-16+$96,929= $41,541,296
  • Mod A000132020-12-16+$64,511= $41,605,807
  • Mod A000152021-02-23+$88,884= $41,694,691
  • Mod A000142021-03-03+$82,841= $41,777,532
  • Mod A000162021-03-09+$106,611= $41,884,143
  • Mod P000112021-06-10+$314,199= $42,198,342
  • Mod P000172021-08-12+$320,957= $42,519,299
  • Mod A000182021-10-21+$11,786= $42,531,085
  • Mod A000202021-10-21+$37,065= $42,568,149
  • Mod A000212021-10-21+$13,324= $42,581,473
  • Mod A000222021-10-21+$3,646= $42,585,119
  • Mod A000232021-10-21+$21,779= $42,606,898
  • Mod A000242021-10-21+$31,418= $42,638,316
  • Mod A000252021-11-19+$134,865= $42,773,181
  • Mod A000272021-11-22+$22,849= $42,796,030
  • Mod A000282021-11-22+$8,851= $42,804,881
  • Mod A000292021-11-22+$13,627= $42,818,508
  • Mod A000302022-01-25+$4,423= $42,822,932
  • Mod A000312022-01-25+$15,931= $42,838,863
  • Mod A000262022-02-22+$248,663= $43,087,526
  • Mod A000322022-02-22+$123,220= $43,210,746
  • Mod A000332022-02-24+$4,754= $43,215,500
  • Mod P000192022-02-28+$2,055,330= $45,270,829
  • Mod A000342022-03-10+$41,120= $45,311,950
  • Mod A000352022-03-15+$14,199= $45,326,149
  • Mod A000372022-03-23+$116,447= $45,442,596
  • Mod A000362022-03-30+$102,888= $45,545,484
  • Mod A000382022-04-22+$45,402= $45,590,885
  • Mod A000392022-06-10-$32,700= $45,558,185
  • Mod A000402022-06-10+$4,758= $45,562,943
  • Mod A000412022-06-15+$135,363= $45,698,305
  • Mod A000432022-07-08+$103,420= $45,801,725
  • Mod A000422022-07-15+$21,083= $45,822,808
  • Mod P000462022-12-02+$971,182= $46,793,989
  • Mod A000492022-12-05+$149,621= $46,943,610
  • Mod A000442023-02-21+$2,456= $46,946,066
  • Mod A000452023-02-21+$54,625= $47,000,692
  • Mod A000472023-02-21+$32,797= $47,033,489
  • Mod A000482023-02-21+$146,899= $47,180,387
  • Mod A000502023-02-22+$249,695= $47,430,082
  • Mod A000512023-03-03+$233,243= $47,663,325
  • Mod A000522023-03-28+$100,000= $47,763,325
  • Mod A000532023-03-28+$64,398= $47,827,723
  • Mod A000542023-03-30+$40,593= $47,868,316
  • Mod A000552023-05-09+$8,342= $47,876,658
  • Mod P000562023-05-22+$280,609= $48,157,267
  • Mod A000582023-08-29-$149,621= $48,007,646
  • Mod A000592023-09-06+$239,482= $48,247,128
  • Mod P000622024-09-03+$112,329= $48,359,457
  • Mod P000632024-09-30+$649,782= $49,009,239
  • Mod P000652025-04-16+$850,509= $49,859,748
  • Mod P000662025-07-28+$33,061= $49,892,809
  • Mod P000672025-10-29+$872,290= $50,765,099
TransactionAction dateThis action (delta)Running totalDescription on this transaction
Base2018-09-25+$40,854,000$40,854,000DESIGN-BUILD CONSTRUCTION
Mod P00003· CHANGE ORDER2019-11-25+$90,000$40,944,000SA-P00003, PROVIDE REPAIRS TO GOVERNMENT PROVIDED WATER PUMP HOUSES
Mod P00002· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2019-12-03+$5,500$40,949,500SA-P00002, PROVIDE ADMIN SUPPLIES
Mod P00004· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2020-01-31+$2,095$40,951,595SA-P00004, PROVIDE ADDITIONAL GROUNDING FOR SECTION 49 IRRIGATION SYSTEM
Mod P00005· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2020-02-12−$48,094$40,903,501SA-P00005, PROVIDE REPAIRS TO GOVERNMENT PROVIDED WATER PUMP HOUSES, DEFINITIZE CO-P00005
Mod P00006· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2020-04-30+$172,428$41,075,929CHANGES AND EXPANSION ALTERATION FOR THE DESIGN OF THE ADMINISTRATION BUILDING /PIC
Mod P00007· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2020-06-08+$6,325$41,082,254CHANGES AND EXPANSION ALTERATION FOR THE DESIGN OF THE ADMINISTRATION BUILDING /PIC P00007 ALTER BOLTS IN TRIP…
Mod P00010· ADDITIONAL WORK (NEW AGREEMENT, JUSTIFICATION REQUIRED)2020-07-24+$4,127$41,086,381PROVIDE IRRIGATION GROUNDING TEST AT CRYPT FIELD # 49
Mod P00008· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2020-09-11+$112,000$41,198,381P00008 PROVIDE ALL SUPERVISION, LABOR, MATERIALS, AND EQUIPMENT TO PROVIDE A INVESTIGATION ON NEEDED REPAIRS T…
Mod P00009· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2020-09-28+$172,198$41,370,578PROVIDE REPLACE TO CEILING SYSTEMS AT FIVE (5) COMMITTAL SHELTERS B, C, D, E, F.
Mod A00011· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2020-10-06+$73,788$41,444,367A00011 PROVIDE INSTALLATION OF UNDERDRAINS AT EXPANSION FIELD 56
Mod A00012· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2020-12-16+$96,929$41,541,296ADDITIONAL SOUND WALL WING DESIGN & CONSTRUCTION
Mod A00013· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2020-12-16+$64,511$41,605,807SA-A00013, BURIAL / GRAVESITE GRID MONUMENTS INSTALLATION
Mod A00015· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2021-02-23+$88,884$41,694,691INSTALLATION OF ADDITIONAL GROUNDING AT CRYPT FIELDS 49, 50, 56, 57, 62, AND 63
Mod A00014· DEFINITIZE CHANGE ORDER2021-03-03+$82,841$41,777,532PROVIDE REPAIRS TO GOVERNMENT PROVIDED WATER PUMP HOUSES DEFINITIZE CO-P00008
Mod A00016· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2021-03-09+$106,611$41,884,143ADDITIONAL WORK FOR CLA-VAL INSTALLATIONS
Mod P00011· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2021-06-10+$314,199$42,198,342CEMETERY ROADS
Mod P00017· CHANGE ORDER2021-08-12+$320,957$42,519,299INSTALATION OF TRAILERS
Mod A00018· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2021-10-21+$11,786$42,531,085SA-A00018 PCO 28 SOUND WALL RELOCATION
Mod A00020· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2021-10-21+$37,065$42,568,149SA-A00020 PCO 26 WIRING REPAIR AT 51A
Mod A00021· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2021-10-21+$13,324$42,581,473SA-A00021 PCO 33 RFP 008 COMMITTAL SHELTER WORK
Mod A00022· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2021-10-21+$3,646$42,585,119SA-A00022 PCO 37 BACKHOE SHED ELECTRICAL
Mod A00023· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2021-10-21+$21,779$42,606,898SA-A00023 PCO 31 BACKHOE SHED REPAIR
Mod A00024· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2021-10-21+$31,418$42,638,316SA-A00024 PCO 32 RFP 010 DRY WELL AT MAINTENANCE AREA
Mod A00025· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2021-11-19+$134,865$42,773,181SA-A00025 PCO 29 RFP 012 PAVE 25A MAINTENANCE YARD
Mod A00027· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2021-11-22+$22,849$42,796,030SA-A00027 PCO 34 SAFETY CORRECTIONS AROUND PROPANE PAD
Mod A00028· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2021-11-22+$8,851$42,804,881SA-A00028 PCO 40 ADDITIONAL FLAT WORK AT COMMITTAL SHELTER G
Mod A00029· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2021-11-22+$13,627$42,818,508SA-A00029 PCO 38 ADMIN BUILDING ASPHALT PATCH
Mod A00030· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2022-01-25+$4,423$42,822,932SA-A00030 PCO 41 SAFETY RAIL IN COMPUTER ROOM
Mod A00031· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2022-01-25+$15,931$42,838,863SA-A00031 PCO 42 SECTION 50 AND PH8 IRRIGATION
Mod A00026· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2022-02-22+$248,663$43,087,526SA-A00026 PCO 36 RESEAL CONCRETE SIDEWALKS
Mod A00032· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2022-02-22+$123,220$43,210,746SA-A00032 PCO 25 REMOVE STORAGE BUILDING / ADD 2 QUONSET HUTS
Mod A00033· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2022-02-24+$4,754$43,215,500SA-A00033 PCO 46 ELECTRICAL UPGRADES IN PIC ADMIN TRAILERS
Mod P00019· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2022-02-28+$2,055,330$45,270,829ADMINISTRATION BUILDING WORK
Mod A00034· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2022-03-10+$41,120$45,311,950SA-A00034 PCO 44 SOLAR PANEL ELECTRICAL BORE REPAIR
Mod A00035· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2022-03-15+$14,199$45,326,149SA-A00035 PCO 47 STORAGE STRUCTURE LOCKERS
Mod A00037· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2022-03-23+$116,447$45,442,596SA-A00037 PCO 035 REPLACE CAPPING AND INLET PROTECTION AT MAINTENANCE COMPLEX
Mod A00036· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2022-03-30+$102,888$45,545,484SA-A00036 PCO 43 25A FENCE AND ELECTRICAL WORK
Mod A00038· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2022-04-22+$45,402$45,590,885SA-A00038 PCO 48 PIC ADMIN FURNITURE
Mod A00039· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2022-06-10−$32,700$45,558,185SA-A00039 PCO 45 DELETE LIGHTNING PROTECTION AT COMMITTAL SHELTER
Mod A00040· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2022-06-10+$4,758$45,562,943SA-A00040 PCO 53 CALVERTON DRIVE HYDROSEEDING AND PCO 54 ASSEMBLY AREA SOD
Mod A00041· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2022-06-15+$135,363$45,698,305SA-A00041 PCO 52 LANDSCAPE CHANGES AT SECTIONS 54 56 57
Mod A00043· CHANGE ORDER2022-07-08+$103,420$45,801,725SA-A00042 INSTALL FENCING
Mod A00042· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2022-07-15+$21,083$45,822,808SA-A00042 PCO 56 COMPUTER ROOM FLOORING RESURFACING
Mod P00046· DEFINITIZE CHANGE ORDER2022-12-02+$971,182$46,793,989PIC BUILDING DEFINITIZATION
Mod A00049· CHANGE ORDER2022-12-05+$149,621$46,943,610CO-A00049 PCO XXX PIC ADMIN ROOF REPLACEMENT
Mod A00044· CHANGE ORDER2023-02-21+$2,456$46,946,066SA-A00042 PCO 56 COMPUTER ROOM FLOORING RESURFACING
Mod A00045· CHANGE ORDER2023-02-21+$54,625$47,000,692SA-A00042 PCO 56 COMPUTER ROOM FLOORING RESURFACING
Mod A00047· CHANGE ORDER2023-02-21+$32,797$47,033,489PIC BUILDING
Mod A00048· CHANGE ORDER2023-02-21+$146,899$47,180,387PIC BUILDING
Mod A00050· CHANGE ORDER2023-02-22+$249,695$47,430,082CO-A00050 PCO 059 PAINTING AND DOOR REPAIR
Mod A00051· CHANGE ORDER2023-03-03+$233,243$47,663,325CO-A00050 PCO 060 FIRE ALARM UPGRADES
Mod A00052· CHANGE ORDER2023-03-28+$100,000$47,763,325CO-A00052 PCO 068 SECTION 57 UNDERDRAINS
Mod A00053· CHANGE ORDER2023-03-28+$64,398$47,827,723CO-A00053 PCO 063 064 067 PIC ADMIN MISC WORK
Mod A00054· CHANGE ORDER2023-03-30+$40,593$47,868,316CO-A00053 PCO 065.1 PIC ADMIN ROOF REPAIR
Mod A00055· CHANGE ORDER2023-05-09+$8,342$47,876,658CO-A00055 PCO 069 MAINTENANCE BUILDING HEAT ISSUE ADDITIONAL WORK
Mod P00056· CHANGE ORDER2023-05-22+$280,609$48,157,267COMPLETE DRAINAGE IN SECTION 57
Mod A00058· CHANGE ORDER2023-08-29−$149,621$48,007,646CO-A00058 PCO 065.2 DESCOPE CO-A00049
Mod A00059· CHANGE ORDER2023-09-06+$239,482$48,247,128CO-A00059 PCO 070 PIC ADMIN FINAL MOD
Mod P00062· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2024-09-03+$112,329$48,359,457MODIFICATION FOR ALTERNATE SITE AREA ON CEMETERY
Mod P00063· CHANGE ORDER2024-09-30+$649,782$49,009,239CHANGE ORDER MODIFICATION FOR ALTERNATE SITE AREA ON CEMETERY
Mod P00065· DEFINITIZE CHANGE ORDER2025-04-16+$850,509$49,859,748DEFINITIZE CHANGE ORDER MODIFICATION FOR ALTERNATE SITE AREA ON CEMETERY
Mod P00066· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2025-07-28+$33,061$49,892,809SUPPLEMENT AGREEMENT FOR INSTALLING ADDITIONAL FLOWERING WATER STATIONS
Mod P00067· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2025-10-29+$872,290$50,765,099SUPPLEMENT AGREEMENT FOR INSTALLING ADDITIONAL FLOWERING WATER STATIONS

Related awards · 7

Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.

Other VA awards to the same recipient (UEI FKDAZLJM9YM3)

AwardOffice · PSC / listingNet obligationsFY
36C10F20C0004OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F) · Y1PZ · CONSTRUCTION OF OTHER NON-BUILDING FACILITIES$0FY2020
36C10F18C3375OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F) · Y1AZ · CONSTRUCTION OF OTHER ADMINISTRATIVE FACILITIES AND SERVICE BUILDINGS$46,114,254FY2018

Other recipients under Y1PZ from OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F) (most recent first)

AwardRecipientOfficeNet obligationsFY
36C10F22C0002VETERAN DESIGN & CONSTRUCTION INCOFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F)$28,956,154FY2022
36C10F21C0002CARIBE TECNO CRLOFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F)$35,935,734FY2021
36C10F20C0011SGC SERVICES, LLCOFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F)$1,295,194FY2020
36C10F19N0024CMP COMMERCIAL CONSTRUCTION INCOFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F)$1,382,571FY2019
36C10F18C3394SUN EAGLE, CORPORATIONOFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F)$33,947,688FY2018