Description
THIS CONTRACT IS TO BUILD A POWER PLANT ON THE VETERANS AFFAIRS MEDICAL CENTER DALLAS CAMPUS.
Base award description: DESIGN AND BUILD A COGENERATION SYSTEM AT VAMC DALLAS, TX.
Modification chain · 44 transactions
Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.
- Base2011-09-14+$22,865,715= $22,865,715
- Mod P000012012-02-14+$95,747= $22,961,462
- Mod P000042012-05-16+$35,356= $22,996,818
- Mod P000082012-06-20-$12,348= $22,984,470
- Mod P000052012-07-10-$10,936= $22,973,534
- Mod P000122012-07-12+$14,646= $22,988,180
- Mod P000092012-07-17-$88,203= $22,899,977
- Mod P000142012-09-07+$1,375= $22,901,352
- Mod P000062012-09-27+$6,300= $22,907,652
- Mod P000072012-10-05+$53,008= $22,960,660
- Mod P000102012-11-08+$0= $22,960,660
- Mod P000152012-11-16+$0= $22,960,660
- Mod P000162013-01-17+$99,858= $23,060,518
- Mod P000132013-02-11-$4,163= $23,056,355
- Mod P000112013-02-13-$196= $23,056,159
- Mod P000172013-02-21+$34,180= $23,090,339
- Mod P000182013-03-12+$18,145= $23,108,484
- Mod P000192013-03-14+$9,135= $23,117,619
- Mod P000032013-05-01+$8,271= $23,125,890
- Mod P000202013-05-03+$8,440= $23,134,330
- Mod P000212013-05-08+$18,103= $23,152,433
- Mod P000232013-06-18+$11,029= $23,163,462
- Mod P000242013-06-21+$9,829= $23,173,291
- Mod P000252013-06-25+$310,666= $23,483,957
- Mod P000222013-07-10+$0= $23,483,957
- Mod P000262013-07-12+$88,328= $23,572,285
- Mod P000022013-07-26+$0= $23,572,285
- Mod P000272013-09-18+$0= $23,572,285
- Mod P000292014-01-06+$79,086= $23,651,371
- Mod P000302014-01-06+$24,885= $23,676,256
- Mod P000282014-05-02+$77,302= $23,753,558
- Mod P000312014-06-03+$40,000= $23,793,558
- Mod P000322014-06-11-$10,919= $23,782,639
- Mod P000332014-06-18+$15,706= $23,798,345
- Mod P000352014-08-14-$1,902= $23,796,443
- Mod P000342014-08-18+$37,625= $23,834,068
- Mod P000362014-09-10+$50,000= $23,884,068
- Mod P000372014-09-11+$0= $23,884,068
- Mod P000382014-11-03-$45,924= $23,838,144
- Mod P000392015-05-13-$9,811= $23,828,333
- Mod P000402015-06-02+$300,000= $24,128,333
- Mod P000412017-07-13-$15,424= $24,112,909
- Mod P000422017-07-13+$367,333= $24,480,242
- Mod P000432017-07-13+$880,000= $25,360,242
| Transaction | Action date | This action (delta) | Running total | Description on this transaction |
|---|---|---|---|---|
| Base | 2011-09-14 | +$22,865,715 | $22,865,715 | DESIGN AND BUILD A COGENERATION SYSTEM AT VAMC DALLAS, TX. |
| Mod P00001· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-02-14 | +$95,747 | $22,961,462 | MODIFICATION TO HAVE THE CONTRACTOR BRING THE DESIGN DOCUMENTS UP TO A 65% LEVEL. |
| Mod P00004· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-05-16 | +$35,356 | $22,996,818 | OTHER FUNCTIONS - MODIFICATION TO HAVE THE CONTRACTOR PROVIDE CONCRETE TESTING SERVICES ON THE POWER PLANT. |
| Mod P00008· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-06-20 | −$12,348 | $22,984,470 | MODIFICATION TO DELETE FOUR INCH GAS LINE FROM THE CONTRACT. |
| Mod P00005· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-07-10 | −$10,936 | $22,973,534 | MODIFICATION TO RECIEVE CREDIT FOR A CONSTRUCTION TRAILER THAT WILL NO LONGER BE USED. |
| Mod P00012· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-07-12 | +$14,646 | $22,988,180 | MODIFICATION TO UTILIZE STAINLESS STEEL INSTEAD OF CARBON STEEL ON A GENERATOR. |
| Mod P00009· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-07-17 | −$88,203 | $22,899,977 | OTHER FUNCTIONS - MODIFICATION TO HAVE THE CONTRACTOR NOT COMPLY WITH THE BLAST RESISTANCE SPECIFICATION. |
| Mod P00014· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-09-07 | +$1,375 | $22,901,352 | OTHER FUNCTIONS - MODIFICATION TO HAVE THE CONTRACTOR CHANGE THE SANITARY SEWER LINE. |
| Mod P00006· CHANGE ORDER | 2012-09-27 | +$6,300 | $22,907,652 | OTHER FUNCTIONS - MODIFICATION TO PROVIDE THE CONTRACTOR A CHANGE ORDER FOR THE DUCT WORK BURNER AND THE GAS L… |
| Mod P00007· CHANGE ORDER | 2012-10-05 | +$53,008 | $22,960,660 | THIS ACTION IS TO PROVIDE THE CONTRACTOR A CHANGE ORDER FOR THE WORK IN FOR THE DESIGN PORTION OF THE ALTERNAT… |
| Mod P00010· CHANGE ORDER | 2012-11-08 | +$0 | $22,960,660 | OTHER FUNCTION THIS ACTION IS TO PROVIDE THE CONTRACTOR ADVANCE PAYMENTS. THE ORIGINAL CONTRACT WAS FOR A COM… |
| Mod P00015· OTHER ADMINISTRATIVE ACTION | 2012-11-16 | +$0 | $22,960,660 | OTHER FUNCTION THIS ACTION IS TO INCORPORATE THE ENGINEERING CHANGES CLAUSE INTO THIS CONTRACT. |
| Mod P00016· OTHER ADMINISTRATIVE ACTION | 2013-01-17 | +$99,858 | $23,060,518 | OTHER FUNCTION THIS ACTION IS FOR A CHANGE ORDER FOR THE ALTERNATE FEED EATON CONSTRUCTION. |
| Mod P00013· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2013-02-11 | −$4,163 | $23,056,355 | OTHER FUNCTION THIS ACTION IS A MODIFICATION FOR THE ALTERNATE ELECTRICAL FEED DESIGN. |
| Mod P00011· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2013-02-13 | −$196 | $23,056,159 | OTHER FUNCTION THIS ACTION IS TO DEFINITIZE THE CHANGE ORDER FOR THE DESIGN WORK TO RE-ROUTE THE GAS LINE. |
| Mod P00017· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2013-02-21 | +$34,180 | $23,090,339 | OTHER FUNCTION THIS FOR STANDARD CONTROLS FOR A CONTROL PLATFORM MODULE. |
| Mod P00018· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2013-03-12 | +$18,145 | $23,108,484 | THIS MODIFICATION IS FOR A FIVE INCH CONDUIT AT BUILDING 87. |
| Mod P00019· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2013-03-14 | +$9,135 | $23,117,619 | THIS MODIFICATION IS TO ADD ELECTRICAL LOAD BREAKS TO THE CONTRACT. |
| Mod P00003· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2013-05-01 | +$8,271 | $23,125,890 | THIS MODIFICATION IS RE-ROUTE THE GAS LINE TO THE ENERGY CENTER. |
| Mod P00020· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2013-05-03 | +$8,440 | $23,134,330 | THIS MODIFICATION IS TO ALLOW FOR LONG TERM STORAGE OF THE TURBINE UNIT. |
| Mod P00021· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2013-05-08 | +$18,103 | $23,152,433 | THIS MODIFICATION IS TO ALLOW FOR ADDITIONAL PIER CASINGS. |
| Mod P00023· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2013-06-18 | +$11,029 | $23,163,462 | THIS MODIFICATION IS TO ALLOW FOR ADDITIONAL FIRE MASS NOTIFICATION DEVICES. THE ORIGINAL CONTRACT WAS TO BUI… |
| Mod P00024· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2013-06-21 | +$9,829 | $23,173,291 | THIS MODIFICATION IS TO REMOVE A FENCE AND SOME CONCRETE FOR THE DALLAS MEDICAL CENTER. THE ORIGINAL CONTRACT… |
| Mod P00025· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2013-06-25 | +$310,666 | $23,483,957 | THIS MODIFICATION IS TO REMOVE A FENCE AND SOME CONCRETE FOR THE DALLAS MEDICAL CENTER. THE ORIGINAL CONTRACT… |
| Mod P00022· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2013-07-10 | +$0 | $23,483,957 | THIS AWARD IS FOR A COMBINED HEAT AND POWER PLANT IN DALLAS TEXAS. |
| Mod P00026· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2013-07-12 | +$88,328 | $23,572,285 | THIS AWARD IS FOR A COMBINED HEAT AND POWER PLANT IN DALLAS TEXAS. |
| Mod P00002· DEFINITIZE CHANGE ORDER | 2013-07-26 | +$0 | $23,572,285 | THIS CONTRACT IS TO BUILD A POWER PLANT ON THE VETERANS AFFAIRS MEDICAL CENTER DALLAS CAMPUS. |
| Mod P00027· DEFINITIZE CHANGE ORDER | 2013-09-18 | +$0 | $23,572,285 | THIS CONTRACT IS TO BUILD A POWER PLANT ON THE VETERANS AFFAIRS MEDICAL CENTER DALLAS CAMPUS. |
| Mod P00029· DEFINITIZE CHANGE ORDER | 2014-01-06 | +$79,086 | $23,651,371 | THIS CONTRACT IS TO BUILD A POWER PLANT ON THE VETERANS AFFAIRS MEDICAL CENTER DALLAS CAMPUS. |
| Mod P00030· DEFINITIZE CHANGE ORDER | 2014-01-06 | +$24,885 | $23,676,256 | THIS CONTRACT IS TO BUILD A POWER PLANT ON THE VETERANS AFFAIRS MEDICAL CENTER DALLAS CAMPUS. |
| Mod P00028· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2014-05-02 | +$77,302 | $23,753,558 | THIS CONTRACT IS TO BUILD A POWER PLANT ON THE VETERANS AFFAIRS MEDICAL CENTER DALLAS CAMPUS. |
| Mod P00031· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2014-06-03 | +$40,000 | $23,793,558 | THIS CONTRACT IS TO BUILD A POWER PLANT ON THE VETERANS AFFAIRS MEDICAL CENTER DALLAS CAMPUS. |
| Mod P00032· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2014-06-11 | −$10,919 | $23,782,639 | THIS CONTRACT IS TO BUILD A POWER PLANT ON THE VETERANS AFFAIRS MEDICAL CENTER DALLAS CAMPUS. |
| Mod P00033· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2014-06-18 | +$15,706 | $23,798,345 | THIS CONTRACT IS TO BUILD A POWER PLANT ON THE VETERANS AFFAIRS MEDICAL CENTER DALLAS CAMPUS. |
| Mod P00035· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2014-08-14 | −$1,902 | $23,796,443 | THIS CONTRACT IS TO BUILD A POWER PLANT ON THE VETERANS AFFAIRS MEDICAL CENTER DALLAS CAMPUS. |
| Mod P00034· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2014-08-18 | +$37,625 | $23,834,068 | THIS CONTRACT IS TO BUILD A POWER PLANT ON THE VETERANS AFFAIRS MEDICAL CENTER DALLAS CAMPUS. |
| Mod P00036· CHANGE ORDER | 2014-09-10 | +$50,000 | $23,884,068 | THIS CONTRACT IS TO BUILD A POWER PLANT ON THE VETERANS AFFAIRS MEDICAL CENTER DALLAS CAMPUS. |
| Mod P00037· CHANGE ORDER | 2014-09-11 | +$0 | $23,884,068 | THIS CONTRACT IS TO BUILD A POWER PLANT ON THE VETERANS AFFAIRS MEDICAL CENTER DALLAS CAMPUS. |
| Mod P00038· DEFINITIZE CHANGE ORDER | 2014-11-03 | −$45,924 | $23,838,144 | THIS CONTRACT IS TO BUILD A POWER PLANT ON THE VETERANS AFFAIRS MEDICAL CENTER DALLAS CAMPUS. |
| Mod P00039· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2015-05-13 | −$9,811 | $23,828,333 | THIS CONTRACT IS TO BUILD A POWER PLANT ON THE VETERANS AFFAIRS MEDICAL CENTER DALLAS CAMPUS. |
| Mod P00040· CHANGE ORDER | 2015-06-02 | +$300,000 | $24,128,333 | THIS CONTRACT IS TO BUILD A POWER PLANT ON THE VETERANS AFFAIRS MEDICAL CENTER DALLAS CAMPUS. |
| Mod P00041· DEFINITIZE CHANGE ORDER | 2017-07-13 | −$15,424 | $24,112,909 | THIS CONTRACT IS TO BUILD A POWER PLANT ON THE VETERANS AFFAIRS MEDICAL CENTER DALLAS CAMPUS. |
| Mod P00042· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2017-07-13 | +$367,333 | $24,480,242 | THIS CONTRACT IS TO BUILD A POWER PLANT ON THE VETERANS AFFAIRS MEDICAL CENTER DALLAS CAMPUS. |
| Mod P00043· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2017-07-13 | +$880,000 | $25,360,242 | THIS CONTRACT IS TO BUILD A POWER PLANT ON THE VETERANS AFFAIRS MEDICAL CENTER DALLAS CAMPUS. |
Related awards · 2
Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.
Other VA awards to the same recipient (UEI GZH9ED5FL2V3)
| Award | Office · PSC / listing | Net obligations | FY |
|---|---|---|---|
| VA101F12C0039 | OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F) · Y1DB · CONSTRUCTION OF LABORATORIES AND CLINICS | $58,590,140 | FY2012 |
| VA101CFMC0039 | OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F) · Y111 · CONSTRUCTION OF OFFICE BUILDINGS | $43,512,526 | FY2009 |
Cite as: Glassbox VA record view · VA contract (USAspending / FPDS) · CONT_AWD_VA701C0171_3600_-NONE-_-NONE- · retrieved 2026-09-26.