Description
TO ADJUST THE CONTRACTOR'S BOND PREMIUM BECAUSE OF THE MODIFICATIONS ISSUED TO THE CONTRACT DURING CONSTRUCTION.
Base award description: BLIND
Modification chain · 46 transactions
Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.
- Base2009-05-29+$14,072,000= $14,072,000
- Mod SA0012010-03-01+$6,516= $14,078,516
- Mod SA0022010-03-01+$7,783= $14,086,299
- Mod SA0042010-03-01+$15,120= $14,101,419
- Mod SA0052010-06-16+$5,377= $14,106,796
- Mod SA0062010-06-16-$2,310= $14,104,485
- Mod SA0072010-08-30+$14,025= $14,118,510
- Mod SA0082010-08-30-$31,080= $14,087,430
- Mod SA0092010-09-21+$7,190= $14,094,620
- Mod SA0102011-01-11+$33,179= $14,127,799
- Mod SA0112011-01-11+$7,898= $14,135,697
- Mod SA0122011-01-11+$13,497= $14,149,194
- Mod SA0132011-01-11+$18,201= $14,167,395
- Mod SA0142011-01-11+$3,884= $14,171,279
- Mod SA0152011-03-10+$3,507= $14,174,786
- Mod SA0162011-03-10+$7,806= $14,182,592
- Mod SA0172011-03-10+$4,090= $14,186,682
- Mod SA0182011-03-10+$44,956= $14,231,638
- Mod SA0192011-05-05+$1,421= $14,233,060
- Mod SA0202011-06-28+$13,684= $14,246,744
- Mod SA0212011-06-28+$2,895= $14,249,639
- Mod SA0382011-06-29+$10,340= $14,259,979
- Mod SA0222011-07-25+$31,923= $14,291,902
- Mod SA0232011-07-25+$2,695= $14,294,596
- Mod SA0322011-07-29+$6,516= $14,301,112
- Mod SA0332011-07-29+$1,812= $14,302,924
- Mod SA0342011-07-29+$6,346= $14,309,270
- Mod SA0352011-07-29+$10,772= $14,320,042
- Mod SA0362011-07-29+$1,573= $14,321,615
- Mod SA0372011-07-29+$5,678= $14,327,293
- Mod SA0392011-07-30-$26,881= $14,300,412
- Mod SA0272011-08-15+$2,969= $14,303,381
- Mod SA0282011-08-15+$1,232= $14,304,613
- Mod SA0292011-08-15+$1,744= $14,306,357
- Mod SA0302011-08-15+$20,265= $14,326,622
- Mod SA0312011-08-15+$3,807= $14,330,429
- Mod TE0012011-08-15+$0= $14,330,429
- Mod SA0402011-09-16+$16,122= $14,346,551
- Mod SA0412011-09-16+$7,601= $14,354,152
- Mod SA0422011-09-16+$997= $14,355,149
- Mod SA0442011-09-26+$770= $14,355,919
- Mod SA0242012-03-28+$27,754= $14,383,673
- Mod SA0252012-03-28+$0= $14,383,673
- Mod SA0262012-03-28+$3,250= $14,386,923
- Mod SA0432012-03-28+$22,897= $14,409,820
- Mod SA0452012-03-28+$2,027= $14,411,847
| Transaction | Action date | This action (delta) | Running total | Description on this transaction |
|---|---|---|---|---|
| Base | 2009-05-29 | +$14,072,000 | $14,072,000 | BLIND |
| Mod SA001· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2010-03-01 | +$6,516 | $14,078,516 | ADD'L YARD INLET IN REMOTE AREAS |
| Mod SA002· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2010-03-01 | +$7,783 | $14,086,299 | REPLACE FIBER OPTIC BOX |
| Mod SA004· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2010-03-01 | +$15,120 | $14,101,419 | CONFLICT IN STORM SEWER |
| Mod SA005· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2010-06-16 | +$5,377 | $14,106,796 | CHANGE IN DOOR SIZES |
| Mod SA006· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2010-06-16 | −$2,310 | $14,104,485 | CHANGE IN DOOR SIZES |
| Mod SA007· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2010-08-30 | +$14,025 | $14,118,510 | PLUMBING FIXTURE CHANGES |
| Mod SA008· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2010-08-30 | −$31,080 | $14,087,430 | HVAC CHANGES |
| Mod SA009· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2010-09-21 | +$7,190 | $14,094,620 | ADDITIONAL EQUIPMENT |
| Mod SA010· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2011-01-11 | +$33,179 | $14,127,799 | ADDITIONAL EQUIPMENT |
| Mod SA011· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2011-01-11 | +$7,898 | $14,135,697 | ADD STEEL FOR EXTERIOR DOOR INSTALLATION |
| Mod SA012· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2011-01-11 | +$13,497 | $14,149,194 | CHANGE IN TRUSS DESIGN |
| Mod SA013· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2011-01-11 | +$18,201 | $14,167,395 | CHILLED WATER LINE EXTENSION |
| Mod SA014· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2011-01-11 | +$3,884 | $14,171,279 | TESTING 9/5 - 10/21 |
| Mod SA015· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2011-03-10 | +$3,507 | $14,174,786 | CHANGE GROUT IN PRE-CAST TO CAULK |
| Mod SA016· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2011-03-10 | +$7,806 | $14,182,592 | TESTING |
| Mod SA017· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2011-03-10 | +$4,090 | $14,186,682 | ELEVATOR CONTROLS |
| Mod SA018· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2011-03-10 | +$44,956 | $14,231,638 | ADD'L FIRE ALARMS |
| Mod SA019· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2011-05-05 | +$1,421 | $14,233,060 | TO PROVIDE TESTING LAB SERVICES UNTIL SUCH TIME AS THE VA AWARDS A TESTING LAB CONTRACT. |
| Mod SA020· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2011-06-28 | +$13,684 | $14,246,744 | DUE TO CONSTANT CHANGES IN ELEVATIONS OF THE CEMETARY ROAD AND PARKING LOTS C AND D, THE ROAD BETWEEN THE PARK… |
| Mod SA021· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2011-06-28 | +$2,895 | $14,249,639 | TO PROVIDE TESTING LAB SERVICES UNTIL SUCH TIME AS THE VA AWARDS A TESTING LAB CONTRACT. |
| Mod SA038· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2011-06-29 | +$10,340 | $14,259,979 | DURING THE SUBMITTAL REVIEW PROCESS THE DOCK LIFT SIZE WAS AN ISSUE. THE STATION, RE AND AE DECIDED THAT THE S… |
| Mod SA022· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2011-07-25 | +$31,923 | $14,291,902 | ASI #18 FROM THE AE PROVIDED CORRECTIVE CHANGES TO THE KITCHEN ELECTRICAL AND GAS SYSTEMS AND RELOCATED THE FA… |
| Mod SA023· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2011-07-25 | +$2,695 | $14,294,596 | THE UPPER BAND OF CAST STONE ON THE SREENED PORCH IS APPLIED TO A POURED IN PLACE BEAM THAT STRETCHES OVER 86… |
| Mod SA032· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2011-07-29 | +$6,516 | $14,301,112 | CLARIFICATION FROM THE AE DETERMINED THAT THE THROUGH THE SLAB PENETRATIONS REQUIRED SHAFT WALL, AND CEILINGS… |
| Mod SA033· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2011-07-29 | +$1,812 | $14,302,924 | THE DRAWINGS DO NOT SHOW A CIRCUIT FOR THE MAGNETIC DOOR HOLD OPENS. PROVIDE A CIRCUIT FOR THE DOORS IN C-10 A… |
| Mod SA034· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2011-07-29 | +$6,346 | $14,309,270 | THE ROAD GRADES IN THE ORIGINAL DESIGN WERE FLAWED AND REQUIRED MULTIPLE RE-DESIGN EFFORTS. THESE EFFORTS RESU… |
| Mod SA035· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2011-07-29 | +$10,772 | $14,320,042 | POWER FOR THE DOOR OPENER CIRCUITS WAS NOT SHOWN ON THE DRAWINGS. AN RFI RESPONSE PROVIDED THE CIRCUITS AND PA… |
| Mod SA036· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2011-07-29 | +$1,573 | $14,321,615 | THE AE SPECIFIED CARPET IN THE PATIENT EXAM ROOM. CARPET IS NOT ALLOWED IN EXAM ROOMS AND NEEDS TO BE REPLACED… |
| Mod SA037· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2011-07-29 | +$5,678 | $14,327,293 | DURING THE REVIEW OF SHOP DRAWINGS, IT WAS DETERMINED THAT THE STAINLESS STEEL SINKS IN THE TRAINING KITCHENS… |
| Mod SA039· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2011-07-30 | −$26,881 | $14,300,412 | DURING THE REVIEW OF THE LANDSCAPE PROJECT, IT WAS DETERMINED THAT SOME OF THE NEW ROADS TO BE INSTALLED IN TH… |
| Mod SA027· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2011-08-15 | +$2,969 | $14,303,381 | TO PROVIDE TESTING LAB SERVICES UNTIL SUCH TIME AS THE VA AWARDS A TESTING LAB CONTRACT. |
| Mod SA028· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2011-08-15 | +$1,232 | $14,304,613 | FOUR KITCHEN CABINETS THAT HAVE A MICROWAVE/VENT FAN ARE OF THE WRONG SIZE. THE CABINETS ARE TOO SHORT AND MAK… |
| Mod SA029· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2011-08-15 | +$1,744 | $14,306,357 | NO PROVISION FOR PLUGGING IN THE AIRCOMPRESSOR DRYER WAS SHOWN ON THE DRAWINGS. A 20A DUPLEX RECEPTACLE WAS NE… |
| Mod SA030· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2011-08-15 | +$20,265 | $14,326,622 | MULTIPLE DISCREPANCIES WERE DISCOVERED BY THE CONTRACTOR AND THE RE IN THE AIR COMPRESSOR INSTALLATION DRAWING… |
| Mod SA031· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2011-08-15 | +$3,807 | $14,330,429 | THE ORIGINAL FIRE ALARM AND FIRE SUPPRESSION REQUIREMENTS WERE CHANGED TO INCORPORATE CHANGES IN THE HVAC DESI… |
| Mod TE001· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-08-15 | +$0 | $14,330,429 | TO ADD 22 CALENDAR DAYS TO THE CONTRACT DUE TO ABNORMAL AMOUNT OF RAINFALL OVER THE COURSE OF THE PROJECT THAT… |
| Mod SA040· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2011-09-16 | +$16,122 | $14,346,551 | THE DRAWINGS SHOWED THE ROOF FLASHING IN THE WRONG ELEVATION FOR THE ROOF PITCH ON THE SOUTH WEST LOW ROOF. TH… |
| Mod SA041· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2011-09-16 | +$7,601 | $14,354,152 | 3 DOWNSPOUT BOOTS WERE NOT SHOWN ON THE DRAWINGS AND NEED TO BE INSTALLED SO THE FLOWER BEDS ARE NOT RUINED BY… |
| Mod SA042· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2011-09-16 | +$997 | $14,355,149 | TO PROVIDE TESTING LAB SERVICES UNTIL SUCH TIME AS THE VA AWARDS A TESTING LAB CONTRACT. |
| Mod SA044· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2011-09-26 | +$770 | $14,355,919 | TRANSITION OF NEW SIDEWALKS INTO OLD CAUSED, IN THE OPINION OF THE STATION SAFETY OFFICER, A TRIPPING HAZARD. |
| Mod SA024· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2012-03-28 | +$27,754 | $14,383,673 | THE AE MADE ERRORS IN THE ELEVATIONS REQUIRED TO CONNECT THE BUILDING SANITARY SEWER LINES TO THE NEW MAIN SAN… |
| Mod SA025· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2012-03-28 | +$0 | $14,383,673 | THE BLAST DOOR REQUIREMENT WAS DELETED AND DOOR HARDWARE NEEDED TO BE RE-SPECIFIED TO MEET THE DOORS THAT REPL… |
| Mod SA026· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2012-03-28 | +$3,250 | $14,386,923 | THE MIRROR SIZES SHOWN ON THE DRAWINGS AND IN THE SPECIFICATIONS WILL NOT FIT DUE TO SINK AND CEILING HEIGHTS.… |
| Mod SA043· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2012-03-28 | +$22,897 | $14,409,820 | THE ELEVATIONS IN THE COURTYARD ARE TOO LOW DUE TO AN ERROR IN THE SITE SURVEY. THE ELEVATIONS NEED TO BE RAIS… |
| Mod SA045· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2012-03-28 | +$2,027 | $14,411,847 | TO ADJUST THE CONTRACTOR'S BOND PREMIUM BECAUSE OF THE MODIFICATIONS ISSUED TO THE CONTRACT DURING CONSTRUCTIO… |
Related awards · 9
Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.
Other VA awards to the same recipient (UEI TWVGJRMK6Z78)
| Award | Office · PSC / listing | Net obligations | FY |
|---|---|---|---|
| VA101CFMC0206 | OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F) · Y141 · CONSTRUCT/HOSPITALS & INFIRMARIES | $318,479,500 | FY2010 |
| VA101CFMC0164 | OFFICE OF CONSTRUCTION & FACILITIES MANAGEMENT · Y141 · CONSTRUCT/HOSPITALS & INFIRMARIES | $33,949,043 | FY2010 |
| VA101CFMC0163 | OFFICE OF CONSTRUCTION & FACILITIES MANAGEMENT · Y141 · CONSTRUCT/HOSPITALS & INFIRMARIES | $38,132,520 | FY2010 |
| VA101CFMC0030 | OFFICE OF CONSTRUCTION & FACILITIES MANAGEMENT · Y141 · CONSTRUCT/HOSPITALS & INFIRMARIES | $14,722,198 | FY2009 |
Other recipients under Y149 from OFFICE OF CONSTRUCTION & FACILITIES MANAGEMENT (most recent first)
| Award | Recipient | Office | Net obligations | FY |
|---|---|---|---|---|
| VACFM05J0037 | TOLAND & MIZELL ARCHITECTS APPLIED ENGINEERING SOLUTIONS JOINT VENTURE | OFFICE OF CONSTRUCTION & FACILITIES MANAGEMENT | $378,544 | FY2011 |
| VA101CFMC0126 | HERNANDEZ CONSULTING INC. | OFFICE OF CONSTRUCTION & FACILITIES MANAGEMENT | $200,226 | FY2011 |
| VACFM05J0036 | TOLAND & MIZELL ARCHITECTS APPLIED ENGINEERING SOLUTIONS JOINT VENTURE | OFFICE OF CONSTRUCTION & FACILITIES MANAGEMENT | $375,315 | FY2010 |
| VACFM05J0035 | TOLAND & MIZELL ARCHITECTS APPLIED ENGINEERING SOLUTIONS JOINT VENTURE | OFFICE OF CONSTRUCTION & FACILITIES MANAGEMENT | $245,048 | FY2010 |
| VACFM05J0034 | TOLAND & MIZELL ARCHITECTS APPLIED ENGINEERING SOLUTIONS JOINT VENTURE | OFFICE OF CONSTRUCTION & FACILITIES MANAGEMENT | $381,867 | FY2010 |