IGF::OT::IGF SEMI-ANNUAL BOILER TESTING AND INSPECTION
Modification chain · 7 transactions
Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.
- Base2013-05-22+$11,659= $11,659
- Mod P000012014-04-14+$11,856= $23,514
- Mod P000022015-04-27+$12,689= $36,203
- Mod P000032016-05-16+$12,689= $48,891
- Mod P000062016-09-06+$833= $49,724
- Mod P000072017-05-04+$13,719= $63,443
- Mod P000082018-12-10-$20,479= $42,964
| Transaction | Action date | This action (delta) | Running total | Description on this transaction |
|---|---|---|---|---|
| Base | 2013-05-22 | +$11,659 | $11,659 | IGF::OT::IGF SEMI-ANNUAL BOILER TESTING AND INSPECTION |
| Mod P00001· EXERCISE AN OPTION | 2014-04-14 | +$11,856 | $23,514 | IGF::OT::IGF SEMI-ANNUAL BOILER TESTING AND INSPECTION |
| Mod P00002· EXERCISE AN OPTION | 2015-04-27 | +$12,689 | $36,203 | IGF::OT::IGF SEMI-ANNUAL BOILER TESTING AND INSPECTION |
| Mod P00003· EXERCISE AN OPTION | 2016-05-16 | +$12,689 | $48,891 | IGF::OT::IGF SEMI-ANNUAL BOILER TESTING AND INSPECTION |
| Mod P00006· OTHER ADMINISTRATIVE ACTION | 2016-09-06 | +$833 | $49,724 | IGF::OT::IGF SEMI-ANNUAL BOILER TESTING AND INSPECTION |
| Mod P00007· EXERCISE AN OPTION | 2017-05-04 | +$13,719 | $63,443 | IGF::OT::IGF SEMI-ANNUAL BOILER TESTING AND INSPECTION |
| Mod P00008· CLOSE OUT | 2018-12-10 | −$20,479 | $42,964 | IGF::OT::IGF SEMI-ANNUAL BOILER TESTING AND INSPECTION |
Related awards · 8
Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.
Other VA awards to the same recipient (UEI D3E2MBU7MAZ5)
| Award | Office · PSC / listing | Net obligations | FY |
|---|---|---|---|
| 36C24624P0120 | 246-NETWORK CONTRACTING OFFICE 6 (36C246) · H945 · OTHER QC/TEST/INSPECT- PLUMBING, HEATING, AND WASTE DISPOSAL EQUIPMENT | $21,780 | FY2024 |
| 36C24122C0054 | 241-NETWORK CONTRACT OFFICE 01 (36C241) · H945 · OTHER QC/TEST/INSPECT- PLUMBING, HEATING, AND WASTE DISPOSAL EQUIPMENT | $70,200 | FY2022 |
| 36C24721C0088 | 247-NETWORK CONTRACT OFFICE 7 (36C247) · H336 · INSPECTION- SPECIAL INDUSTRY MACHINERY | $19,000 | FY2021 |
| 36C24420P0823 | 244-NETWORK CONTRACT OFFICE 4 (36C244) · J045 · MAINT/REPAIR/REBUILD OF EQUIPMENT- PLUMBING, HEATING, AND WASTE DISPOSAL EQUIPMENT | $0 | FY2020 |
| 36C24120P0663 | 241-NETWORK CONTRACT OFFICE 01 (36C241) · J044 · MAINT/REPAIR/REBUILD OF EQUIPMENT- FURNACE, STEAM PLANT, AND DRYING EQUIPMENT; NUCLEAR REACTORS | $193,120 | FY2020 |
| 36C25520P0455 | 255-NETWORK CONTRACT OFFICE 15 (36C255) · J044 · MAINT/REPAIR/REBUILD OF EQUIPMENT- FURNACE, STEAM PLANT, AND DRYING EQUIPMENT; NUCLEAR REACTORS | $0 | FY2020 |
Other recipients under H344 from 241-NETWORK CONTRACT OFFICE 01 (36C241) (most recent first)
| Award | Recipient | Office | Net obligations | FY |
|---|---|---|---|---|
| 36C24118P1685 | BOILER INSPECTION & ENGINEERING INC | 241-NETWORK CONTRACT OFFICE 01 (36C241) | $2,342 | FY2018 |
| VA24117F1754 | BOILER EFFICIENCY INSTITUTE, LLC | 241-NETWORK CONTRACT OFFICE 01 (36C241) | $4,700 | FY2017 |
Cite as: Glassbox VA record view · VA contract (USAspending / FPDS) · CONT_AWD_VA24113C0135_3600_-NONE-_-NONE- · retrieved 2026-09-26.