Award recordCONTRACT

LEE & RYAN ENVIRONMENTAL CONSULTING, INCORPORATED

PIID VA244C1427· VHA· 529-BUTLER· Y149 · CONSTRUCT/OTHER HOSPITAL BLDGS· FY2010· $3,903,570 net obligations· UEI RSUZTCPDU9B3· IN

Description

OTHER FUNCTION - REPLACE BOILER PLANT. MOD P00014 TIME EXTENSION 58 CALENDAR DAYS. COMPLETION DATE 7/24/2013.

Base award description: REPLACE BOILER PLANT.

First action · last action
2010-09-27 · 2014-02-07
Transactions
20
First transaction's obligation
$3,587,000
Base + all options value (sum of deltas)
$3,903,570
Extent competed
FULL AND OPEN COMPETITION AFTER EXCLUSION OF SOURCES
Other than full & open authority
—
Set-aside
SERVICE DISABLED VETERAN OWNED SMALL BUSINESS SET-ASIDE
Offers received
5
SDVOSB flag on record
Yes (self-representation)
NAICS
236220 · COMMERCIAL AND INSTITUTIONAL BUILDING CONSTRUCTION

Modification chain · 20 transactions

Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.

$3,956,987$0Base award · 2010-09-27 · this action $3,587,000 · running total $3,587,000Modification 1 · 2011-08-01 · this action $0 · running total $3,587,000Modification P0002 · 2011-10-26 · this action $98,797 · running total $3,685,797Modification P0003 · 2011-11-30 · this action $0 · running total $3,685,797Modification P0004 · 2012-01-06 · this action $37,951 · running total $3,723,748Modification P0005 · 2012-01-06 · this action $89,359 · running total $3,813,107Modification P0006 · 2012-04-17 · this action $0 · running total $3,813,107Modification P0007 · 2012-05-29 · this action $0 · running total $3,813,107Modification P0008 · 2012-06-21 · this action $63,358 · running total $3,876,465Modification P00009 · 2012-10-16 · this action $0 · running total $3,876,465Modification P00010 · 2012-10-29 · this action $0 · running total $3,876,465Modification P00011 · 2013-01-04 · this action $0 · running total $3,876,465Modification P00012 · 2013-03-07 · this action $0 · running total $3,876,465Modification P00013 · 2013-04-08 · this action $80,523 · running total $3,956,987Modification P00014 · 2013-07-16 · this action $0 · running total $3,956,987Modification P00015 · 2013-09-17 · this action $0 · running total $3,956,987Modification P00016 · 2013-10-29 · this action -$43,417 · running total $3,913,570Modification P00017 · 2013-12-30 · this action $0 · running total $3,913,570Modification P00018 · 2014-01-22 · this action $0 · running total $3,913,570Modification P00019 · 2014-02-07 · this action -$10,000 · running total $3,903,570
  • Base2010-09-27+$3,587,000= $3,587,000
  • Mod 12011-08-01+$0= $3,587,000
  • Mod P00022011-10-26+$98,797= $3,685,797
  • Mod P00032011-11-30+$0= $3,685,797
  • Mod P00042012-01-06+$37,951= $3,723,748
  • Mod P00052012-01-06+$89,359= $3,813,107
  • Mod P00062012-04-17+$0= $3,813,107
  • Mod P00072012-05-29+$0= $3,813,107
  • Mod P00082012-06-21+$63,358= $3,876,465
  • Mod P000092012-10-16+$0= $3,876,465
  • Mod P000102012-10-29+$0= $3,876,465
  • Mod P000112013-01-04+$0= $3,876,465
  • Mod P000122013-03-07+$0= $3,876,465
  • Mod P000132013-04-08+$80,523= $3,956,987
  • Mod P000142013-07-16+$0= $3,956,987
  • Mod P000152013-09-17+$0= $3,956,987
  • Mod P000162013-10-29-$43,417= $3,913,570
  • Mod P000172013-12-30+$0= $3,913,570
  • Mod P000182014-01-22+$0= $3,913,570
  • Mod P000192014-02-07-$10,000= $3,903,570
TransactionAction dateThis action (delta)Running totalDescription on this transaction
Base2010-09-27+$3,587,000$3,587,000REPLACE BOILER PLANT.
Mod 1· CHANGE ORDER2011-08-01+$0$3,587,000REPLACE BOILER PLANT.
Mod P0002· CHANGE ORDER2011-10-26+$98,797$3,685,797REPLACE BOILER PLANT. MOD P0002 CHANGE ORDERS
Mod P0003· CHANGE ORDER2011-11-30+$0$3,685,797REPLACE BOILER PLANT. MOD P0002 CHANGE ORDERS
Mod P0004· CHANGE ORDER2012-01-06+$37,951$3,723,748REPLACE BOILER PLANT. MOD P0002 CHANGE ORDERS
Mod P0005· CHANGE ORDER2012-01-06+$89,359$3,813,107REPLACE BOILER PLANT. MOD P0002 CHANGE ORDERS
Mod P0006· CHANGE ORDER2012-04-17+$0$3,813,107REPLACE BOILER PLANT. MOD P0006 TIME EXTENSION
Mod P0007· CHANGE ORDER2012-05-29+$0$3,813,107REPLACE BOILER PLANT. MOD P0007 TIME EXTENSION
Mod P0008· CHANGE ORDER2012-06-21+$63,358$3,876,465OTHER FUNCTIONS - REPLACE BOILER PLANT. MOD P0008 TIME EXTENSION AND ADDITIONAL WORK.
Mod P00009· CHANGE ORDER2012-10-16+$0$3,876,465OTHER FUNCTIONS - REPLACE BOILER PLANT. MOD P0008 TIME EXTENSION AND ADDITIONAL WORK.
Mod P00010· CHANGE ORDER2012-10-29+$0$3,876,465OTHER FUNCTIONS - REPLACE BOILER PLANT. MOD P0008 TIME EXTENSION AND ADDITIONAL WORK.
Mod P00011· CHANGE ORDER2013-01-04+$0$3,876,465OTHER FUNCTIONS - REPLACE BOILER PLANT. MOD P0008 TIME EXTENSION AND ADDITIONAL WORK.
Mod P00012· CHANGE ORDER2013-03-07+$0$3,876,465OTHER FUNCTIONS - REPLACE BOILER PLANT. MOD P00012 TIME EXTENSION 55 CALENDAR DAYS. COMPLETION DATE 3/31/2013…
Mod P00013· CHANGE ORDER2013-04-08+$80,523$3,956,987OTHER FUNCTIONS - REPLACE BOILER PLANT. MOD P00012 TIME EXTENSION 55 CALENDAR DAYS. COMPLETION DATE 3/31/2013…
Mod P00014· CHANGE ORDER2013-07-16+$0$3,956,987OTHER FUNCTION - REPLACE BOILER PLANT. MOD P00014 TIME EXTENSION 58 CALENDAR DAYS. COMPLETION DATE 7/24/2013.
Mod P00015· CHANGE ORDER2013-09-17+$0$3,956,987OTHER FUNCTION - REPLACE BOILER PLANT. MOD P00014 TIME EXTENSION 58 CALENDAR DAYS. COMPLETION DATE 7/24/2013.
Mod P00016· CHANGE ORDER2013-10-29−$43,417$3,913,570OTHER FUNCTION - REPLACE BOILER PLANT. MOD P00016 TIME EXTENSION 58 CALENDAR DAYS. COMPLETION DATE 11/15/2013…
Mod P00017· CHANGE ORDER2013-12-30+$0$3,913,570OTHER FUNCTION - REPLACE BOILER PLANT. MOD P00014 TIME EXTENSION 58 CALENDAR DAYS. COMPLETION DATE 7/24/2013.
Mod P00018· CHANGE ORDER2014-01-22+$0$3,913,570OTHER FUNCTION - REPLACE BOILER PLANT. MOD P00014 TIME EXTENSION 58 CALENDAR DAYS. COMPLETION DATE 7/24/2013.
Mod P00019· CHANGE ORDER2014-02-07−$10,000$3,903,570OTHER FUNCTION - REPLACE BOILER PLANT. MOD P00014 TIME EXTENSION 58 CALENDAR DAYS. COMPLETION DATE 7/24/2013.

Related awards · 7

Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.

Other VA awards to the same recipient (UEI RSUZTCPDU9B3)

AwardOffice · PSC / listingNet obligationsFY
VA24614J1607246-NETWORK CONTRACTING OFFICE 6 · Z1DZ · MAINTENANCE OF OTHER HOSPITAL BUILDINGS$499,258FY2014
VA24614J1602246-NETWORK CONTRACTING OFFICE 6 · Z1DZ · MAINTENANCE OF OTHER HOSPITAL BUILDINGS$499,842FY2014
VA24614J5417246-NETWORK CONTRACTING OFFICE 6 · Z1DA · MAINTENANCE OF HOSPITALS AND INFIRMARIES$13,500FY2014
VA24614P5336246-NETWORK CONTRACTING OFFICE 6 · Z2DA · REPAIR OR ALTERATION OF HOSPITALS AND INFIRMARIES$3,670FY2014
VA24614J0163246-NETWORK CONTRACTING OFFICE 6 · Z1DZ · MAINTENANCE OF OTHER HOSPITAL BUILDINGS$320,656FY2014
VA24614J0162246-NETWORK CONTRACTING OFFICE 6 · Z1LZ · MAINTENANCE OF PARKING FACILITIES$449,728FY2014

Other recipients under Y149 from 529-BUTLER (most recent first)

AwardRecipientOfficeNet obligationsFY
VA244C1436R. A. GLANCY & SONS, INC.529-BUTLER$3,459,143FY2011