Description
IGF::OT::IGF 674-Z40001&VA257-14-C-0018 URGENT CARE REPLACE-MENT MOD #16 NO COST TIME EXT. EXECUTED, POP ENDS 7-31-16.
Base award description: IGF::OT::IGF 674-Z40001&VA257-14-C-0018 URGENT CARE REPLACEMENT CONSTRUCTION CONTRACT.
Modification chain · 17 transactions
Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.
- Base2013-12-31+$7,028,000= $7,028,000
- Mod P000012014-08-04+$21,397= $7,049,397
- Mod P000022014-09-15+$31,755= $7,081,152
- Mod P000032014-12-09+$86,383= $7,167,535
- Mod P000042015-03-02+$63,410= $7,230,945
- Mod P000052015-09-14+$21,484= $7,252,429
- Mod P000062015-09-22+$91,589= $7,344,017
- Mod P000072015-10-05+$84,645= $7,428,662
- Mod P000082015-10-15+$12,701= $7,441,363
- Mod P000092015-10-23+$0= $7,441,363
- Mod P000102015-11-24+$40,164= $7,481,527
- Mod P000112015-12-03+$70,611= $7,552,138
- Mod P000122016-01-15+$91,528= $7,643,666
- Mod P000132016-03-22+$95,508= $7,739,174
- Mod P000142016-04-20+$36,491= $7,775,665
- Mod P000152016-06-22+$8,341= $7,784,006
- Mod P000162016-07-02+$0= $7,784,006
| Transaction | Action date | This action (delta) | Running total | Description on this transaction |
|---|---|---|---|---|
| Base | 2013-12-31 | +$7,028,000 | $7,028,000 | IGF::OT::IGF 674-Z40001&VA257-14-C-0018 URGENT CARE REPLACEMENT CONSTRUCTION CONTRACT. |
| Mod P00001· CHANGE ORDER | 2014-08-04 | +$21,397 | $7,049,397 | IGF::OT::IGF 674-Z40001&VA257-14-C-0018 URGENT CARE REPLACEMENT CONSTRUCTION CONTRACT, MOD P00001 FOR $21,397 |
| Mod P00002· CHANGE ORDER | 2014-09-15 | +$31,755 | $7,081,152 | IGF::OT::IGF 674-Z40001&VA257-14-C-0018 URGENT CARE REPLACEMENT MOD P00001 FOR +$21,397; MOD P00002 +$31,755&+… |
| Mod P00003· CHANGE ORDER | 2014-12-09 | +$86,383 | $7,167,535 | IGF::OT::IGF 674-Z40001&VA257-14-C-0018 CONSTRUCT AN URGENT CARE REPLACEMENT BLDG. MOD #1 FOR +$21,397; MOD #2… |
| Mod P00004· CHANGE ORDER | 2015-03-02 | +$63,410 | $7,230,945 | IGF::OT::IGF 674-Z40001&VA257-14-C-0018 CONSTRUCT AN URGENT CARE REPLACEMENT BLDG. MOD #1 FOR +$21,397; MOD #2… |
| Mod P00005· CHANGE ORDER | 2015-09-14 | +$21,484 | $7,252,429 | IGF::OT::IGF 674-Z40001&VA257-14-C-0018 CONSTRUCT AN URGENT CARE REPLACEMENT BLDG. MOD #1 FOR +$21,397; MOD #2… |
| Mod P00006· CHANGE ORDER | 2015-09-22 | +$91,589 | $7,344,017 | IGF::OT::IGF 674-Z40001&VA257-14-C-0018 CONSTRUCT AN URGENT CARE REPLACEMENT BLDG. MOD #1 FOR +$21,397; MOD #2… |
| Mod P00007· CHANGE ORDER | 2015-10-05 | +$84,645 | $7,428,662 | IGF::OT::IGF 674-Z40001&VA257-14-C-0018 CONSTRUCT AN URGENT CARE REPLACEMENT BLDG. 10/5/15 MOD #7 +84,645.06 +… |
| Mod P00008· CHANGE ORDER | 2015-10-15 | +$12,701 | $7,441,363 | IGF::OT::IGF 674-Z40001&VA257-14-C-0018 URGENT CARE REPLACEMENT BLDG. 10/15/15 MOD #8 +12,700.64 +5 DAYS, INST… |
| Mod P00009· CHANGE ORDER | 2015-10-23 | +$0 | $7,441,363 | IGF::OT::IGF 674-Z40001&VA257-14-C-0018 URGENT CARE REPLACEMENT BLDG. 10/23/15 MOD #9 NO COST ADD +51 DAYS, CO… |
| Mod P00010· CHANGE ORDER | 2015-11-24 | +$40,164 | $7,481,527 | IGF::OT::IGF 674-Z40001&VA257-14-C-0018 URGENT CARE REPLACEMENT BLDG. 11/24/15 MOD #10 ADD +$40,163.53 TO RE-R… |
| Mod P00011· CHANGE ORDER | 2015-12-03 | +$70,611 | $7,552,138 | IGF::OT::IGF 674-Z40001&VA257-14-C-0018 URGENT CARE REPLACEMENT BLDG. 12/3/15 MOD #11 ADD +$70,611.22 TO ADD M… |
| Mod P00012· CHANGE ORDER | 2016-01-15 | +$91,528 | $7,643,666 | IGF::OT::IGF 674-Z40001&VA257-14-C-0018 URGENT CARE REPLACEMENT BLDG. 12/10/15 MOD #12 ADD +$91,528.00 ADDING… |
| Mod P00013· CHANGE ORDER | 2016-03-22 | +$95,508 | $7,739,174 | IGF::OT::IGF 674-Z40001&VA257-14-C-0018 URGENT CARE REPLACEMENT BLDG. 12/10/15 MOD #13 ADD +$95,508.00 ADDING… |
| Mod P00014· CHANGE ORDER | 2016-04-20 | +$36,491 | $7,775,665 | IGF::OT::IGF 674-Z40001&VA257-14-C-0018 URGENT CARE REPLACEMENT BLDG. 12/10/15 MOD #14 ADD +$36,491.00 ELECTRI… |
| Mod P00015· CHANGE ORDER | 2016-06-22 | +$8,341 | $7,784,006 | IGF::OT::IGF 674-Z40001&VA257-14-C-0018 URGENT CARE REPLACEMENT 6/22/16 MOD #15 ADD +$8,341.00 TO PROVIDE ELEC… |
| Mod P00016· CHANGE ORDER | 2016-07-02 | +$0 | $7,784,006 | IGF::OT::IGF 674-Z40001&VA257-14-C-0018 URGENT CARE REPLACE-MENT MOD #16 NO COST TIME EXT. EXECUTED, POP ENDS… |
Related awards · 6
Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.
Other VA awards to the same recipient (UEI MGGBMZVP2M17)
| Award | Office · PSC / listing | Net obligations | FY |
|---|---|---|---|
| 36C78618C0266 | NATIONAL CEMETERY ADMIN (36C786) · Y1AZ · CONSTRUCTION OF OTHER ADMINISTRATIVE FACILITIES AND SERVICE BUILDINGS | $6,070,738 | FY2018 |
| VA70114C0027 | PCAC NATIONAL ENERGY BUSINESS CENTER (36E776) · Y1MZ · CONSTRUCTION OF EPG FACILITIES - OTHER, INCLUDING TRANSMISSION | $5,583,273 | FY2014 |
| VA25614C0079 | 256-NETWORK CONTRACT OFFICE 16 · Y1LZ · CONSTRUCTION OF PARKING FACILITIES | $1,437,027 | FY2014 |
| VA25613C0228 | 256-NETWORK CONTRACT OFFICE 16 · Y1DA · CONSTRUCTION OF HOSPITALS AND INFIRMARIES | $2,371,321 | FY2013 |
| VA25613C0207 | 256-NETWORK CONTRACT OFFICE 16 · Y1DA · CONSTRUCTION OF HOSPITALS AND INFIRMARIES | $350,903 | FY2013 |
| VA25613C0198 | 256-NETWORK CONTRACT OFFICE 16 · Y1JZ · CONSTRUCTION OF MISCELLANEOUS BUILDINGS | $436,300 | FY2013 |
Cite as: Glassbox VA record view · VA contract (USAspending / FPDS) · CONT_AWD_VA25714C0018_3600_-NONE-_-NONE- · retrieved 2026-09-26.