CLOSELY ASSOCIATED - CONSTRUCT DOM II, TWO BUILDINGS, FOR THE BUTLER VA, BUTLER, PA
Base award description: CONSTRUCT DOM II, TWO BUILDINGS, FOR THE BUTLER VA, BUTLER, PA
Modification chain · 9 transactions
Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.
- Base2011-03-31+$3,174,454= $3,174,454
- Mod 12012-01-06+$29,597= $3,204,051
- Mod 22012-01-06+$74,687= $3,278,738
- Mod 32012-05-03+$53,771= $3,332,509
- Mod P000042012-09-07-$46,796= $3,285,714
- Mod P000052013-01-25+$26,188= $3,311,901
- Mod P000062013-03-15+$74,123= $3,386,025
- Mod P000072013-03-15+$71,168= $3,457,192
- Mod P000082013-05-15+$1,951= $3,459,143
| Transaction | Action date | This action (delta) | Running total | Description on this transaction |
|---|---|---|---|---|
| Base | 2011-03-31 | +$3,174,454 | $3,174,454 | CONSTRUCT DOM II, TWO BUILDINGS, FOR THE BUTLER VA, BUTLER, PA |
| Mod 1· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2012-01-06 | +$29,597 | $3,204,051 | CONSTRUCT DOM II, TWO BUILDINGS, FOR THE BUTLER VA, BUTLER, PA |
| Mod 2· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2012-01-06 | +$74,687 | $3,278,738 | CONSTRUCT DOM II, TWO BUILDINGS, FOR THE BUTLER VA, BUTLER, PA |
| Mod 3· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2012-05-03 | +$53,771 | $3,332,509 | CLOSELY ASSOCIATED - CONSTRUCT DOM II, TWO BUILDINGS, FOR THE BUTLER VA, BUTLER, PA |
| Mod P00004· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2012-09-07 | −$46,796 | $3,285,714 | CLOSELY ASSOCIATED - CONSTRUCT DOM II, TWO BUILDINGS, FOR THE BUTLER VA, BUTLER, PA |
| Mod P00005· CHANGE ORDER | 2013-01-25 | +$26,188 | $3,311,901 | CLOSELY ASSOCIATED - CONSTRUCT DOM II, TWO BUILDINGS, FOR THE BUTLER VA, BUTLER, PA |
| Mod P00006· CHANGE ORDER | 2013-03-15 | +$74,123 | $3,386,025 | CLOSELY ASSOCIATED - CONSTRUCT DOM II, TWO BUILDINGS, FOR THE BUTLER VA, BUTLER, PA |
| Mod P00007· CHANGE ORDER | 2013-03-15 | +$71,168 | $3,457,192 | CLOSELY ASSOCIATED - CONSTRUCT DOM II, TWO BUILDINGS, FOR THE BUTLER VA, BUTLER, PA |
| Mod P00008· CHANGE ORDER | 2013-05-15 | +$1,951 | $3,459,143 | CLOSELY ASSOCIATED - CONSTRUCT DOM II, TWO BUILDINGS, FOR THE BUTLER VA, BUTLER, PA |
Related awards · 7
Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.
Other VA awards to the same recipient (UEI H8L3C6PAFRH6)
| Award | Office · PSC / listing | Net obligations | FY |
|---|---|---|---|
| 36C24425N0528 | 244-NETWORK CONTRACT OFFICE 4 (36C244) · Z2DA · REPAIR OR ALTERATION OF HOSPITALS AND INFIRMARIES | $60,307 | FY2025 |
| 36C24425C0007 | 244-NETWORK CONTRACT OFFICE 4 (36C244) · Z1DA · MAINTENANCE OF HOSPITALS AND INFIRMARIES | $6,834,937 | FY2025 |
| 36C24423C0014 | 244-NETWORK CONTRACT OFFICE 4 (36C244) · Y1FZ · CONSTRUCTION OF OTHER RESIDENTIAL BUILDINGS | $543,000 | FY2023 |
| 36C24423N0353 | 244-NETWORK CONTRACT OFFICE 4 (36C244) · Z2DA · REPAIR OR ALTERATION OF HOSPITALS AND INFIRMARIES | $6,562,657 | FY2023 |
| 36C24422N1035 | 244-NETWORK CONTRACT OFFICE 4 (36C244) · Z2DA · REPAIR OR ALTERATION OF HOSPITALS AND INFIRMARIES | $0 | FY2022 |
| 36C24422N0900 | 244-NETWORK CONTRACT OFFICE 4 (36C244) · Y1NZ · CONSTRUCTION OF OTHER UTILITIES | $5,839,247 | FY2022 |
Other recipients under Y149 from 529-BUTLER (most recent first)
| Award | Recipient | Office | Net obligations | FY |
|---|---|---|---|---|
| VA244C1427 | LEE & RYAN ENVIRONMENTAL CONSULTING, INCORPORATED | 529-BUTLER | $3,903,570 | FY2010 |
Cite as: Glassbox VA record view · VA contract (USAspending / FPDS) · CONT_AWD_VA244C1436_3600_-NONE-_-NONE- · retrieved 2026-09-26.