Description
MOD FOR FINISH WORK
Base award description: SCI CONSTRUCTION PROJECT
Modification chain · 15 transactions
Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.
- Base2009-09-21+$4,291,475= $4,291,475
- Mod 12010-04-08+$6,191= $4,297,666
- Mod 22010-09-29+$3,043= $4,300,709
- Mod 32010-09-29+$22,500= $4,323,209
- Mod 42010-11-30+$21,068= $4,344,277
- Mod 52011-01-12+$50,398= $4,394,675
- Mod 62011-03-01+$12,022= $4,406,697
- Mod 72011-03-30+$6,386= $4,413,083
- Mod 82011-05-09+$14,391= $4,427,474
- Mod 92011-06-07+$1,389= $4,428,863
- Mod 102011-09-13+$44,106= $4,472,969
- Mod P000112011-10-06+$13,500= $4,486,469
- Mod P000122011-11-16+$71,237= $4,557,706
- Mod P000132011-12-20+$117,091= $4,674,797
- Mod P000142012-01-20+$17,543= $4,692,340
| Transaction | Action date | This action (delta) | Running total | Description on this transaction |
|---|---|---|---|---|
| Base | 2009-09-21 | +$4,291,475 | $4,291,475 | SCI CONSTRUCTION PROJECT |
| Mod 1· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2010-04-08 | +$6,191 | $4,297,666 | SCI CONSTRUCTION PROJECT |
| Mod 2· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2010-09-29 | +$3,043 | $4,300,709 | SCI CONSTRUCTION PROJECT MOD 2 STOOP WORK |
| Mod 3· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2010-09-29 | +$22,500 | $4,323,209 | SCI CONSTRUCTION PROJECT |
| Mod 4· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2010-11-30 | +$21,068 | $4,344,277 | SCI CONSTRUCTION PROJECT |
| Mod 5· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-01-12 | +$50,398 | $4,394,675 | SCI CONSTRUCTION PROJECT |
| Mod 6· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-03-01 | +$12,022 | $4,406,697 | MOD 6 FOR LIGHTING, ROOF, AND TIE-IN DETAILS |
| Mod 7· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-03-30 | +$6,386 | $4,413,083 | MOD 7 CHILL WATER PIPING |
| Mod 8· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-05-09 | +$14,391 | $4,427,474 | MOD #8 FOR ROOF REVISION TO CONTRACT |
| Mod 9· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-06-07 | +$1,389 | $4,428,863 | MOD 9 BACKFLOW PREVENTOR |
| Mod 10· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-09-13 | +$44,106 | $4,472,969 | MOD 10 FOR CANOPY, DOOR, CEILING TILE, AND CERAMIC TILE WORK |
| Mod P00011· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-10-06 | +$13,500 | $4,486,469 | MOD FOR DELAY |
| Mod P00012· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-11-16 | +$71,237 | $4,557,706 | MOD FOR ROOF WORK |
| Mod P00013· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-12-20 | +$117,091 | $4,674,797 | MOD FOR VFD RELATED WORK |
| Mod P00014· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-01-20 | +$17,543 | $4,692,340 | MOD FOR FINISH WORK |
Related awards · 11
Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.
Other VA awards to the same recipient (UEI FL4GMWFL1L28)
| Award | Office · PSC / listing | Net obligations | FY |
|---|---|---|---|
| VA590C10212 | 246-NETWORK CONTRACTING OFFICE 6 · Z149 · MAINT-REP-ALT/OTHER HOSPITAL BLDGS | $213,447 | FY2011 |
| VA246C0668 | 246-NETWORK CONTRACTING OFFICE 6 · Y149 · CONSTRUCT/OTHER HOSPITAL BLDGS | $3,629,883 | FY2011 |
| VA246C0630 | 246-NETWORK CONTRACTING OFFICE 6 · Z149 · MAINT-REP-ALT/OTHER HOSPITAL BLDGS | $0 | FY2010 |
| VA590C00573 | 246-NETWORK CONTRACTING OFFICE 6 · Z149 · MAINT-REP-ALT/OTHER HOSPITAL BLDGS | $57,644 | FY2010 |
| VA246C0513 | 246-NETWORK CONTRACTING OFFICE 6 · Y149 · CONSTRUCT/OTHER HOSPITAL BLDGS | $566,466 | FY2009 |
| V590C80559 | 590S-HAMPTON SMALL PURCHASE · J045 · MAINT-REP OF PLUMBING-HEATING EQ | $1,300 | FY2008 |
Other recipients under Y149 from 246-NETWORK CONTRACTING OFFICE 6 (most recent first)
| Award | Recipient | Office | Net obligations | FY |
|---|---|---|---|---|
| VA565C10412 | MODULAR MANAGEMENT GROUP INC | 246-NETWORK CONTRACTING OFFICE 6 | $2,331,724 | FY2011 |
| VA637C10684 | DAVKO SERVICES, LLC | 246-NETWORK CONTRACTING OFFICE 6 | $10,000 | FY2011 |
| VA637C10680 | BOYKIN CONTRACTING GROUP, INC. | 246-NETWORK CONTRACTING OFFICE 6 | $10,000 | FY2011 |
| VA637C10678 | VYKON INCORPORATED | 246-NETWORK CONTRACTING OFFICE 6 | $10,000 | FY2011 |
| VA637C10685 | LEE & RYAN ENVIRONMENTAL CONSULTING, INCORPORATED | 246-NETWORK CONTRACTING OFFICE 6 | $10,000 | FY2011 |
Cite as: Glassbox VA record view · VA contract (USAspending / FPDS) · CONT_AWD_VA246C0498_3600_-NONE-_-NONE- · retrieved 2026-09-26.