CONTRACTOR TO PROVIDE ALL LABOR AND MATERIALS TO COMPLETE PROJECT HVAC CORRECTIONS BUILDING 3 AND 6 AT THE VA BLACK HILLS HEALTH CARE SYSTEM, HOT SPRINGS, SD
Modification chain · 19 transactions
Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.
- Base2009-06-23+$1,202,000= $1,202,000
- Mod 12010-08-01+$13,463= $1,215,463
- Mod SA102010-09-08+$2,655= $1,218,118
- Mod SA112010-09-08+$2,335= $1,220,453
- Mod 122011-02-09+$4,669= $1,225,122
- Mod 132011-02-09+$7,174= $1,232,296
- Mod 142011-02-09+$3,435= $1,235,731
- Mod SA152011-04-06+$0= $1,235,731
- Mod SA162011-06-08+$2,391= $1,238,122
- Mod SA16A2011-09-11+$1,880= $1,240,002
- Mod COO2011-09-21+$0= $1,240,002
- Mod SA172011-10-04+$0= $1,240,002
- Mod SA182011-10-25+$17,102= $1,257,104
- Mod SA192011-11-03+$2,492= $1,259,596
- Mod SA202011-11-03+$780= $1,260,376
- Mod SA212012-03-06+$7,638= $1,268,014
- Mod SA222012-03-06+$3,682= $1,271,696
- Mod SA232012-04-27+$554= $1,272,250
- Mod P000032012-07-25+$8,248= $1,280,498
| Transaction | Action date | This action (delta) | Running total | Description on this transaction |
|---|---|---|---|---|
| Base | 2009-06-23 | +$1,202,000 | $1,202,000 | CONTRACTOR TO PROVIDE ALL LABOR AND MATERIALS TO COMPLETE PROJECT HVAC CORRECTIONS BUILDING 3 AND 6 AT THE VA… |
| Mod 1· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2010-08-01 | +$13,463 | $1,215,463 | CONTRACTOR TO PROVIDE ALL LABOR AND MATERIALS TO COMPLETE PROJECT HVAC CORRECTIONS BUILDING 3 AND 6 AT THE VA… |
| Mod SA10· CHANGE ORDER | 2010-09-08 | +$2,655 | $1,218,118 | CONTRACTOR TO PROVIDE ALL LABOR AND MATERIALS TO COMPLETE PROJECT HVAC CORRECTIONS BUILDING 3 AND 6 AT THE VA… |
| Mod SA11· CHANGE ORDER | 2010-09-08 | +$2,335 | $1,220,453 | CONTRACTOR TO PROVIDE ALL LABOR AND MATERIALS TO COMPLETE PROJECT HVAC CORRECTIONS BUILDING 3 AND 6 AT THE VA… |
| Mod 12· CHANGE ORDER | 2011-02-09 | +$4,669 | $1,225,122 | CONTRACTOR TO PROVIDE ALL LABOR AND MATERIALS TO COMPLETE PROJECT HVAC CORRECTIONS BUILDING 3 AND 6 AT THE VA… |
| Mod 13· CHANGE ORDER | 2011-02-09 | +$7,174 | $1,232,296 | CONTRACTOR TO PROVIDE ALL LABOR AND MATERIALS TO COMPLETE PROJECT HVAC CORRECTIONS BUILDING 3 AND 6 AT THE VA… |
| Mod 14· CHANGE ORDER | 2011-02-09 | +$3,435 | $1,235,731 | CONTRACTOR TO PROVIDE ALL LABOR AND MATERIALS TO COMPLETE PROJECT HVAC CORRECTIONS BUILDING 3 AND 6 AT THE VA… |
| Mod SA15· CHANGE ORDER | 2011-04-06 | +$0 | $1,235,731 | CONTRACTOR TO PROVIDE ALL LABOR AND MATERIALS TO COMPLETE PROJECT HVAC CORRECTIONS BUILDING 3 AND 6 AT THE VA… |
| Mod SA16· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-06-08 | +$2,391 | $1,238,122 | CONTRACTOR TO PROVIDE ALL LABOR AND MATERIALS TO COMPLETE PROJECT HVAC CORRECTIONS BUILDING 3 AND 6 AT THE VA… |
| Mod SA16A· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-09-11 | +$1,880 | $1,240,002 | CONTRACTOR TO PROVIDE ALL LABOR AND MATERIALS TO COMPLETE PROJECT HVAC CORRECTIONS BUILDING 3 AND 6 AT THE VA… |
| Mod COO· CHANGE ORDER | 2011-09-21 | +$0 | $1,240,002 | CONTRACTOR TO PROVIDE ALL LABOR AND MATERIALS TO COMPLETE PROJECT HVAC CORRECTIONS BUILDING 3 AND 6 AT THE VA… |
| Mod SA17· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-10-04 | +$0 | $1,240,002 | CONTRACTOR TO PROVIDE ALL LABOR AND MATERIALS TO COMPLETE PROJECT HVAC CORRECTIONS BUILDING 3 AND 6 AT THE VA… |
| Mod SA18· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-10-25 | +$17,102 | $1,257,104 | CONTRACTOR TO PROVIDE ALL LABOR AND MATERIALS TO COMPLETE PROJECT HVAC CORRECTIONS BUILDING 3 AND 6 AT THE VA… |
| Mod SA19· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-11-03 | +$2,492 | $1,259,596 | CONTRACTOR TO PROVIDE ALL LABOR AND MATERIALS TO COMPLETE PROJECT HVAC CORRECTIONS BUILDING 3 AND 6 AT THE VA… |
| Mod SA20· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-11-03 | +$780 | $1,260,376 | CONTRACTOR TO PROVIDE ALL LABOR AND MATERIALS TO COMPLETE PROJECT HVAC CORRECTIONS BUILDING 3 AND 6 AT THE VA… |
| Mod SA21· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-03-06 | +$7,638 | $1,268,014 | CONTRACTOR TO PROVIDE ALL LABOR AND MATERIALS TO COMPLETE PROJECT HVAC CORRECTIONS BUILDING 3 AND 6 AT THE VA… |
| Mod SA22· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-03-06 | +$3,682 | $1,271,696 | CONTRACTOR TO PROVIDE ALL LABOR AND MATERIALS TO COMPLETE PROJECT HVAC CORRECTIONS BUILDING 3 AND 6 AT THE VA… |
| Mod SA23· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-04-27 | +$554 | $1,272,250 | CONTRACTOR TO PROVIDE ALL LABOR AND MATERIALS TO COMPLETE PROJECT HVAC CORRECTIONS BUILDING 3 AND 6 AT THE VA… |
| Mod P00003· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-07-25 | +$8,248 | $1,280,498 | CONTRACTOR TO PROVIDE ALL LABOR AND MATERIALS TO COMPLETE PROJECT HVAC CORRECTIONS BUILDING 3 AND 6 AT THE VA… |
Related awards · 11
Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.
Other VA awards to the same recipient (UEI SC89KKMN3F25)
| Award | Office · PSC / listing | Net obligations | FY |
|---|---|---|---|
| VA263C1173 | 568-VA BLACK HILLS HEALTH CARE SYSTEM · Z149 · MAINT-REP-ALT/OTHER HOSPITAL BLDGS | $304,848 | FY2011 |
| VA263C0989 | 568-VA BLACK HILLS HEALTH CARE SYSTEM · Z149 · MAINT-REP-ALT/OTHER HOSPITAL BLDGS | $259,326 | FY2010 |
| V568C00725 | 568-VA BLACK HILLS HEALTH CARE SYSTEM · Z141 · MAINT-REP-ALT/HOSPITALS & INFIRMARY | $4,917 | FY2010 |
| VA263C0813 | 568-VA BLACK HILLS HEALTH CARE SYSTEM · Z141 · MAINT-REP-ALT/HOSPITALS & INFIRMARY | $22,203 | FY2009 |
| VA263C0649 | 568-VA BLACK HILLS HEALTH CARE SYSTEM · Z245 · MAINT-REP-ALT/WATER SUPPLY | $68,210 | FY2009 |
| VARA263C0646 | 568-VA BLACK HILLS HEALTH CARE SYSTEM · Y245 · CONSTRUCT/WATER SUPPLY | $37,674 | FY2009 |
Other recipients under Z141 from 568-VA BLACK HILLS HEALTH CARE SYSTEM (most recent first)
| Award | Recipient | Office | Net obligations | FY |
|---|---|---|---|---|
| VA263C1373 | JOURNEY CONSTRUCTION, INC. | 568-VA BLACK HILLS HEALTH CARE SYSTEM | $259,712 | FY2011 |
| VA263C1350 | GCH CONSTRUCTION COMPANY | 568-VA BLACK HILLS HEALTH CARE SYSTEM | $89,400 | FY2011 |
| VA263C1331 | GCH CONSTRUCTION COMPANY | 568-VA BLACK HILLS HEALTH CARE SYSTEM | $126,517 | FY2011 |
| VA263C1311 | BOULDER HILL CONSTRUCTION LLC | 568-VA BLACK HILLS HEALTH CARE SYSTEM | $8,504 | FY2011 |
| VA263C1235 | GCH CONSTRUCTION COMPANY | 568-VA BLACK HILLS HEALTH CARE SYSTEM | $105,332 | FY2011 |