Description
IGF::OT::IGF CHANGE ORDER FOR 4B CONSTRUCTION
Base award description: IGF::OT::IGF OTHER FUNCTIONS - MENTAL HEALTH OUTPATIENT RENOVATION
Modification chain · 12 transactions
Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.
- Base2012-06-25+$2,985,000= $2,985,000
- Mod P000012013-05-15-$1,131= $2,983,869
- Mod P000022013-05-16+$5,825= $2,989,694
- Mod P000032013-06-07+$49,208= $3,038,901
- Mod P000042013-07-30+$92,894= $3,131,795
- Mod P000052013-09-03+$92,075= $3,223,870
- Mod P000062013-09-19+$52,443= $3,276,313
- Mod P000072013-12-23+$52,659= $3,328,972
- Mod P000082014-01-24+$33,324= $3,362,296
- Mod P000092014-04-10+$46,841= $3,409,138
- Mod P000112014-08-13+$48,467= $3,457,605
- Mod P000102014-12-10+$473,391= $3,930,996
| Transaction | Action date | This action (delta) | Running total | Description on this transaction |
|---|---|---|---|---|
| Base | 2012-06-25 | +$2,985,000 | $2,985,000 | IGF::OT::IGF OTHER FUNCTIONS - MENTAL HEALTH OUTPATIENT RENOVATION |
| Mod P00001· CHANGE ORDER | 2013-05-15 | −$1,131 | $2,983,869 | IGF::OT::IGF CHANGE ORDER FOR 4B CONSTRUCTION |
| Mod P00002· CHANGE ORDER | 2013-05-16 | +$5,825 | $2,989,694 | IGF::OT::IGF CHANGE ORDER FOR 4B CONSTRUCTION |
| Mod P00003· CHANGE ORDER | 2013-06-07 | +$49,208 | $3,038,901 | IGF::OT::IGF CHANGE ORDER FOR 4B CONSTRUCTION |
| Mod P00004· CHANGE ORDER | 2013-07-30 | +$92,894 | $3,131,795 | IGF::OT::IGF CHANGE ORDER FOR 4B CONSTRUCTION |
| Mod P00005· CHANGE ORDER | 2013-09-03 | +$92,075 | $3,223,870 | IGF::OT::IGF CHANGE ORDER FOR 4B CONSTRUCTION |
| Mod P00006· CHANGE ORDER | 2013-09-19 | +$52,443 | $3,276,313 | IGF::OT::IGF CHANGE ORDER FOR 4B CONSTRUCTION |
| Mod P00007· CHANGE ORDER | 2013-12-23 | +$52,659 | $3,328,972 | IGF::OT::IGF CHANGE ORDER FOR 4B CONSTRUCTION |
| Mod P00008· CHANGE ORDER | 2014-01-24 | +$33,324 | $3,362,296 | IGF::OT::IGF CHANGE ORDER FOR 4B CONSTRUCTION |
| Mod P00009· CHANGE ORDER | 2014-04-10 | +$46,841 | $3,409,138 | IGF::OT::IGF CHANGE ORDER FOR 4B CONSTRUCTION |
| Mod P00011· CHANGE ORDER | 2014-08-13 | +$48,467 | $3,457,605 | IGF::OT::IGF CHANGE ORDER FOR 4B CONSTRUCTION |
| Mod P00010· CHANGE ORDER | 2014-12-10 | +$473,391 | $3,930,996 | IGF::OT::IGF CHANGE ORDER FOR 4B CONSTRUCTION |
Related awards · 8
Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.
Other VA awards to the same recipient (UEI CZZMSDNWB6J1)
| Award | Office · PSC / listing | Net obligations | FY |
|---|---|---|---|
| VA24413C0160 | 503-ALTOONA · Y1AZ · CONSTRUCTION OF OTHER ADMINISTRATIVE FACILITIES AND SERVICE BUILDINGS | $16,273 | FY2013 |
| VA24413D0470 | 503-ALTOONA · Y1AA · CONSTRUCTION OF OFFICE BUILDINGS | $0 | FY2013 |
| VA24413J1997 | 503-ALTOONA · Y1AA · CONSTRUCTION OF OFFICE BUILDINGS | $0 | FY2013 |
| VA24412C0441 | 244-NETWORK CONTRACT OFFICE 4 (36C244) · Z2DA · REPAIR OR ALTERATION OF HOSPITALS AND INFIRMARIES | $8,138,766 | FY2012 |
| VA24512C0148 | 613-MARTINSBURG · Y1DZ · CONSTRUCTION OF OTHER HOSPITAL BUILDINGS | $9,811 | FY2012 |
| VA24412C0349 | 503-ALTOONA · Z1DA · MAINTENANCE OF HOSPITALS AND INFIRMARIES | $898,287 | FY2012 |
Other recipients under Y1DA from 540-CLARKSBURG (most recent first)
| Award | Recipient | Office | Net obligations | FY |
|---|---|---|---|---|
| VA24413C0208 | BOYKIN CONTRACTING GROUP, INC. | 540-CLARKSBURG | $40,179 | FY2013 |
| VA24412C0085 | DOUGLAS P. FLEMING, LLC | 540-CLARKSBURG | $945,307 | FY2012 |
Cite as: Glassbox VA record view · VA contract (USAspending / FPDS) · CONT_AWD_VA24412C0307_3600_-NONE-_-NONE- · retrieved 2026-09-26.