Description
IGF::OT::IGF CONSTRUCTION TO CORRECT SEISMIC DEFICIENCIES, BLDG. 100 NURSING TOWER AND COMMUNITY LIVING CENTER, PROJECT NO. 663-406, VA PUGET SOUND HEALTHCARE SYSTEM, SEATTLE DIVISION MODIFICATION P00133 TO DEFINITIZE P00101 AND RESOLVE OUTSTANDING CHANGE ITEMS FOR CLOSE OUT OF CONTRACT
Base award description: CONSTRUCTION TO CORRECT SEISMIC DEFICIENCIES, BLDG. 100 NURSING TOWER AND COMMUNITY LIVING CENTER, PROJECT NO. 663-406, VA PUGET SOUND HEALTHCARE SYSTEM, SEATTLE DIVISION
Modification chain · 104 transactions
Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.
- Base2012-10-10+$30,579,000= $30,579,000
- Mod P000022014-01-02+$98,943= $30,677,943
- Mod P000062014-02-25+$10,972= $30,688,915
- Mod P000032014-02-26+$12,000= $30,700,915
- Mod P000082014-04-18+$37,000= $30,737,915
- Mod P000102014-04-18+$80,000= $30,817,915
- Mod P000112014-04-18+$70,000= $30,887,915
- Mod P000132014-06-03+$78,000= $30,965,915
- Mod P000142014-06-12+$0= $30,965,915
- Mod P000122014-06-27+$18,000= $30,983,915
- Mod P000162014-07-22+$27,167= $31,011,082
- Mod P000152014-07-23+$0= $31,011,082
- Mod P000172014-08-06+$23,274= $31,034,356
- Mod P000182014-08-06+$12,043= $31,046,399
- Mod P000192014-08-06+$4,299= $31,050,698
- Mod P000202014-08-08+$9,148= $31,059,846
- Mod P000212014-08-15+$0= $31,059,846
- Mod P000012014-08-19+$25,961= $31,085,807
- Mod P000052014-09-16+$13,943= $31,099,750
- Mod P000222014-09-30+$44,658= $31,144,408
- Mod P000242014-10-17+$38,339= $31,182,747
- Mod P000252014-10-31+$4,550= $31,187,297
- Mod P000262014-11-03+$9,900= $31,197,197
- Mod P000302014-11-21+$0= $31,197,197
- Mod P000312014-12-12+$26,000= $31,223,197
- Mod P000562014-12-12+$18,500= $31,241,697
- Mod P000492014-12-20+$4,000= $31,245,697
- Mod P000482014-12-30+$6,300= $31,251,997
- Mod P000552014-12-30+$3,821= $31,255,818
- Mod P000592014-12-30+$10,203= $31,266,021
- Mod P000362015-01-22+$13,000= $31,279,021
- Mod P000502015-01-22+$3,471= $31,282,492
- Mod P000512015-01-22+$14,000= $31,296,492
- Mod P000542015-01-22+$16,814= $31,313,306
- Mod P000572015-01-22+$5,200= $31,318,506
- Mod P000582015-01-22+$21,000= $31,339,506
- Mod P000652015-01-22+$20,600= $31,360,106
- Mod P000272015-01-30+$0= $31,360,106
- Mod P000292015-02-25+$18,118= $31,378,224
- Mod P000342015-02-25+$16,000= $31,394,224
- Mod P000402015-02-25+$16,100= $31,410,324
- Mod P000462015-02-25+$4,900= $31,415,224
- Mod P000522015-02-25+$0= $31,415,224
- Mod P000622015-02-25+$10,000= $31,425,224
- Mod P000642015-02-25+$2,162= $31,427,386
- Mod P000772015-03-24+$8,000= $31,435,386
- Mod P000352015-03-31+$68,515= $31,503,901
- Mod P000612015-03-31+$29,985= $31,533,886
- Mod P000672015-04-02+$19,900= $31,553,786
- Mod P000682015-04-28+$4,200= $31,557,986
- Mod P000692015-04-28+$14,734= $31,572,720
- Mod P000702015-04-29+$2,350= $31,575,070
- Mod P000722015-04-29+$4,900= $31,579,970
- Mod P000732015-04-29+$3,746= $31,583,716
- Mod P000792015-04-29+$5,000= $31,588,716
- Mod P000762015-05-08+$7,864= $31,596,580
- Mod P000472015-05-26+$19,000= $31,615,580
- Mod P000802015-07-06+$0= $31,615,580
- Mod P000712015-08-05+$2,100= $31,617,680
- Mod P000742015-08-05+$2,012= $31,619,692
- Mod P000752015-08-05+$37,000= $31,656,692
- Mod P000812015-08-05+$9,000= $31,665,692
- Mod P000822015-08-05+$2,100= $31,667,792
- Mod P000832015-08-05+$1,108= $31,668,900
- Mod P000882015-08-05+$16,038= $31,684,938
- Mod P000912015-08-05+$12,832= $31,697,770
- Mod P000922015-08-05+$10,000= $31,707,770
- Mod P000932015-08-05+$4,262= $31,712,032
- Mod P000942015-08-05+$30,690= $31,742,722
- Mod P000332015-08-31+$0= $31,742,722
- Mod P000952015-08-31+$0= $31,742,722
- Mod P000892015-09-24+$3,500= $31,746,222
- Mod P000962015-09-24+$5,758= $31,751,980
- Mod P000972015-09-24+$10,789= $31,762,769
- Mod P000982015-09-24+$62,758= $31,825,527
- Mod P000992015-09-24+$13,403= $31,838,930
- Mod P001002015-09-24+$95,000= $31,933,930
- Mod P001012015-09-30+$71,412= $32,005,342
- Mod P000452015-12-15+$19,900= $32,025,242
- Mod P001022015-12-15+$55,130= $32,080,372
- Mod P001032015-12-15+$76,314= $32,156,686
- Mod P001042015-12-16+$30,000= $32,186,686
- Mod P001052015-12-21+$70,000= $32,256,686
- Mod P001062015-12-21+$47,000= $32,303,686
- Mod P001082016-03-04+$74,919= $32,378,605
- Mod P001102016-03-04+$73,963= $32,452,568
- Mod P001112016-03-04+$87,827= $32,540,395
- Mod P001072016-03-08-$34,747= $32,505,648
- Mod P001132016-04-08+$15,891= $32,521,539
- Mod P001142016-04-08+$63,528= $32,585,067
- Mod P001152016-04-08+$52,911= $32,637,978
- Mod P001162016-04-08+$92,833= $32,730,811
- Mod P001172016-04-29+$10,269= $32,741,080
- Mod P001182016-04-29+$25,919= $32,766,999
- Mod P001192016-04-29+$99,799= $32,866,798
- Mod P001202016-04-29+$19,978= $32,886,776
- Mod P001212016-04-29+$29,989= $32,916,765
- Mod P001222016-04-29+$99,841= $33,016,606
- Mod P001252016-06-06+$22,529= $33,039,135
- Mod P001262016-06-06+$38,128= $33,077,263
- Mod P001272016-06-06+$79,410= $33,156,673
- Mod P001282016-06-06+$38,128= $33,194,801
- Mod P001292016-07-11+$43,697= $33,238,498
- Mod P001332016-11-21+$427,832= $33,666,330
| Transaction | Action date | This action (delta) | Running total | Description on this transaction |
|---|---|---|---|---|
| Base | 2012-10-10 | +$30,579,000 | $30,579,000 | CONSTRUCTION TO CORRECT SEISMIC DEFICIENCIES, BLDG. 100 NURSING TOWER AND COMMUNITY LIVING CENTER, PROJECT NO.… |
| Mod P00002· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2014-01-02 | +$98,943 | $30,677,943 | IGF::OT::IGF CONSTRUCTION TO CORRECT SEISMIC DEFICIENCIES, PROJECT NO. 663-406, ADDED TASKING IN 7W |
| Mod P00006· CHANGE ORDER | 2014-02-25 | +$10,972 | $30,688,915 | IGF::OT::IGF CONSTRUCTION TO CORRECT SEISMIC DEFICIENCIES, BLDG. 100 NURSING TOWER AND COMMUNITY LIVING CENTER… |
| Mod P00003· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2014-02-26 | +$12,000 | $30,700,915 | IGF::OT::IGF CONSTRUCTION TO CORRECT SEISMIC DEFICIENCIES, BLDG. 100 NURSING TOWER AND COMMUNITY LIVING CENTER… |
| Mod P00008· CHANGE ORDER | 2014-04-18 | +$37,000 | $30,737,915 | IGF::OT::IGF CONSTRUCTION TO CORRECT SEISMIC DEFICIENCIES, BLDG. 100 NURSING TOWER AND COMMUNITY LIVING CENTER… |
| Mod P00010· CHANGE ORDER | 2014-04-18 | +$80,000 | $30,817,915 | IGF::OT::IGF CONSTRUCTION TO CORRECT SEISMIC DEFICIENCIES, BLDG. 100 NURSING TOWER AND COMMUNITY LIVING CENTER… |
| Mod P00011· CHANGE ORDER | 2014-04-18 | +$70,000 | $30,887,915 | IGF::OT::IGF CONSTRUCTION TO CORRECT SEISMIC DEFICIENCIES, BLDG. 100 NURSING TOWER AND COMMUNITY LIVING CENTER… |
| Mod P00013· CHANGE ORDER | 2014-06-03 | +$78,000 | $30,965,915 | IGF::OT::IGF CONSTRUCTION TO CORRECT SEISMIC DEFICIENCIES, BLDG. 100 NURSING TOWER AND COMMUNITY LIVING CENTER… |
| Mod P00014· CHANGE ORDER | 2014-06-12 | +$0 | $30,965,915 | IGF::OT::IGF CONSTRUCTION TO CORRECT SEISMIC DEFICIENCIES, BLDG. 100 NURSING TOWER AND COMMUNITY LIVING CENTER… |
| Mod P00012· CHANGE ORDER | 2014-06-27 | +$18,000 | $30,983,915 | IGF::OT::IGF CONSTRUCTION TO CORRECT SEISMIC DEFICIENCIES, BLDG. 100 NURSING TOWER AND COMMUNITY LIVING CENTER… |
| Mod P00016· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2014-07-22 | +$27,167 | $31,011,082 | IGF::OT::IGF CONSTRUCTION TO CORRECT SEISMIC DEFICIENCIES, BLDG. 100 NURSING TOWER AND COMMUNITY LIVING CENTER… |
| Mod P00015· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2014-07-23 | +$0 | $31,011,082 | IGF::OT::IGF CONSTRUCTION TO CORRECT SEISMIC DEFICIENCIES, BLDG. 100 NURSING TOWER AND COMMUNITY LIVING CENTER… |
| Mod P00017· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2014-08-06 | +$23,274 | $31,034,356 | IGF::OT::IGF CONSTRUCTION TO CORRECT SEISMIC DEFICIENCIES, BLDG. 100 NURSING TOWER AND COMMUNITY LIVING CENTER… |
| Mod P00018· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2014-08-06 | +$12,043 | $31,046,399 | IGF::OT::IGF CONSTRUCTION TO CORRECT SEISMIC DEFICIENCIES, BLDG. 100 NURSING TOWER AND COMMUNITY LIVING CENTER… |
| Mod P00019· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2014-08-06 | +$4,299 | $31,050,698 | IGF::OT::IGF CONSTRUCTION TO CORRECT SEISMIC DEFICIENCIES, BLDG. 100 NURSING TOWER AND COMMUNITY LIVING CENTER… |
| Mod P00020· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2014-08-08 | +$9,148 | $31,059,846 | IGF::OT::IGF CONSTRUCTION TO CORRECT SEISMIC DEFICIENCIES, BLDG. 100 NURSING TOWER AND COMMUNITY LIVING CENTER… |
| Mod P00021· CHANGE ORDER | 2014-08-15 | +$0 | $31,059,846 | IGF::OT::IGF CONSTRUCTION TO CORRECT SEISMIC DEFICIENCIES, BLDG. 100 NURSING TOWER AND COMMUNITY LIVING CENTER… |
| Mod P00001· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2014-08-19 | +$25,961 | $31,085,807 | WORK TO PROVIDE IT INFRASTRUCTURE TO THE RESIDENT ENGINEER TRAILER AS DEFINED IN RFP-0003. IGF::OT::IGF |
| Mod P00005· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2014-09-16 | +$13,943 | $31,099,750 | IGF::OT::IGF CONSTRUCTION TO CORRECT SEISMIC DEFICIENCIES, BLDG. 100 NURSING TOWER AND COMMUNITY LIVING CENTER… |
| Mod P00022· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2014-09-30 | +$44,658 | $31,144,408 | IGF::OT::IGF CONSTRUCTION TO CORRECT SEISMIC DEFICIENCIES, BLDG. 100 NURSING TOWER AND COMMUNITY LIVING CENTER… |
| Mod P00024· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2014-10-17 | +$38,339 | $31,182,747 | IGF::OT::IGF CONSTRUCTION TO CORRECT SEISMIC DEFICIENCIES, BLDG. 100 NURSING TOWER AND COMMUNITY LIVING CENTER… |
| Mod P00025· CHANGE ORDER | 2014-10-31 | +$4,550 | $31,187,297 | IGF::OT::IGF CONSTRUCTION TO CORRECT SEISMIC DEFICIENCIES, BLDG. 100 NURSING TOWER AND COMMUNITY LIVING CENTER… |
| Mod P00026· CHANGE ORDER | 2014-11-03 | +$9,900 | $31,197,197 | IGF::OT::IGF CONSTRUCTION TO CORRECT SEISMIC DEFICIENCIES, BLDG. 100 NURSING TOWER AND COMMUNITY LIVING CENTER… |
| Mod P00030· CHANGE ORDER | 2014-11-21 | +$0 | $31,197,197 | IGF::OT::IGF CONSTRUCTION TO CORRECT SEISMIC DEFICIENCIES, BLDG. 100 NURSING TOWER AND COMMUNITY LIVING CENTER… |
| Mod P00031· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2014-12-12 | +$26,000 | $31,223,197 | IGF::OT::IGF CONSTRUCTION TO CORRECT SEISMIC DEFICIENCIES, BLDG. 100 NURSING TOWER AND COMMUNITY LIVING CENTER… |
| Mod P00056· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2014-12-12 | +$18,500 | $31,241,697 | IGF::OT::IGF CONSTRUCTION TO CORRECT SEISMIC DEFICIENCIES, BLDG. 100 NURSING TOWER AND COMMUNITY LIVING CENTER… |
| Mod P00049· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2014-12-20 | +$4,000 | $31,245,697 | IGF::OT::IGF CONSTRUCTION TO CORRECT SEISMIC DEFICIENCIES, BLDG. 100 NURSING TOWER AND COMMUNITY LIVING CENTER… |
| Mod P00048· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2014-12-30 | +$6,300 | $31,251,997 | IGF::OT::IGF CONSTRUCTION TO CORRECT SEISMIC DEFICIENCIES, BLDG. 100 NURSING TOWER AND COMMUNITY LIVING CENTER… |
| Mod P00055· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2014-12-30 | +$3,821 | $31,255,818 | IGF::OT::IGF CONSTRUCTION TO CORRECT SEISMIC DEFICIENCIES, BLDG. 100 NURSING TOWER AND COMMUNITY LIVING CENTER… |
| Mod P00059· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2014-12-30 | +$10,203 | $31,266,021 | IGF::OT::IGF CONSTRUCTION TO CORRECT SEISMIC DEFICIENCIES, BLDG. 100 NURSING TOWER AND COMMUNITY LIVING CENTER… |
| Mod P00036· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2015-01-22 | +$13,000 | $31,279,021 | IGF::OT::IGF CONSTRUCTION TO CORRECT SEISMIC DEFICIENCIES, BLDG. 100 NURSING TOWER AND COMMUNITY LIVING CENTER… |
| Mod P00050· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2015-01-22 | +$3,471 | $31,282,492 | IGF::OT::IGF CONSTRUCTION TO CORRECT SEISMIC DEFICIENCIES, BLDG. 100 NURSING TOWER AND COMMUNITY LIVING CENTER… |
| Mod P00051· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2015-01-22 | +$14,000 | $31,296,492 | IGF::OT::IGF CONSTRUCTION TO CORRECT SEISMIC DEFICIENCIES, BLDG. 100 NURSING TOWER AND COMMUNITY LIVING CENTER… |
| Mod P00054· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2015-01-22 | +$16,814 | $31,313,306 | IGF::OT::IGF CONSTRUCTION TO CORRECT SEISMIC DEFICIENCIES, BLDG. 100 NURSING TOWER AND COMMUNITY LIVING CENTER… |
| Mod P00057· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2015-01-22 | +$5,200 | $31,318,506 | IGF::OT::IGF CONSTRUCTION TO CORRECT SEISMIC DEFICIENCIES, BLDG. 100 NURSING TOWER AND COMMUNITY LIVING CENTER… |
| Mod P00058· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2015-01-22 | +$21,000 | $31,339,506 | IGF::OT::IGF CONSTRUCTION TO CORRECT SEISMIC DEFICIENCIES, BLDG. 100 NURSING TOWER AND COMMUNITY LIVING CENTER… |
| Mod P00065· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2015-01-22 | +$20,600 | $31,360,106 | IGF::OT::IGF CONSTRUCTION TO CORRECT SEISMIC DEFICIENCIES, BLDG. 100 NURSING TOWER AND COMMUNITY LIVING CENTER… |
| Mod P00027· CHANGE ORDER | 2015-01-30 | +$0 | $31,360,106 | IGF::OT::IGF CONSTRUCTION TO CORRECT SEISMIC DEFICIENCIES, BLDG. 100 NURSING TOWER AND COMMUNITY LIVING CENTER… |
| Mod P00029· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2015-02-25 | +$18,118 | $31,378,224 | IGF::OT::IGF CONSTRUCTION TO CORRECT SEISMIC DEFICIENCIES, BLDG. 100 NURSING TOWER AND COMMUNITY LIVING CENTER… |
| Mod P00034· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2015-02-25 | +$16,000 | $31,394,224 | IGF::OT::IGF CONSTRUCTION TO CORRECT SEISMIC DEFICIENCIES, BLDG. 100 NURSING TOWER AND COMMUNITY LIVING CENTER… |
| Mod P00040· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2015-02-25 | +$16,100 | $31,410,324 | IGF::OT::IGF CONSTRUCTION TO CORRECT SEISMIC DEFICIENCIES, BLDG. 100 NURSING TOWER AND COMMUNITY LIVING CENTER… |
| Mod P00046· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2015-02-25 | +$4,900 | $31,415,224 | IGF::OT::IGF CONSTRUCTION TO CORRECT SEISMIC DEFICIENCIES, BLDG. 100 NURSING TOWER AND COMMUNITY LIVING CENTER… |
| Mod P00052· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2015-02-25 | +$0 | $31,415,224 | IGF::OT::IGF CONSTRUCTION TO CORRECT SEISMIC DEFICIENCIES, BLDG. 100 NURSING TOWER AND COMMUNITY LIVING CENTER… |
| Mod P00062· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2015-02-25 | +$10,000 | $31,425,224 | IGF::OT::IGF CONSTRUCTION TO CORRECT SEISMIC DEFICIENCIES, BLDG. 100 NURSING TOWER AND COMMUNITY LIVING CENTER… |
| Mod P00064· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2015-02-25 | +$2,162 | $31,427,386 | IGF::OT::IGF CONSTRUCTION TO CORRECT SEISMIC DEFICIENCIES, BLDG. 100 NURSING TOWER AND COMMUNITY LIVING CENTER… |
| Mod P00077· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2015-03-24 | +$8,000 | $31,435,386 | IGF::OT::IGF CONSTRUCTION TO CORRECT SEISMIC DEFICIENCIES, BLDG. 100 NURSING TOWER AND COMMUNITY LIVING CENTER… |
| Mod P00035· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2015-03-31 | +$68,515 | $31,503,901 | IGF::OT::IGF CONSTRUCTION TO CORRECT SEISMIC DEFICIENCIES, BLDG. 100 NURSING TOWER AND COMMUNITY LIVING CENTER… |
| Mod P00061· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2015-03-31 | +$29,985 | $31,533,886 | IGF::OT::IGF CONSTRUCTION TO CORRECT SEISMIC DEFICIENCIES, BLDG. 100 NURSING TOWER AND COMMUNITY LIVING CENTER… |
| Mod P00067· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2015-04-02 | +$19,900 | $31,553,786 | IGF::OT::IGF CONSTRUCTION TO CORRECT SEISMIC DEFICIENCIES, BLDG. 100 NURSING TOWER AND COMMUNITY LIVING CENTER… |
| Mod P00068· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2015-04-28 | +$4,200 | $31,557,986 | IGF::OT::IGF CONSTRUCTION TO CORRECT SEISMIC DEFICIENCIES, BLDG. 100 NURSING TOWER AND COMMUNITY LIVING CENTER… |
| Mod P00069· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2015-04-28 | +$14,734 | $31,572,720 | IGF::OT::IGF CONSTRUCTION TO CORRECT SEISMIC DEFICIENCIES, BLDG. 100 NURSING TOWER AND COMMUNITY LIVING CENTER… |
| Mod P00070· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2015-04-29 | +$2,350 | $31,575,070 | IGF::OT::IGF CONSTRUCTION TO CORRECT SEISMIC DEFICIENCIES, BLDG. 100 NURSING TOWER AND COMMUNITY LIVING CENTER… |
| Mod P00072· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2015-04-29 | +$4,900 | $31,579,970 | IGF::OT::IGF CONSTRUCTION TO CORRECT SEISMIC DEFICIENCIES, BLDG. 100 NURSING TOWER AND COMMUNITY LIVING CENTER… |
| Mod P00073· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2015-04-29 | +$3,746 | $31,583,716 | IGF::OT::IGF CONSTRUCTION TO CORRECT SEISMIC DEFICIENCIES, BLDG. 100 NURSING TOWER AND COMMUNITY LIVING CENTER… |
| Mod P00079· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2015-04-29 | +$5,000 | $31,588,716 | IGF::OT::IGF CONSTRUCTION TO CORRECT SEISMIC DEFICIENCIES, BLDG. 100 NURSING TOWER AND COMMUNITY LIVING CENTER… |
| Mod P00076· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2015-05-08 | +$7,864 | $31,596,580 | IGF::OT::IGF CONSTRUCTION TO CORRECT SEISMIC DEFICIENCIES, BLDG. 100 NURSING TOWER AND COMMUNITY LIVING CENTER… |
| Mod P00047· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2015-05-26 | +$19,000 | $31,615,580 | IGF::OT::IGF CONSTRUCTION TO CORRECT SEISMIC DEFICIENCIES, BLDG. 100 NURSING TOWER AND COMMUNITY LIVING CENTER… |
| Mod P00080· OTHER ADMINISTRATIVE ACTION | 2015-07-06 | +$0 | $31,615,580 | CONSTRUCTION TO CORRECT SEISMIC DEFICIENCIES, BLDG. 100 NURSING TOWER AND COMMUNITY LIVING CENTER, PROJECT NO.… |
| Mod P00071· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2015-08-05 | +$2,100 | $31,617,680 | IGF::OT::IGF CONSTRUCTION TO CORRECT SEISMIC DEFICIENCIES, BLDG. 100 NURSING TOWER AND COMMUNITY LIVING CENTER… |
| Mod P00074· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2015-08-05 | +$2,012 | $31,619,692 | IGF::OT::IGF CONSTRUCTION TO CORRECT SEISMIC DEFICIENCIES, BLDG. 100 NURSING TOWER AND COMMUNITY LIVING CENTER… |
| Mod P00075· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2015-08-05 | +$37,000 | $31,656,692 | IGF::OT::IGF CONSTRUCTION TO CORRECT SEISMIC DEFICIENCIES, BLDG. 100 NURSING TOWER AND COMMUNITY LIVING CENTER… |
| Mod P00081· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2015-08-05 | +$9,000 | $31,665,692 | IGF::OT::IGF CONSTRUCTION TO CORRECT SEISMIC DEFICIENCIES, BLDG. 100 NURSING TOWER AND COMMUNITY LIVING CENTER… |
| Mod P00082· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2015-08-05 | +$2,100 | $31,667,792 | IGF::OT::IGF CONSTRUCTION TO CORRECT SEISMIC DEFICIENCIES, BLDG. 100 NURSING TOWER AND COMMUNITY LIVING CENTER… |
| Mod P00083· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2015-08-05 | +$1,108 | $31,668,900 | IGF::OT::IGF CONSTRUCTION TO CORRECT SEISMIC DEFICIENCIES, BLDG. 100 NURSING TOWER AND COMMUNITY LIVING CENTER… |
| Mod P00088· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2015-08-05 | +$16,038 | $31,684,938 | IGF::OT::IGF CONSTRUCTION TO CORRECT SEISMIC DEFICIENCIES, BLDG. 100 NURSING TOWER AND COMMUNITY LIVING CENTER… |
| Mod P00091· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2015-08-05 | +$12,832 | $31,697,770 | IGF::OT::IGF CONSTRUCTION TO CORRECT SEISMIC DEFICIENCIES, BLDG. 100 NURSING TOWER AND COMMUNITY LIVING CENTER… |
| Mod P00092· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2015-08-05 | +$10,000 | $31,707,770 | IGF::OT::IGF CONSTRUCTION TO CORRECT SEISMIC DEFICIENCIES, BLDG. 100 NURSING TOWER AND COMMUNITY LIVING CENTER… |
| Mod P00093· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2015-08-05 | +$4,262 | $31,712,032 | IGF::OT::IGF CONSTRUCTION TO CORRECT SEISMIC DEFICIENCIES, BLDG. 100 NURSING TOWER AND COMMUNITY LIVING CENTER… |
| Mod P00094· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2015-08-05 | +$30,690 | $31,742,722 | IGF::OT::IGF CONSTRUCTION TO CORRECT SEISMIC DEFICIENCIES, BLDG. 100 NURSING TOWER AND COMMUNITY LIVING CENTER… |
| Mod P00033· CHANGE ORDER | 2015-08-31 | +$0 | $31,742,722 | CONSTRUCTION TO CORRECT SEISMIC DEFICIENCIES, BLDG. 100 NURSING TOWER AND COMMUNITY LIVING CENTER, PROJECT NO.… |
| Mod P00095· CHANGE ORDER | 2015-08-31 | +$0 | $31,742,722 | CONSTRUCTION TO CORRECT SEISMIC DEFICIENCIES, BLDG. 100 NURSING TOWER AND COMMUNITY LIVING CENTER, PROJECT NO.… |
| Mod P00089· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2015-09-24 | +$3,500 | $31,746,222 | IGF::OT::IGF CONSTRUCTION TO CORRECT SEISMIC DEFICIENCIES, BLDG. 100 NURSING TOWER AND COMMUNITY LIVING CENTER… |
| Mod P00096· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2015-09-24 | +$5,758 | $31,751,980 | IGF::OT::IGF CONSTRUCTION TO CORRECT SEISMIC DEFICIENCIES, BLDG. 100 NURSING TOWER AND COMMUNITY LIVING CENTER… |
| Mod P00097· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2015-09-24 | +$10,789 | $31,762,769 | IGF::OT::IGF CONSTRUCTION TO CORRECT SEISMIC DEFICIENCIES, BLDG. 100 NURSING TOWER AND COMMUNITY LIVING CENTER… |
| Mod P00098· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2015-09-24 | +$62,758 | $31,825,527 | IGF::OT::IGF CONSTRUCTION TO CORRECT SEISMIC DEFICIENCIES, BLDG. 100 NURSING TOWER AND COMMUNITY LIVING CENTER… |
| Mod P00099· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2015-09-24 | +$13,403 | $31,838,930 | IGF::OT::IGF CONSTRUCTION TO CORRECT SEISMIC DEFICIENCIES, BLDG. 100 NURSING TOWER AND COMMUNITY LIVING CENTER… |
| Mod P00100· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2015-09-24 | +$95,000 | $31,933,930 | CONSTRUCTION TO CORRECT SEISMIC DEFICIENCIES, BLDG. 100 NURSING TOWER AND COMMUNITY LIVING CENTER, PROJECT NO.… |
| Mod P00101· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2015-09-30 | +$71,412 | $32,005,342 | CONSTRUCTION TO CORRECT SEISMIC DEFICIENCIES, BLDG. 100 NURSING TOWER AND COMMUNITY LIVING CENTER, PROJECT NO.… |
| Mod P00045· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2015-12-15 | +$19,900 | $32,025,242 | IGF::OT::IGF CONSTRUCTION TO CORRECT SEISMIC DEFICIENCIES, BLDG. 100 NURSING TOWER AND COMMUNITY LIVING CENTER… |
| Mod P00102· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2015-12-15 | +$55,130 | $32,080,372 | IGF::OT::IGF CONSTRUCTION TO CORRECT SEISMIC DEFICIENCIES, BLDG. 100 NURSING TOWER AND COMMUNITY LIVING CENTER… |
| Mod P00103· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2015-12-15 | +$76,314 | $32,156,686 | IGF::OT::IGF CONSTRUCTION TO CORRECT SEISMIC DEFICIENCIES, BLDG. 100 NURSING TOWER AND COMMUNITY LIVING CENTER… |
| Mod P00104· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2015-12-16 | +$30,000 | $32,186,686 | IGF::OT::IGF CONSTRUCTION TO CORRECT SEISMIC DEFICIENCIES, BLDG. 100 NURSING TOWER AND COMMUNITY LIVING CENTER… |
| Mod P00105· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2015-12-21 | +$70,000 | $32,256,686 | IGF::OT::IGF CONSTRUCTION TO CORRECT SEISMIC DEFICIENCIES, BLDG. 100 NURSING TOWER AND COMMUNITY LIVING CENTER… |
| Mod P00106· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2015-12-21 | +$47,000 | $32,303,686 | IGF::OT::IGF CONSTRUCTION TO CORRECT SEISMIC DEFICIENCIES, BLDG. 100 NURSING TOWER AND COMMUNITY LIVING CENTER… |
| Mod P00108· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2016-03-04 | +$74,919 | $32,378,605 | IGF::OT::IGF CONSTRUCTION TO CORRECT SEISMIC DEFICIENCIES, BLDG. 100 NURSING TOWER AND COMMUNITY LIVING CENTER… |
| Mod P00110· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2016-03-04 | +$73,963 | $32,452,568 | IGF::OT::IGF CONSTRUCTION TO CORRECT SEISMIC DEFICIENCIES, BLDG. 100 NURSING TOWER AND COMMUNITY LIVING CENTER… |
| Mod P00111· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2016-03-04 | +$87,827 | $32,540,395 | IGF::OT::IGF CONSTRUCTION TO CORRECT SEISMIC DEFICIENCIES, BLDG. 100 NURSING TOWER AND COMMUNITY LIVING CENTER… |
| Mod P00107· OTHER ADMINISTRATIVE ACTION | 2016-03-08 | −$34,747 | $32,505,648 | CONSTRUCTION TO CORRECT SEISMIC DEFICIENCIES, BLDG. 100 NURSING TOWER AND COMMUNITY LIVING CENTER, PROJECT NO.… |
| Mod P00113· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2016-04-08 | +$15,891 | $32,521,539 | IGF::OT::IGF CONSTRUCTION TO CORRECT SEISMIC DEFICIENCIES, BLDG. 100 NURSING TOWER AND COMMUNITY LIVING CENTER… |
| Mod P00114· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2016-04-08 | +$63,528 | $32,585,067 | IGF::OT::IGF CONSTRUCTION TO CORRECT SEISMIC DEFICIENCIES, BLDG. 100 NURSING TOWER AND COMMUNITY LIVING CENTER… |
| Mod P00115· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2016-04-08 | +$52,911 | $32,637,978 | IGF::OT::IGF CONSTRUCTION TO CORRECT SEISMIC DEFICIENCIES, BLDG. 100 NURSING TOWER AND COMMUNITY LIVING CENTER… |
| Mod P00116· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2016-04-08 | +$92,833 | $32,730,811 | IGF::OT::IGF CONSTRUCTION TO CORRECT SEISMIC DEFICIENCIES, BLDG. 100 NURSING TOWER AND COMMUNITY LIVING CENTER… |
| Mod P00117· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2016-04-29 | +$10,269 | $32,741,080 | IGF::OT::IGF CONSTRUCTION TO CORRECT SEISMIC DEFICIENCIES, BLDG. 100 NURSING TOWER AND COMMUNITY LIVING CENTER… |
| Mod P00118· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2016-04-29 | +$25,919 | $32,766,999 | IGF::OT::IGF CONSTRUCTION TO CORRECT SEISMIC DEFICIENCIES, BLDG. 100 NURSING TOWER AND COMMUNITY LIVING CENTER… |
| Mod P00119· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2016-04-29 | +$99,799 | $32,866,798 | IGF::OT::IGF CONSTRUCTION TO CORRECT SEISMIC DEFICIENCIES, BLDG. 100 NURSING TOWER AND COMMUNITY LIVING CENTER… |
| Mod P00120· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2016-04-29 | +$19,978 | $32,886,776 | IGF::OT::IGF CONSTRUCTION TO CORRECT SEISMIC DEFICIENCIES, BLDG. 100 NURSING TOWER AND COMMUNITY LIVING CENTER… |
| Mod P00121· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2016-04-29 | +$29,989 | $32,916,765 | IGF::OT::IGF CONSTRUCTION TO CORRECT SEISMIC DEFICIENCIES, BLDG. 100 NURSING TOWER AND COMMUNITY LIVING CENTER… |
| Mod P00122· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2016-04-29 | +$99,841 | $33,016,606 | IGF::OT::IGF CONSTRUCTION TO CORRECT SEISMIC DEFICIENCIES, BLDG. 100 NURSING TOWER AND COMMUNITY LIVING CENTER… |
| Mod P00125· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2016-06-06 | +$22,529 | $33,039,135 | IGF::OT::IGF CONSTRUCTION TO CORRECT SEISMIC DEFICIENCIES, BLDG. 100 NURSING TOWER AND COMMUNITY LIVING CENTER… |
| Mod P00126· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2016-06-06 | +$38,128 | $33,077,263 | IGF::OT::IGF CONSTRUCTION TO CORRECT SEISMIC DEFICIENCIES, BLDG. 100 NURSING TOWER AND COMMUNITY LIVING CENTER… |
| Mod P00127· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2016-06-06 | +$79,410 | $33,156,673 | IGF::OT::IGF CONSTRUCTION TO CORRECT SEISMIC DEFICIENCIES, BLDG. 100 NURSING TOWER AND COMMUNITY LIVING CENTER… |
| Mod P00128· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2016-06-06 | +$38,128 | $33,194,801 | IGF::OT::IGF CONSTRUCTION TO CORRECT SEISMIC DEFICIENCIES, BLDG. 100 NURSING TOWER AND COMMUNITY LIVING CENTER… |
| Mod P00129· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2016-07-11 | +$43,697 | $33,238,498 | IGF::OT::IGF CONSTRUCTION TO CORRECT SEISMIC DEFICIENCIES, BLDG. 100 NURSING TOWER AND COMMUNITY LIVING CENTER… |
| Mod P00133· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2016-11-21 | +$427,832 | $33,666,330 | IGF::OT::IGF CONSTRUCTION TO CORRECT SEISMIC DEFICIENCIES, BLDG. 100 NURSING TOWER AND COMMUNITY LIVING CENTER… |
Related awards · 6
Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.
Other VA awards to the same recipient (UEI N64NCQ58JL25)
| Award | Office · PSC / listing | Net obligations | FY |
|---|---|---|---|
| 36C10F23C0007 | OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F) · Y1DA · CONSTRUCTION OF HOSPITALS AND INFIRMARIES | $215,172,226 | FY2023 |
Other recipients under Y1DA from OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F) (most recent first)
| Award | Recipient | Office | Net obligations | FY |
|---|---|---|---|---|
| 36C10F26C0014 | PROJECT MANAGEMENT SOLUTIONS LLC | OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F) | $2,229,000 | FY2026 |
| 36C10F26C0013 | V&C GENERAL CONTRACTOR LLC | OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F) | $2,518,650 | FY2026 |
| 36C10F23N0064 | SSPC LLC | OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F) | $421,407 | FY2023 |
| 36C10F23C0003 | DAV ENERGY SOLUTIONS, INC. | OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F) | $175,181 | FY2023 |
| 36C10F22N0055 | SPUR DESIGN, LLC | OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F) | $963,203 | FY2022 |
Cite as: Glassbox VA record view · VA contract (USAspending / FPDS) · CONT_AWD_VA101F13C0005_3600_-NONE-_-NONE- · retrieved 2026-09-26.