Description
CONSTRUCT WOMEN'S CLINIC MODIFICATION #3 ELECTRICAL AND DRAINAGE WORK
Base award description: CONSTRUCT WOMEN'S CLINIC
Modification chain · 6 transactions
Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.
- Base2010-11-05+$3,381,361= $3,381,361
- Mod 12011-05-03+$9,846= $3,391,207
- Mod 22011-05-03+$34,891= $3,426,098
- Mod 32011-09-01+$132,066= $3,558,164
- Mod 42011-10-03+$73,522= $3,631,686
- Mod P000052012-04-27-$1,803= $3,629,883
| Transaction | Action date | This action (delta) | Running total | Description on this transaction |
|---|---|---|---|---|
| Base | 2010-11-05 | +$3,381,361 | $3,381,361 | CONSTRUCT WOMEN'S CLINIC |
| Mod 1· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-05-03 | +$9,846 | $3,391,207 | CONSTRUCT WOMEN'S CLINIC MOD #1 FOR FIRE HYDRANT AND ASSOCIATED WORK |
| Mod 2· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-05-03 | +$34,891 | $3,426,098 | CONSTRUCT WOMEN'S CLINIC MODIFICATION #2 TRANSITE PIPE ABATEMENT |
| Mod 3· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-09-01 | +$132,066 | $3,558,164 | CONSTRUCT WOMEN'S CLINIC MODIFICATION #3 ELECTRICAL AND DRAINAGE WORK |
| Mod 4· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-10-03 | +$73,522 | $3,631,686 | CONSTRUCT WOMEN'S CLINIC MODIFICATION #3 ELECTRICAL AND DRAINAGE WORK |
| Mod P00005· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-04-27 | −$1,803 | $3,629,883 | CONSTRUCT WOMEN'S CLINIC MODIFICATION #3 ELECTRICAL AND DRAINAGE WORK |
Related awards · 11
Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.
Other VA awards to the same recipient (UEI FL4GMWFL1L28)
| Award | Office · PSC / listing | Net obligations | FY |
|---|---|---|---|
| VA590C10212 | 246-NETWORK CONTRACTING OFFICE 6 · Z149 · MAINT-REP-ALT/OTHER HOSPITAL BLDGS | $213,447 | FY2011 |
| VA590C00573 | 246-NETWORK CONTRACTING OFFICE 6 · Z149 · MAINT-REP-ALT/OTHER HOSPITAL BLDGS | $57,644 | FY2010 |
| VA246C0630 | 246-NETWORK CONTRACTING OFFICE 6 · Z149 · MAINT-REP-ALT/OTHER HOSPITAL BLDGS | $0 | FY2010 |
| VA246C0513 | 246-NETWORK CONTRACTING OFFICE 6 · Y149 · CONSTRUCT/OTHER HOSPITAL BLDGS | $566,466 | FY2009 |
| VA246C0498 | 246-NETWORK CONTRACTING OFFICE 6 · Y149 · CONSTRUCT/OTHER HOSPITAL BLDGS | $4,692,340 | FY2009 |
| V590C80559 | 590S-HAMPTON SMALL PURCHASE · J045 · MAINT-REP OF PLUMBING-HEATING EQ | $1,300 | FY2008 |
Other recipients under Y149 from 246-NETWORK CONTRACTING OFFICE 6 (most recent first)
| Award | Recipient | Office | Net obligations | FY |
|---|---|---|---|---|
| VA565C10412 | MODULAR MANAGEMENT GROUP INC | 246-NETWORK CONTRACTING OFFICE 6 | $2,331,724 | FY2011 |
| VA637C10684 | DAVKO SERVICES, LLC | 246-NETWORK CONTRACTING OFFICE 6 | $10,000 | FY2011 |
| VA637C10680 | BOYKIN CONTRACTING GROUP, INC. | 246-NETWORK CONTRACTING OFFICE 6 | $10,000 | FY2011 |
| VA637C10678 | VYKON INCORPORATED | 246-NETWORK CONTRACTING OFFICE 6 | $10,000 | FY2011 |
| VA637C10685 | LEE & RYAN ENVIRONMENTAL CONSULTING, INCORPORATED | 246-NETWORK CONTRACTING OFFICE 6 | $10,000 | FY2011 |
Cite as: Glassbox VA record view · VA contract (USAspending / FPDS) · CONT_AWD_VA246C0668_3600_-NONE-_-NONE- · retrieved 2026-09-26.