Description
CONTRACTOR TO PROVIDE ALL LABOR AND MATERIALS TO COMPLETE PROJECT 568-11-208 RENOVATE 3A OFFICE SPACE AT THE VA BLACK HILLS HEALTH CARE SYSTEM, HOT SPRINGS, SD.
Modification chain · 5 transactions
Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.
- Base2011-02-23+$300,919= $300,919
- Mod SA12011-05-06+$1,628= $302,547
- Mod SA22011-06-27+$1,487= $304,034
- Mod SA32011-07-26+$775= $304,809
- Mod SA42011-07-26+$39= $304,848
| Transaction | Action date | This action (delta) | Running total | Description on this transaction |
|---|---|---|---|---|
| Base | 2011-02-23 | +$300,919 | $300,919 | CONTRACTOR TO PROVIDE ALL LABOR AND MATERIALS TO COMPLETE PROJECT 568-11-208 RENOVATE 3A OFFICE SPACE AT THE V… |
| Mod SA1· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-05-06 | +$1,628 | $302,547 | CONTRACTOR TO PROVIDE ALL LABOR AND MATERIALS TO COMPLETE PROJECT 568-11-208 RENOVATE 3A OFFICE SPACE AT THE V… |
| Mod SA2· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-06-27 | +$1,487 | $304,034 | CONTRACTOR TO PROVIDE ALL LABOR AND MATERIALS TO COMPLETE PROJECT 568-11-208 RENOVATE 3A OFFICE SPACE AT THE V… |
| Mod SA3· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-07-26 | +$775 | $304,809 | CONTRACTOR TO PROVIDE ALL LABOR AND MATERIALS TO COMPLETE PROJECT 568-11-208 RENOVATE 3A OFFICE SPACE AT THE V… |
| Mod SA4· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-07-26 | +$39 | $304,848 | CONTRACTOR TO PROVIDE ALL LABOR AND MATERIALS TO COMPLETE PROJECT 568-11-208 RENOVATE 3A OFFICE SPACE AT THE V… |
Related awards · 11
Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.
Other VA awards to the same recipient (UEI SC89KKMN3F25)
| Award | Office · PSC / listing | Net obligations | FY |
|---|---|---|---|
| VA263C0989 | 568-VA BLACK HILLS HEALTH CARE SYSTEM · Z149 · MAINT-REP-ALT/OTHER HOSPITAL BLDGS | $259,326 | FY2010 |
| V568C00725 | 568-VA BLACK HILLS HEALTH CARE SYSTEM · Z141 · MAINT-REP-ALT/HOSPITALS & INFIRMARY | $4,917 | FY2010 |
| VA263C0813 | 568-VA BLACK HILLS HEALTH CARE SYSTEM · Z141 · MAINT-REP-ALT/HOSPITALS & INFIRMARY | $22,203 | FY2009 |
| VA263C0649 | 568-VA BLACK HILLS HEALTH CARE SYSTEM · Z245 · MAINT-REP-ALT/WATER SUPPLY | $68,210 | FY2009 |
| VARA263C0646 | 568-VA BLACK HILLS HEALTH CARE SYSTEM · Y245 · CONSTRUCT/WATER SUPPLY | $37,674 | FY2009 |
| VA263RA0680 | 568-VA BLACK HILLS HEALTH CARE SYSTEM · Z141 · MAINT-REP-ALT/HOSPITALS & INFIRMARY | $661,660 | FY2009 |
Other recipients under Z149 from 568-VA BLACK HILLS HEALTH CARE SYSTEM (most recent first)
| Award | Recipient | Office | Net obligations | FY |
|---|---|---|---|---|
| VA263C1317 | MMCI, LLC | 568-VA BLACK HILLS HEALTH CARE SYSTEM | $22,365 | FY2011 |
| VA263C1312 | JE HURLEY INC. | 568-VA BLACK HILLS HEALTH CARE SYSTEM | $627,600 | FY2011 |
| VA263C1176 | BOULDER HILL CONSTRUCTION LLC | 568-VA BLACK HILLS HEALTH CARE SYSTEM | $181,970 | FY2011 |
| VA568P1Z009 | KONE INC | 568-VA BLACK HILLS HEALTH CARE SYSTEM | $49,920 | FY2011 |
| VA263C1171 | PRECISION MECHANICAL, LLP | 568-VA BLACK HILLS HEALTH CARE SYSTEM | $257,325 | FY2011 |
Cite as: Glassbox VA record view · VA contract (USAspending / FPDS) · CONT_AWD_VA263C1173_3600_-NONE-_-NONE- · retrieved 2026-09-26.