Description
IGF::OT::IGF MODIFICATION P00032 TO INCORPORATE RFCO 151 - TIE IN PIPING
Base award description: IGF::OT::IGF OTHER FUNCTIONS - PROJECT 646-367 SPD AND SECURITY DOCK.
Modification chain · 26 transactions
Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.
- Base2012-09-26+$6,819,000= $6,819,000
- Mod P000062014-03-21+$0= $6,819,000
- Mod P000072014-06-25+$94,154= $6,913,154
- Mod P000102014-10-22+$12,496= $6,925,650
- Mod P000112014-12-04+$74,307= $6,999,957
- Mod P000122014-12-17+$0= $6,999,957
- Mod P000132015-06-17+$25,657= $7,025,614
- Mod P000142015-06-17+$68,056= $7,093,670
- Mod P000152015-06-17+$72,872= $7,166,542
- Mod P000162015-11-18-$1,399= $7,165,143
- Mod P000172016-01-20+$23,724= $7,188,867
- Mod P000182016-02-09-$25,708= $7,163,160
- Mod P000192016-03-30+$0= $7,163,160
- Mod P000202016-12-21+$700,000= $7,863,160
- Mod P000212017-02-09+$261,614= $8,124,773
- Mod P000222017-03-02-$51,339= $8,073,434
- Mod P000232017-03-28-$231= $8,073,203
- Mod P000242017-03-29+$30,053= $8,103,256
- Mod P000252017-04-03+$0= $8,103,256
- Mod P000262017-04-04+$1,499= $8,104,755
- Mod P000272017-04-26-$5,314= $8,099,441
- Mod P000282017-05-10+$0= $8,099,441
- Mod P000292017-05-18+$9,142= $8,108,583
- Mod P000302017-06-06-$1,421= $8,107,162
- Mod P000312017-06-07+$13,538= $8,120,700
- Mod P000322017-08-17+$18,066= $8,138,766
| Transaction | Action date | This action (delta) | Running total | Description on this transaction |
|---|---|---|---|---|
| Base | 2012-09-26 | +$6,819,000 | $6,819,000 | IGF::OT::IGF OTHER FUNCTIONS - PROJECT 646-367 SPD AND SECURITY DOCK. |
| Mod P00006· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2014-03-21 | +$0 | $6,819,000 | TIME EXTENSION - PROJECT 646-367 SPD AND SECURITY DOCK. IGF::OT::IGF |
| Mod P00007· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2014-06-25 | +$94,154 | $6,913,154 | TIME EXTENSION AND ADDITIONA WORK - PROJECT 646-367 SPD AND SECURITY DOCK. IGF::OT::IGF |
| Mod P00010· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2014-10-22 | +$12,496 | $6,925,650 | PROJECT 646-367 SPD AND SECURITY DOCK. IGF::OT::IGF |
| Mod P00011· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2014-12-04 | +$74,307 | $6,999,957 | PROJECT 646-367 SPD AND SECURITY DOCK. IGF::OT::IGF |
| Mod P00012· OTHER ADMINISTRATIVE ACTION | 2014-12-17 | +$0 | $6,999,957 | PROJECT 646-367 SPD AND SECURITY DOCK. CHANGE CO TO MIKE KOONTZ. IGF::OT::IGF |
| Mod P00013· CHANGE ORDER | 2015-06-17 | +$25,657 | $7,025,614 | IGF::OT::IGF MODIFICATION P00013 |
| Mod P00014· CHANGE ORDER | 2015-06-17 | +$68,056 | $7,093,670 | IGF::OT::IGF MODIFICATION P00014 |
| Mod P00015· CHANGE ORDER | 2015-06-17 | +$72,872 | $7,166,542 | IGF::OT::IGF MODIFICATION P00015 |
| Mod P00016· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2015-11-18 | −$1,399 | $7,165,143 | IGF::OT::IGF DELETE COLUMN WRAPS. |
| Mod P00017· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2016-01-20 | +$23,724 | $7,188,867 | IGF::OT::IGF REVISE LIFT 3 FOUNDATIONS. |
| Mod P00018· CHANGE ORDER | 2016-02-09 | −$25,708 | $7,163,160 | IGF::OT::IGF RFCO #125, 126, 128 AND 129 |
| Mod P00019· OTHER ADMINISTRATIVE ACTION | 2016-03-30 | +$0 | $7,163,160 | IGF::OT::IGF CHANGE COR FROM STEVE TO AARON |
| Mod P00020· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2016-12-21 | +$700,000 | $7,863,160 | IGF::OT::IGF SETTLEMENT AGREEMENT FOR INSTALLMENT 1 |
| Mod P00021· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2017-02-09 | +$261,614 | $8,124,773 | IGF::OT::IGF SETTLEMENT AGREEMENT FOR INSTALLMENT 2 |
| Mod P00022· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2017-03-02 | −$51,339 | $8,073,434 | IGF::OT::IGF RFCO'S 132, 133R2, 134, 135 AND 136. |
| Mod P00023· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2017-03-28 | −$231 | $8,073,203 | IGF::OT::IGF RFCO'S 138 AND 139. |
| Mod P00024· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2017-03-29 | +$30,053 | $8,103,256 | IGF::OT::IGF RFCO'S 137, 142 AND 143. |
| Mod P00025· OTHER ADMINISTRATIVE ACTION | 2017-04-03 | +$0 | $8,103,256 | IGF::OT::IGF CHANGE OF ADMINISTRATIVE CONTRACTING OFFICER |
| Mod P00026· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2017-04-04 | +$1,499 | $8,104,755 | IGF::OT::IGF MODIFICATION P00026 RAILING CHANGE |
| Mod P00027· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLIES) | 2017-04-26 | −$5,314 | $8,099,441 | IGF::OT::IGF MODIFICATION P00027 SHEET FLOORING AND LIGHTING CHANGE |
| Mod P00028· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLIES) | 2017-05-10 | +$0 | $8,099,441 | IGF::OT::IGF MODIFICATION P00028 NO COST SCHEDULE EXTENSION |
| Mod P00029· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLIES) | 2017-05-18 | +$9,142 | $8,108,583 | IGF::OT::IGF MODIFICATION P00029 ADD REPAIR OF CONDENSING UNIT VALVE |
| Mod P00030· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLIES) | 2017-06-06 | −$1,421 | $8,107,162 | IGF::OT::IGF MODIFICATION P00030 TO INCORPORATE RFCO 146R1, RFCO 148 AND RFCO 149R1 |
| Mod P00031· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2017-06-07 | +$13,538 | $8,120,700 | IGF::OT::IGF MODIFICATION P00031 TO INCORPORATE RFCO 150 - INSTALL NEW SPRINKLER PIPING IN CORRIDOR E |
| Mod P00032· CHANGE ORDER | 2017-08-17 | +$18,066 | $8,138,766 | IGF::OT::IGF MODIFICATION P00032 TO INCORPORATE RFCO 151 - TIE IN PIPING |
Related awards · 11
Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.
Other VA awards to the same recipient (UEI CZZMSDNWB6J1)
| Award | Office · PSC / listing | Net obligations | FY |
|---|---|---|---|
| VA24413C0160 | 503-ALTOONA · Y1AZ · CONSTRUCTION OF OTHER ADMINISTRATIVE FACILITIES AND SERVICE BUILDINGS | $16,273 | FY2013 |
| VA24413D0470 | 503-ALTOONA · Y1AA · CONSTRUCTION OF OFFICE BUILDINGS | $0 | FY2013 |
| VA24413J1997 | 503-ALTOONA · Y1AA · CONSTRUCTION OF OFFICE BUILDINGS | $0 | FY2013 |
| VA24512C0148 | 613-MARTINSBURG · Y1DZ · CONSTRUCTION OF OTHER HOSPITAL BUILDINGS | $9,811 | FY2012 |
| VA24412C0349 | 503-ALTOONA · Z1DA · MAINTENANCE OF HOSPITALS AND INFIRMARIES | $898,287 | FY2012 |
| VA24412C0307 | 540-CLARKSBURG · Y1DA · CONSTRUCTION OF HOSPITALS AND INFIRMARIES | $3,930,996 | FY2012 |
Other recipients under Z2DA from 244-NETWORK CONTRACT OFFICE 4 (36C244) (most recent first)
| Award | Recipient | Office | Net obligations | FY |
|---|---|---|---|---|
| 36C24426C0059 | J & G SOLUTIONS LLC | 244-NETWORK CONTRACT OFFICE 4 (36C244) | $343,000 | FY2026 |
| 36C24426C0055 | SIGMA GROUP USA LLC | 244-NETWORK CONTRACT OFFICE 4 (36C244) | $30,437 | FY2026 |
| 36C24426N0795 | ANCHOR CONTRACTING, LLC | 244-NETWORK CONTRACT OFFICE 4 (36C244) | $141,228 | FY2026 |
| 36C24426C0053 | HOME MAINTENANCE GROUP LLC | 244-NETWORK CONTRACT OFFICE 4 (36C244) | $58,949 | FY2026 |
| 36C24426C0039 | J & G SOLUTIONS LLC | 244-NETWORK CONTRACT OFFICE 4 (36C244) | $11,600 | FY2026 |
Cite as: Glassbox VA record view · VA contract (USAspending / FPDS) · CONT_AWD_VA24412C0441_3600_-NONE-_-NONE- · retrieved 2026-09-26.