Award recordCONTRACT

BRASFIELD & GORRIE LLC

PIID VA101CFMC0163· VA Staff Offices· OFFICE OF CONSTRUCTION & FACILITIES MANAGEMENT· Y141 · CONSTRUCT/HOSPITALS & INFIRMARIES· FY2010· $38,132,520 net obligations· UEI TWVGJRMK6Z78· AL

Description

SA-171, DELETE REMAINING SITE CONCRETE

Base award description: PARKING

First action · last action
2009-11-09 · 2014-06-16
Transactions
157
First transaction's obligation
$29,953,159
Base + all options value (sum of deltas)
$38,132,520
Extent competed
FULL AND OPEN COMPETITION
Other than full & open authority
—
Set-aside
NO SET ASIDE USED.
Offers received
18
SDVOSB flag on record
No
NAICS
236220 · COMMERCIAL AND INSTITUTIONAL BUILDING CONSTRUCTION

Modification chain · 157 transactions

Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.

$38,173,852$0Base award · 2009-11-09 · this action $29,953,159 · running total $29,953,159Modification SA001 · 2010-02-18 · this action $2,513 · running total $29,955,672Modification CO01E · 2010-03-03 · this action $543,998 · running total $30,499,670Modification SA002 · 2010-03-08 · this action $99,939 · running total $30,599,609Modification SA003 · 2010-03-30 · this action $99,939 · running total $30,699,548Modification SA004 · 2010-04-06 · this action $99,995 · running total $30,799,543Modification SA005 · 2010-04-06 · this action $82,133 · running total $30,881,676Modification SA006 · 2010-04-09 · this action $15,184 · running total $30,896,860Modification SA008 · 2010-05-05 · this action $5,249 · running total $30,902,109Modification SA009 · 2010-05-05 · this action $0 · running total $30,902,109Modification SA010 · 2010-05-05 · this action $783 · running total $30,902,892Modification SA012 · 2010-05-05 · this action $2,025 · running total $30,904,917Modification SA014 · 2010-05-05 · this action $6,613 · running total $30,911,530Modification SA015 · 2010-05-11 · this action $2,316 · running total $30,913,846Modification SA016 · 2010-05-14 · this action $35,427 · running total $30,949,273Modification SA017 · 2010-05-14 · this action $4,107 · running total $30,953,380Modification SA018 · 2010-05-18 · this action $6,530 · running total $30,959,910Modification SA019 · 2010-05-24 · this action $8,335 · running total $30,968,245Modification SA20 · 2010-05-24 · this action $1,015 · running total $30,969,260Modification SA22 · 2010-06-16 · this action $1,239 · running total $30,970,499Modification SA23 · 2010-06-16 · this action $21,069 · running total $30,991,568Modification SA24 · 2010-06-25 · this action $955 · running total $30,992,523Modification SA25 · 2010-06-25 · this action $24,471 · running total $31,016,994Modification SA26 · 2010-06-25 · this action $97,874 · running total $31,114,868Modification SA27 · 2010-06-28 · this action $15,123 · running total $31,129,991Modification SA011 · 2010-08-06 · this action $2,266 · running total $31,132,257Modification SA030 · 2010-08-11 · this action -$27,801 · running total $31,104,456Modification SA031 · 2010-08-11 · this action $2,712 · running total $31,107,168Modification SA032 · 2010-09-16 · this action $14,995 · running total $31,122,163Modification SA033 · 2010-09-16 · this action $12,161 · running total $31,134,324Modification SA035 · 2010-09-23 · this action -$398 · running total $31,133,926Modification SA041 · 2010-11-04 · this action $0 · running total $31,133,926Modification SA036 · 2010-11-05 · this action $4,313,003 · running total $35,446,929Modification SA007 · 2010-11-24 · this action $2,242 · running total $35,449,171Modification SA046 · 2011-02-04 · this action $36,472 · running total $35,485,643Modification SA047 · 2011-02-09 · this action $11,430 · running total $35,497,073Modification SA048 · 2011-02-09 · this action $14,094 · running total $35,511,167Modification SA049 · 2011-02-10 · this action $10,718 · running total $35,521,885Modification SA050 · 2011-02-10 · this action $12,161 · running total $35,534,046Modification SA052 · 2011-02-10 · this action $66,588 · running total $35,600,634Modification SA053 · 2011-02-10 · this action $39,533 · running total $35,640,167Modification SA056 · 2011-04-15 · this action $9,571 · running total $35,649,738Modification SA057 · 2011-04-15 · this action $1,145 · running total $35,650,883Modification SA058 · 2011-04-15 · this action $4,976 · running total $35,655,859Modification SA059 · 2011-04-15 · this action -$8,290 · running total $35,647,569Modification SA060 · 2011-04-15 · this action -$7,773 · running total $35,639,796Modification SA054 · 2011-04-27 · this action $24,849 · running total $35,664,645Modification SA055 · 2011-04-27 · this action $2,863 · running total $35,667,508Modification SA037 · 2011-05-03 · this action $35,864 · running total $35,703,372Modification SA038 · 2011-05-03 · this action $31,442 · running total $35,734,814Modification SA039 · 2011-05-03 · this action $19,378 · running total $35,754,192Modification SA040 · 2011-05-03 · this action $70,359 · running total $35,824,551Modification SA042 · 2011-05-03 · this action $17,251 · running total $35,841,802Modification SA043 · 2011-05-03 · this action $16,797 · running total $35,858,599Modification SA044 · 2011-05-03 · this action $5,778 · running total $35,864,377Modification SA045 · 2011-05-03 · this action $2,152 · running total $35,866,529Modification SA062 · 2011-06-16 · this action $24,108 · running total $35,890,637Modification SA063 · 2011-06-16 · this action $2,098 · running total $35,892,735Modification SA064 · 2011-06-16 · this action $3,149 · running total $35,895,884Modification SA065 · 2011-06-16 · this action $5,464 · running total $35,901,348Modification SA066 · 2011-06-16 · this action $12,152 · running total $35,913,500Modification SA067 · 2011-06-16 · this action $7,637 · running total $35,921,137Modification SA068 · 2011-06-16 · this action $3,079 · running total $35,924,216Modification SA069 · 2011-06-16 · this action $31,015 · running total $35,955,231Modification SA061 · 2011-06-22 · this action $15,464 · running total $35,970,695Modification SA070 · 2011-07-21 · this action $1,111 · running total $35,971,806Modification SA071 · 2011-07-21 · this action $3,967 · running total $35,975,773Modification SA072 · 2011-07-21 · this action $6,205 · running total $35,981,978Modification SA073 · 2011-07-21 · this action $3,556 · running total $35,985,534Modification SA074 · 2011-07-21 · this action $4,464 · running total $35,989,998Modification SA075 · 2011-07-21 · this action $1,263 · running total $35,991,261Modification SA078 · 2011-07-22 · this action $21,990 · running total $36,013,251Modification SA079 · 2011-08-14 · this action $21,010 · running total $36,034,261Modification SA081 · 2011-08-14 · this action $3,923 · running total $36,038,184Modification SA080 · 2011-08-21 · this action $11,581 · running total $36,049,765Modification SA082 · 2011-08-21 · this action $28,611 · running total $36,078,376Modification SA083 · 2011-08-21 · this action $3,614 · running total $36,081,990Modification SA084 · 2011-08-24 · this action $8,706 · running total $36,090,696Modification SA085 · 2011-08-24 · this action $2,701 · running total $36,093,397Modification SA076 · 2011-08-26 · this action $474,019 · running total $36,567,416Modification SA077 · 2011-08-26 · this action $333,318 · running total $36,900,734Modification SA086 · 2011-08-28 · this action $0 · running total $36,900,734Modification SA087 · 2011-09-05 · this action $4,844 · running total $36,905,578Modification SA088 · 2011-09-05 · this action $26,816 · running total $36,932,394Modification SA089 · 2011-09-05 · this action -$17,450 · running total $36,914,944Modification SA090 · 2011-09-05 · this action $9,987 · running total $36,924,931Modification SA091 · 2011-09-05 · this action $4,606 · running total $36,929,537Modification SA092 · 2011-10-01 · this action $5,785 · running total $36,935,322Modification SA093 · 2011-10-01 · this action $19,213 · running total $36,954,535Modification SA094 · 2011-10-01 · this action $4,980 · running total $36,959,515Modification SA095 · 2011-10-01 · this action $1,458 · running total $36,960,973Modification SA096 · 2011-10-01 · this action $2,251 · running total $36,963,224Modification SA097 · 2011-11-11 · this action $17,047 · running total $36,980,271Modification SA098 · 2011-11-11 · this action $5,383 · running total $36,985,654Modification SA099 · 2011-11-11 · this action $4,588 · running total $36,990,242Modification SA100 · 2011-11-11 · this action $9,544 · running total $36,999,786Modification SA101 · 2011-11-11 · this action $1,565 · running total $37,001,351Modification SA102 · 2011-11-11 · this action $19,272 · running total $37,020,623Modification SA103 · 2011-11-11 · this action -$3,770 · running total $37,016,853Modification SA104 · 2011-11-11 · this action $3,689 · running total $37,020,542Modification SA105 · 2011-12-19 · this action $21,805 · running total $37,042,347Modification SA106 · 2011-12-19 · this action $5,929 · running total $37,048,276Modification SA107 · 2011-12-19 · this action $6,563 · running total $37,054,839Modification SA108 · 2011-12-19 · this action $2,051 · running total $37,056,890Modification SA109 · 2011-12-19 · this action $7,768 · running total $37,064,658Modification SA110 · 2012-02-04 · this action $4,163 · running total $37,068,821Modification SA111 · 2012-02-04 · this action $34,734 · running total $37,103,555Modification SA112 · 2012-02-04 · this action $23,374 · running total $37,126,929Modification SA113 · 2012-02-04 · this action $54,274 · running total $37,181,203Modification SA114 · 2012-02-04 · this action $36,438 · running total $37,217,641Modification SA115 · 2012-02-04 · this action $50,755 · running total $37,268,396Modification SA116 · 2012-02-04 · this action $27,415 · running total $37,295,811Modification SA118 · 2012-02-04 · this action $4,293 · running total $37,300,104Modification SA119 · 2012-02-14 · this action $284,446 · running total $37,584,550Modification SA120 · 2012-02-18 · this action $3,930 · running total $37,588,480Modification SA121 · 2012-02-18 · this action $1,139 · running total $37,589,619Modification SA122 · 2012-02-18 · this action $2,863 · running total $37,592,482Modification SA123 · 2012-02-18 · this action $10,646 · running total $37,603,128Modification SA124 · 2012-02-18 · this action $76,534 · running total $37,679,662Modification SA125 · 2012-02-18 · this action $2,573 · running total $37,682,235Modification SA126 · 2012-02-18 · this action $19,169 · running total $37,701,404Modification SA127 · 2012-02-18 · this action $2,054 · running total $37,703,458Modification SA128 · 2012-03-18 · this action $2,967 · running total $37,706,425Modification SA133 · 2012-03-18 · this action $5,957 · running total $37,712,382Modification SA134 · 2012-03-18 · this action $5,477 · running total $37,717,859Modification SA129 · 2012-03-20 · this action $4,872 · running total $37,722,731Modification SA130 · 2012-03-20 · this action $6,431 · running total $37,729,162Modification SA131 · 2012-03-20 · this action $1,020 · running total $37,730,182Modification SA132 · 2012-03-20 · this action $6,181 · running total $37,736,363Modification SA135 · 2012-03-31 · this action $36,115 · running total $37,772,478Modification SA117 · 2012-04-02 · this action $99,017 · running total $37,871,495Modification SA137 · 2012-04-14 · this action $8,664 · running total $37,880,159Modification SA138 · 2012-04-14 · this action $2,188 · running total $37,882,347Modification SA136 · 2012-04-16 · this action $5,074 · running total $37,887,421Modification SA139 · 2012-04-16 · this action $35,101 · running total $37,922,522Modification SA140 · 2012-05-12 · this action $24,886 · running total $37,947,408Modification SA141 · 2012-05-12 · this action $1,976 · running total $37,949,384Modification SA142 · 2012-05-12 · this action $2,256 · running total $37,951,640Modification SA143 · 2012-05-12 · this action $1,450 · running total $37,953,090Modification SA144 · 2012-05-27 · this action $36,681 · running total $37,989,771Modification SA145 · 2012-05-27 · this action $5,271 · running total $37,995,042Modification SA146 · 2012-05-27 · this action $1,652 · running total $37,996,694Modification SA147 · 2012-05-27 · this action $1,510 · running total $37,998,204Modification SA148 · 2012-05-27 · this action $1,132 · running total $37,999,336Modification SA149 · 2012-05-27 · this action $3,090 · running total $38,002,426Modification SA151 · 2012-05-27 · this action $5,210 · running total $38,007,636Modification SA150 · 2012-05-29 · this action $3,628 · running total $38,011,264Modification SA152 · 2012-07-07 · this action $38,555 · running total $38,049,819Modification SA153 · 2012-07-07 · this action $2,655 · running total $38,052,474Modification SA154 · 2012-07-07 · this action $4,187 · running total $38,056,661Modification SA155 · 2012-07-07 · this action $137 · running total $38,056,798Modification SA156 · 2012-07-07 · this action $308 · running total $38,057,106Modification P00005 · 2013-09-23 · this action $2,827 · running total $38,059,933Modification P00007 · 2013-09-26 · this action $48,392 · running total $38,108,325Modification P00002 · 2014-06-16 · this action $1,376 · running total $38,109,701Modification P00004 · 2014-06-16 · this action $64,151 · running total $38,173,852Modification P00006 · 2014-06-16 · this action -$41,332 · running total $38,132,520
  • Base2009-11-09+$29,953,159= $29,953,159
  • Mod SA0012010-02-18+$2,513= $29,955,672
  • Mod CO01E2010-03-03+$543,998= $30,499,670
  • Mod SA0022010-03-08+$99,939= $30,599,609
  • Mod SA0032010-03-30+$99,939= $30,699,548
  • Mod SA0042010-04-06+$99,995= $30,799,543
  • Mod SA0052010-04-06+$82,133= $30,881,676
  • Mod SA0062010-04-09+$15,184= $30,896,860
  • Mod SA0082010-05-05+$5,249= $30,902,109
  • Mod SA0092010-05-05+$0= $30,902,109
  • Mod SA0102010-05-05+$783= $30,902,892
  • Mod SA0122010-05-05+$2,025= $30,904,917
  • Mod SA0142010-05-05+$6,613= $30,911,530
  • Mod SA0152010-05-11+$2,316= $30,913,846
  • Mod SA0162010-05-14+$35,427= $30,949,273
  • Mod SA0172010-05-14+$4,107= $30,953,380
  • Mod SA0182010-05-18+$6,530= $30,959,910
  • Mod SA0192010-05-24+$8,335= $30,968,245
  • Mod SA202010-05-24+$1,015= $30,969,260
  • Mod SA222010-06-16+$1,239= $30,970,499
  • Mod SA232010-06-16+$21,069= $30,991,568
  • Mod SA242010-06-25+$955= $30,992,523
  • Mod SA252010-06-25+$24,471= $31,016,994
  • Mod SA262010-06-25+$97,874= $31,114,868
  • Mod SA272010-06-28+$15,123= $31,129,991
  • Mod SA0112010-08-06+$2,266= $31,132,257
  • Mod SA0302010-08-11-$27,801= $31,104,456
  • Mod SA0312010-08-11+$2,712= $31,107,168
  • Mod SA0322010-09-16+$14,995= $31,122,163
  • Mod SA0332010-09-16+$12,161= $31,134,324
  • Mod SA0352010-09-23-$398= $31,133,926
  • Mod SA0412010-11-04+$0= $31,133,926
  • Mod SA0362010-11-05+$4,313,003= $35,446,929
  • Mod SA0072010-11-24+$2,242= $35,449,171
  • Mod SA0462011-02-04+$36,472= $35,485,643
  • Mod SA0472011-02-09+$11,430= $35,497,073
  • Mod SA0482011-02-09+$14,094= $35,511,167
  • Mod SA0492011-02-10+$10,718= $35,521,885
  • Mod SA0502011-02-10+$12,161= $35,534,046
  • Mod SA0522011-02-10+$66,588= $35,600,634
  • Mod SA0532011-02-10+$39,533= $35,640,167
  • Mod SA0562011-04-15+$9,571= $35,649,738
  • Mod SA0572011-04-15+$1,145= $35,650,883
  • Mod SA0582011-04-15+$4,976= $35,655,859
  • Mod SA0592011-04-15-$8,290= $35,647,569
  • Mod SA0602011-04-15-$7,773= $35,639,796
  • Mod SA0542011-04-27+$24,849= $35,664,645
  • Mod SA0552011-04-27+$2,863= $35,667,508
  • Mod SA0372011-05-03+$35,864= $35,703,372
  • Mod SA0382011-05-03+$31,442= $35,734,814
  • Mod SA0392011-05-03+$19,378= $35,754,192
  • Mod SA0402011-05-03+$70,359= $35,824,551
  • Mod SA0422011-05-03+$17,251= $35,841,802
  • Mod SA0432011-05-03+$16,797= $35,858,599
  • Mod SA0442011-05-03+$5,778= $35,864,377
  • Mod SA0452011-05-03+$2,152= $35,866,529
  • Mod SA0622011-06-16+$24,108= $35,890,637
  • Mod SA0632011-06-16+$2,098= $35,892,735
  • Mod SA0642011-06-16+$3,149= $35,895,884
  • Mod SA0652011-06-16+$5,464= $35,901,348
  • Mod SA0662011-06-16+$12,152= $35,913,500
  • Mod SA0672011-06-16+$7,637= $35,921,137
  • Mod SA0682011-06-16+$3,079= $35,924,216
  • Mod SA0692011-06-16+$31,015= $35,955,231
  • Mod SA0612011-06-22+$15,464= $35,970,695
  • Mod SA0702011-07-21+$1,111= $35,971,806
  • Mod SA0712011-07-21+$3,967= $35,975,773
  • Mod SA0722011-07-21+$6,205= $35,981,978
  • Mod SA0732011-07-21+$3,556= $35,985,534
  • Mod SA0742011-07-21+$4,464= $35,989,998
  • Mod SA0752011-07-21+$1,263= $35,991,261
  • Mod SA0782011-07-22+$21,990= $36,013,251
  • Mod SA0792011-08-14+$21,010= $36,034,261
  • Mod SA0812011-08-14+$3,923= $36,038,184
  • Mod SA0802011-08-21+$11,581= $36,049,765
  • Mod SA0822011-08-21+$28,611= $36,078,376
  • Mod SA0832011-08-21+$3,614= $36,081,990
  • Mod SA0842011-08-24+$8,706= $36,090,696
  • Mod SA0852011-08-24+$2,701= $36,093,397
  • Mod SA0762011-08-26+$474,019= $36,567,416
  • Mod SA0772011-08-26+$333,318= $36,900,734
  • Mod SA0862011-08-28+$0= $36,900,734
  • Mod SA0872011-09-05+$4,844= $36,905,578
  • Mod SA0882011-09-05+$26,816= $36,932,394
  • Mod SA0892011-09-05-$17,450= $36,914,944
  • Mod SA0902011-09-05+$9,987= $36,924,931
  • Mod SA0912011-09-05+$4,606= $36,929,537
  • Mod SA0922011-10-01+$5,785= $36,935,322
  • Mod SA0932011-10-01+$19,213= $36,954,535
  • Mod SA0942011-10-01+$4,980= $36,959,515
  • Mod SA0952011-10-01+$1,458= $36,960,973
  • Mod SA0962011-10-01+$2,251= $36,963,224
  • Mod SA0972011-11-11+$17,047= $36,980,271
  • Mod SA0982011-11-11+$5,383= $36,985,654
  • Mod SA0992011-11-11+$4,588= $36,990,242
  • Mod SA1002011-11-11+$9,544= $36,999,786
  • Mod SA1012011-11-11+$1,565= $37,001,351
  • Mod SA1022011-11-11+$19,272= $37,020,623
  • Mod SA1032011-11-11-$3,770= $37,016,853
  • Mod SA1042011-11-11+$3,689= $37,020,542
  • Mod SA1052011-12-19+$21,805= $37,042,347
  • Mod SA1062011-12-19+$5,929= $37,048,276
  • Mod SA1072011-12-19+$6,563= $37,054,839
  • Mod SA1082011-12-19+$2,051= $37,056,890
  • Mod SA1092011-12-19+$7,768= $37,064,658
  • Mod SA1102012-02-04+$4,163= $37,068,821
  • Mod SA1112012-02-04+$34,734= $37,103,555
  • Mod SA1122012-02-04+$23,374= $37,126,929
  • Mod SA1132012-02-04+$54,274= $37,181,203
  • Mod SA1142012-02-04+$36,438= $37,217,641
  • Mod SA1152012-02-04+$50,755= $37,268,396
  • Mod SA1162012-02-04+$27,415= $37,295,811
  • Mod SA1182012-02-04+$4,293= $37,300,104
  • Mod SA1192012-02-14+$284,446= $37,584,550
  • Mod SA1202012-02-18+$3,930= $37,588,480
  • Mod SA1212012-02-18+$1,139= $37,589,619
  • Mod SA1222012-02-18+$2,863= $37,592,482
  • Mod SA1232012-02-18+$10,646= $37,603,128
  • Mod SA1242012-02-18+$76,534= $37,679,662
  • Mod SA1252012-02-18+$2,573= $37,682,235
  • Mod SA1262012-02-18+$19,169= $37,701,404
  • Mod SA1272012-02-18+$2,054= $37,703,458
  • Mod SA1282012-03-18+$2,967= $37,706,425
  • Mod SA1332012-03-18+$5,957= $37,712,382
  • Mod SA1342012-03-18+$5,477= $37,717,859
  • Mod SA1292012-03-20+$4,872= $37,722,731
  • Mod SA1302012-03-20+$6,431= $37,729,162
  • Mod SA1312012-03-20+$1,020= $37,730,182
  • Mod SA1322012-03-20+$6,181= $37,736,363
  • Mod SA1352012-03-31+$36,115= $37,772,478
  • Mod SA1172012-04-02+$99,017= $37,871,495
  • Mod SA1372012-04-14+$8,664= $37,880,159
  • Mod SA1382012-04-14+$2,188= $37,882,347
  • Mod SA1362012-04-16+$5,074= $37,887,421
  • Mod SA1392012-04-16+$35,101= $37,922,522
  • Mod SA1402012-05-12+$24,886= $37,947,408
  • Mod SA1412012-05-12+$1,976= $37,949,384
  • Mod SA1422012-05-12+$2,256= $37,951,640
  • Mod SA1432012-05-12+$1,450= $37,953,090
  • Mod SA1442012-05-27+$36,681= $37,989,771
  • Mod SA1452012-05-27+$5,271= $37,995,042
  • Mod SA1462012-05-27+$1,652= $37,996,694
  • Mod SA1472012-05-27+$1,510= $37,998,204
  • Mod SA1482012-05-27+$1,132= $37,999,336
  • Mod SA1492012-05-27+$3,090= $38,002,426
  • Mod SA1512012-05-27+$5,210= $38,007,636
  • Mod SA1502012-05-29+$3,628= $38,011,264
  • Mod SA1522012-07-07+$38,555= $38,049,819
  • Mod SA1532012-07-07+$2,655= $38,052,474
  • Mod SA1542012-07-07+$4,187= $38,056,661
  • Mod SA1552012-07-07+$137= $38,056,798
  • Mod SA1562012-07-07+$308= $38,057,106
  • Mod P000052013-09-23+$2,827= $38,059,933
  • Mod P000072013-09-26+$48,392= $38,108,325
  • Mod P000022014-06-16+$1,376= $38,109,701
  • Mod P000042014-06-16+$64,151= $38,173,852
  • Mod P000062014-06-16-$41,332= $38,132,520
TransactionAction dateThis action (delta)Running totalDescription on this transaction
Base2009-11-09+$29,953,159$29,953,159PARKING
Mod SA001· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-02-18+$2,513$29,955,672MODIFY WAREHOUSE SHOWER VALVES
Mod CO01E· EXERCISE AN OPTION2010-03-03+$543,998$30,499,670EXERCISE OPTIONS
Mod SA002· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-03-08+$99,939$30,599,609ELEVATOR CHANGES, PARKING
Mod SA003· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-03-30+$99,939$30,699,548PAYMENT OF PRESCAST MEMBERS OFF SITE
Mod SA004· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-04-06+$99,995$30,799,543WAREHOUSE EXTERIOR
Mod SA005· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-04-06+$82,133$30,881,676INTERIOR CHANGES, WAREHOUSE
Mod SA006· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-04-09+$15,184$30,896,860REVISED CIVIL DRAWINGS
Mod SA008· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-05-05+$5,249$30,902,109WAREHOUSE STRUCTURAL COORDINATION
Mod SA009· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-05-05+$0$30,902,109PRECAST COLUMN CLAR, NO CHANGE DOLLARS OR TIME
Mod SA010· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-05-05+$783$30,902,892REVISED DUCT CONNECTION
Mod SA012· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-05-05+$2,025$30,904,917HALL STATION CONTROLS WAREHOUSE
Mod SA014· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-05-05+$6,613$30,911,530EMERGENCY EROSION CONTROL MEASURE REPAIR
Mod SA015· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-05-11+$2,316$30,913,846PARTNERING
Mod SA016· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-05-14+$35,427$30,949,273WAREHOUSE DOOR REVISIONS
Mod SA017· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-05-14+$4,107$30,953,380WAREHOUSE ELEVATOR LOBBY REVISIONS
Mod SA018· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-05-18+$6,530$30,959,910ADD BID OPTIONS ADDITIONAL GARAGE LEVELS
Mod SA019· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-05-24+$8,335$30,968,245MECHANICAL COORDINATION WAREHOUSE
Mod SA20· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-05-24+$1,015$30,969,260EXTERIOR LIGHT REVISIONS
Mod SA22· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-06-16+$1,239$30,970,499SANITARY SLOPE AND ROUTING
Mod SA23· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-06-16+$21,069$30,991,568CONNECTION COORDINATION
Mod SA24· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-06-25+$955$30,992,523ARCH COORD WAREHOUSE
Mod SA25· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-06-25+$24,471$31,016,994SWEEPING & INLET PROTECTION
Mod SA26· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-06-25+$97,874$31,114,868NORTH PROPERTY LINE STABILIZATION
Mod SA27· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-06-28+$15,123$31,129,991ELECTRIAL DRAWING CLAR
Mod SA011· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-08-06+$2,266$31,132,257ELEVATOR STRUCTURAL REVISIONS
Mod SA030· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-08-11−$27,801$31,104,456ELECTRIAL DRAWING CLAR ELEVATOR CONTROL CREDIT
Mod SA031· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-08-11+$2,712$31,107,168ELECTRIAL DRAWING CLAR TILT UP PANEL CONNECTION
Mod SA032· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-09-16+$14,995$31,122,163DOOR COORDINATION
Mod SA033· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-09-16+$12,161$31,134,324FLAMMABLE STORAGE REVISION
Mod SA035· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-09-23−$398$31,133,926WAREHOUSE ACCESS PANELS
Mod SA041· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-11-04+$0$31,133,926PAYMENT OF SITE MATERIAL PG METALS
Mod SA036· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-11-05+$4,313,003$35,446,929PARKING GARAGES, LEVEL 4
Mod SA007· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-11-24+$2,242$35,449,171THE PURPOSE OF THIS SA IS TO REIMBURSE ANY ADMINISTRATIVE COST THE CONTRACTOR AND HIS SUBCONTRACTORS INCURRED…
Mod SA046· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-02-04+$36,472$35,485,643DUCT BANK CONFLICT
Mod SA047· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-02-09+$11,430$35,497,073DUCT BANK T15(A)CONFLICT
Mod SA048· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-02-09+$14,094$35,511,167REVISIONS POWER CIRCUITS
Mod SA049· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-02-10+$10,718$35,521,885ELECTRICAL POWER REVISIONS
Mod SA050· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-02-10+$12,161$35,534,046WH EQUIPMENT STARTERS
Mod SA052· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-02-10+$66,588$35,600,634PRECAST CHANGES
Mod SA053· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-02-10+$39,533$35,640,167PARTITION REVISION
Mod SA056· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI2011-04-15+$9,571$35,649,738EXTERIOR GLASS
Mod SA057· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI2011-04-15+$1,145$35,650,883DUPLEX RECEPTACLE
Mod SA058· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI2011-04-15+$4,976$35,655,859ADD WALL
Mod SA059· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI2011-04-15−$8,290$35,647,569CHANGE HARDWARE
Mod SA060· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI2011-04-15−$7,773$35,639,796CREDIT MATERIAL DUCT BANK
Mod SA054· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-04-27+$24,849$35,664,645CURTAIN WALL AS PER THE RESPONSE AND SKETCH PROVIDED WITH RFI 316.
Mod SA055· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-04-27+$2,863$35,667,508DDC DEVICE LOCATIONS AND CLARIFY POWER REQUIREMENTS AS PER THE RESPONSE TO RFI #213.
Mod SA037· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-05-03+$35,864$35,703,372ADDITIONAL JOINTS IN THE EAST AND WEST PARKING GARAGE AS DESCRIBED IN RFI 155 AND 184.
Mod SA038· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-05-03+$31,442$35,734,814PROVIDE ALL LABOR, MATERIALS, AND EQUIPMENT TO PROVIDE REINFORCEMENT IN WASH BACKS AND AROUND FLOOR DRAINS IN…
Mod SA039· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-05-03+$19,378$35,754,192REVISED SPECIFICATIONS 08 71 00 DATED 06/22/10 AND RFI RESPONSE 182.
Mod SA040· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-05-03+$70,359$35,824,551STRUCTURAL AND ARCHITECTURAL REVISIONS TO THE WAREHOUSE CURTAINWALLS ON DRAWINGS DATED 06/22/10.
Mod SA042· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-05-03+$17,251$35,841,802CMU WALL REINFORCING AS DESCRIBED IN RFI RESPONSE #217.
Mod SA043· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-05-03+$16,797$35,858,599ENCASE WITH CONCRETE THE DUCTBANK THAT CONNECTS THE EAST AND WEST PARKING GARAGES.
Mod SA044· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-05-03+$5,778$35,864,377INSTALL VAPOR SHIELD DRY-IN WITH "WRAP SHIELD" IN AREAS WHERE METAL PANELS ARE TO BE INSTALLED.
Mod SA045· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-05-03+$2,152$35,866,529BRUSHED STAINLESS STEEL CLAD PANELS PER MARKED SHOP DRAWINGS (14 24 00 W 04R1).
Mod SA062· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-06-16+$24,108$35,890,637STORM PIPE CONFLICT WITH EXISTING UTILITIES AS DESCRIBED IN RFI 314.
Mod SA063· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-06-16+$2,098$35,892,735HAND RAIL.
Mod SA064· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-06-16+$3,149$35,895,884MECHANICAL AND ELECTRICAL
Mod SA065· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-06-16+$5,464$35,901,348PAINT STRUCTURE/MEP IN SHADED AREAS OF 2ND FLOOR NOT SHOWN ON THE CONTRACT DOCUMENTS.
Mod SA066· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-06-16+$12,152$35,913,500DWGS TITLED CPR D-0048 DATED 02/02/11 ISSUED WITH RFP D-0053
Mod SA067· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-06-16+$7,637$35,921,137COMMUNICATIONS BLOCK
Mod SA068· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-06-16+$3,079$35,924,216HVAC OPENINGS AS A RESULT OF RFI 179.
Mod SA069· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-06-16+$31,015$35,955,231VC TO CC
Mod SA061· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-06-22+$15,464$35,970,695WAREHOUSE LEVEL 3 DECK EDGE ANGLE
Mod SA070· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-07-21+$1,111$35,971,806DRYWALL TRANSITION
Mod SA071· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-07-21+$3,967$35,975,773EXTERIOR SHEATHING AT SOFFITS.
Mod SA072· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-07-21+$6,205$35,981,978FLUID APPLIED FLOORING
Mod SA073· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-07-21+$3,556$35,985,534WAREHOUSE DOOR PLATE
Mod SA074· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-07-21+$4,464$35,989,998STAIRWELL STUDS
Mod SA075· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-07-21+$1,263$35,991,261STIFFENER PLATES
Mod SA078· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-07-22+$21,990$36,013,251ADD CARD READERS
Mod SA079· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-08-14+$21,010$36,034,261INCORPORATE OWNER REQUESTED CHANGES
Mod SA081· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-08-14+$3,923$36,038,184ADD SPECIFICATION
Mod SA080· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-08-21+$11,581$36,049,765INSTALL CONFLICT BOX WHERE 24" STORM CONFLICTS WITH 6" STEAM
Mod SA082· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-08-21+$28,611$36,078,376REVISE TOILET COMPARTMENTS
Mod SA083· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-08-21+$3,614$36,081,990POWER DOOR OPERATORS
Mod SA084· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-08-24+$8,706$36,090,696REINFORCING
Mod SA085· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-08-24+$2,701$36,093,397COVER PLATES
Mod SA076· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-08-26+$474,019$36,567,416PROVIDE ALL LABOR, MATERIALS, AND EQUPMENT TO PROVIDE TEMPORARY/PERMANENT POWER TO THE WAREHOUSE AND PG ACCOMO…
Mod SA077· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-08-26+$333,318$36,900,734PROVIDE ALL LABOR, MATERIALS, AND EQUIPMENT TO CORRECT ELECTRICAL DEFICIENCIES THAT WERE NOT CORRECTED BY THE…
Mod SA086· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-08-28+$0$36,900,734INCORPORATE DRAWINGS PROVIDED WITH RFP D-0048 INTO THE CONTRACT DRAWINGS, BECAUSE OF DIMENSION CHANGES DURING…
Mod SA087· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-09-05+$4,844$36,905,578LID TIE-IN
Mod SA088· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-09-05+$26,816$36,932,394METAL WALL PANELS AND SUPPORT
Mod SA089· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-09-05−$17,450$36,914,944PROVIDE CREDIT FOR OVAL DUCT THAT NEEDED FIELD REPAIR DUE TO POOR FABRICATION.
Mod SA090· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-09-05+$9,987$36,924,931CHANGE FINISH OF WAREHOUSE SITE WALL TO PROVIDE CONSISTENCY TO CAMPUS FINISHES.
Mod SA091· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-09-05+$4,606$36,929,537REVISE FIRE ALARM FIXTURE MOUNTING LOCATIONS
Mod SA092· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-10-01+$5,785$36,935,322CIRCUIT BREAKERS
Mod SA093· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-10-01+$19,213$36,954,535STARTERS
Mod SA094· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-10-01+$4,980$36,959,515ELECTRICAL AND ARCHITECTURAL
Mod SA095· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-10-01+$1,458$36,960,973CONDENSATE PUMP
Mod SA096· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-10-01+$2,251$36,963,224JAMB DOOR
Mod SA097· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-11-11+$17,047$36,980,271ADD ADDITIONAL SUPPORT TO THE LOUVERS
Mod SA098· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-11-11+$5,383$36,985,654ADD ADDITIONAL ANGLE
Mod SA099· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-11-11+$4,588$36,990,242REROUTE PIPING
Mod SA100· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-11-11+$9,544$36,999,786LOWER THE RECLAIM IRRIGATION LINE BECAUSE INCORRECTLY INSTALLED BY A PREVIOUS PACKAGE.
Mod SA101· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-11-11+$1,565$37,001,351PROVIDE CORRECT HARDWARE FOR GATE BECAUSE NONE WAS SHOWN ON THE CONTRACT DRAWINGS
Mod SA102· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-11-11+$19,272$37,020,623PROVIDE ADDITONAL GENERATOR RENTAL
Mod SA103· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-11-11−$3,770$37,016,853CREDIT FOR STAIN IN LIEU OF COLORED CONCRETE.
Mod SA104· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-11-11+$3,689$37,020,542CALK CEILING GRID
Mod SA105· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-12-19+$21,805$37,042,347REVISE WH SANITARY LINE TO AVOID CONFLICT WITH SITE WALL FOUNDATION.
Mod SA106· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-12-19+$5,929$37,048,276CHIP UNDER EXISTING DUCT BANK IN CONFLICT WITH SANITARY INSTALLATION.
Mod SA107· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-12-19+$6,563$37,054,839ADD PROTECTION TO CURTAIN WALL ALONG MEZZANINE LEVEL IN ADDITON RELOCATE DRAIN THAT IS CLOSE TO STAIRS.
Mod SA108· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-12-19+$2,051$37,056,890ADD EMERGENCY POWER TO THE SMS AND CCTV BECAUSE IT WAS OMMITTED FROM THE CONTRAT DRAWINGS.
Mod SA109· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-12-19+$7,768$37,064,658PROVIDE REVISED CONNECTIONS TO WH ELEVATOR SUMP PUMPS BECAUSE THEY WERE INCORRECTLY SHOWN ON THE CONTRACT DRAW…
Mod SA110· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2012-02-04+$4,163$37,068,821REVISE PIT LADDER AND GUARDRAIL TO COMPLY WITH OSHA 1910.23 (A) (2) AND 1926.1053 (A) (13) AND AN EXIT SIGN TO…
Mod SA111· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2012-02-04+$34,734$37,103,555NCLUDE THE INTERIOR, ARCHITECTURAL, AND ELECTRICAL DRAWINGS TO ADD BASE, CORNER GUARDS, AND DISCONNECT SWITCH…
Mod SA112· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2012-02-04+$23,374$37,126,929NCLUDE ELECTRICAL DRAWINGS TO ADD POWER FOR THE DRYER FOR 3 AIR COMPRESSORS. THIS POWER REQUIREMENT WAS OMITT…
Mod SA113· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2012-02-04+$54,274$37,181,203INCLUDE MECHANICAL AND ELECTRICAL DRAWINGS TO ADD A STEAM TRAP MONITOR. THIS MONITOR WAS LOCATED IN EVERY OTH…
Mod SA114· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2012-02-04+$36,438$37,217,641MODIFY THE PIT LIGHTS TO PROVIDE ADEQUATE FOOT CANDLES.
Mod SA115· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2012-02-04+$50,755$37,268,396ADD 800A DISCONNECT AS PER THE REPOSNE TO RFI 554 BECAUSE THE DISTANCE BETWEEN THE TRANSFORMER AND PANEL EXCEE…
Mod SA116· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2012-02-04+$27,415$37,295,811PROVIDE EMERGENCY GENERATORS TO WAREHOUSE AND PG UNTIL ADJACENT CEP IS PUT INTO OPERATION.
Mod SA118· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2012-02-04+$4,293$37,300,104INCORPORATE CUSTOM COLOR BECASUE AE CHANGED EXTERIOR COLORS TO COORDINATE WITH REST OF CAMPUS THAT WAS STILL I…
Mod SA119· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2012-02-14+$284,446$37,584,550PROVIDE TEMPORARY BOILER AND CHILLER UNTIL ADJACENT CEP IS OPERATION SO MC CAN TAKE EARLY OCCUPENCY AND UTILIZ…
Mod SA120· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2012-02-18+$3,930$37,588,480PROVIDE SOLID PANEL AT MAN GATE BECUASE THE GATE IS UNSECURE PER RESPONSE TO RFI 597.
Mod SA121· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2012-02-18+$1,139$37,589,619PROVIDE TWO STEAM CATHODIC DIELECTRIC ISOLATORS THAT WERE OMITTED FROM PACKAGE 1A PER THE RESPONSE TO RFI 549.
Mod SA122· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2012-02-18+$2,863$37,592,482UPGRADE FLUID APPLIED FLOORING TO ACCOMODATE SOG MOISTURE CONTENT.
Mod SA123· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2012-02-18+$10,646$37,603,128UPGRADE LOUVER FINSIH TO PROVIDE A LONGER WARRANTY.
Mod SA124· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2012-02-18+$76,534$37,679,662PROVIDE ALL LABOR, MATERIALS, AND EQUIPMENT TO POWDER COAT THE WAREHOUSE CANOPY. COLOR AS SELECTED VIA EMAIL…
Mod SA125· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2012-02-18+$2,573$37,682,235INCLUDE REVISED ELECTRICAL DRAWINGS TO ADD DATA DROPS IN THE ELEVATOR MACHINE ROOMS TO ACCOMMODATE THE ELEVATO…
Mod SA126· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2012-02-18+$19,169$37,701,404UPGRADE SEALER IN SUBSTATION ROOMS AND ELECTRICAL ROOMS TO PROVIDE ADDITIONAL DURABILITY. APPLY SEALER TO STA…
Mod SA127· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2012-02-18+$2,054$37,703,458ADD ANGLE ALONG SLAB EDGE AT SCISSOR LIFT, THIS ANGLE WAS OMITTED FROM CONTRACTO DOCUMENTS. TOTAL COST OF THI…
Mod SA128· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2012-03-18+$2,967$37,706,425CHANGE PARTION TYPE TO SHAFT WALL, BECAUSE ORIGINAL DETAIL WAS UNCONSTRUCTABLE.
Mod SA133· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2012-03-18+$5,957$37,712,382PROVIDE AN ELEVATOR OPERATOR SO THE FACILITY CAN MOVE FURNITURE IN EARLY.
Mod SA134· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2012-03-18+$5,477$37,717,859ADD WOOD NAILER TO CANOPY EDGE DETAILS AND INSULATION TO ACCOMODATE WOOD NAILER BECAUSE THERE WAS INSUFFICIENT…
Mod SA129· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2012-03-20+$4,872$37,722,731CHANGE WALL TYPE TO SHAFT WALL BECAUSE OF UNCONSTRUCTABLE CONDITIONS.
Mod SA130· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2012-03-20+$6,431$37,729,162PROVIDE DETAIL AS PROVIDED IN THE RESPONSE TO RFI 328, THIS DETAIL WAS OMITTED FROM THE CONTRACT DOCUMENTS.
Mod SA131· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2012-03-20+$1,020$37,730,182PER THE RESPOSNE TO RFI 341 ADD CORNER GUARDS TO COLUMNS, THESE COLUMNS DID NOT SHOW TO HAVE GUARDS SHOWN ON T…
Mod SA132· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2012-03-20+$6,181$37,736,363COORDINATE THE SHADE POCKET WITH REVISIONS TO THE CURTAIN WALL, DETAILS WERE OMMITTED FROM THE CONTRACT DRAWIN…
Mod SA135· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2012-03-31+$36,115$37,772,478RELOCATE THE GREASE TRAP TO SHORTEN THE LINE DISTANCE AND REDUCE THE RISK OF CLOGS AND UNWANTED MAINTANENCE.
Mod SA117· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2012-04-02+$99,017$37,871,495PERFORM MOISTURE MITIGATION TO ENSURE PROPER ADHESION OF RESILIENT FLOORING.
Mod SA137· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2012-04-14+$8,664$37,880,159THIS RE OFFICE REQUESTED THE CONTRACTOR TO RESTRING ONE OF THE BARRIER CABLES IN THE PARKING GARAGE BECAUSE TH…
Mod SA138· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2012-04-14+$2,188$37,882,347PROVIDE ADDITIONAL SUPPORT TO TOILET PARTITIONS BECAUSE AS DESIGNED AND INSTALLED THERE WAS INSUFFICIENT SUPPO…
Mod SA136· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2012-04-16+$5,074$37,887,421ADD A SLOT DRAIN AT THE TOP LEVEL RAMP IN BOTH GARAGES BECAUSE OF THE AMOUNT OF WATER THAT ACCUMULATES AT THES…
Mod SA139· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2012-04-16+$35,101$37,922,522ADD MIDPOINT CONNECTION TO SOUTH CURTAIN WALL THAT WAS NOT SHOWN ON THE DRAWINGS. COMPENSATE CONTRACTOR FOR R…
Mod SA140· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2012-05-12+$24,886$37,947,408PROVIDE A PROPOSAL TO INCLUDE ALL LABOR, MATERIALS, AND EQUIPMENT TO INCORPORATE THOSE RESPONSES TO RFIS 32, 3…
Mod SA141· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2012-05-12+$1,976$37,949,384PROVIDE STAINLESS STEEL DOOR IN LIUE OF ALUMINUM AS SHOWN ON THE DOOR SCHEDULE AND PROVIDED IN THE RESPONSE TO…
Mod SA142· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2012-05-12+$2,256$37,951,640INCREASE THE SIZE OF THE DAMPER AND GRILL SIZE BECASUE IT IS NECCESSARY TO RELOCATE BECAUSE OF CONFLICT WITH T…
Mod SA143· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2012-05-12+$1,450$37,953,090ADD A FAUX MULLION AT THE GAP BETWEEN THE GLASS AND STAIR, BECAUSE THERE WAS NO DETAIL ON THE DRAWING TO ADDRE…
Mod SA144· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2012-05-27+$36,681$37,989,771RELOCATE ELECTRICAL COMPONENTS AS A RESULT OF THE JOIST SPACING BEING REVISED TO WITHSTAND THE LOAD OF THE EQU…
Mod SA145· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2012-05-27+$5,271$37,995,042ADD TILT PANEL CONNECTIONS TO ACCOMODATE THE GEOMETRY CHANGE IN PANELS
Mod SA146· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2012-05-27+$1,652$37,996,694CHANGE EXHAUST FAN TYPE DURING SUBMITTAL REVIEW BECASUE THE WRONG ONE WAS SHOWON ON THE SCHEDULE.
Mod SA147· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2012-05-27+$1,510$37,998,204ADD FALL PROTECTION TO SMALL MECHANICAL UTILITY ROOF TO COMPLY WITH OSHA. TOTAL COST OF THIS CHANGE: $1,510.…
Mod SA148· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2012-05-27+$1,132$37,999,336PROVIDE ADDITIONAL INSULATION AT THE PG SUBSTATION ROOMS BECASUE THE INSULLATION SPECIFIED IN INSUFFICIENT TO…
Mod SA149· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2012-05-27+$3,090$38,002,426PROVIDE ALUMINUM SHEET CLOSURES TO STAIRWELL CURTAIN FRAME THAT WERE NOT SHOWN ON DRAWINGS.
Mod SA151· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2012-05-27+$5,210$38,007,636MAKE MODIFICAITON TO FA TO COMPLETE INSTALLATION AND BE IN COMPLIANCE FOR BUILDING OCCUPANCY. THESE DEVICES W…
Mod SA150· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2012-05-29+$3,628$38,011,264ADD CAPABILITY FOR FA DIRECT SHUT DOWNOF AHU'S IN FIRE ALARM EVENT, THIS SEQUENCE WAS NOT IDENTIFIED ON CONTAC…
Mod SA152· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2012-07-07+$38,555$38,049,819INCORPORATE REVISIONS TO HVAC, ELECTRICAL, AND ARCHITECTURAL DRAWINGS THAT AFFECT THE ELEVATORS THAT WERE DEEM…
Mod SA153· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2012-07-07+$2,655$38,052,474PROVDE ADDITIONAL FIRE ALARMS NEEDED THAT WERE NOT SHOWN ON THE DRAWINGS.
Mod SA154· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2012-07-07+$4,187$38,056,661ADD SENSORS THAT WERE NOT SHOWN ON THE DRAWINGS AS A RESULT OF RFI 141.
Mod SA155· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2012-07-07+$137$38,056,798EXTEND CHAIN HOIST BEAM BECAUSE OF CONFLICT WITH FINSIH CEILING.
Mod SA156· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2012-07-07+$308$38,057,106ADD REDUCERS TO DUCT TIE IN BECAUSE IT WAS IMPROPERLY SHOWN ON THE DRAWINGS.
Mod P00005· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2013-09-23+$2,827$38,059,933SA-170, RFI 686 CART WASH RETURN DESIGN
Mod P00007· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2013-09-26+$48,392$38,108,325SA-172, BOND PREMIUM ADJUSTMENT
Mod P00002· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2014-06-16+$1,376$38,109,701SA-168: COR 426 EXAMINE AND WELD HOIST BEAM
Mod P00004· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2014-06-16+$64,151$38,173,852SA-169, PARKING GARAGE THRESHOLD INSPECTIONS
Mod P00006· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2014-06-16−$41,332$38,132,520SA-171, DELETE REMAINING SITE CONCRETE

Related awards · 9

Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.

Other VA awards to the same recipient (UEI TWVGJRMK6Z78)

AwardOffice · PSC / listingNet obligationsFY
VA101CFMC0206OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F) · Y141 · CONSTRUCT/HOSPITALS & INFIRMARIES$318,479,500FY2010
VA101CFMC0164OFFICE OF CONSTRUCTION & FACILITIES MANAGEMENT · Y141 · CONSTRUCT/HOSPITALS & INFIRMARIES$33,949,043FY2010
VA101CFMC0041OFFICE OF CONSTRUCTION & FACILITIES MANAGEMENT · Y149 · CONSTRUCT/OTHER HOSPITAL BLDGS$14,411,847FY2009
VA101CFMC0030OFFICE OF CONSTRUCTION & FACILITIES MANAGEMENT · Y141 · CONSTRUCT/HOSPITALS & INFIRMARIES$14,722,198FY2009

Other recipients under Y141 from OFFICE OF CONSTRUCTION & FACILITIES MANAGEMENT (most recent first)

AwardRecipientOfficeNet obligationsFY
VA101CFMC0167THE R.E.M. ENGINEERING CO INCOFFICE OF CONSTRUCTION & FACILITIES MANAGEMENT$384,303FY2011
VA101CFMC0130TTL ASSOCIATES INCOFFICE OF CONSTRUCTION & FACILITIES MANAGEMENT$101,742FY2011
VA101CFMC0111WALSH CONSTRUCTION PUERTO RICOOFFICE OF CONSTRUCTION & FACILITIES MANAGEMENT$52,457,646FY2010
VA101CFMC0085ARCHER WESTERN/DEMARIA JOINT VENTURE IIIOFFICE OF CONSTRUCTION & FACILITIES MANAGEMENT$58,427,947FY2010
VACFM05I0064N.K. BHANDARI, ARCHITECTURE & ENGINEERING, P.C.OFFICE OF CONSTRUCTION & FACILITIES MANAGEMENT$114,946FY2010

Cite as: Glassbox VA record view · VA contract (USAspending / FPDS) · CONT_AWD_VA101CFMC0163_3600_-NONE-_-NONE- · retrieved 2026-09-26.