Award recordCONTRACT

KIEWIT-TURNER A JOINT VENTURE

PIID VA101CFMC0100· VA Staff Offices· OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F)· Y141 · CONSTRUCT/HOSPITALS & INFIRMARIES· FY2010· $678,462,349 net obligations· UEI W8F9CKD8QJQ6· CO

Description

INCORPORATE CORRECT WD

Base award description: DENVER REPLACEMENT MEDICAL CENTER FACILITY, AURORA, CO

First action · last action
2010-08-31 · 2017-06-27
Transactions
551
First transaction's obligation
$1,313,100
Base + all options value (sum of deltas)
$1,896,785,751
Extent competed
FULL AND OPEN COMPETITION
Other than full & open authority
—
Set-aside
NO SET ASIDE USED.
Offers received
5
SDVOSB flag on record
No
NAICS
236220 · COMMERCIAL AND INSTITUTIONAL BUILDING CONSTRUCTION

Modification chain · 551 transactions

Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.

$678,495,654$0Base award · 2010-08-31 · this action $1,313,100 · running total $1,313,100Modification SA001 · 2010-11-30 · this action $83,418 · running total $1,396,518Modification AC001 · 2011-01-11 · this action $0 · running total $1,396,518Modification AC002 · 2011-02-09 · this action $0 · running total $1,396,518Modification SA002 · 2011-02-10 · this action $1,124 · running total $1,397,642Modification SA003 · 2011-02-10 · this action $3,275 · running total $1,400,917Modification SA004 · 2011-04-08 · this action $22,463,597 · running total $23,864,514Modification SA005 · 2011-07-19 · this action $13,414 · running total $23,877,928Modification SA006 · 2011-09-07 · this action $21,725,000 · running total $45,602,928Modification AC003 · 2011-10-03 · this action $0 · running total $45,602,928Modification SA007 · 2011-11-18 · this action $580,209,251 · running total $625,812,179Modification AC004 · 2012-03-14 · this action $0 · running total $625,812,179Modification CO01N · 2012-05-01 · this action $0 · running total $625,812,179Modification CO01O · 2012-05-01 · this action $0 · running total $625,812,179Modification CO01A · 2012-05-24 · this action $4,252 · running total $625,816,431Modification CO01B · 2012-05-24 · this action $25,000 · running total $625,841,431Modification CO01C · 2012-05-24 · this action $60,000 · running total $625,901,431Modification CO01D · 2012-05-24 · this action $41,099 · running total $625,942,530Modification CO01E · 2012-05-24 · this action $5,500 · running total $625,948,029Modification CO01F · 2012-05-24 · this action $12,739 · running total $625,960,768Modification CO01G · 2012-05-24 · this action $14,970 · running total $625,975,738Modification CO01H · 2012-05-24 · this action $26,400 · running total $626,002,138Modification CO01I · 2012-05-24 · this action $14,500 · running total $626,016,638Modification CO01J · 2012-05-24 · this action $30,000 · running total $626,046,638Modification CO01K · 2012-05-24 · this action $2,330 · running total $626,048,968Modification CO01L · 2012-05-24 · this action $25,000 · running total $626,073,968Modification CO01M · 2012-05-24 · this action $1,265 · running total $626,075,233Modification CO01R · 2012-05-25 · this action $40,000 · running total $626,115,233Modification CO01S · 2012-05-25 · this action -$11,000 · running total $626,104,233Modification CO01T · 2012-05-31 · this action $10,000 · running total $626,114,233Modification AC005 · 2012-06-05 · this action $0 · running total $626,114,233Modification CO01Q · 2012-06-22 · this action $17,550 · running total $626,131,783Modification CO01U · 2012-06-22 · this action -$15,374 · running total $626,116,409Modification CO01X · 2012-06-22 · this action $3,200 · running total $626,119,609Modification CO01Y · 2012-06-22 · this action $41,000 · running total $626,160,609Modification CO02A · 2012-06-22 · this action $22,000 · running total $626,182,609Modification CO01V · 2012-06-26 · this action -$11,000 · running total $626,171,609Modification AC006 · 2012-07-09 · this action $0 · running total $626,171,609Modification CO01Z · 2012-07-11 · this action $76,573 · running total $626,248,182Modification CO02B · 2012-07-11 · this action $5,887 · running total $626,254,069Modification CO02E · 2012-07-17 · this action $35,000 · running total $626,289,069Modification CO01P · 2012-07-25 · this action $9,000 · running total $626,298,069Modification CO01W · 2012-07-25 · this action $85,000 · running total $626,383,069Modification CO02C · 2012-07-25 · this action $5,000 · running total $626,388,069Modification CO02D · 2012-07-25 · this action $8,500 · running total $626,396,569Modification CO02F · 2012-07-25 · this action $1,500 · running total $626,398,069Modification CO02I · 2012-07-26 · this action $4,000 · running total $626,402,069Modification CO02J · 2012-07-26 · this action $5,000 · running total $626,407,069Modification CO02L · 2012-07-27 · this action $34,000 · running total $626,441,069Modification CO02K · 2012-07-30 · this action $4,000 · running total $626,445,069Modification SA010 · 2012-08-03 · this action -$11,000 · running total $626,434,069Modification AC007 · 2012-08-10 · this action $0 · running total $626,434,069Modification AC008 · 2012-08-10 · this action $0 · running total $626,434,069Modification AC009 · 2012-08-10 · this action $0 · running total $626,434,069Modification CO02H · 2012-08-16 · this action $10,000 · running total $626,444,069Modification CO02Q · 2012-09-17 · this action $50,000 · running total $626,494,069Modification CO02S · 2012-09-30 · this action $1,000 · running total $626,495,069Modification P00010 · 2012-10-10 · this action $4,000 · running total $626,499,069Modification P00014 · 2012-10-17 · this action $6,000 · running total $626,505,069Modification P00017 · 2012-10-24 · this action -$17,550 · running total $626,487,519Modification A00010 · 2012-10-29 · this action $0 · running total $626,487,519Modification A00011 · 2012-10-29 · this action $0 · running total $626,487,519Modification P00009 · 2012-10-29 · this action -$2,500 · running total $626,485,019Modification P00016 · 2012-10-29 · this action $0 · running total $626,485,019Modification P00001 · 2012-10-30 · this action $99,500 · running total $626,584,519Modification P00015 · 2012-10-30 · this action $6,000 · running total $626,590,519Modification P00020 · 2012-11-13 · this action $2,000 · running total $626,592,519Modification P00021 · 2012-11-16 · this action $724 · running total $626,593,243Modification P00022 · 2012-11-16 · this action $1,676 · running total $626,594,919Modification P00024 · 2012-12-13 · this action -$26,000 · running total $626,568,919Modification A00012 · 2013-01-29 · this action $0 · running total $626,568,919Modification CO02M · 2013-02-15 · this action $5,000 · running total $626,573,919Modification P00040 · 2013-02-20 · this action $73,588 · running total $626,647,507Modification P00032 · 2013-02-21 · this action $1,020 · running total $626,648,527Modification P00033 · 2013-02-24 · this action $1,281 · running total $626,649,808Modification P00048 · 2013-02-26 · this action $61,455 · running total $626,711,263Modification P00055 · 2013-02-28 · this action $0 · running total $626,711,263Modification P00057 · 2013-03-06 · this action -$11,000 · running total $626,700,263Modification P00056 · 2013-03-07 · this action $20,000 · running total $626,720,263Modification P00068 · 2013-03-08 · this action $0 · running total $626,720,263Modification P00060 · 2013-03-11 · this action $28,000 · running total $626,748,263Modification P00045 · 2013-03-14 · this action $1,700 · running total $626,749,963Modification P00046 · 2013-03-14 · this action $1,500 · running total $626,751,463Modification P00096 · 2013-03-15 · this action $0 · running total $626,751,463Modification P00081 · 2013-03-18 · this action $15,000 · running total $626,766,463Modification P00038 · 2013-03-19 · this action $106,646 · running total $626,873,109Modification P00030 · 2013-03-20 · this action $4,342 · running total $626,877,451Modification P00034 · 2013-03-20 · this action $3,296 · running total $626,880,747Modification P00084 · 2013-03-20 · this action $15,000 · running total $626,895,747Modification P00069 · 2013-03-21 · this action -$1,794 · running total $626,893,954Modification P00073 · 2013-03-21 · this action $0 · running total $626,893,954Modification P00059 · 2013-04-04 · this action $14,443 · running total $626,908,397Modification P00085 · 2013-04-04 · this action $249,663 · running total $627,158,060Modification P00090 · 2013-04-09 · this action $47,331 · running total $627,205,391Modification P00103 · 2013-04-09 · this action $4,821 · running total $627,210,212Modification P00104 · 2013-04-09 · this action $8,293 · running total $627,218,505Modification P00105 · 2013-04-09 · this action $11,581 · running total $627,230,086Modification P00106 · 2013-04-09 · this action $29,094 · running total $627,259,180Modification P00107 · 2013-04-09 · this action $225,655 · running total $627,484,835Modification P00109 · 2013-04-09 · this action $94,335 · running total $627,579,170Modification P00071 · 2013-04-10 · this action -$6,359 · running total $627,572,811Modification P00113 · 2013-04-10 · this action $152,804 · running total $627,725,615Modification P00114 · 2013-04-10 · this action $163,077 · running total $627,888,692Modification P00108 · 2013-04-11 · this action $449,000 · running total $628,337,692Modification P00116 · 2013-04-12 · this action $195,448 · running total $628,533,140Modification P00122 · 2013-04-12 · this action $1,174,261 · running total $629,707,401Modification P00035 · 2013-04-15 · this action $0 · running total $629,707,401Modification P00131 · 2013-04-15 · this action $80,500 · running total $629,787,901Modification P00086 · 2013-04-16 · this action $35,000 · running total $629,822,901Modification P00026 · 2013-04-17 · this action $2,361 · running total $629,825,262Modification P00027 · 2013-04-17 · this action $8,618 · running total $629,833,880Modification P00134 · 2013-04-17 · this action $85,515 · running total $629,919,395Modification P00094 · 2013-04-18 · this action $1,200 · running total $629,920,595Modification P00119 · 2013-04-23 · this action $150,000 · running total $630,070,595Modification P00141 · 2013-04-25 · this action $0 · running total $630,070,595Modification P00146 · 2013-05-15 · this action $11,000 · running total $630,081,595Modification P00070 · 2013-05-21 · this action $2,443,364 · running total $632,524,959Modification P00148 · 2013-05-31 · this action $11,000 · running total $632,535,959Modification P00151 · 2013-05-31 · this action $11,800 · running total $632,547,759Modification P00087 · 2013-06-05 · this action $41,460 · running total $632,589,219Modification P00149 · 2013-06-06 · this action $1,021 · running total $632,590,240Modification P00162 · 2013-06-07 · this action $140,000 · running total $632,730,240Modification P00147 · 2013-06-11 · this action $5,000 · running total $632,735,240Modification P00164 · 2013-06-11 · this action $7,804 · running total $632,743,044Modification P00140 · 2013-06-14 · this action $0 · running total $632,743,044Modification P00168 · 2013-06-14 · this action $8,500 · running total $632,751,544Modification P00157 · 2013-06-15 · this action $6,702 · running total $632,758,246Modification P00159 · 2013-06-17 · this action $0 · running total $632,758,246Modification P00170 · 2013-06-20 · this action $5,000 · running total $632,763,246Modification P00130 · 2013-06-21 · this action -$430 · running total $632,762,816Modification P00161 · 2013-06-21 · this action $7,275 · running total $632,770,091Modification P00177 · 2013-06-21 · this action $10,500 · running total $632,780,591Modification P00178 · 2013-06-21 · this action $16,980 · running total $632,797,571Modification P00179 · 2013-06-24 · this action $25,000 · running total $632,822,571Modification P00058 · 2013-06-25 · this action $18,408 · running total $632,840,979Modification P00092 · 2013-06-26 · this action $975 · running total $632,841,954Modification P00181 · 2013-06-26 · this action $6,786 · running total $632,848,740Modification P00037 · 2013-06-27 · this action -$3,932 · running total $632,844,808Modification P00169 · 2013-06-28 · this action $0 · running total $632,844,808Modification P00183 · 2013-06-28 · this action $31,000 · running total $632,875,808Modification P00064 · 2013-06-30 · this action -$43 · running total $632,875,765Modification P00111 · 2013-06-30 · this action -$3,725 · running total $632,872,040Modification P00039 · 2013-07-03 · this action $0 · running total $632,872,040Modification P00066 · 2013-07-03 · this action -$7,674 · running total $632,864,366Modification P00118 · 2013-07-03 · this action $11,774 · running total $632,876,140Modification P00199 · 2013-07-03 · this action $10,000 · running total $632,886,140Modification P00195 · 2013-07-07 · this action $800 · running total $632,886,940Modification P00143 · 2013-07-14 · this action $165,984 · running total $633,052,924Modification P00112 · 2013-07-16 · this action $79,744 · running total $633,132,668Modification P00083 · 2013-07-17 · this action $15,000 · running total $633,147,668Modification P00028 · 2013-07-19 · this action $1,475 · running total $633,149,143Modification P00065 · 2013-07-22 · this action $3,662 · running total $633,152,805Modification P00095 · 2013-07-22 · this action $43,500 · running total $633,196,305Modification P00121 · 2013-07-23 · this action $153,236 · running total $633,349,541Modification P00067 · 2013-07-30 · this action -$20,185 · running total $633,329,356Modification P00076 · 2013-07-30 · this action -$2,991 · running total $633,326,365Modification P00203 · 2013-08-01 · this action $16,600 · running total $633,342,965Modification P00041 · 2013-08-02 · this action $72,162 · running total $633,415,127Modification P00204 · 2013-08-02 · this action $6,200 · running total $633,421,327Modification P00128 · 2013-08-05 · this action -$18,800 · running total $633,402,527Modification P00175 · 2013-08-09 · this action $102,000 · running total $633,504,527Modification P00079 · 2013-08-12 · this action $2,409 · running total $633,506,936Modification P00080 · 2013-08-12 · this action $9,801 · running total $633,516,737Modification P00099 · 2013-08-12 · this action $15,331 · running total $633,532,068Modification P00209 · 2013-08-12 · this action $1,000 · running total $633,533,068Modification P00221 · 2013-08-12 · this action $3,958 · running total $633,537,026Modification P00160 · 2013-08-13 · this action $5,500 · running total $633,542,526Modification P00197 · 2013-08-14 · this action $6,500 · running total $633,549,026Modification P00216 · 2013-08-14 · this action $4,000 · running total $633,553,026Modification P00054 · 2013-08-16 · this action $1,434 · running total $633,554,460Modification P00062 · 2013-08-16 · this action $345 · running total $633,554,805Modification P00078 · 2013-08-16 · this action -$4,265 · running total $633,550,540Modification P00082 · 2013-08-16 · this action -$16,929 · running total $633,533,611Modification P00089 · 2013-08-16 · this action $282 · running total $633,533,893Modification P00115 · 2013-08-16 · this action -$14,896 · running total $633,518,997Modification P00120 · 2013-08-16 · this action $305,991 · running total $633,824,988Modification P00124 · 2013-08-16 · this action $71 · running total $633,825,059Modification P00126 · 2013-08-16 · this action $22,788 · running total $633,847,847Modification P00136 · 2013-08-16 · this action -$60 · running total $633,847,787Modification P00185 · 2013-08-16 · this action $17,018 · running total $633,864,805Modification P00196 · 2013-08-16 · this action $10,000 · running total $633,874,805Modification P00206 · 2013-08-16 · this action $2,400,000 · running total $636,274,805Modification P00207 · 2013-08-16 · this action $127,382 · running total $636,402,187Modification P00227 · 2013-08-16 · this action $72,700 · running total $636,474,887Modification P00205 · 2013-08-20 · this action $9,600 · running total $636,484,487Modification P00231 · 2013-08-22 · this action $941 · running total $636,485,428Modification P00237 · 2013-08-23 · this action $0 · running total $636,485,428Modification P00051 · 2013-08-29 · this action $0 · running total $636,485,428Modification P00242 · 2013-08-29 · this action $0 · running total $636,485,428Modification P00029 · 2013-08-30 · this action $448 · running total $636,485,876Modification P00132 · 2013-08-30 · this action $81,785 · running total $636,567,661Modification P00153 · 2013-08-30 · this action $329 · running total $636,567,990Modification P00163 · 2013-08-30 · this action $1,647 · running total $636,569,637Modification P00176 · 2013-08-30 · this action $864 · running total $636,570,501Modification P00219 · 2013-08-30 · this action $1,553 · running total $636,572,054Modification P00174 · 2013-09-03 · this action $28,247 · running total $636,600,301Modification P00249 · 2013-09-04 · this action $36,200 · running total $636,636,501Modification P00044 · 2013-09-11 · this action $13,488 · running total $636,649,989Modification P00224 · 2013-09-14 · this action $42,000 · running total $636,691,989Modification P00186 · 2013-09-16 · this action $133 · running total $636,692,122Modification P00223 · 2013-09-16 · this action -$7,290 · running total $636,684,832Modification P00208 · 2013-09-25 · this action $50,716 · running total $636,735,548Modification P00025 · 2013-10-02 · this action $11,086 · running total $636,746,634Modification P00075 · 2013-10-02 · this action $12,864 · running total $636,759,498Modification P00097 · 2013-10-02 · this action $1,574 · running total $636,761,072Modification P00278 · 2013-10-02 · this action $0 · running total $636,761,072Modification P00110 · 2013-10-03 · this action -$7 · running total $636,761,065Modification P00129 · 2013-10-03 · this action $63,703 · running total $636,824,768Modification P00222 · 2013-10-09 · this action $47,357 · running total $636,872,125Modification P00275 · 2013-10-09 · this action $7,371 · running total $636,879,496Modification P00117 · 2013-10-10 · this action $2,300 · running total $636,881,796Modification P00098 · 2013-10-16 · this action $3,461 · running total $636,885,257Modification P00245 · 2013-10-16 · this action $117,586 · running total $637,002,843Modification P00269 · 2013-10-16 · this action -$3,253 · running total $636,999,590Modification P00127 · 2013-10-18 · this action $3,000 · running total $637,002,590Modification P00158 · 2013-10-18 · this action $4,685 · running total $637,007,275Modification P00250 · 2013-10-18 · this action $28,921 · running total $637,036,196Modification P00302 · 2013-10-21 · this action $3,000 · running total $637,039,196Modification P00305 · 2013-10-22 · this action $13,000 · running total $637,052,196Modification P00218 · 2013-10-23 · this action $20,597 · running total $637,072,793Modification P00047 · 2013-10-24 · this action -$14,377 · running total $637,058,416Modification P00202 · 2013-10-25 · this action $161 · running total $637,058,577Modification P00306 · 2013-10-25 · this action $0 · running total $637,058,577Modification P00212 · 2013-10-29 · this action $1,249 · running total $637,059,826Modification P00289 · 2013-10-29 · this action $7,221 · running total $637,067,047Modification P00077 · 2013-10-30 · this action $58,000 · running total $637,125,047Modification P00152 · 2013-10-30 · this action $3,344 · running total $637,128,391Modification P00172 · 2013-10-30 · this action $667 · running total $637,129,058Modification P00215 · 2013-10-30 · this action $17,650 · running total $637,146,708Modification P00235 · 2013-10-30 · this action -$13,452 · running total $637,133,256Modification P00254 · 2013-10-30 · this action $287 · running total $637,133,543Modification P00265 · 2013-10-30 · this action $31,906 · running total $637,165,449Modification P00220 · 2013-11-01 · this action $7,673 · running total $637,173,122Modification P00294 · 2013-11-01 · this action $2,586 · running total $637,175,708Modification P00297 · 2013-11-01 · this action $10,099 · running total $637,185,807Modification P00298 · 2013-11-04 · this action $10,739 · running total $637,196,546Modification P00133 · 2013-11-06 · this action $5,907 · running total $637,202,453Modification P00288 · 2013-11-07 · this action -$19 · running total $637,202,434Modification P00295 · 2013-11-07 · this action $39,269 · running total $637,241,703Modification P00287 · 2013-11-12 · this action $10,743 · running total $637,252,446Modification P00296 · 2013-11-12 · this action $10,939 · running total $637,263,385Modification P00190 · 2013-11-15 · this action $13,260 · running total $637,276,645Modification P00200 · 2013-11-19 · this action $2,601 · running total $637,279,246Modification P00225 · 2013-11-19 · this action $2,559 · running total $637,281,805Modification P00277 · 2013-11-19 · this action $1,714 · running total $637,283,519Modification P00213 · 2013-11-20 · this action $14,474 · running total $637,297,993Modification P00318 · 2013-11-20 · this action -$105 · running total $637,297,888Modification P00300 · 2013-11-21 · this action $5,954 · running total $637,303,842Modification P00328 · 2013-11-21 · this action $0 · running total $637,303,842Modification P00330 · 2013-11-21 · this action $0 · running total $637,303,842Modification P00327 · 2013-11-26 · this action $11,000 · running total $637,314,842Modification P00317 · 2013-11-27 · this action $2,776 · running total $637,317,618Modification P00320 · 2013-11-27 · this action $8,536 · running total $637,326,154Modification P00319 · 2013-12-05 · this action -$241 · running total $637,325,913Modification P00100 · 2013-12-12 · this action $9,501 · running total $637,335,414Modification P00342 · 2013-12-20 · this action $0 · running total $637,335,414Modification P00150 · 2014-01-09 · this action -$9,649 · running total $637,325,765Modification P00312 · 2014-01-09 · this action -$411 · running total $637,325,354Modification P00031 · 2014-01-14 · this action -$2,437 · running total $637,322,917Modification P00315 · 2014-01-20 · this action -$89,194 · running total $637,233,723Modification P00282 · 2014-01-22 · this action $541,787 · running total $637,775,510Modification P00322 · 2014-01-22 · this action $4,772 · running total $637,780,282Modification P00261 · 2014-01-28 · this action -$42,660 · running total $637,737,622Modification P00229 · 2014-01-30 · this action -$2,980 · running total $637,734,642Modification P00283 · 2014-01-30 · this action $1,199 · running total $637,735,841Modification P00343 · 2014-02-03 · this action $1,159 · running total $637,737,000Modification P00324 · 2014-02-06 · this action -$48,706 · running total $637,688,294Modification P00201 · 2014-02-11 · this action $6,192 · running total $637,694,486Modification P00332 · 2014-02-11 · this action $6,161 · running total $637,700,647Modification P00358 · 2014-02-11 · this action -$20,888 · running total $637,679,759Modification P00214 · 2014-02-18 · this action -$19,952 · running total $637,659,808Modification P00409 · 2014-02-18 · this action $0 · running total $637,659,808Modification P00276 · 2014-02-20 · this action $2,984 · running total $637,662,792Modification P00359 · 2014-02-20 · this action $2,061 · running total $637,664,853Modification P00403 · 2014-02-20 · this action -$313,035 · running total $637,351,817Modification P00411 · 2014-02-20 · this action $0 · running total $637,351,817Modification P00414 · 2014-02-20 · this action $0 · running total $637,351,817Modification P00415 · 2014-02-20 · this action $0 · running total $637,351,817Modification P00406 · 2014-02-21 · this action $240,000 · running total $637,591,817Modification P00187 · 2014-02-25 · this action $0 · running total $637,591,817Modification P00400 · 2014-02-26 · this action $0 · running total $637,591,817Modification P00301 · 2014-03-17 · this action $1,466 · running total $637,593,283Modification P00326 · 2014-03-17 · this action -$5,170 · running total $637,588,113Modification P00438 · 2014-03-20 · this action $0 · running total $637,588,113Modification P00184 · 2014-03-21 · this action $0 · running total $637,588,113Modification P00364 · 2014-03-21 · this action $0 · running total $637,588,113Modification P00451 · 2014-03-21 · this action $3,341 · running total $637,591,454Modification P00456 · 2014-03-21 · this action $0 · running total $637,591,454Modification P00389 · 2014-03-24 · this action $0 · running total $637,591,454Modification P00138 · 2014-03-25 · this action $0 · running total $637,591,454Modification P00309 · 2014-03-25 · this action $4,791 · running total $637,596,245Modification P00193 · 2014-03-26 · this action -$385,751 · running total $637,210,494Modification P00395 · 2014-03-26 · this action $1,583 · running total $637,212,077Modification P00426 · 2014-03-27 · this action $3,401 · running total $637,215,478Modification P00377 · 2014-03-31 · this action $4,670 · running total $637,220,148Modification P00418 · 2014-03-31 · this action $8,830 · running total $637,228,978Modification P00424 · 2014-03-31 · this action $4,107 · running total $637,233,085Modification P00473 · 2014-03-31 · this action $400 · running total $637,233,485Modification P00482 · 2014-03-31 · this action $0 · running total $637,233,485Modification P00372 · 2014-04-02 · this action $94,599 · running total $637,328,084Modification P00217 · 2014-04-03 · this action $3,660 · running total $637,331,744Modification P00405 · 2014-04-07 · this action $1,957,272 · running total $639,289,016Modification P00427 · 2014-04-07 · this action $5,427 · running total $639,294,443Modification P00433 · 2014-04-07 · this action $27,936 · running total $639,322,379Modification P00437 · 2014-04-07 · this action $894 · running total $639,323,273Modification P00370 · 2014-04-08 · this action -$1,851,988 · running total $637,471,285Modification P00378 · 2014-04-08 · this action $5,763,890 · running total $643,235,175Modification P00380 · 2014-04-08 · this action $4,498,754 · running total $647,733,929Modification P00416 · 2014-04-08 · this action $1,438 · running total $647,735,367Modification P00061 · 2014-04-09 · this action -$600 · running total $647,734,767Modification P00410 · 2014-04-09 · this action $26,000 · running total $647,760,767Modification P00393 · 2014-04-15 · this action -$1,400 · running total $647,759,367Modification P00394 · 2014-04-15 · this action $824 · running total $647,760,191Modification P00399 · 2014-04-15 · this action -$5,744 · running total $647,754,447Modification P00509 · 2014-04-15 · this action -$6,735 · running total $647,747,712Modification P00523 · 2014-04-16 · this action $18,442 · running total $647,766,154Modification P00513 · 2014-04-18 · this action $82,402 · running total $647,848,556Modification P00516 · 2014-04-18 · this action $987,866 · running total $648,836,422Modification P00518 · 2014-04-18 · this action $325,403 · running total $649,161,825Modification P00520 · 2014-04-18 · this action $138,970 · running total $649,300,795Modification P00521 · 2014-04-18 · this action $849,506 · running total $650,150,301Modification P00522 · 2014-04-18 · this action $510,115 · running total $650,660,416Modification P00544 · 2014-04-21 · this action $0 · running total $650,660,416Modification P00545 · 2014-04-21 · this action $0 · running total $650,660,416Modification P00434 · 2014-04-22 · this action $405 · running total $650,660,821Modification P00449 · 2014-04-22 · this action $4,738 · running total $650,665,559Modification P00467 · 2014-04-22 · this action -$9,495 · running total $650,656,064Modification P00540 · 2014-04-22 · this action $6,756,231 · running total $657,412,295Modification P00542 · 2014-04-22 · this action $0 · running total $657,412,295Modification P00435 · 2014-04-25 · this action -$665 · running total $657,411,630Modification P00465 · 2014-04-25 · this action -$13,376 · running total $657,398,254Modification P00503 · 2014-04-25 · this action $0 · running total $657,398,254Modification P00373 · 2014-04-29 · this action $232 · running total $657,398,485Modification P00232 · 2014-04-30 · this action $6,552 · running total $657,405,038Modification P00299 · 2014-04-30 · this action $5,257 · running total $657,410,295Modification P00547 · 2014-04-30 · this action $0 · running total $657,410,295Modification P00548 · 2014-04-30 · this action $0 · running total $657,410,295Modification P00429 · 2014-05-01 · this action -$48,580 · running total $657,361,715Modification P00390 · 2014-05-12 · this action $9,432 · running total $657,371,147Modification P00436 · 2014-05-13 · this action $12,728 · running total $657,383,875Modification P00543 · 2014-05-13 · this action $0 · running total $657,383,875Modification P00613 · 2014-05-14 · this action $0 · running total $657,383,875Modification P00461 · 2014-05-15 · this action $37,354 · running total $657,421,229Modification P00444 · 2014-05-20 · this action $9,287 · running total $657,430,516Modification P00614 · 2014-05-21 · this action -$218,847 · running total $657,211,669Modification P00555 · 2014-05-29 · this action $419,623 · running total $657,631,292Modification P00656 · 2014-05-29 · this action $0 · running total $657,631,292Modification P00642 · 2014-06-04 · this action $54,752 · running total $657,686,044Modification P00611 · 2014-06-09 · this action $0 · running total $657,686,044Modification P00583 · 2014-06-13 · this action $5,095 · running total $657,691,139Modification P00271 · 2014-06-20 · this action -$6,680 · running total $657,684,459Modification P00495 · 2014-06-26 · this action $1,900 · running total $657,686,359Modification P00554 · 2014-06-30 · this action $6,264,180 · running total $663,950,539Modification P00531 · 2014-07-08 · this action $94,379 · running total $664,044,918Modification P00740 · 2014-07-18 · this action $0 · running total $664,044,918Modification P00396 · 2014-07-24 · this action $1,542 · running total $664,046,460Modification P00668 · 2014-07-24 · this action $200,000 · running total $664,246,460Modification P00369 · 2014-07-25 · this action -$703,960 · running total $663,542,500Modification P00655 · 2014-07-25 · this action -$147,400 · running total $663,395,100Modification P00747 · 2014-07-25 · this action $8,350 · running total $663,403,450Modification P00565 · 2014-07-29 · this action $3,497 · running total $663,406,946Modification P00446 · 2014-07-30 · this action $62,650 · running total $663,469,596Modification P00539 · 2014-07-31 · this action $5,041 · running total $663,474,637Modification P00680 · 2014-07-31 · this action $3,976,523 · running total $667,451,160Modification P00693 · 2014-07-31 · this action $0 · running total $667,451,160Modification P00460 · 2014-08-01 · this action $0 · running total $667,451,160Modification P00588 · 2014-08-01 · this action $2,976 · running total $667,454,136Modification P00499 · 2014-08-05 · this action $1,326 · running total $667,455,462Modification P00774 · 2014-08-15 · this action $915 · running total $667,456,377Modification P00551 · 2014-08-20 · this action $16,010 · running total $667,472,387Modification P00592 · 2014-08-20 · this action $12,026 · running total $667,484,413Modification P00780 · 2014-08-20 · this action $26,863 · running total $667,511,276Modification P00483 · 2014-08-22 · this action $14,081 · running total $667,525,357Modification P00487 · 2014-08-22 · this action -$1,309 · running total $667,524,048Modification P00488 · 2014-08-25 · this action $23,531 · running total $667,547,579Modification P00524 · 2014-08-26 · this action -$28,430 · running total $667,519,149Modification P00468 · 2014-08-27 · this action $3,927 · running total $667,523,076Modification P00541 · 2014-08-27 · this action $520 · running total $667,523,596Modification P00314 · 2014-08-28 · this action $2,946 · running total $667,526,542Modification P00291 · 2014-08-29 · this action $4,880 · running total $667,531,422Modification P00375 · 2014-08-29 · this action $25,695 · running total $667,557,117Modification P00454 · 2014-09-02 · this action $12,175 · running total $667,569,293Modification P00425 · 2014-09-03 · this action -$523 · running total $667,568,770Modification P00498 · 2014-09-03 · this action -$841 · running total $667,567,929Modification P00716 · 2014-09-03 · this action -$1 · running total $667,567,928Modification P00772 · 2014-09-08 · this action -$14,379,238 · running total $653,188,690Modification P00489 · 2014-09-11 · this action $10,232 · running total $653,198,922Modification P00408 · 2014-09-17 · this action $2,909 · running total $653,201,831Modification P00602 · 2014-09-19 · this action $8,390 · running total $653,210,221Modification P00649 · 2014-09-19 · this action $1,355 · running total $653,211,576Modification P00167 · 2014-09-22 · this action $70,000 · running total $653,281,576Modification P00171 · 2014-09-22 · this action $2,000 · running total $653,283,576Modification P00182 · 2014-09-22 · this action $30,000 · running total $653,313,576Modification P00233 · 2014-09-22 · this action $93,614 · running total $653,407,190Modification P00243 · 2014-09-22 · this action $9,780 · running total $653,416,970Modification P00258 · 2014-09-22 · this action $3,263 · running total $653,420,233Modification P00263 · 2014-09-22 · this action $9,565 · running total $653,429,798Modification P00264 · 2014-09-22 · this action $26,952 · running total $653,456,750Modification P00280 · 2014-09-22 · this action $4,821 · running total $653,461,571Modification P00292 · 2014-09-22 · this action $5,000 · running total $653,466,571Modification P00308 · 2014-09-22 · this action $27,100 · running total $653,493,671Modification P00311 · 2014-09-22 · this action $18,000 · running total $653,511,671Modification P00313 · 2014-09-22 · this action $4,000 · running total $653,515,671Modification P00316 · 2014-09-22 · this action $3,500 · running total $653,519,171Modification P00329 · 2014-09-22 · this action $9,000 · running total $653,528,171Modification P00333 · 2014-09-22 · this action -$28,000 · running total $653,500,171Modification P00335 · 2014-09-22 · this action $43,850 · running total $653,544,021Modification P00336 · 2014-09-22 · this action -$20,000 · running total $653,524,021Modification P00341 · 2014-09-22 · this action $35,000 · running total $653,559,021Modification P00347 · 2014-09-22 · this action $2,476 · running total $653,561,497Modification P00349 · 2014-09-22 · this action $6,200 · running total $653,567,697Modification P00353 · 2014-09-22 · this action $3,324 · running total $653,571,021Modification P00354 · 2014-09-22 · this action $7,000 · running total $653,578,021Modification P00357 · 2014-09-22 · this action $14,000 · running total $653,592,021Modification P00360 · 2014-09-22 · this action $19,768 · running total $653,611,789Modification P00363 · 2014-09-22 · this action $3,738 · running total $653,615,527Modification P00371 · 2014-09-22 · this action $3,000 · running total $653,618,527Modification P00376 · 2014-09-22 · this action $2,998 · running total $653,621,525Modification P00381 · 2014-09-22 · this action $7,739 · running total $653,629,264Modification P00382 · 2014-09-22 · this action $1,950 · running total $653,631,214Modification P00391 · 2014-09-22 · this action -$1,200 · running total $653,630,014Modification P00398 · 2014-09-22 · this action $13,199 · running total $653,643,213Modification P00401 · 2014-09-22 · this action $36,200 · running total $653,679,413Modification P00407 · 2014-09-22 · this action $6,000 · running total $653,685,413Modification P00413 · 2014-09-22 · this action -$28,960 · running total $653,656,453Modification P00417 · 2014-09-22 · this action $59,282 · running total $653,715,735Modification P00428 · 2014-09-22 · this action $17,000 · running total $653,732,735Modification P00432 · 2014-09-22 · this action $3,000 · running total $653,735,735Modification P00441 · 2014-09-22 · this action $2,682 · running total $653,738,417Modification P00442 · 2014-09-22 · this action $34,612 · running total $653,773,029Modification P00443 · 2014-09-22 · this action $14,403 · running total $653,787,432Modification P00452 · 2014-09-22 · this action $0 · running total $653,787,432Modification P00453 · 2014-09-22 · this action $0 · running total $653,787,432Modification P00457 · 2014-09-22 · this action $27,400 · running total $653,814,832Modification P00459 · 2014-09-22 · this action $614 · running total $653,815,446Modification P00462 · 2014-09-22 · this action $20,000 · running total $653,835,446Modification P00463 · 2014-09-22 · this action $33,580 · running total $653,869,026Modification P00464 · 2014-09-22 · this action -$6,937 · running total $653,862,089Modification P00466 · 2014-09-22 · this action $0 · running total $653,862,089Modification P00469 · 2014-09-22 · this action $5,000 · running total $653,867,089Modification P00477 · 2014-09-22 · this action $44,035 · running total $653,911,124Modification P00484 · 2014-09-22 · this action $77,844 · running total $653,988,968Modification P00491 · 2014-09-22 · this action $4,020 · running total $653,992,988Modification P00492 · 2014-09-22 · this action $5,718 · running total $653,998,706Modification P00496 · 2014-09-22 · this action $23,000 · running total $654,021,706Modification P00572 · 2014-09-22 · this action $10,035 · running total $654,031,741Modification P00574 · 2014-09-22 · this action $3,679 · running total $654,035,420Modification P00386 · 2014-09-23 · this action $56,852 · running total $654,092,272Modification P00504 · 2014-09-23 · this action $0 · running total $654,092,272Modification P00508 · 2014-09-23 · this action $24,342 · running total $654,116,614Modification P00511 · 2014-09-23 · this action $2,500 · running total $654,119,114Modification P00519 · 2014-09-23 · this action $1,720 · running total $654,120,834Modification P00528 · 2014-09-23 · this action $10,000 · running total $654,130,834Modification P00536 · 2014-09-23 · this action $1,500 · running total $654,132,334Modification P00538 · 2014-09-23 · this action $1,120 · running total $654,133,454Modification P00550 · 2014-09-23 · this action $862 · running total $654,134,316Modification P00558 · 2014-09-23 · this action $1,356 · running total $654,135,672Modification P00562 · 2014-09-23 · this action $0 · running total $654,135,672Modification P00566 · 2014-09-23 · this action $0 · running total $654,135,672Modification P00568 · 2014-09-23 · this action $0 · running total $654,135,672Modification P00569 · 2014-09-23 · this action $0 · running total $654,135,672Modification P00570 · 2014-09-23 · this action $0 · running total $654,135,672Modification P00571 · 2014-09-23 · this action $750 · running total $654,136,422Modification P00573 · 2014-09-23 · this action $550 · running total $654,136,972Modification P00589 · 2014-09-23 · this action $0 · running total $654,136,972Modification P00590 · 2014-09-23 · this action $12,579 · running total $654,149,551Modification P00597 · 2014-09-23 · this action $900 · running total $654,150,451Modification P00608 · 2014-09-23 · this action $4,977 · running total $654,155,428Modification P00612 · 2014-09-23 · this action $2,628 · running total $654,158,056Modification P00615 · 2014-09-23 · this action $2,974 · running total $654,161,030Modification P00616 · 2014-09-23 · this action $10,000 · running total $654,171,030Modification P00617 · 2014-09-23 · this action -$77,787 · running total $654,093,243Modification P00618 · 2014-09-23 · this action $800 · running total $654,094,043Modification P00621 · 2014-09-23 · this action $74,220 · running total $654,168,263Modification P00622 · 2014-09-23 · this action $1,800 · running total $654,170,063Modification P00623 · 2014-09-23 · this action -$6,377 · running total $654,163,686Modification P00626 · 2014-09-23 · this action $6,729 · running total $654,170,415Modification P00627 · 2014-09-23 · this action $0 · running total $654,170,415Modification P00629 · 2014-09-23 · this action $9,000 · running total $654,179,415Modification P00632 · 2014-09-23 · this action -$21,614 · running total $654,157,801Modification P00633 · 2014-09-23 · this action $12,000 · running total $654,169,801Modification P00634 · 2014-09-23 · this action $7,614 · running total $654,177,415Modification P00635 · 2014-09-23 · this action $47,537 · running total $654,224,952Modification P00636 · 2014-09-23 · this action $295 · running total $654,225,247Modification P00637 · 2014-09-23 · this action $11,177 · running total $654,236,424Modification P00639 · 2014-09-23 · this action $28,978 · running total $654,265,402Modification P00640 · 2014-09-23 · this action $0 · running total $654,265,402Modification P00643 · 2014-09-24 · this action $7,300 · running total $654,272,702Modification P00648 · 2014-09-24 · this action $90,000 · running total $654,362,702Modification P00650 · 2014-09-24 · this action -$6,010 · running total $654,356,692Modification P00651 · 2014-09-24 · this action $30,835 · running total $654,387,527Modification P00652 · 2014-09-24 · this action -$3,211 · running total $654,384,316Modification P00653 · 2014-09-24 · this action $39,724 · running total $654,424,040Modification P00657 · 2014-09-24 · this action -$39,818 · running total $654,384,222Modification P00658 · 2014-09-24 · this action $1,440 · running total $654,385,662Modification P00659 · 2014-09-24 · this action -$1,395 · running total $654,384,267Modification P00661 · 2014-09-24 · this action -$63,564 · running total $654,320,703Modification P00665 · 2014-09-24 · this action $0 · running total $654,320,703Modification P00669 · 2014-09-24 · this action -$38,907 · running total $654,281,796Modification P00671 · 2014-09-24 · this action $58,000 · running total $654,339,796Modification P00672 · 2014-09-24 · this action -$39,375 · running total $654,300,421Modification P00676 · 2014-09-24 · this action $17,442 · running total $654,317,863Modification P00679 · 2014-09-24 · this action $21,461 · running total $654,339,324Modification P00681 · 2014-09-24 · this action $3,300 · running total $654,342,624Modification P00682 · 2014-09-24 · this action $19,531 · running total $654,362,155Modification P00683 · 2014-09-24 · this action $6,000 · running total $654,368,155Modification P00687 · 2014-09-24 · this action $35,000 · running total $654,403,155Modification P00689 · 2014-09-24 · this action $11,865 · running total $654,415,020Modification P00692 · 2014-09-24 · this action $2,331 · running total $654,417,351Modification P00694 · 2014-09-24 · this action $9,000 · running total $654,426,351Modification P00695 · 2014-09-24 · this action $15,000 · running total $654,441,351Modification P00698 · 2014-09-24 · this action $1,200 · running total $654,442,551Modification P00701 · 2014-09-24 · this action -$71,282 · running total $654,371,269Modification P00707 · 2014-09-24 · this action $0 · running total $654,371,269Modification P00710 · 2014-09-24 · this action $41,783 · running total $654,413,052Modification P00719 · 2014-09-24 · this action $1,877 · running total $654,414,929Modification P00720 · 2014-09-24 · this action $1,743 · running total $654,416,672Modification P00721 · 2014-09-24 · this action $0 · running total $654,416,672Modification P00722 · 2014-09-24 · this action $28,863 · running total $654,445,535Modification P00723 · 2014-09-24 · this action $10,456 · running total $654,455,991Modification P00724 · 2014-09-24 · this action $0 · running total $654,455,991Modification P00726 · 2014-09-24 · this action $2,613 · running total $654,458,604Modification P00727 · 2014-09-24 · this action $2,063 · running total $654,460,667Modification P00728 · 2014-09-24 · this action $5,099 · running total $654,465,766Modification P00730 · 2014-09-24 · this action $21,481 · running total $654,487,247Modification P00731 · 2014-09-24 · this action $1,600 · running total $654,488,847Modification P00732 · 2014-09-24 · this action $2,400 · running total $654,491,247Modification P00734 · 2014-09-24 · this action $2,675 · running total $654,493,922Modification P00735 · 2014-09-24 · this action $4,002 · running total $654,497,924Modification P00739 · 2014-09-24 · this action $5,118 · running total $654,503,042Modification P00746 · 2014-09-24 · this action $8,600 · running total $654,511,642Modification P00748 · 2014-09-24 · this action $29,000 · running total $654,540,642Modification P00750 · 2014-09-24 · this action -$12,821 · running total $654,527,821Modification P00755 · 2014-09-24 · this action $1,190 · running total $654,529,011Modification P00775 · 2014-09-24 · this action $2,000 · running total $654,531,011Modification P00779 · 2014-09-24 · this action $13,000 · running total $654,544,011Modification P00781 · 2014-09-24 · this action -$2,869 · running total $654,541,142Modification P00782 · 2014-09-24 · this action $25,375 · running total $654,566,517Modification P00787 · 2014-09-24 · this action $455 · running total $654,566,972Modification P00809 · 2014-09-24 · this action $50,990 · running total $654,617,962Modification P00812 · 2014-09-24 · this action $6,000 · running total $654,623,962Modification P00816 · 2014-09-24 · this action $4,350 · running total $654,628,312Modification P00532 · 2014-09-25 · this action $13,502 · running total $654,641,814Modification P00581 · 2014-10-16 · this action $7,922 · running total $654,649,736Modification P00713 · 2014-10-31 · this action -$523,317 · running total $654,126,419Modification P00851 · 2014-11-05 · this action $269,000 · running total $654,395,419Modification P00910 · 2014-11-21 · this action $235 · running total $654,395,654Modification P01052 · 2016-04-19 · this action $20,000,000 · running total $674,395,654Modification P01053 · 2016-05-18 · this action $3,000,000 · running total $677,395,654Modification P01054 · 2016-11-30 · this action $1,100,000 · running total $678,495,654Modification P01055 · 2017-06-27 · this action -$33,305 · running total $678,462,349
  • Base2010-08-31+$1,313,100= $1,313,100
  • Mod SA0012010-11-30+$83,418= $1,396,518
  • Mod AC0012011-01-11+$0= $1,396,518
  • Mod AC0022011-02-09+$0= $1,396,518
  • Mod SA0022011-02-10+$1,124= $1,397,642
  • Mod SA0032011-02-10+$3,275= $1,400,917
  • Mod SA0042011-04-08+$22,463,597= $23,864,514
  • Mod SA0052011-07-19+$13,414= $23,877,928
  • Mod SA0062011-09-07+$21,725,000= $45,602,928
  • Mod AC0032011-10-03+$0= $45,602,928
  • Mod SA0072011-11-18+$580,209,251= $625,812,179
  • Mod AC0042012-03-14+$0= $625,812,179
  • Mod CO01N2012-05-01+$0= $625,812,179
  • Mod CO01O2012-05-01+$0= $625,812,179
  • Mod CO01A2012-05-24+$4,252= $625,816,431
  • Mod CO01B2012-05-24+$25,000= $625,841,431
  • Mod CO01C2012-05-24+$60,000= $625,901,431
  • Mod CO01D2012-05-24+$41,099= $625,942,530
  • Mod CO01E2012-05-24+$5,500= $625,948,029
  • Mod CO01F2012-05-24+$12,739= $625,960,768
  • Mod CO01G2012-05-24+$14,970= $625,975,738
  • Mod CO01H2012-05-24+$26,400= $626,002,138
  • Mod CO01I2012-05-24+$14,500= $626,016,638
  • Mod CO01J2012-05-24+$30,000= $626,046,638
  • Mod CO01K2012-05-24+$2,330= $626,048,968
  • Mod CO01L2012-05-24+$25,000= $626,073,968
  • Mod CO01M2012-05-24+$1,265= $626,075,233
  • Mod CO01R2012-05-25+$40,000= $626,115,233
  • Mod CO01S2012-05-25-$11,000= $626,104,233
  • Mod CO01T2012-05-31+$10,000= $626,114,233
  • Mod AC0052012-06-05+$0= $626,114,233
  • Mod CO01Q2012-06-22+$17,550= $626,131,783
  • Mod CO01U2012-06-22-$15,374= $626,116,409
  • Mod CO01X2012-06-22+$3,200= $626,119,609
  • Mod CO01Y2012-06-22+$41,000= $626,160,609
  • Mod CO02A2012-06-22+$22,000= $626,182,609
  • Mod CO01V2012-06-26-$11,000= $626,171,609
  • Mod AC0062012-07-09+$0= $626,171,609
  • Mod CO01Z2012-07-11+$76,573= $626,248,182
  • Mod CO02B2012-07-11+$5,887= $626,254,069
  • Mod CO02E2012-07-17+$35,000= $626,289,069
  • Mod CO01P2012-07-25+$9,000= $626,298,069
  • Mod CO01W2012-07-25+$85,000= $626,383,069
  • Mod CO02C2012-07-25+$5,000= $626,388,069
  • Mod CO02D2012-07-25+$8,500= $626,396,569
  • Mod CO02F2012-07-25+$1,500= $626,398,069
  • Mod CO02I2012-07-26+$4,000= $626,402,069
  • Mod CO02J2012-07-26+$5,000= $626,407,069
  • Mod CO02L2012-07-27+$34,000= $626,441,069
  • Mod CO02K2012-07-30+$4,000= $626,445,069
  • Mod SA0102012-08-03-$11,000= $626,434,069
  • Mod AC0072012-08-10+$0= $626,434,069
  • Mod AC0082012-08-10+$0= $626,434,069
  • Mod AC0092012-08-10+$0= $626,434,069
  • Mod CO02H2012-08-16+$10,000= $626,444,069
  • Mod CO02Q2012-09-17+$50,000= $626,494,069
  • Mod CO02S2012-09-30+$1,000= $626,495,069
  • Mod P000102012-10-10+$4,000= $626,499,069
  • Mod P000142012-10-17+$6,000= $626,505,069
  • Mod P000172012-10-24-$17,550= $626,487,519
  • Mod A000102012-10-29+$0= $626,487,519
  • Mod A000112012-10-29+$0= $626,487,519
  • Mod P000092012-10-29-$2,500= $626,485,019
  • Mod P000162012-10-29+$0= $626,485,019
  • Mod P000012012-10-30+$99,500= $626,584,519
  • Mod P000152012-10-30+$6,000= $626,590,519
  • Mod P000202012-11-13+$2,000= $626,592,519
  • Mod P000212012-11-16+$724= $626,593,243
  • Mod P000222012-11-16+$1,676= $626,594,919
  • Mod P000242012-12-13-$26,000= $626,568,919
  • Mod A000122013-01-29+$0= $626,568,919
  • Mod CO02M2013-02-15+$5,000= $626,573,919
  • Mod P000402013-02-20+$73,588= $626,647,507
  • Mod P000322013-02-21+$1,020= $626,648,527
  • Mod P000332013-02-24+$1,281= $626,649,808
  • Mod P000482013-02-26+$61,455= $626,711,263
  • Mod P000552013-02-28+$0= $626,711,263
  • Mod P000572013-03-06-$11,000= $626,700,263
  • Mod P000562013-03-07+$20,000= $626,720,263
  • Mod P000682013-03-08+$0= $626,720,263
  • Mod P000602013-03-11+$28,000= $626,748,263
  • Mod P000452013-03-14+$1,700= $626,749,963
  • Mod P000462013-03-14+$1,500= $626,751,463
  • Mod P000962013-03-15+$0= $626,751,463
  • Mod P000812013-03-18+$15,000= $626,766,463
  • Mod P000382013-03-19+$106,646= $626,873,109
  • Mod P000302013-03-20+$4,342= $626,877,451
  • Mod P000342013-03-20+$3,296= $626,880,747
  • Mod P000842013-03-20+$15,000= $626,895,747
  • Mod P000692013-03-21-$1,794= $626,893,954
  • Mod P000732013-03-21+$0= $626,893,954
  • Mod P000592013-04-04+$14,443= $626,908,397
  • Mod P000852013-04-04+$249,663= $627,158,060
  • Mod P000902013-04-09+$47,331= $627,205,391
  • Mod P001032013-04-09+$4,821= $627,210,212
  • Mod P001042013-04-09+$8,293= $627,218,505
  • Mod P001052013-04-09+$11,581= $627,230,086
  • Mod P001062013-04-09+$29,094= $627,259,180
  • Mod P001072013-04-09+$225,655= $627,484,835
  • Mod P001092013-04-09+$94,335= $627,579,170
  • Mod P000712013-04-10-$6,359= $627,572,811
  • Mod P001132013-04-10+$152,804= $627,725,615
  • Mod P001142013-04-10+$163,077= $627,888,692
  • Mod P001082013-04-11+$449,000= $628,337,692
  • Mod P001162013-04-12+$195,448= $628,533,140
  • Mod P001222013-04-12+$1,174,261= $629,707,401
  • Mod P000352013-04-15+$0= $629,707,401
  • Mod P001312013-04-15+$80,500= $629,787,901
  • Mod P000862013-04-16+$35,000= $629,822,901
  • Mod P000262013-04-17+$2,361= $629,825,262
  • Mod P000272013-04-17+$8,618= $629,833,880
  • Mod P001342013-04-17+$85,515= $629,919,395
  • Mod P000942013-04-18+$1,200= $629,920,595
  • Mod P001192013-04-23+$150,000= $630,070,595
  • Mod P001412013-04-25+$0= $630,070,595
  • Mod P001462013-05-15+$11,000= $630,081,595
  • Mod P000702013-05-21+$2,443,364= $632,524,959
  • Mod P001482013-05-31+$11,000= $632,535,959
  • Mod P001512013-05-31+$11,800= $632,547,759
  • Mod P000872013-06-05+$41,460= $632,589,219
  • Mod P001492013-06-06+$1,021= $632,590,240
  • Mod P001622013-06-07+$140,000= $632,730,240
  • Mod P001472013-06-11+$5,000= $632,735,240
  • Mod P001642013-06-11+$7,804= $632,743,044
  • Mod P001402013-06-14+$0= $632,743,044
  • Mod P001682013-06-14+$8,500= $632,751,544
  • Mod P001572013-06-15+$6,702= $632,758,246
  • Mod P001592013-06-17+$0= $632,758,246
  • Mod P001702013-06-20+$5,000= $632,763,246
  • Mod P001302013-06-21-$430= $632,762,816
  • Mod P001612013-06-21+$7,275= $632,770,091
  • Mod P001772013-06-21+$10,500= $632,780,591
  • Mod P001782013-06-21+$16,980= $632,797,571
  • Mod P001792013-06-24+$25,000= $632,822,571
  • Mod P000582013-06-25+$18,408= $632,840,979
  • Mod P000922013-06-26+$975= $632,841,954
  • Mod P001812013-06-26+$6,786= $632,848,740
  • Mod P000372013-06-27-$3,932= $632,844,808
  • Mod P001692013-06-28+$0= $632,844,808
  • Mod P001832013-06-28+$31,000= $632,875,808
  • Mod P000642013-06-30-$43= $632,875,765
  • Mod P001112013-06-30-$3,725= $632,872,040
  • Mod P000392013-07-03+$0= $632,872,040
  • Mod P000662013-07-03-$7,674= $632,864,366
  • Mod P001182013-07-03+$11,774= $632,876,140
  • Mod P001992013-07-03+$10,000= $632,886,140
  • Mod P001952013-07-07+$800= $632,886,940
  • Mod P001432013-07-14+$165,984= $633,052,924
  • Mod P001122013-07-16+$79,744= $633,132,668
  • Mod P000832013-07-17+$15,000= $633,147,668
  • Mod P000282013-07-19+$1,475= $633,149,143
  • Mod P000652013-07-22+$3,662= $633,152,805
  • Mod P000952013-07-22+$43,500= $633,196,305
  • Mod P001212013-07-23+$153,236= $633,349,541
  • Mod P000672013-07-30-$20,185= $633,329,356
  • Mod P000762013-07-30-$2,991= $633,326,365
  • Mod P002032013-08-01+$16,600= $633,342,965
  • Mod P000412013-08-02+$72,162= $633,415,127
  • Mod P002042013-08-02+$6,200= $633,421,327
  • Mod P001282013-08-05-$18,800= $633,402,527
  • Mod P001752013-08-09+$102,000= $633,504,527
  • Mod P000792013-08-12+$2,409= $633,506,936
  • Mod P000802013-08-12+$9,801= $633,516,737
  • Mod P000992013-08-12+$15,331= $633,532,068
  • Mod P002092013-08-12+$1,000= $633,533,068
  • Mod P002212013-08-12+$3,958= $633,537,026
  • Mod P001602013-08-13+$5,500= $633,542,526
  • Mod P001972013-08-14+$6,500= $633,549,026
  • Mod P002162013-08-14+$4,000= $633,553,026
  • Mod P000542013-08-16+$1,434= $633,554,460
  • Mod P000622013-08-16+$345= $633,554,805
  • Mod P000782013-08-16-$4,265= $633,550,540
  • Mod P000822013-08-16-$16,929= $633,533,611
  • Mod P000892013-08-16+$282= $633,533,893
  • Mod P001152013-08-16-$14,896= $633,518,997
  • Mod P001202013-08-16+$305,991= $633,824,988
  • Mod P001242013-08-16+$71= $633,825,059
  • Mod P001262013-08-16+$22,788= $633,847,847
  • Mod P001362013-08-16-$60= $633,847,787
  • Mod P001852013-08-16+$17,018= $633,864,805
  • Mod P001962013-08-16+$10,000= $633,874,805
  • Mod P002062013-08-16+$2,400,000= $636,274,805
  • Mod P002072013-08-16+$127,382= $636,402,187
  • Mod P002272013-08-16+$72,700= $636,474,887
  • Mod P002052013-08-20+$9,600= $636,484,487
  • Mod P002312013-08-22+$941= $636,485,428
  • Mod P002372013-08-23+$0= $636,485,428
  • Mod P000512013-08-29+$0= $636,485,428
  • Mod P002422013-08-29+$0= $636,485,428
  • Mod P000292013-08-30+$448= $636,485,876
  • Mod P001322013-08-30+$81,785= $636,567,661
  • Mod P001532013-08-30+$329= $636,567,990
  • Mod P001632013-08-30+$1,647= $636,569,637
  • Mod P001762013-08-30+$864= $636,570,501
  • Mod P002192013-08-30+$1,553= $636,572,054
  • Mod P001742013-09-03+$28,247= $636,600,301
  • Mod P002492013-09-04+$36,200= $636,636,501
  • Mod P000442013-09-11+$13,488= $636,649,989
  • Mod P002242013-09-14+$42,000= $636,691,989
  • Mod P001862013-09-16+$133= $636,692,122
  • Mod P002232013-09-16-$7,290= $636,684,832
  • Mod P002082013-09-25+$50,716= $636,735,548
  • Mod P000252013-10-02+$11,086= $636,746,634
  • Mod P000752013-10-02+$12,864= $636,759,498
  • Mod P000972013-10-02+$1,574= $636,761,072
  • Mod P002782013-10-02+$0= $636,761,072
  • Mod P001102013-10-03-$7= $636,761,065
  • Mod P001292013-10-03+$63,703= $636,824,768
  • Mod P002222013-10-09+$47,357= $636,872,125
  • Mod P002752013-10-09+$7,371= $636,879,496
  • Mod P001172013-10-10+$2,300= $636,881,796
  • Mod P000982013-10-16+$3,461= $636,885,257
  • Mod P002452013-10-16+$117,586= $637,002,843
  • Mod P002692013-10-16-$3,253= $636,999,590
  • Mod P001272013-10-18+$3,000= $637,002,590
  • Mod P001582013-10-18+$4,685= $637,007,275
  • Mod P002502013-10-18+$28,921= $637,036,196
  • Mod P003022013-10-21+$3,000= $637,039,196
  • Mod P003052013-10-22+$13,000= $637,052,196
  • Mod P002182013-10-23+$20,597= $637,072,793
  • Mod P000472013-10-24-$14,377= $637,058,416
  • Mod P002022013-10-25+$161= $637,058,577
  • Mod P003062013-10-25+$0= $637,058,577
  • Mod P002122013-10-29+$1,249= $637,059,826
  • Mod P002892013-10-29+$7,221= $637,067,047
  • Mod P000772013-10-30+$58,000= $637,125,047
  • Mod P001522013-10-30+$3,344= $637,128,391
  • Mod P001722013-10-30+$667= $637,129,058
  • Mod P002152013-10-30+$17,650= $637,146,708
  • Mod P002352013-10-30-$13,452= $637,133,256
  • Mod P002542013-10-30+$287= $637,133,543
  • Mod P002652013-10-30+$31,906= $637,165,449
  • Mod P002202013-11-01+$7,673= $637,173,122
  • Mod P002942013-11-01+$2,586= $637,175,708
  • Mod P002972013-11-01+$10,099= $637,185,807
  • Mod P002982013-11-04+$10,739= $637,196,546
  • Mod P001332013-11-06+$5,907= $637,202,453
  • Mod P002882013-11-07-$19= $637,202,434
  • Mod P002952013-11-07+$39,269= $637,241,703
  • Mod P002872013-11-12+$10,743= $637,252,446
  • Mod P002962013-11-12+$10,939= $637,263,385
  • Mod P001902013-11-15+$13,260= $637,276,645
  • Mod P002002013-11-19+$2,601= $637,279,246
  • Mod P002252013-11-19+$2,559= $637,281,805
  • Mod P002772013-11-19+$1,714= $637,283,519
  • Mod P002132013-11-20+$14,474= $637,297,993
  • Mod P003182013-11-20-$105= $637,297,888
  • Mod P003002013-11-21+$5,954= $637,303,842
  • Mod P003282013-11-21+$0= $637,303,842
  • Mod P003302013-11-21+$0= $637,303,842
  • Mod P003272013-11-26+$11,000= $637,314,842
  • Mod P003172013-11-27+$2,776= $637,317,618
  • Mod P003202013-11-27+$8,536= $637,326,154
  • Mod P003192013-12-05-$241= $637,325,913
  • Mod P001002013-12-12+$9,501= $637,335,414
  • Mod P003422013-12-20+$0= $637,335,414
  • Mod P001502014-01-09-$9,649= $637,325,765
  • Mod P003122014-01-09-$411= $637,325,354
  • Mod P000312014-01-14-$2,437= $637,322,917
  • Mod P003152014-01-20-$89,194= $637,233,723
  • Mod P002822014-01-22+$541,787= $637,775,510
  • Mod P003222014-01-22+$4,772= $637,780,282
  • Mod P002612014-01-28-$42,660= $637,737,622
  • Mod P002292014-01-30-$2,980= $637,734,642
  • Mod P002832014-01-30+$1,199= $637,735,841
  • Mod P003432014-02-03+$1,159= $637,737,000
  • Mod P003242014-02-06-$48,706= $637,688,294
  • Mod P002012014-02-11+$6,192= $637,694,486
  • Mod P003322014-02-11+$6,161= $637,700,647
  • Mod P003582014-02-11-$20,888= $637,679,759
  • Mod P002142014-02-18-$19,952= $637,659,808
  • Mod P004092014-02-18+$0= $637,659,808
  • Mod P002762014-02-20+$2,984= $637,662,792
  • Mod P003592014-02-20+$2,061= $637,664,853
  • Mod P004032014-02-20-$313,035= $637,351,817
  • Mod P004112014-02-20+$0= $637,351,817
  • Mod P004142014-02-20+$0= $637,351,817
  • Mod P004152014-02-20+$0= $637,351,817
  • Mod P004062014-02-21+$240,000= $637,591,817
  • Mod P001872014-02-25+$0= $637,591,817
  • Mod P004002014-02-26+$0= $637,591,817
  • Mod P003012014-03-17+$1,466= $637,593,283
  • Mod P003262014-03-17-$5,170= $637,588,113
  • Mod P004382014-03-20+$0= $637,588,113
  • Mod P001842014-03-21+$0= $637,588,113
  • Mod P003642014-03-21+$0= $637,588,113
  • Mod P004512014-03-21+$3,341= $637,591,454
  • Mod P004562014-03-21+$0= $637,591,454
  • Mod P003892014-03-24+$0= $637,591,454
  • Mod P001382014-03-25+$0= $637,591,454
  • Mod P003092014-03-25+$4,791= $637,596,245
  • Mod P001932014-03-26-$385,751= $637,210,494
  • Mod P003952014-03-26+$1,583= $637,212,077
  • Mod P004262014-03-27+$3,401= $637,215,478
  • Mod P003772014-03-31+$4,670= $637,220,148
  • Mod P004182014-03-31+$8,830= $637,228,978
  • Mod P004242014-03-31+$4,107= $637,233,085
  • Mod P004732014-03-31+$400= $637,233,485
  • Mod P004822014-03-31+$0= $637,233,485
  • Mod P003722014-04-02+$94,599= $637,328,084
  • Mod P002172014-04-03+$3,660= $637,331,744
  • Mod P004052014-04-07+$1,957,272= $639,289,016
  • Mod P004272014-04-07+$5,427= $639,294,443
  • Mod P004332014-04-07+$27,936= $639,322,379
  • Mod P004372014-04-07+$894= $639,323,273
  • Mod P003702014-04-08-$1,851,988= $637,471,285
  • Mod P003782014-04-08+$5,763,890= $643,235,175
  • Mod P003802014-04-08+$4,498,754= $647,733,929
  • Mod P004162014-04-08+$1,438= $647,735,367
  • Mod P000612014-04-09-$600= $647,734,767
  • Mod P004102014-04-09+$26,000= $647,760,767
  • Mod P003932014-04-15-$1,400= $647,759,367
  • Mod P003942014-04-15+$824= $647,760,191
  • Mod P003992014-04-15-$5,744= $647,754,447
  • Mod P005092014-04-15-$6,735= $647,747,712
  • Mod P005232014-04-16+$18,442= $647,766,154
  • Mod P005132014-04-18+$82,402= $647,848,556
  • Mod P005162014-04-18+$987,866= $648,836,422
  • Mod P005182014-04-18+$325,403= $649,161,825
  • Mod P005202014-04-18+$138,970= $649,300,795
  • Mod P005212014-04-18+$849,506= $650,150,301
  • Mod P005222014-04-18+$510,115= $650,660,416
  • Mod P005442014-04-21+$0= $650,660,416
  • Mod P005452014-04-21+$0= $650,660,416
  • Mod P004342014-04-22+$405= $650,660,821
  • Mod P004492014-04-22+$4,738= $650,665,559
  • Mod P004672014-04-22-$9,495= $650,656,064
  • Mod P005402014-04-22+$6,756,231= $657,412,295
  • Mod P005422014-04-22+$0= $657,412,295
  • Mod P004352014-04-25-$665= $657,411,630
  • Mod P004652014-04-25-$13,376= $657,398,254
  • Mod P005032014-04-25+$0= $657,398,254
  • Mod P003732014-04-29+$232= $657,398,485
  • Mod P002322014-04-30+$6,552= $657,405,038
  • Mod P002992014-04-30+$5,257= $657,410,295
  • Mod P005472014-04-30+$0= $657,410,295
  • Mod P005482014-04-30+$0= $657,410,295
  • Mod P004292014-05-01-$48,580= $657,361,715
  • Mod P003902014-05-12+$9,432= $657,371,147
  • Mod P004362014-05-13+$12,728= $657,383,875
  • Mod P005432014-05-13+$0= $657,383,875
  • Mod P006132014-05-14+$0= $657,383,875
  • Mod P004612014-05-15+$37,354= $657,421,229
  • Mod P004442014-05-20+$9,287= $657,430,516
  • Mod P006142014-05-21-$218,847= $657,211,669
  • Mod P005552014-05-29+$419,623= $657,631,292
  • Mod P006562014-05-29+$0= $657,631,292
  • Mod P006422014-06-04+$54,752= $657,686,044
  • Mod P006112014-06-09+$0= $657,686,044
  • Mod P005832014-06-13+$5,095= $657,691,139
  • Mod P002712014-06-20-$6,680= $657,684,459
  • Mod P004952014-06-26+$1,900= $657,686,359
  • Mod P005542014-06-30+$6,264,180= $663,950,539
  • Mod P005312014-07-08+$94,379= $664,044,918
  • Mod P007402014-07-18+$0= $664,044,918
  • Mod P003962014-07-24+$1,542= $664,046,460
  • Mod P006682014-07-24+$200,000= $664,246,460
  • Mod P003692014-07-25-$703,960= $663,542,500
  • Mod P006552014-07-25-$147,400= $663,395,100
  • Mod P007472014-07-25+$8,350= $663,403,450
  • Mod P005652014-07-29+$3,497= $663,406,946
  • Mod P004462014-07-30+$62,650= $663,469,596
  • Mod P005392014-07-31+$5,041= $663,474,637
  • Mod P006802014-07-31+$3,976,523= $667,451,160
  • Mod P006932014-07-31+$0= $667,451,160
  • Mod P004602014-08-01+$0= $667,451,160
  • Mod P005882014-08-01+$2,976= $667,454,136
  • Mod P004992014-08-05+$1,326= $667,455,462
  • Mod P007742014-08-15+$915= $667,456,377
  • Mod P005512014-08-20+$16,010= $667,472,387
  • Mod P005922014-08-20+$12,026= $667,484,413
  • Mod P007802014-08-20+$26,863= $667,511,276
  • Mod P004832014-08-22+$14,081= $667,525,357
  • Mod P004872014-08-22-$1,309= $667,524,048
  • Mod P004882014-08-25+$23,531= $667,547,579
  • Mod P005242014-08-26-$28,430= $667,519,149
  • Mod P004682014-08-27+$3,927= $667,523,076
  • Mod P005412014-08-27+$520= $667,523,596
  • Mod P003142014-08-28+$2,946= $667,526,542
  • Mod P002912014-08-29+$4,880= $667,531,422
  • Mod P003752014-08-29+$25,695= $667,557,117
  • Mod P004542014-09-02+$12,175= $667,569,293
  • Mod P004252014-09-03-$523= $667,568,770
  • Mod P004982014-09-03-$841= $667,567,929
  • Mod P007162014-09-03-$1= $667,567,928
  • Mod P007722014-09-08-$14,379,238= $653,188,690
  • Mod P004892014-09-11+$10,232= $653,198,922
  • Mod P004082014-09-17+$2,909= $653,201,831
  • Mod P006022014-09-19+$8,390= $653,210,221
  • Mod P006492014-09-19+$1,355= $653,211,576
  • Mod P001672014-09-22+$70,000= $653,281,576
  • Mod P001712014-09-22+$2,000= $653,283,576
  • Mod P001822014-09-22+$30,000= $653,313,576
  • Mod P002332014-09-22+$93,614= $653,407,190
  • Mod P002432014-09-22+$9,780= $653,416,970
  • Mod P002582014-09-22+$3,263= $653,420,233
  • Mod P002632014-09-22+$9,565= $653,429,798
  • Mod P002642014-09-22+$26,952= $653,456,750
  • Mod P002802014-09-22+$4,821= $653,461,571
  • Mod P002922014-09-22+$5,000= $653,466,571
  • Mod P003082014-09-22+$27,100= $653,493,671
  • Mod P003112014-09-22+$18,000= $653,511,671
  • Mod P003132014-09-22+$4,000= $653,515,671
  • Mod P003162014-09-22+$3,500= $653,519,171
  • Mod P003292014-09-22+$9,000= $653,528,171
  • Mod P003332014-09-22-$28,000= $653,500,171
  • Mod P003352014-09-22+$43,850= $653,544,021
  • Mod P003362014-09-22-$20,000= $653,524,021
  • Mod P003412014-09-22+$35,000= $653,559,021
  • Mod P003472014-09-22+$2,476= $653,561,497
  • Mod P003492014-09-22+$6,200= $653,567,697
  • Mod P003532014-09-22+$3,324= $653,571,021
  • Mod P003542014-09-22+$7,000= $653,578,021
  • Mod P003572014-09-22+$14,000= $653,592,021
  • Mod P003602014-09-22+$19,768= $653,611,789
  • Mod P003632014-09-22+$3,738= $653,615,527
  • Mod P003712014-09-22+$3,000= $653,618,527
  • Mod P003762014-09-22+$2,998= $653,621,525
  • Mod P003812014-09-22+$7,739= $653,629,264
  • Mod P003822014-09-22+$1,950= $653,631,214
  • Mod P003912014-09-22-$1,200= $653,630,014
  • Mod P003982014-09-22+$13,199= $653,643,213
  • Mod P004012014-09-22+$36,200= $653,679,413
  • Mod P004072014-09-22+$6,000= $653,685,413
  • Mod P004132014-09-22-$28,960= $653,656,453
  • Mod P004172014-09-22+$59,282= $653,715,735
  • Mod P004282014-09-22+$17,000= $653,732,735
  • Mod P004322014-09-22+$3,000= $653,735,735
  • Mod P004412014-09-22+$2,682= $653,738,417
  • Mod P004422014-09-22+$34,612= $653,773,029
  • Mod P004432014-09-22+$14,403= $653,787,432
  • Mod P004522014-09-22+$0= $653,787,432
  • Mod P004532014-09-22+$0= $653,787,432
  • Mod P004572014-09-22+$27,400= $653,814,832
  • Mod P004592014-09-22+$614= $653,815,446
  • Mod P004622014-09-22+$20,000= $653,835,446
  • Mod P004632014-09-22+$33,580= $653,869,026
  • Mod P004642014-09-22-$6,937= $653,862,089
  • Mod P004662014-09-22+$0= $653,862,089
  • Mod P004692014-09-22+$5,000= $653,867,089
  • Mod P004772014-09-22+$44,035= $653,911,124
  • Mod P004842014-09-22+$77,844= $653,988,968
  • Mod P004912014-09-22+$4,020= $653,992,988
  • Mod P004922014-09-22+$5,718= $653,998,706
  • Mod P004962014-09-22+$23,000= $654,021,706
  • Mod P005722014-09-22+$10,035= $654,031,741
  • Mod P005742014-09-22+$3,679= $654,035,420
  • Mod P003862014-09-23+$56,852= $654,092,272
  • Mod P005042014-09-23+$0= $654,092,272
  • Mod P005082014-09-23+$24,342= $654,116,614
  • Mod P005112014-09-23+$2,500= $654,119,114
  • Mod P005192014-09-23+$1,720= $654,120,834
  • Mod P005282014-09-23+$10,000= $654,130,834
  • Mod P005362014-09-23+$1,500= $654,132,334
  • Mod P005382014-09-23+$1,120= $654,133,454
  • Mod P005502014-09-23+$862= $654,134,316
  • Mod P005582014-09-23+$1,356= $654,135,672
  • Mod P005622014-09-23+$0= $654,135,672
  • Mod P005662014-09-23+$0= $654,135,672
  • Mod P005682014-09-23+$0= $654,135,672
  • Mod P005692014-09-23+$0= $654,135,672
  • Mod P005702014-09-23+$0= $654,135,672
  • Mod P005712014-09-23+$750= $654,136,422
  • Mod P005732014-09-23+$550= $654,136,972
  • Mod P005892014-09-23+$0= $654,136,972
  • Mod P005902014-09-23+$12,579= $654,149,551
  • Mod P005972014-09-23+$900= $654,150,451
  • Mod P006082014-09-23+$4,977= $654,155,428
  • Mod P006122014-09-23+$2,628= $654,158,056
  • Mod P006152014-09-23+$2,974= $654,161,030
  • Mod P006162014-09-23+$10,000= $654,171,030
  • Mod P006172014-09-23-$77,787= $654,093,243
  • Mod P006182014-09-23+$800= $654,094,043
  • Mod P006212014-09-23+$74,220= $654,168,263
  • Mod P006222014-09-23+$1,800= $654,170,063
  • Mod P006232014-09-23-$6,377= $654,163,686
  • Mod P006262014-09-23+$6,729= $654,170,415
  • Mod P006272014-09-23+$0= $654,170,415
  • Mod P006292014-09-23+$9,000= $654,179,415
  • Mod P006322014-09-23-$21,614= $654,157,801
  • Mod P006332014-09-23+$12,000= $654,169,801
  • Mod P006342014-09-23+$7,614= $654,177,415
  • Mod P006352014-09-23+$47,537= $654,224,952
  • Mod P006362014-09-23+$295= $654,225,247
  • Mod P006372014-09-23+$11,177= $654,236,424
  • Mod P006392014-09-23+$28,978= $654,265,402
  • Mod P006402014-09-23+$0= $654,265,402
  • Mod P006432014-09-24+$7,300= $654,272,702
  • Mod P006482014-09-24+$90,000= $654,362,702
  • Mod P006502014-09-24-$6,010= $654,356,692
  • Mod P006512014-09-24+$30,835= $654,387,527
  • Mod P006522014-09-24-$3,211= $654,384,316
  • Mod P006532014-09-24+$39,724= $654,424,040
  • Mod P006572014-09-24-$39,818= $654,384,222
  • Mod P006582014-09-24+$1,440= $654,385,662
  • Mod P006592014-09-24-$1,395= $654,384,267
  • Mod P006612014-09-24-$63,564= $654,320,703
  • Mod P006652014-09-24+$0= $654,320,703
  • Mod P006692014-09-24-$38,907= $654,281,796
  • Mod P006712014-09-24+$58,000= $654,339,796
  • Mod P006722014-09-24-$39,375= $654,300,421
  • Mod P006762014-09-24+$17,442= $654,317,863
  • Mod P006792014-09-24+$21,461= $654,339,324
  • Mod P006812014-09-24+$3,300= $654,342,624
  • Mod P006822014-09-24+$19,531= $654,362,155
  • Mod P006832014-09-24+$6,000= $654,368,155
  • Mod P006872014-09-24+$35,000= $654,403,155
  • Mod P006892014-09-24+$11,865= $654,415,020
  • Mod P006922014-09-24+$2,331= $654,417,351
  • Mod P006942014-09-24+$9,000= $654,426,351
  • Mod P006952014-09-24+$15,000= $654,441,351
  • Mod P006982014-09-24+$1,200= $654,442,551
  • Mod P007012014-09-24-$71,282= $654,371,269
  • Mod P007072014-09-24+$0= $654,371,269
  • Mod P007102014-09-24+$41,783= $654,413,052
  • Mod P007192014-09-24+$1,877= $654,414,929
  • Mod P007202014-09-24+$1,743= $654,416,672
  • Mod P007212014-09-24+$0= $654,416,672
  • Mod P007222014-09-24+$28,863= $654,445,535
  • Mod P007232014-09-24+$10,456= $654,455,991
  • Mod P007242014-09-24+$0= $654,455,991
  • Mod P007262014-09-24+$2,613= $654,458,604
  • Mod P007272014-09-24+$2,063= $654,460,667
  • Mod P007282014-09-24+$5,099= $654,465,766
  • Mod P007302014-09-24+$21,481= $654,487,247
  • Mod P007312014-09-24+$1,600= $654,488,847
  • Mod P007322014-09-24+$2,400= $654,491,247
  • Mod P007342014-09-24+$2,675= $654,493,922
  • Mod P007352014-09-24+$4,002= $654,497,924
  • Mod P007392014-09-24+$5,118= $654,503,042
  • Mod P007462014-09-24+$8,600= $654,511,642
  • Mod P007482014-09-24+$29,000= $654,540,642
  • Mod P007502014-09-24-$12,821= $654,527,821
  • Mod P007552014-09-24+$1,190= $654,529,011
  • Mod P007752014-09-24+$2,000= $654,531,011
  • Mod P007792014-09-24+$13,000= $654,544,011
  • Mod P007812014-09-24-$2,869= $654,541,142
  • Mod P007822014-09-24+$25,375= $654,566,517
  • Mod P007872014-09-24+$455= $654,566,972
  • Mod P008092014-09-24+$50,990= $654,617,962
  • Mod P008122014-09-24+$6,000= $654,623,962
  • Mod P008162014-09-24+$4,350= $654,628,312
  • Mod P005322014-09-25+$13,502= $654,641,814
  • Mod P005812014-10-16+$7,922= $654,649,736
  • Mod P007132014-10-31-$523,317= $654,126,419
  • Mod P008512014-11-05+$269,000= $654,395,419
  • Mod P009102014-11-21+$235= $654,395,654
  • Mod P010522016-04-19+$20,000,000= $674,395,654
  • Mod P010532016-05-18+$3,000,000= $677,395,654
  • Mod P010542016-11-30+$1,100,000= $678,495,654
  • Mod P010552017-06-27-$33,305= $678,462,349
TransactionAction dateThis action (delta)Running totalDescription on this transaction
Base2010-08-31+$1,313,100$1,313,100DENVER REPLACEMENT MEDICAL CENTER FACILITY, AURORA, CO
Mod SA001· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-11-30+$83,418$1,396,518ROOM MOCK-UPS FOR REPLACEMENT MEDICAL CENTER ECHCS, AURORA, CO
Mod AC001· OTHER ADMINISTRATIVE ACTION2011-01-11+$0$1,396,518REPLACEMENT MEDICAL CENTER ECVHCS - CHANGE BID SCHEDULE TO MATCH DESIGN PACKAGES.
Mod AC002· OTHER ADMINISTRATIVE ACTION2011-02-09+$0$1,396,518REPLACEMENT MEDICAL CENTER ECVHCS - INCORPORATE REVISED FAR CLAUSE 52.204-10.
Mod SA002· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-02-10+$1,124$1,397,642MODIFICATION TO ROOM MOCK-UPS FOR REPLACEMENT MEDICAL CENTER ECHCS, AURORA, CO
Mod SA003· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-02-10+$3,275$1,400,917PARTNERING MEETING FOR REPLACEMENT MEDICAL CENTER ECHCS, AURORA, CO
Mod SA004· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-04-08+$22,463,597$23,864,514REPLACEMENT MEDICAL CENTER ECHCS, AURORA, CO EXERCISE OF OPTION 0002AA01 AND PORTION OF 0002AA02 (RFP 003)
Mod SA005· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-07-19+$13,414$23,877,928MODIFY SCI MOCK-UP FOR REPLACEMENT MEDICAL CENTER ECHCS, AURORA, CO
Mod SA006· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-09-07+$21,725,000$45,602,928CHANGE CEILING PRICE FOR REPLACEMENT MEDICAL CENTER ECHCS, AURORA, CO
Mod AC003· OTHER ADMINISTRATIVE ACTION2011-10-03+$0$45,602,928REPLACEMENT MEDICAL CENTER ECVHCS - INCORPORATE REVISED FAR CLAUSE 52.204-10.
Mod SA007· EXERCISE AN OPTION2011-11-18+$580,209,251$625,812,179TO INCREASE CLIN 0001, EXERCISE OPTION CLIN 0002 AND ADJUST THE CEILING PRICE FOR REPLACEMENT MEDICAL CENTER E…
Mod AC004· OTHER ADMINISTRATIVE ACTION2012-03-14+$0$625,812,179REPLACEMENT MEDICAL CENTER ECVHCS - INCORPORATE REVISED FAR CLAUSE 52.204-10.
Mod CO01N· EXERCISE AN OPTION2012-05-01+$0$625,812,179CO-01N PROVIDES CLARIFICATION TO THE ISSUE OF FIELD PAINTING ACCESS DOORS IN DIFFERENT WALL FINISHES THROUGHOU…
Mod CO01O· EXERCISE AN OPTION2012-05-01+$0$625,812,179IN ACCORDANCE WITH THE FOLLOWING JSI 015 DOCUMENTS, THE ROOMS LISTED IN MARKERBOARD SCHEDULE (9 PAGES REVISED…
Mod CO01A· EXERCISE AN OPTION2012-05-24+$4,252$625,816,431JVT REVISED THE TILE LAYOUT AT ALL NEW BATHROOMS; A ROW OF TILE WAS ADDED.
Mod CO01B· EXERCISE AN OPTION2012-05-24+$25,000$625,841,431ASBESTOS WAS FOUND AT DAT WHILE PERFORMING EXCAVATION.
Mod CO01C· EXERCISE AN OPTION2012-05-24+$60,000$625,901,431LEAD PAINT WAS FOUND IN BUILDING 614. CHANGE ORDER WAS MADE TO ABATE LEAD PAINT.
Mod CO01D· EXERCISE AN OPTION2012-05-24+$41,099$625,942,530ASBESTOS FOUND AT BUILDING 609 CRAWLSPACE WHILE PERFORMING ASBESTOS ABATEMENT. THIS PORTION OF WORK WAS NOT…
Mod CO01E· EXERCISE AN OPTION2012-05-24+$5,500$625,948,029CO-01E COVERS COST ASSOCIATED WITH THE APPLICATION/INSTALLATION OF ADDITIONAL FIREPROOFING IN ACCORDANCE WITH…
Mod CO01F· EXERCISE AN OPTION2012-05-24+$12,739$625,960,768THE PURPOSE OF CO-01F IS TO REMOVE ASBESTOS CLAD PIPE ON SITE AND ABANDONED STEAM TUNNEL ON MONTVIEW.
Mod CO01G· EXERCISE AN OPTION2012-05-24+$14,970$625,975,738CO-01G ADDRESSES THE RELOCATION OF AN EXISTING STORM SEWER IN CONFLICT ON MONTVIEW.
Mod CO01H· EXERCISE AN OPTION2012-05-24+$26,400$626,002,138CO-01H INCORPORATES THE FOLLOWING CHANGES AS A RESULT OF ISSUANCE OF JSI #11.
Mod CO01I· EXERCISE AN OPTION2012-05-24+$14,500$626,016,638CO-01I INCORPORATES ABATEMENT OF AN ADDITIONAL LENGTH OF PIPE ON THE SITE WEST OF DAT EXCAVATION.
Mod CO01J· EXERCISE AN OPTION2012-05-24+$30,000$626,046,638CO-01J INCORPORATES THE ABATEMENT OF ASBESTOS ON PIPING COUPLINGS IN BUILDING 608.
Mod CO01K· EXERCISE AN OPTION2012-05-24+$2,330$626,048,968CO-01K INCORPORATES THE INSTALLATION OF ADDITIONAL FIRE SPRINKLER SYSTEM HANGERS THROUGHOUT CBS.
Mod CO01L· EXERCISE AN OPTION2012-05-24+$25,000$626,073,968CO-01L INCORPORATES THE ABATEMENT OF ASBESTOS, ACM PIPE INSULATION AND BURIED FRIABLE ACM FOUND IN THE CBC-CON…
Mod CO01M· EXERCISE AN OPTION2012-05-24+$1,265$626,075,233CO-01M INCORPORATES THE REMOVAL OF EXISTING AND INSTALLATION OF NEW PIPES TO REPLACE THOSE ORIGINALLY LEAKING…
Mod CO01R· EXERCISE AN OPTION2012-05-25+$40,000$626,115,233BASED ON THE INFORMATION FROM STEAM TUNNEL REMOVAL, AND POT-HOLE INFORMATION. IT IS CLEAR THAT ASBESTOS WILL…
Mod CO01S· EXERCISE AN OPTION2012-05-25−$11,000$626,104,233IN THE ORIGINAL CONTRACT DRAWINGS, IT WAS DISCOVERED THAT SOME OF THE PRECAST CONCRETE SHEAR WALL FORCES WERE…
Mod CO01T· EXERCISE AN OPTION2012-05-31+$10,000$626,114,233KT STARTED OSI PHASE 3 STORM SEWER INSTALLATION AND FOUND ACM TUNNEL/LINE. BASED ON KT'S INFORMATION THE TUNN…
Mod AC005· OTHER ADMINISTRATIVE ACTION2012-06-05+$0$626,114,233RESCIND AC-004
Mod CO01Q· EXERCISE AN OPTION2012-06-22+$17,550$626,131,783CO-01Q ADDRESSES ITEMS ON THE CBS 4TH FLOOR RAISED BOTH BY A DOD CONTROLLED AREA SURVEY AND AS REQUESTED BY BU…
Mod CO01U· EXERCISE AN OPTION2012-06-22−$15,374$626,116,409SUBMITTAL 08 71 00 - 3 PROVIDED INFORMATION FOR CBS DOOR HARDWARE CHANGES. THE PURPOSE OF CO-01U IS TO START…
Mod CO01X· EXERCISE AN OPTION2012-06-22+$3,200$626,119,609MEDICAL CENTER REQUESTS MODIFICATION ON AN EXISTING PARKING LOT AT THE EAST SIDE OF CBS. THE CHANGES ARE ADD…
Mod CO01Y· EXERCISE AN OPTION2012-06-22+$41,000$626,160,609ACM FOUND AT MOUNTVIEW 81+50 ON 5/25/2012 AND WHEELING STREET STATION 10+65 ON 6/1/2012. CO-01Y IS PREPARED TO…
Mod CO02A· EXERCISE AN OPTION2012-06-22+$22,000$626,182,6092" STEEL GASLINE WITH ACM WRAPPING WAS FOUND WITHIN THE VA PROPERTY. CO-02A IS BEING ISSUED TO ALLOW KT CONTI…
Mod CO01V· EXERCISE AN OPTION2012-06-26−$11,000$626,171,609IN THE ORIGINAL CONTRACT DRAWINGS, IT WAS DISCOVERED THAT SOME OF THE PRECAST CONCRETE SHEAR WALL FORCES WERE…
Mod AC006· OTHER ADMINISTRATIVE ACTION2012-07-09+$0$626,171,609AMENDMENT OF CONTRACT DOCUMENT SPECIFICATION SECTION 03 30 00, SUB-PARAGRAPHT 1.5.D.5.
Mod CO01Z· CHANGE ORDER2012-07-11+$76,573$626,248,182CO-01Z IS ISSUED TO CAPTURE THE COST FOR CENTURYLINK TELECON PEDESTALS RELOCATION THAT IS NOT COVERED IN THE O…
Mod CO02B· CHANGE ORDER2012-07-11+$5,887$626,254,069ON 6/8/2012, KT INDICATED AN EXISTING 24" WATER LINE FOR OSI 12" WATER LINE TIE IN WAS AT 6 FEET LOWER THAN WH…
Mod CO02E· CHANGE ORDER2012-07-17+$35,000$626,289,069KT SUBMITTED DIFFERING SITE NOTIFICATION THAT INDICATED ACM WAS FOUND AT CLC FOOTPRINT WHEN REMOVING EXISTING…
Mod CO01P· CHANGE ORDER2012-07-25+$9,000$626,298,069ABATEMENT OF UNFORSEEN ACM INSULATED PIPE, DISCOVERED NEAR THE NORTHEAST CORNER OF POOL BUILDING 614 WHILE EX…
Mod CO01W· CHANGE ORDER2012-07-25+$85,000$626,383,069RFP 19 WAS PROVIDED TO KT, AND CO-01G WITH $14,970 INCREASED TO CONTRACT WAS ISSUED TO KT. IT WAS LATER FOUND…
Mod CO02C· CHANGE ORDER2012-07-25+$5,000$626,388,069ACM WAS FOUND AT THE WEST OF PSN AND SOUTH OF THE FUTURE CLC BUILDING. THIS IS APPROXIMATELY AT THE WEST AREA…
Mod CO02D· CHANGE ORDER2012-07-25+$8,500$626,396,569ACM WAS FOUND AT WHEELING STREET @ STATION 13+10. THE OSI CREW FOUND AN EXISTING CONCRETE TUNNEL AND ACM COMT…
Mod CO02F· CHANGE ORDER2012-07-25+$1,500$626,398,069WHILE INSTALLING MH B-1, AN EXISTING 12" RCP WAS AT THE VICINITY. EXISTING 12" RCP NEEDS TO BE CUT AND TIE IN…
Mod CO02I· CHANGE ORDER2012-07-26+$4,000$626,402,069ON 5/2/2012, THE CITY OF AURORA INFORMED KT THAT THE SPACING BETWEEN THE RELOCATED STORM SEWER LINE AND THE EX…
Mod CO02J· CHANGE ORDER2012-07-26+$5,000$626,407,069DURING OSI CONSTRUCTION PHASE, AN UNKNOWN QWEST LINE WAS DISCOVERED AT THE INTERSECTION OF MONTVIEW AND VICTO…
Mod CO02L· CHANGE ORDER2012-07-27+$34,000$626,441,069KT SUBMITED PCO 85 AND REQUEST EQUIPMENT STANDBY COSTS BECAUSE UNFORSEEN CONDITIONS WERE FOUND FOR THE OSI. A…
Mod CO02K· CHANGE ORDER2012-07-30+$4,000$626,445,069ON 2/21/2012, KT DISCOVERED A LARGE UNMARKED CONCRETE DUCTBANK THAT IS APPROXIMATELY 5' BELOW GRADE DURING OSI…
Mod SA010· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2012-08-03−$11,000$626,434,069REPLACEMENT MEDICAL CENTER ECHCS, AURORA, CO )PSN PARKING STAFF NORTH, BUILDING 11: SLABN ELEVATION&SHEAR WALL…
Mod AC007· OTHER ADMINISTRATIVE ACTION2012-08-10+$0$626,434,069REPLACEMENT MEDICAL CENTER ECVHCS - ADMINISTRATIVE CHANGE FROM BOC 2850 TO 3220.
Mod AC008· OTHER ADMINISTRATIVE ACTION2012-08-10+$0$626,434,069REPLACEMENT MEDICAL CENTER ECVHCS -SA-003 ADMINISTRATIVE CHANGE FROM BOC 2850 TO 3220.
Mod AC009· OTHER ADMINISTRATIVE ACTION2012-08-10+$0$626,434,069REPLACEMENT MEDICAL CENTER ECVHCS -SA-003 ADMINISTRATIVE CHANGE FROM BOC 2850 TO 3220.
Mod CO02H· CHANGE ORDER2012-08-16+$10,000$626,444,069THIS OFFICE IS REQUESTING THAT YOU PROVIDE THE NEW EXTERIOR CLADDING FOR THE CLINIC BUILDING (SOUTH), (CBS) TH…
Mod CO02Q· CHANGE ORDER2012-09-17+$50,000$626,494,069ON JULY 16, 2012, DURING INSTALLATION OF THE OFF-SITE INFRASTRUCTURE (OSI) ON MONTVIEW, IT WAS DISCOVERED THAT…
Mod CO02S· CHANGE ORDER2012-09-30+$1,000$626,495,0691. 06.SS.000.A: REVISE TWO TOP OF PIER ELEVATIONS ALONG GRID 06-3 FROM 85 -0 TO 83 -8 PER SS.X044. 2. 06.SS.00…
Mod P00010· CHANGE ORDER2012-10-10+$4,000$626,499,069REPLACEMENT WATER LINE THE CITY REQUESTED.
Mod P00014· CHANGE ORDER2012-10-17+$6,000$626,505,069UNKNOWN CENTURY LINK DUCK BANK
Mod P00017· CHANGE ORDER2012-10-24−$17,550$626,487,5191. 06.SS.000.A: REVISE TWO TOP OF PIER ELEVATIONS ALONG GRID 06-3 FROM 85 -0 TO 83 -8 PER SS.X044. 2. 06.SS.00…
Mod A00010· OTHER ADMINISTRATIVE ACTION2012-10-29+$0$626,487,519ADMINISTRATIVE MODIFICATION
Mod A00011· OTHER ADMINISTRATIVE ACTION2012-10-29+$0$626,487,519ADMINISTRATIVE MODIFICATION
Mod P00009· CHANGE ORDER2012-10-29−$2,500$626,485,0191ENC/IBN UNDERSLAB 1. JSI 030
Mod P00016· CHANGE ORDER2012-10-29+$0$626,485,019PVN AND PVS REDESIGN EXCAVATION, ELEVATION, AND DRILLED PIERS.
Mod P00001· CHANGE ORDER2012-10-30+$99,500$626,584,519ASBESTOS REMOVAL
Mod P00015· CHANGE ORDER2012-10-30+$6,000$626,590,519INSTALLATIONS OF VALVES
Mod P00020· CHANGE ORDER2012-11-13+$2,000$626,592,519CO-03G THERAPEUTIC POOLS AT IBN
Mod P00021· CHANGE ORDER2012-11-16+$724$626,593,243CO-02X DSC - OSI PIPES WITH ACM MASTIC
Mod P00022· CHANGE ORDER2012-11-16+$1,676$626,594,91924 INCH CMP PIPE MONTVIEW
Mod P00024· CHANGE ORDER2012-12-13−$26,000$626,568,919WATERPROOFING CREDIT
Mod A00012· OTHER ADMINISTRATIVE ACTION2013-01-29+$0$626,568,919ADMINISTRATIVE MODIFICATION ADD 52.232-99
Mod CO02M· CHANGE ORDER2013-02-15+$5,000$626,573,919DURING OSI CONSTRUCTION PHASE, AN UNKNOWN QWEST LINE WAS DISCOVERED AT THE INTERSECTION OF MONTVIEW AND VICTO…
Mod P00040· CHANGE ORDER2013-02-20+$73,588$626,647,507OSI EXCEL SWITCH CABINET RELOCATION - EXCEL'S DESIGN AND CONSTURCTION FEE
Mod P00032· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2013-02-21+$1,020$626,648,527CBS SECURITY SYSTEM MAINT
Mod P00033· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2013-02-24+$1,281$626,649,808CBS ALERTON SYSTEM UNLOCK
Mod P00048· CHANGE ORDER2013-02-26+$61,455$626,711,263CO ASSOCIATED WITH JSI 19, FOR EARTHWORK ONLY
Mod P00055· OTHER ADMINISTRATIVE ACTION2013-02-28+$0$626,711,263ADMINISTRATIVE MODIFICATION
Mod P00057· CHANGE ORDER2013-03-06−$11,000$626,700,263JSI #050 MISC STRUCTURAL STEEL REVISIONS
Mod P00056· CHANGE ORDER2013-03-07+$20,000$626,720,263CO-03G THERAPEUTIC POOLS AT IBN
Mod P00068· OTHER ADMINISTRATIVE ACTION2013-03-08+$0$626,720,263OFFSITE STORED MATERIAL PAYMENT
Mod P00060· CHANGE ORDER2013-03-11+$28,000$626,748,263CO-03G THERAPEUTIC POOLS AT IBN
Mod P00045· CHANGE ORDER2013-03-14+$1,700$626,749,963CHANGE ORDER TO MODIFY POWER IN CBS LEVEL 4 DOD ROOM 10-04-B7-01.
Mod P00046· CHANGE ORDER2013-03-14+$1,500$626,751,463TO MODIFY INSTALLATION OF CBS LEVELS 3&4 EMERGENCY LIGHTING AS OUTLINED IN JSI 023.
Mod P00096· OTHER ADMINISTRATIVE ACTION2013-03-15+$0$626,751,463ADMINISTRATIVE MODIFICATION ADD 52.215-22&52.215-23
Mod P00081· CHANGE ORDER2013-03-18+$15,000$626,766,463SAFETY SOFTWARE UPGRADE ON VA SERVER
Mod P00038· OTHER ADMINISTRATIVE ACTION2013-03-19+$106,646$626,873,109SETTLEMENT BY DETERMINATION DEFINITIZES CO-02L (PCO85) AND ESTABLISHES EQUIPMENT STANDBY RATES FOR PCO136. REP…
Mod P00030· OTHER ADMINISTRATIVE ACTION2013-03-20+$4,342$626,877,451SA-025 TEMP SIGNAGES FOR CBS
Mod P00034· OTHER ADMINISTRATIVE ACTION2013-03-20+$3,296$626,880,747SA-029 EMBED BASE PLATE
Mod P00084· CHANGE ORDER2013-03-20+$15,000$626,895,747WATERPROOFING CREDIT
Mod P00069· OTHER ADMINISTRATIVE ACTION2013-03-21−$1,794$626,893,954SA-008 SETTLEMENT BY DETERMINATION FOR CBS 1ST AND 3RD FLOOR FIREPROOFING
Mod P00073· OTHER ADMINISTRATIVE ACTION2013-03-21+$0$626,893,954SETTLEMENT BY DETERMINATION SD - P00073, CBS DOOR HARDWARE - REPLACEMENT MEDICAL CENTER, EASTERN COLORADO HEAL…
Mod P00059· OTHER ADMINISTRATIVE ACTION2013-04-04+$14,443$626,908,397SD SA-009 CBS L4 FIREPROOFING
Mod P00085· CHANGE ORDER2013-04-04+$249,663$627,158,060CHANGE ORDER TO RELOCATE AND INSTALL UTILITIES ON WHEELING ST (OSI)
Mod P00090· CHANGE ORDER2013-04-09+$47,331$627,205,391001 CM-00124 RFI #230-FAN POWERED BOX CHANGE 002 CM-00161 RFI#299-EXISITNG SHAFT WALLS 003 CM-00198 UNKNOWN MH…
Mod P00103· CHANGE ORDER2013-04-09+$4,821$627,210,212ASBESTOS ABATEMENT OF BLDG 608
Mod P00104· CHANGE ORDER2013-04-09+$8,293$627,218,505DIFFERING SITE CONDITION UNIDENTIFIED ASBESTOS PIPE IN BLDG 608.
Mod P00105· CHANGE ORDER2013-04-09+$11,581$627,230,086BLDG 608 UNWARRANTED CLEARANCE
Mod P00106· CHANGE ORDER2013-04-09+$29,094$627,259,180REMOVAL OF ACM ON CEILING IN BLDG 608.
Mod P00107· CHANGE ORDER2013-04-09+$225,655$627,484,835CM-00139 - ACM EXTRA PIPE INSULATION - BLDG 608.
Mod P00109· CHANGE ORDER2013-04-09+$94,335$627,579,170CHANGE ORDER FOR ACM - CENTERRE/DAROTECH
Mod P00071· OTHER ADMINISTRATIVE ACTION2013-04-10−$6,359$627,572,811SUPPLEMENTAL AGREEMENT, SETTLEMENT BY DETERMINATION - CENTURYLINK TELECOM PEDESTALS
Mod P00113· CHANGE ORDER2013-04-10+$152,804$627,725,615CO - CM-227 CDI-9(ONLY - DOES NOT INCLUDE 8) OSI DOCUMENT CHANGES
Mod P00114· CHANGE ORDER2013-04-10+$163,077$627,888,692CDI-8, OSI DOC CHANGES CO - CM-125 CDI-8 OSI DOCUMENT CHANGES
Mod P00108· CHANGE ORDER2013-04-11+$449,000$628,337,692EXTENDED OVERHEAD FOR 2ND TEIR SUBCONTRACTOR DARO TECH DEMOLITION AND HAZARDOUS WASTE ABATEMENT.
Mod P00116· CHANGE ORDER2013-04-12+$195,448$628,533,140CLIN 0001 CHANGES CO - CM-223 CHANGE TO CLIN 0001
Mod P00122· DEFINITIZE CHANGE ORDER2013-04-12+$1,174,261$629,707,401SA-008 SETTLEMENT BY DETERMINATION FOR CBS 95% TO 100% CD CM-15.
Mod P00035· CHANGE ORDER2013-04-15+$0$629,707,401CO-03G THERAPEUTIC POOLS AT IBN
Mod P00131· CHANGE ORDER2013-04-15+$80,500$629,787,901TO REPAIR EQUIPMENT THAT FAILED CBS LEAK TEST 4TH FLOOR CM-0056
Mod P00086· CHANGE ORDER2013-04-16+$35,000$629,822,901ENC PIPE GALLERY DRAINAGE
Mod P00026· CHANGE ORDER2013-04-17+$2,361$629,825,262CO-02X DSC - OSI PIPES WITH ACM MASTIC
Mod P00027· CHANGE ORDER2013-04-17+$8,618$629,833,880CO-02X DSC - OSI PIPES WITH ACM MASTIC
Mod P00134· CHANGE ORDER2013-04-17+$85,515$629,919,395001 CM-00124 RFI #230-FAN POWERED BOX CHANGE 002 CM-00161 RFI#299-EXISITNG SHAFT WALLS 003 CM-00198 UNKNOWN MH…
Mod P00094· CHANGE ORDER2013-04-18+$1,200$629,920,595SEQUENTIAL KEY STAMPING OF NEW VA KEYCARDS
Mod P00119· CHANGE ORDER2013-04-23+$150,000$630,070,595WATERPROOFING CREDIT
Mod P00141· OTHER ADMINISTRATIVE ACTION2013-04-25+$0$630,070,595CHANGE FUNDING LINE OF P00038. REPLACEMENT MEDICAL CENTER, EASTERN COLORADO HEALTHCARE SYSTEM AURORA, COLORAD…
Mod P00146· EXERCISE AN OPTION2013-05-15+$11,000$630,081,595REROUTE PROPOSED STORM SEWER TO AVOID AN ABANDONED STEAM VAULT (ACM CONTAINING) ON E. 19TH PLACE
Mod P00070· CHANGE ORDER2013-05-21+$2,443,364$632,524,959CO-03G THERAPEUTIC POOLS AT IBN
Mod P00148· CHANGE ORDER2013-05-31+$11,000$632,535,959DEMO MOCK UPS ON LEETSDALE
Mod P00151· CHANGE ORDER2013-05-31+$11,800$632,547,7591. 06.SS.000.A: REVISE TWO TOP OF PIER ELEVATIONS ALONG GRID 06-3 FROM 85 -0 TO 83 -8 PER SS.X044. 2. 06.SS.00…
Mod P00087· CHANGE ORDER2013-06-05+$41,460$632,589,219001 - CM-00243 ACM IN CBN 002 - CM-00463 ASBESTOS AT NW PSN 003 - CM-00531 ACM @ CBN COMM DUCT BANK 004 - CM-0…
Mod P00149· DEFINITIZE CHANGE ORDER2013-06-06+$1,021$632,590,240SD - P00149, CBS EXTERIOR CLADDING REVISIONS - REPLACEMENT MEDICAL CENTER, EASTERN COLORADO HEALTHCARE SYSTEM…
Mod P00162· CHANGE ORDER2013-06-07+$140,000$632,730,240CHANGE ORDER TO ENC.
Mod P00147· CHANGE ORDER2013-06-11+$5,000$632,735,240WATERPROOFING CREDIT
Mod P00164· CHANGE ORDER2013-06-11+$7,804$632,743,044001 CM-00124 RFI #230-FAN POWERED BOX CHANGE 002 CM-00161 RFI#299-EXISITNG SHAFT WALLS 003 CM-00198 UNKNOWN MH…
Mod P00140· OTHER ADMINISTRATIVE ACTION2013-06-14+$0$632,743,044FUNDING SITE WAS INCORRECT ON P00114
Mod P00168· EXERCISE AN OPTION2013-06-14+$8,500$632,751,544BASED ON THE INFORMATION FROM STEAM TUNNEL REMOVAL, AND POT-HOLE INFORMATION. IT IS CLEAR THAT ASBESTOS WILL…
Mod P00157· CHANGE ORDER2013-06-15+$6,702$632,758,246001 CM-00124 RFI #230-FAN POWERED BOX CHANGE 002 CM-00161 RFI#299-EXISITNG SHAFT WALLS 003 CM-00198 UNKNOWN MH…
Mod P00159· CHANGE ORDER2013-06-17+$0$632,758,246001 CM-00124 RFI #230-FAN POWERED BOX CHANGE 002 CM-00161 RFI#299-EXISITNG SHAFT WALLS 003 CM-00198 UNKNOWN MH…
Mod P00170· OTHER ADMINISTRATIVE ACTION2013-06-20+$5,000$632,763,246THIS ADMINISTRATIVE CHANGE IS TO CORRECT AN ERROR IN THE FUNDING SITE ON P00116 FROM "554CA2501H.13" TO "554CA…
Mod P00130· DEFINITIZE CHANGE ORDER2013-06-21−$430$632,762,816SD - CM-00431: DEFINITIZE CO-02W ADDING SYNTHETIC FIBER TO IBS SLAB
Mod P00161· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2013-06-21+$7,275$632,770,091VA MOVE TO CBS
Mod P00177· EXERCISE AN OPTION2013-06-21+$10,500$632,780,591BASED ON THE INFORMATION FROM STEAM TUNNEL REMOVAL, AND POT-HOLE INFORMATION. IT IS CLEAR THAT ASBESTOS WILL…
Mod P00178· EXERCISE AN OPTION2013-06-21+$16,980$632,797,571BASED ON THE INFORMATION FROM STEAM TUNNEL REMOVAL, AND POT-HOLE INFORMATION. IT IS CLEAR THAT ASBESTOS WILL…
Mod P00179· CHANGE ORDER2013-06-24+$25,000$632,822,571REMOVE THE WEST REMAINING SECTION OF ACM STEAM TUNNEL IN CONFLICT WITH NEW OSI UTILITIES BEING INSTALLED THROU…
Mod P00058· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2013-06-25+$18,408$632,840,979CM-00319 SUPPLY OF GATORS
Mod P00092· CHANGE ORDER2013-06-26+$975$632,841,954SEQUENTIAL KEY STAMPING OF NEW VA KEYCARDS
Mod P00181· CHANGE ORDER2013-06-26+$6,786$632,848,7401. 06.SS.000.A: REVISE TWO TOP OF PIER ELEVATIONS ALONG GRID 06-3 FROM 85 -0 TO 83 -8 PER SS.X044. 2. 06.SS.00…
Mod P00037· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2013-06-27−$3,932$632,844,808SA MICRO INC. DEDUCTION FROM KT CONTRACT TO DESIGN THE GRADE BEAM AND PIER AT THE CONFLICT WITHIN THE CONCOURS…
Mod P00169· OTHER ADMINISTRATIVE ACTION2013-06-28+$0$632,844,808THIS ADMINISTRATIVE CHANGE IS TO CORRECT AN ERROR IN THE FUNDING SITE ON P00116 FROM "554CA2501H.13" TO "554CA…
Mod P00183· CHANGE ORDER2013-06-28+$31,000$632,875,808ENC PIPE GALLERY
Mod P00064· OTHER ADMINISTRATIVE ACTION2013-06-30−$43$632,875,765SD - CM-0107 MODIFY BATHROOM TILES
Mod P00111· DEFINITIZE CHANGE ORDER2013-06-30−$3,725$632,872,040WATERPROOFING CREDIT
Mod P00039· CHANGE ORDER2013-07-03+$0$632,872,040SEQUENTIAL KEY STAMPING OF NEW VA KEYCARDS
Mod P00066· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2013-07-03−$7,674$632,864,366TO DEFINITIZE CO-01F, CLOSE CM-00136 OSI STEAM TUNNEL DEMO, PARTIAL ASBESTOS WORK
Mod P00118· DEFINITIZE CHANGE ORDER2013-07-03+$11,774$632,876,140SD - CM-317 DOOR HARDWARE REVISIONS AT THE CBS BUILDING
Mod P00199· CHANGE ORDER2013-07-03+$10,000$632,886,140JSI-25 - RFP D-0050 MISC. STRUCTURAL STEEL REVISIONS
Mod P00195· EXERCISE AN OPTION2013-07-07+$800$632,886,940BASED ON THE INFORMATION FROM STEAM TUNNEL REMOVAL, AND POT-HOLE INFORMATION. IT IS CLEAR THAT ASBESTOS WILL…
Mod P00143· DEFINITIZE CHANGE ORDER2013-07-14+$165,984$633,052,924CO - CM-00649 ACM PVN RAMP LOADING DOCK
Mod P00112· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2013-07-16+$79,744$633,132,668SA - CM-00277 ACM REMOVAL ALONG WHEELING STREET
Mod P00083· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2013-07-17+$15,000$633,147,668CM-00247 TEMP HEAT FOR BLDGS. 608, 609&614. PROVIDE ALL LABOR, MATERIALS AND EQUIPMENT TO SUPPLY TEMPORARY HE…
Mod P00028· DEFINITIZE CHANGE ORDER2013-07-19+$1,475$633,149,143PROVIDE ALL LABOR, EQUIPMENT, MATERIALS, AND SUPERVISION TO REMOVE AND REPAIR THE LEAKING FIRE PROTECTION PIPE…
Mod P00065· DEFINITIZE CHANGE ORDER2013-07-22+$3,662$633,152,805STANDBY @ DAT FOUNDATION
Mod P00095· DEFINITIZE CHANGE ORDER2013-07-22+$43,500$633,196,305REPLACEMENT CBS AIR DUCT
Mod P00121· DEFINITIZE CHANGE ORDER2013-07-23+$153,236$633,349,541MOISTURE MITIGATION IN CBS BLDG., 1ST FLOOR
Mod P00067· DEFINITIZE CHANGE ORDER2013-07-30−$20,185$633,329,356ACM DAT DEFINITIZE BY SETTLEMENT BY DETERMINATION
Mod P00076· DEFINITIZE CHANGE ORDER2013-07-30−$2,991$633,326,365ACM FOR CONCOURSE/DAT DEFINITIZE BY SETTLE BY DETERMINATION.
Mod P00203· EXERCISE AN OPTION2013-08-01+$16,600$633,342,965BASED ON THE INFORMATION FROM STEAM TUNNEL REMOVAL, AND POT-HOLE INFORMATION. IT IS CLEAR THAT ASBESTOS WILL…
Mod P00041· OTHER ADMINISTRATIVE ACTION2013-08-02+$72,162$633,415,127SETTLEMENT BY DETERMINATION MODIFICDATION FOR OFF-SITE INSTALLATION STORMWATER CONFLICT - ROCKY MOUNTAIN EXCAV…
Mod P00204· EXERCISE AN OPTION2013-08-02+$6,200$633,421,327BASED ON THE INFORMATION FROM STEAM TUNNEL REMOVAL, AND POT-HOLE INFORMATION. IT IS CLEAR THAT ASBESTOS WILL…
Mod P00128· CHANGE ORDER2013-08-05−$18,800$633,402,527SEQUENTIAL KEY STAMPING OF NEW VA KEYCARDS
Mod P00175· CHANGE ORDER2013-08-09+$102,000$633,504,527PROVIDE ALL LABOR, MATERIALS, EQUIPMENT, AND SUPERVISION TO INSTALL 10 PCC ON E. 17TH PLACE (OSI) WITHIN THE L…
Mod P00079· DEFINITIZE CHANGE ORDER2013-08-12+$2,409$633,506,936SD - CM-0199 CBS ADDED FIRE SPRINKLER HANGERS
Mod P00080· DEFINITIZE CHANGE ORDER2013-08-12+$9,801$633,516,737ACM POOL BLDG
Mod P00099· DEFINITIZE CHANGE ORDER2013-08-12+$15,331$633,532,068SETTLEMENT BY DETERMINATION - ACM PSN
Mod P00209· EXERCISE AN OPTION2013-08-12+$1,000$633,533,068BASED ON THE INFORMATION FROM STEAM TUNNEL REMOVAL, AND POT-HOLE INFORMATION. IT IS CLEAR THAT ASBESTOS WILL…
Mod P00221· CHANGE ORDER2013-08-12+$3,958$633,537,026CHANGE ORDER TO MODIFY POWER IN CBS LEVEL 4 DOD ROOM 10-04-B7-01.
Mod P00160· CHANGE ORDER2013-08-13+$5,500$633,542,526001 CM-00124 RFI #230-FAN POWERED BOX CHANGE 002 CM-00161 RFI#299-EXISITNG SHAFT WALLS 003 CM-00198 UNKNOWN MH…
Mod P00197· EXERCISE AN OPTION2013-08-14+$6,500$633,549,026BASED ON THE INFORMATION FROM STEAM TUNNEL REMOVAL, AND POT-HOLE INFORMATION. IT IS CLEAR THAT ASBESTOS WILL…
Mod P00216· EXERCISE AN OPTION2013-08-14+$4,000$633,553,026BASED ON THE INFORMATION FROM STEAM TUNNEL REMOVAL, AND POT-HOLE INFORMATION. IT IS CLEAR THAT ASBESTOS WILL…
Mod P00054· DEFINITIZE CHANGE ORDER2013-08-16+$1,434$633,554,460SD CM-0313 - STORM/GAS LINE CONFLICT W/INLET B-1
Mod P00062· DEFINITIZE CHANGE ORDER2013-08-16+$345$633,554,805SD CM-00088 UTILITY POTHOLING @ NW OF CBS BLDG
Mod P00078· DEFINITIZE CHANGE ORDER2013-08-16−$4,265$633,550,540SD - CM-0230 ACM REMOVAL AT CBC
Mod P00082· DEFINITIZE CHANGE ORDER2013-08-16−$16,929$633,533,611SD - P00082 - CM-00344 ACM REMOVAL AT CLC
Mod P00089· DEFINITIZE CHANGE ORDER2013-08-16+$282$633,533,893DSC UNKNOWN QWEST LINE.
Mod P00115· DEFINITIZE CHANGE ORDER2013-08-16−$14,896$633,518,997SD - P00115 CM00302 PCO 125 ACM BLACK MASTIC PIPE AT XANADU ST. THIS CONTRACT MODIFICATION DEFINITIZES CO-02A…
Mod P00120· DEFINITIZE CHANGE ORDER2013-08-16+$305,991$633,824,988SD: CM-0087 OSI DIV 3 SPEC CHANGES
Mod P00124· DEFINITIZE CHANGE ORDER2013-08-16+$71$633,825,059SD - P00124 CM00194 PCO 064 UNKNOWN XCEL DUCTBANK AT MONTVIEW ST. THIS CONTRACT MODIFICATION DEFINITIZES CO-0…
Mod P00126· DEFINITIZE CHANGE ORDER2013-08-16+$22,788$633,847,847SD - CM-00174 CBS LEVEL 3 SIM LAB
Mod P00136· DEFINITIZE CHANGE ORDER2013-08-16−$60$633,847,787SD - CM-00303 LABOR TO TIE-IN TO EXISTING 24" WATER MAIN AT LOWER ELEVATION
Mod P00185· DEFINITIZE CHANGE ORDER2013-08-16+$17,018$633,864,805ELAVATOR SLEEVES
Mod P00196· EXERCISE AN OPTION2013-08-16+$10,000$633,874,805BASED ON THE INFORMATION FROM STEAM TUNNEL REMOVAL, AND POT-HOLE INFORMATION. IT IS CLEAR THAT ASBESTOS WILL…
Mod P00206· CHANGE ORDER2013-08-16+$2,400,000$636,274,805JSI42 PVN&PVS PARKING GARAGE REDESIGN
Mod P00207· CHANGE ORDER2013-08-16+$127,382$636,402,187CO CM-700, ACM IN PVN RAMP #5
Mod P00227· EXERCISE AN OPTION2013-08-16+$72,700$636,474,887BASED ON THE INFORMATION FROM STEAM TUNNEL REMOVAL, AND POT-HOLE INFORMATION. IT IS CLEAR THAT ASBESTOS WILL…
Mod P00205· EXERCISE AN OPTION2013-08-20+$9,600$636,484,487BASED ON THE INFORMATION FROM STEAM TUNNEL REMOVAL, AND POT-HOLE INFORMATION. IT IS CLEAR THAT ASBESTOS WILL…
Mod P00231· CHANGE ORDER2013-08-22+$941$636,485,428CHANGE ORDER TO MODIFY POWER IN CBS LEVEL 4 DOD ROOM 10-04-B7-01.
Mod P00237· EXERCISE AN OPTION2013-08-23+$0$636,485,428BASED ON THE INFORMATION FROM STEAM TUNNEL REMOVAL, AND POT-HOLE INFORMATION. IT IS CLEAR THAT ASBESTOS WILL…
Mod P00051· DEFINITIZE CHANGE ORDER2013-08-29+$0$636,485,428SD CM0236 PCO 55R1 24" CMP PIPE - MONTVIEW
Mod P00242· OTHER ADMINISTRATIVE ACTION2013-08-29+$0$636,485,428FAR 52.216-17(H) BILLING PRICE CHANGE SCENAIRO 2.
Mod P00029· DEFINITIZE CHANGE ORDER2013-08-30+$448$636,485,876SD-024 DOOR HARDWARE CHANGE (RFI 385)
Mod P00132· DEFINITIZE CHANGE ORDER2013-08-30+$81,785$636,567,661SD CM-151 ACM ABATEMENT B/609 CRAWLSPACE
Mod P00153· DEFINITIZE CHANGE ORDER2013-08-30+$329$636,567,990SD CM328, LEAD-JOINT PIPE HYDRANT @ MONTVIEW/WHEELING
Mod P00163· DEFINITIZE CHANGE ORDER2013-08-30+$1,647$636,569,637SD FOR CM 0359 UNIDENTIFIED STEAMLINE.
Mod P00176· DEFINITIZE CHANGE ORDER2013-08-30+$864$636,570,501SD CM-353 ADDITIONAL ACM ABATEMENT 608, 609
Mod P00219· DEFINITIZE CHANGE ORDER2013-08-30+$1,553$636,572,054SETTLEMENT BY DETERMINATION CBS HAND DIGGING AROUND ELECTRICAL CONDUIT.
Mod P00174· EXERCISE AN OPTION2013-09-03+$28,247$636,600,301CM-00038 - ADD INLET PROTECTION
Mod P00249· CHANGE ORDER2013-09-04+$36,200$636,636,501BLDG 608 UNWARRANTED CLEARANCE
Mod P00044· DEFINITIZE CHANGE ORDER2013-09-11+$13,488$636,649,989DEFINITIZE P00087 ACM
Mod P00224· EXERCISE AN OPTION2013-09-14+$42,000$636,691,989BASED ON THE INFORMATION FROM STEAM TUNNEL REMOVAL, AND POT-HOLE INFORMATION. IT IS CLEAR THAT ASBESTOS WILL…
Mod P00186· CHANGE ORDER2013-09-16+$133$636,692,122CHANGE ORDER TO MODIFY POWER IN CBS LEVEL 4 DOD ROOM 10-04-B7-01.
Mod P00223· CHANGE ORDER2013-09-16−$7,290$636,684,832JSI 36&JSI 42, PVS
Mod P00208· EXERCISE AN OPTION2013-09-25+$50,716$636,735,548BASED ON THE INFORMATION FROM STEAM TUNNEL REMOVAL, AND POT-HOLE INFORMATION. IT IS CLEAR THAT ASBESTOS WILL…
Mod P00025· DEFINITIZE CHANGE ORDER2013-10-02+$11,086$636,746,634RME MOB AND DEMOB
Mod P00075· DEFINITIZE CHANGE ORDER2013-10-02+$12,864$636,759,498ACM MONTVIEW AND VICTOR
Mod P00097· DEFINITIZE CHANGE ORDER2013-10-02+$1,574$636,761,072REPLACEMENT MEDICAL CENTER ECHCS, AURORA, CBS DDC NAMING CONVENTION CHANGE.
Mod P00278· DEFINITIZE CHANGE ORDER2013-10-02+$0$636,761,072OSI EXCEL SWITCH CABINET RELOCATION - EXCEL'S DESIGN AND CONSTURCTION FEESD - DEFINITIZING P00114 $0.00
Mod P00110· DEFINITIZE CHANGE ORDER2013-10-03−$7$636,761,065ACM MONTVIEW STEAM PIPE.
Mod P00129· DEFINITIZE CHANGE ORDER2013-10-03+$63,703$636,824,768SA CM-177 RFP#15R LEAD ABATE B/614
Mod P00222· DEFINITIZE CHANGE ORDER2013-10-09+$47,357$636,872,125SD CM484 CBS ADDED DUCT LINER
Mod P00275· DEFINITIZE CHANGE ORDER2013-10-09+$7,371$636,879,496SD DESIGN CHANGES TO RECTIFY THE CHANGES FROM CDI 8&9 DOC CHANGES DEFINITIZING P00113
Mod P00117· DEFINITIZE CHANGE ORDER2013-10-10+$2,300$636,881,796SD - P00117 CM00273 PCO 073 OSI SEPARATION COLLAR. THIS CONTRACT MODIFICATION DEFINITIZES CO-02I DATED 07/25/…
Mod P00098· OTHER ADMINISTRATIVE ACTION2013-10-16+$3,461$636,885,257SD - CM-0018 CBS WATREPROOFING/DRAINAGE JS1 #13
Mod P00245· DEFINITIZE CHANGE ORDER2013-10-16+$117,586$637,002,843(SD) CM-00501, JSI-51 OSI PHASE 4 WATER LINE
Mod P00269· DEFINITIZE CHANGE ORDER2013-10-16−$3,253$636,999,590PNEUMATIC TUBES SD FOR COFD
Mod P00127· DEFINITIZE CHANGE ORDER2013-10-18+$3,000$637,002,590SD: ACM ON MONTVIEW STATION 81+50
Mod P00158· DEFINITIZE CHANGE ORDER2013-10-18+$4,685$637,007,275SD FOR CHANGE DOOR HARDWARE @CBS/RFI RESPONSES
Mod P00250· DEFINITIZE CHANGE ORDER2013-10-18+$28,921$637,036,196SD CM482, OSI TREE CONFLICT AT WHEELING
Mod P00302· CHANGE ORDER2013-10-21+$3,000$637,039,196CHANGE ORDER TO MODIFY POWER IN CBS LEVEL 4 DOD ROOM 10-04-B7-01.
Mod P00305· CHANGE ORDER2013-10-22+$13,000$637,052,196BLDG 608 UNWARRANTED CLEARANCE
Mod P00218· DEFINITIZE CHANGE ORDER2013-10-23+$20,597$637,072,793FRI 150 - FINISHES AT STAIR 3 CBS
Mod P00047· DEFINITIZE CHANGE ORDER2013-10-24−$14,377$637,058,416SURVEY FOR OSI DEFINITIZE.
Mod P00202· DEFINITIZE CHANGE ORDER2013-10-25+$161$637,058,577SD FOR CM 00622/PCO 0339
Mod P00306· OTHER ADMINISTRATIVE ACTION2013-10-25+$0$637,058,577FAR 52.216-17(H) BILLING PRICE CHANGE SCENAIRO 2. BILLING PRICE ADJUSTMENT FOR SEPTEMBER 2013
Mod P00212· DEFINITIZE CHANGE ORDER2013-10-29+$1,249$637,059,826TO CORRECT FUNDING ASSOCIATED WITH P00071.
Mod P00289· DEFINITIZE CHANGE ORDER2013-10-29+$7,221$637,067,047ENC PIPE GALLERY REDUNDANT HVAC PIPING.
Mod P00077· DEFINITIZE CHANGE ORDER2013-10-30+$58,000$637,125,047SD CM152 WHEEELING WATER MAIN PVN FOOTPRINT
Mod P00152· DEFINITIZE CHANGE ORDER2013-10-30+$3,344$637,128,391SD CM469, CORRECT ELEVATION OF WATER QUALITY UNIT @MONTVIEW
Mod P00172· DEFINITIZE CHANGE ORDER2013-10-30+$667$637,129,058CM554, RELOCATE CBS LEVEL 1 CW PIPE
Mod P00215· DEFINITIZE CHANGE ORDER2013-10-30+$17,650$637,146,708CM 711 UPGRADE ELEVATORS PE 5&PE 6 FROM 5,000LBS TO 6,000LBS
Mod P00235· DEFINITIZE CHANGE ORDER2013-10-30−$13,452$637,133,256SD - P00235 CM472 - CBS TUBE STEEL ON 2ND, 3RD&4TH FLOORS
Mod P00254· DEFINITIZE CHANGE ORDER2013-10-30+$287$637,133,543SD CM-444 CBS L3/L4 EMERGENCY LIGHTS
Mod P00265· DEFINITIZE CHANGE ORDER2013-10-30+$31,906$637,165,449SD FOR WATERPROOFING.
Mod P00220· DEFINITIZE CHANGE ORDER2013-11-01+$7,673$637,173,122SETTLEMENT BY DETERMINATION TO DEFINITIZE P00020 FOR THERAPEUTIC POOL AT IBN.
Mod P00294· DEFINITIZE CHANGE ORDER2013-11-01+$2,586$637,175,708SETTLEMENT BY DETERMINATION TO CLOSE CM #859 INSTALL FLOOR BOXES AT IBN.
Mod P00297· DEFINITIZE CHANGE ORDER2013-11-01+$10,099$637,185,807SETTLEMENT BY DETERMINATION TO DEFINITIZE CO P00197 AND CLOSE CM 704.
Mod P00298· DEFINITIZE CHANGE ORDER2013-11-04+$10,739$637,196,546SD TO DEFINITIZE P00168 AND CLOSE CM753 FOR ACM PIPE AT WHEELING ST AND E. 19TH PLACE.
Mod P00133· DEFINITIZE CHANGE ORDER2013-11-06+$5,907$637,202,453SD TO DEFINITIZE CO-01W - RECONSTRUCTION OF A STORMLINE ON VICTOR/MONTVIEW (OSI).
Mod P00288· DEFINITIZE CHANGE ORDER2013-11-07−$19$637,202,434MOVE 2 CAN LIGHTS IN RE OFFICE (CBS) NEAR FRONT ENTRACNE.
Mod P00295· DEFINITIZE CHANGE ORDER2013-11-07+$39,269$637,241,703SD TO DEFINITIZE P00205 WHEELING GRADE CONFLICT.
Mod P00287· DEFINITIZE CHANGE ORDER2013-11-12+$10,743$637,252,446SD TO DEFINITIZE CO P00146 TO REROUTE PROPOSED STORM SEWER TO AVOID AN ABANDONED STEAM VAULT (ACM CONTAINING)…
Mod P00296· DEFINITIZE CHANGE ORDER2013-11-12+$10,939$637,263,385SD TO DEFINITIZE P00204 FOR WORK ON STORMLINE.
Mod P00190· DEFINITIZE CHANGE ORDER2013-11-15+$13,260$637,276,645THIS MODIFICATION RELATES TO CM00290 (P00090 ITEM 4), CM00298 (P00090 ITEM 5), CM00365 (P00090 ITEM 6), AND CM…
Mod P00200· DEFINITIZE CHANGE ORDER2013-11-19+$2,601$637,279,246SD TO PAY FOR LABOR, MATERIAL, AND EQUIPMENT TO MANAGE THE BONE FOUND DURING PSN PIER DRILLING.
Mod P00225· DEFINITIZE CHANGE ORDER2013-11-19+$2,559$637,281,805SD CBS ADDITIONAL PATCH ON SOG.
Mod P00277· DEFINITIZE CHANGE ORDER2013-11-19+$1,714$637,283,519SD TO INSTALL TWO ADDITIONAL LINEAR DIFFUSER TYPE AIR DEVICES IN THE 1ST FLOOR OF THE IBS BUILDING.
Mod P00213· DEFINITIZE CHANGE ORDER2013-11-20+$14,474$637,297,993SD CBS ADDITIONAL CUT AND PATCH ON SOG.
Mod P00318· DEFINITIZE CHANGE ORDER2013-11-20−$105$637,297,888SD TO DEFINITIZE P00157 FOR THE REMOVAL OF AN UNFORSEEN STEAM VAULT ON WHEELING ST AT STATION 17+50.
Mod P00300· DEFINITIZE CHANGE ORDER2013-11-21+$5,954$637,303,842SD TO PROVIDE MARKER BOARDS AT THE CBS BUILDING.
Mod P00328· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2013-11-21+$0$637,303,842FAR 52.216-17(H) BILLING PRICE CHANGE SCENAIRO 2. BILLING PRICE ADJUSTMENT FOR OCTOBER 2013
Mod P00330· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2013-11-21+$0$637,303,842AGREEMENT FOR GENERAL CONDITION FOR MECHANICAL SUBCONTRACTORS.
Mod P00327· EXERCISE AN OPTION2013-11-26+$11,000$637,314,842BASED ON THE INFORMATION FROM STEAM TUNNEL REMOVAL, AND POT-HOLE INFORMATION. IT IS CLEAR THAT ASBESTOS WILL…
Mod P00317· DEFINITIZE CHANGE ORDER2013-11-27+$2,776$637,317,618SD CM-00727, OSI - MOVE STORM SEWER TO AVOID ELECTRICAL VAULT E. 19TH PLACE
Mod P00320· DEFINITIZE CHANGE ORDER2013-11-27+$8,536$637,326,154TO DEFINITIZE P00084 AND CLOSE CM584.SD CM-00584, JSI-10 CBS SIGNAGE REVISIONS
Mod P00319· DEFINITIZE CHANGE ORDER2013-12-05−$241$637,325,913TO DEFINITIZE P00177. EXISITING WATERLINE RELOCATION MONTVIEW ST. SD CM-00251, OSI - DSC EXISTING WATERLINE MO…
Mod P00100· DEFINITIZE CHANGE ORDER2013-12-12+$9,501$637,335,414SD TO DEFINITIZE CO-02D ABATE ACM.
Mod P00342· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2013-12-20+$0$637,335,414FAR 52.216-17(H) BILLING PRICE CHANGE SCENAIRO 2. BILLING PRICE ADJUSTMENT FOR NOVEMBER 2013
Mod P00150· DEFINITIZE CHANGE ORDER2014-01-09−$9,649$637,325,765SD: CM-312 RELOCATE XCEL TRANSFORMER
Mod P00312· DEFINITIZE CHANGE ORDER2014-01-09−$411$637,325,354TO DEFINITIZE P00014 AND P00195 AND CLOSE CM434. TELECOM CONFLICT WITH ELIPTICAL PIPE.SD CM-00434 OSI ELIPTIC…
Mod P00031· DEFINITIZE CHANGE ORDER2014-01-14−$2,437$637,322,917SD TO DEFINITIZE CO-01X FOR CBS PARKING LOT STRIPING.
Mod P00315· DEFINITIZE CHANGE ORDER2014-01-20−$89,194$637,233,723SD CM-00468 FOUNDATION DRAIN CREDIT
Mod P00282· DEFINITIZE CHANGE ORDER2014-01-22+$541,787$637,775,510SD CM377.016 ENC CONCRETE
Mod P00322· DEFINITIZE CHANGE ORDER2014-01-22+$4,772$637,780,282SD CM263 - RFI 424 - CRACK TREATMENT-3RD FLOOR AT THE CBS.
Mod P00261· DEFINITIZE CHANGE ORDER2014-01-28−$42,660$637,737,622SD P000261 - PVS LAGGING CREDIT (PCO 451, CM 793)
Mod P00229· DEFINITIZE CHANGE ORDER2014-01-30−$2,980$637,734,642SD CM-00751 IBS FOOD SERVICE ITEM 386 CREDIT
Mod P00283· DEFINITIZE CHANGE ORDER2014-01-30+$1,199$637,735,841SD CM324 RECONFIGURE THE VA AREA OF THE 2ND FLOOR OF CBS.
Mod P00343· DEFINITIZE CHANGE ORDER2014-02-03+$1,159$637,737,000SD CM 0700 - ACM FOUND AT PVN RAMP NO. 5
Mod P00324· DEFINITIZE CHANGE ORDER2014-02-06−$48,706$637,688,294SD CM-377.022 DEWATERING COFD S-0785
Mod P00201· DEFINITIZE CHANGE ORDER2014-02-11+$6,192$637,694,486SD - OSI XCEL SWITCH CABINET RELOCATE
Mod P00332· DEFINITIZE CHANGE ORDER2014-02-11+$6,161$637,700,647SD - CM-00221 VA NO EPA DOCS - B/614 DELAY.
Mod P00358· DEFINITIZE CHANGE ORDER2014-02-11−$20,888$637,679,759CM 00294 (SA) - IBN EXCAVATION CREDIT
Mod P00214· DEFINITIZE CHANGE ORDER2014-02-18−$19,952$637,659,808SD DEFINITIZE CO-2R ACM CMS 343, 388, 504&580
Mod P00409· CHANGE ORDER2014-02-18+$0$637,659,808CO P409 TE UPDATE #5 (PERIOD ENDING 11/30/2011)
Mod P00276· DEFINITIZE CHANGE ORDER2014-02-20+$2,984$637,662,792SD CM637 RFI 1815 ADD FLOOR DRAIN (D-97)
Mod P00359· DEFINITIZE CHANGE ORDER2014-02-20+$2,061$637,664,853SD - CM00773: JSI 057, ADD A RECEPTACLE TO RANGE IN KITCHEN 10-01-B2-02
Mod P00403· DEFINITIZE CHANGE ORDER2014-02-20−$313,035$637,351,817DEFINITIZING (P00108), EXT. OVERHEAD AND DELAY FOR DAROTECH SD DEFINITIZE DAROTECH P00108 CM# 357
Mod P00411· DEFINITIZE CHANGE ORDER2014-02-20+$0$637,351,817SD CM781.001 DSC ELECTRICAL/SEWER CONFLICT RME DELAY
Mod P00414· CHANGE ORDER2014-02-20+$0$637,351,817CONTRACT COMPLETION DATE CHANGE FROM 4/24/2015 TO 05/15/2015. UPDATE 7.
Mod P00415· CHANGE ORDER2014-02-20+$0$637,351,817CHANGE CONTRACT COMPLETION FORM 05/15/2015 TO 05/25/2015. UPDATE 8.
Mod P00406· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2014-02-21+$240,000$637,591,817PARKING VISITOR NORTH (PVN) PARKING GARAGE UP SIZING RAMP AND LOADING DOCK AREAS
Mod P00187· DEFINITIZE CHANGE ORDER2014-02-25+$0$637,591,817SA: CM00124 RFI #230 FAN POWERED BOX CHANGE.
Mod P00400· OTHER ADMINISTRATIVE ACTION2014-02-26+$0$637,591,817DAT DRAIN REVISION/RFI 1353A
Mod P00301· DEFINITIZE CHANGE ORDER2014-03-17+$1,466$637,593,283SD CM00056 CBS L4 FAILED LEAK TEST DEFINITIZES CO P00131 ISSUED FOR $80,500
Mod P00326· DEFINITIZE CHANGE ORDER2014-03-17−$5,170$637,588,113CM-640 ACM FOUND AT CBC
Mod P00438· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2014-03-20+$0$637,588,113FAR 52.216-17(H) BILLING PRICE CHANGE SCENAIRO 2. BILLING PRICE ADJUSTMENT FOR JANUARY 2014
Mod P00184· CHANGE ORDER2014-03-21+$0$637,588,113SEQUENTIAL KEY STAMPING OF NEW VA KEYCARDS
Mod P00364· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2014-03-21+$0$637,588,113FAR 52.216-17(H) BILLING PRICE CHANGE SCENAIRO 2. BILLING PRICE ADJUSTMENT FOR DECEMBER 2013
Mod P00451· DEFINITIZE CHANGE ORDER2014-03-21+$3,341$637,591,454SD TO DEFINITIZE P00199 (CHANGE ORDER) FOR CM0420 AND JSI 25.
Mod P00456· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2014-03-21+$0$637,591,454FAR 52.216-17(H) BILLING PRICE CHANGE SCENAIRO 2. BILLING PRICE ADJUSTMENT FOR FEBRUARY 2014
Mod P00389· CHANGE ORDER2014-03-24+$0$637,591,454001 CM-00124 RFI #230-FAN POWERED BOX CHANGE 002 CM-00161 RFI#299-EXISITNG SHAFT WALLS 003 CM-00198 UNKNOWN MH…
Mod P00138· DEFINITIZE CHANGE ORDER2014-03-25+$0$637,591,454SD - CM-00149 ACM ABATEMENT UNIT RATES
Mod P00309· OTHER ADMINISTRATIVE ACTION2014-03-25+$4,791$637,596,245REROUTE OF PIPE/RFI 1870.
Mod P00193· CHANGE ORDER2014-03-26−$385,751$637,210,494CO CM - 00415 - JSI #21 / RFP # D-0046 - PENETRATING SEALER @ GARAGE TOPPING SLABS: PSN, PVN, AND PVS.
Mod P00395· CHANGE ORDER2014-03-26+$1,583$637,212,077001 CM-00124 RFI #230-FAN POWERED BOX CHANGE 002 CM-00161 RFI#299-EXISITNG SHAFT WALLS 003 CM-00198 UNKNOWN MH…
Mod P00426· CHANGE ORDER2014-03-27+$3,401$637,215,478001 CM-00124 RFI #230-FAN POWERED BOX CHANGE 002 CM-00161 RFI#299-EXISITNG SHAFT WALLS 003 CM-00198 UNKNOWN MH…
Mod P00377· CHANGE ORDER2014-03-31+$4,670$637,220,148001 CM-00124 RFI #230-FAN POWERED BOX CHANGE 002 CM-00161 RFI#299-EXISITNG SHAFT WALLS 003 CM-00198 UNKNOWN MH…
Mod P00418· EXERCISE AN OPTION2014-03-31+$8,830$637,228,978BASED ON THE INFORMATION FROM STEAM TUNNEL REMOVAL, AND POT-HOLE INFORMATION. IT IS CLEAR THAT ASBESTOS WILL…
Mod P00424· CHANGE ORDER2014-03-31+$4,107$637,233,085001 CM-00124 RFI #230-FAN POWERED BOX CHANGE 002 CM-00161 RFI#299-EXISITNG SHAFT WALLS 003 CM-00198 UNKNOWN MH…
Mod P00473· CHANGE ORDER2014-03-31+$400$637,233,485REMOVAL OF ACM ON CEILING IN BLDG 608.
Mod P00482· CHANGE ORDER2014-03-31+$0$637,233,485CHANGE ORDER FOR ACM - CENTERRE/DAROTECH
Mod P00372· CHANGE ORDER2014-04-02+$94,599$637,328,084SD TO DEFINITIZE CHANGE ORDER P90 TO UPGRADE EXISITING SHAFT WALLS FOR FIRE RATED COMPLIANCE IN THE CBS.
Mod P00217· EXERCISE AN OPTION2014-04-03+$3,660$637,331,744BASED ON THE INFORMATION FROM STEAM TUNNEL REMOVAL, AND POT-HOLE INFORMATION. IT IS CLEAR THAT ASBESTOS WILL…
Mod P00405· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2014-04-07+$1,957,272$639,289,016FAR 52.216-17(H) BILLING PRICE CHANGE SCENAIRO 2. BILLING PRICE ADJUSTMENT FOR OCTOBER 2013
Mod P00427· EXERCISE AN OPTION2014-04-07+$5,427$639,294,443BASED ON THE INFORMATION FROM STEAM TUNNEL REMOVAL, AND POT-HOLE INFORMATION. IT IS CLEAR THAT ASBESTOS WILL…
Mod P00433· EXERCISE AN OPTION2014-04-07+$27,936$639,322,379BASED ON THE INFORMATION FROM STEAM TUNNEL REMOVAL, AND POT-HOLE INFORMATION. IT IS CLEAR THAT ASBESTOS WILL…
Mod P00437· CHANGE ORDER2014-04-07+$894$639,323,273OSI EXCEL SWITCH CABINET RELOCATION - EXCEL'S DESIGN AND CONSTURCTION FEE
Mod P00370· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2014-04-08−$1,851,988$637,471,285FAR 52.216-17(H) BILLING PRICE CHANGE SCENAIRO 2. BILLING PRICE ADJUSTMENT FOR OCTOBER 2013
Mod P00378· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2014-04-08+$5,763,890$643,235,175REA PKG#25B MECHANCIAL/ GCH
Mod P00380· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2014-04-08+$4,498,754$647,733,929FAR 52.216-17(H) BILLING PRICE CHANGE SCENAIRO 2. BILLING PRICE ADJUSTMENT FOR OCTOBER 2013
Mod P00416· DEFINITIZE CHANGE ORDER2014-04-08+$1,438$647,735,367CM759, (SA) OSI - DSC @ 17+37 TO 18+00 ELECT. DUCTBANK
Mod P00061· DEFINITIZE CHANGE ORDER2014-04-09−$600$647,734,767C0089, MAINTAIN EXISTING FLOORS IN CBS TELECOM ROOM
Mod P00410· CHANGE ORDER2014-04-09+$26,000$647,760,767(CO) CM 728.001/ PCO 0523 - REMOABLE BOLLARDS AT PVN.
Mod P00393· CHANGE ORDER2014-04-15−$1,400$647,759,367001 CM-00124 RFI #230-FAN POWERED BOX CHANGE 002 CM-00161 RFI#299-EXISITNG SHAFT WALLS 003 CM-00198 UNKNOWN MH…
Mod P00394· CHANGE ORDER2014-04-15+$824$647,760,191SD TO INSTALL PLUMBING FOR DAT L3 DRAINS PER RFI 1616 (CM 00783).
Mod P00399· CHANGE ORDER2014-04-15−$5,744$647,754,447SD TO PROVIDE FOR THE SOW AS DEFINED IN RFP D-143 (REVISED), WHICH INCLUDES EIGHT (8) CHANGES TO RETURN OF SUB…
Mod P00509· CHANGE ORDER2014-04-15−$6,735$647,747,712001 CM-00124 RFI #230-FAN POWERED BOX CHANGE 002 CM-00161 RFI#299-EXISITNG SHAFT WALLS 003 CM-00198 UNKNOWN MH…
Mod P00523· EXERCISE AN OPTION2014-04-16+$18,442$647,766,154BASED ON THE INFORMATION FROM STEAM TUNNEL REMOVAL, AND POT-HOLE INFORMATION. IT IS CLEAR THAT ASBESTOS WILL…
Mod P00513· EXERCISE AN OPTION2014-04-18+$82,402$647,848,556BASED ON THE INFORMATION FROM STEAM TUNNEL REMOVAL, AND POT-HOLE INFORMATION. IT IS CLEAR THAT ASBESTOS WILL…
Mod P00516· EXERCISE AN OPTION2014-04-18+$987,866$648,836,422REA PACKAGE #27 LOW VOLTAGE
Mod P00518· EXERCISE AN OPTION2014-04-18+$325,403$649,161,825BASED ON THE INFORMATION FROM STEAM TUNNEL REMOVAL, AND POT-HOLE INFORMATION. IT IS CLEAR THAT ASBESTOS WILL…
Mod P00520· EXERCISE AN OPTION2014-04-18+$138,970$649,300,795OVERHEAD COILING DOORS&GRILLES, BP#58, CM377.02
Mod P00521· EXERCISE AN OPTION2014-04-18+$849,506$650,150,301REA#38, STRUCTURAL CONCRETE
Mod P00522· DEFINITIZE CHANGE ORDER2014-04-18+$510,115$650,660,416REA PKG#48 ARCHITECTURAL PRECAST
Mod P00544· CHANGE ORDER2014-04-21+$0$650,660,416001 CM-00124 RFI #230-FAN POWERED BOX CHANGE 002 CM-00161 RFI#299-EXISITNG SHAFT WALLS 003 CM-00198 UNKNOWN MH…
Mod P00545· CHANGE ORDER2014-04-21+$0$650,660,416001 CM-00124 RFI #230-FAN POWERED BOX CHANGE 002 CM-00161 RFI#299-EXISITNG SHAFT WALLS 003 CM-00198 UNKNOWN MH…
Mod P00434· EXERCISE AN OPTION2014-04-22+$405$650,660,821BASED ON THE INFORMATION FROM STEAM TUNNEL REMOVAL, AND POT-HOLE INFORMATION. IT IS CLEAR THAT ASBESTOS WILL…
Mod P00449· DEFINITIZE CHANGE ORDER2014-04-22+$4,738$650,665,559TO DEFINITIZE P00085 WHEELING RELOCATION OSI.
Mod P00467· EXERCISE AN OPTION2014-04-22−$9,495$650,656,064BASED ON THE INFORMATION FROM STEAM TUNNEL REMOVAL, AND POT-HOLE INFORMATION. IT IS CLEAR THAT ASBESTOS WILL…
Mod P00540· EXERCISE AN OPTION2014-04-22+$6,756,231$657,412,295BASED ON THE INFORMATION FROM STEAM TUNNEL REMOVAL, AND POT-HOLE INFORMATION. IT IS CLEAR THAT ASBESTOS WILL…
Mod P00542· CHANGE ORDER2014-04-22+$0$657,412,295001 CM-00124 RFI #230-FAN POWERED BOX CHANGE 002 CM-00161 RFI#299-EXISITNG SHAFT WALLS 003 CM-00198 UNKNOWN MH…
Mod P00435· CHANGE ORDER2014-04-25−$665$657,411,630BLDG 608 UNWARRANTED CLEARANCE
Mod P00465· EXERCISE AN OPTION2014-04-25−$13,376$657,398,254BASED ON THE INFORMATION FROM STEAM TUNNEL REMOVAL, AND POT-HOLE INFORMATION. IT IS CLEAR THAT ASBESTOS WILL…
Mod P00503· CHANGE ORDER2014-04-25+$0$657,398,254001 CM-00124 RFI #230-FAN POWERED BOX CHANGE 002 CM-00161 RFI#299-EXISITNG SHAFT WALLS 003 CM-00198 UNKNOWN MH…
Mod P00373· CHANGE ORDER2014-04-29+$232$657,398,485001 CM-00124 RFI #230-FAN POWERED BOX CHANGE 002 CM-00161 RFI#299-EXISITNG SHAFT WALLS 003 CM-00198 UNKNOWN MH…
Mod P00232· EXERCISE AN OPTION2014-04-30+$6,552$657,405,038BASED ON THE INFORMATION FROM STEAM TUNNEL REMOVAL, AND POT-HOLE INFORMATION. IT IS CLEAR THAT ASBESTOS WILL…
Mod P00299· CHANGE ORDER2014-04-30+$5,257$657,410,295CHANGE ORDER TO MODIFY POWER IN CBS LEVEL 4 DOD ROOM 10-04-B7-01.
Mod P00547· CHANGE ORDER2014-04-30+$0$657,410,295001 CM-00124 RFI #230-FAN POWERED BOX CHANGE 002 CM-00161 RFI#299-EXISITNG SHAFT WALLS 003 CM-00198 UNKNOWN MH…
Mod P00548· CHANGE ORDER2014-04-30+$0$657,410,295001 CM-00124 RFI #230-FAN POWERED BOX CHANGE 002 CM-00161 RFI#299-EXISITNG SHAFT WALLS 003 CM-00198 UNKNOWN MH…
Mod P00429· CHANGE ORDER2014-05-01−$48,580$657,361,715001 CM-00124 RFI #230-FAN POWERED BOX CHANGE 002 CM-00161 RFI#299-EXISITNG SHAFT WALLS 003 CM-00198 UNKNOWN MH…
Mod P00390· DEFINITIZE CHANGE ORDER2014-05-12+$9,432$657,371,147CM00575 PVN PIER CAP / GRADE BEAM
Mod P00436· EXERCISE AN OPTION2014-05-13+$12,728$657,383,875BASED ON THE INFORMATION FROM STEAM TUNNEL REMOVAL, AND POT-HOLE INFORMATION. IT IS CLEAR THAT ASBESTOS WILL…
Mod P00543· CHANGE ORDER2014-05-13+$0$657,383,875001 CM-00124 RFI #230-FAN POWERED BOX CHANGE 002 CM-00161 RFI#299-EXISITNG SHAFT WALLS 003 CM-00198 UNKNOWN MH…
Mod P00613· DEFINITIZE CHANGE ORDER2014-05-14+$0$657,383,875SD: CM00557 PCO 400 KITCHEN GREASE VENT
Mod P00461· CHANGE ORDER2014-05-15+$37,354$657,421,229SD TO MODIFY EXISTING PARKING LOT AT THE INTERSECTION OF URSULA STREET AND COLFAX AVE.
Mod P00444· DEFINITIZE CHANGE ORDER2014-05-20+$9,287$657,430,516TO DEFINITIZE P00085 WHEELING RELOCATION OSI.
Mod P00614· CHANGE ORDER2014-05-21−$218,847$657,211,669CO (RFP D-0213) VR #280 NURSE CALL CONDUIT IN INTERSTITIAL SPACES
Mod P00555· DEFINITIZE CHANGE ORDER2014-05-29+$419,623$657,631,292SETTLEMENT BY DETERMINATION - ELEVATORS- REA #72.
Mod P00656· EXERCISE AN OPTION2014-05-29+$0$657,631,292SETTLEMENT BY DETERMINATION, DEFINITIZE P00540, MECHANICAL REA #25C.
Mod P00642· EXERCISE AN OPTION2014-06-04+$54,752$657,686,044CM1108, RFI 2695: FAR 52.243-4&VAAR 852.236-88-B
Mod P00611· CHANGE ORDER2014-06-09+$0$657,686,0441. 06.SS.000.A: REVISE TWO TOP OF PIER ELEVATIONS ALONG GRID 06-3 FROM 85 -0 TO 83 -8 PER SS.X044. 2. 06.SS.00…
Mod P00583· CHANGE ORDER2014-06-13+$5,095$657,691,139001 CM-00124 RFI #230-FAN POWERED BOX CHANGE 002 CM-00161 RFI#299-EXISITNG SHAFT WALLS 003 CM-00198 UNKNOWN MH…
Mod P00271· DEFINITIZE CHANGE ORDER2014-06-20−$6,680$657,684,459SD CM-739 VR 101 LV CREDIT (D-91)
Mod P00495· DEFINITIZE CHANGE ORDER2014-06-26+$1,900$657,686,359SA DEFINITIZE'S CO-01V. (CM 00286 PCO 87 JSI #14 BLDG 11 - NORTH SHEAR WALL DRAWINGS)
Mod P00554· DEFINITIZE CHANGE ORDER2014-06-30+$6,264,180$663,950,539REA PKG #26, BERG ELECTRIC
Mod P00531· DEFINITIZE CHANGE ORDER2014-07-08+$94,379$664,044,918SD: CM377.035, REA #50, ROOFING&ABOVE GROUND WATERPROOFING
Mod P00740· CHANGE ORDER2014-07-18+$0$664,044,918OSI EXCEL SWITCH CABINET RELOCATION - EXCEL'S DESIGN AND CONSTRUCTION FEE
Mod P00396· CHANGE ORDER2014-07-24+$1,542$664,046,460001 CM-00124 RFI #230-FAN POWERED BOX CHANGE 002 CM-00161 RFI#299-EXISITNG SHAFT WALLS 003 CM-00198 UNKNOWN MH…
Mod P00668· CHANGE ORDER2014-07-24+$200,000$664,246,460ASBESTOS ON WHEELING STREET CO: ACM WHEELING STREET
Mod P00369· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2014-07-25−$703,960$663,542,500SD FOR TERRAZZO CREDIT OF ($703,960.00); RELATING TO CM 377.018, BP 132, PCO 258 AND COFD LETTER DATED 12/11/2…
Mod P00655· CHANGE ORDER2014-07-25−$147,400$663,395,100001 CM-00124 RFI #230-FAN POWERED BOX CHANGE 002 CM-00161 RFI#299-EXISITNG SHAFT WALLS 003 CM-00198 UNKNOWN MH…
Mod P00747· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2014-07-25+$8,350$663,403,450FAR 52.243-4 - CHANGES&VAAR 852.236-88-B - CHANGES, SUPPLEMENT. JSI CD REVISIONS TO LANDSCAPE GATE HARDWARE&E…
Mod P00565· CHANGE ORDER2014-07-29+$3,497$663,406,946001 CM-00124 RFI #230-FAN POWERED BOX CHANGE 002 CM-00161 RFI#299-EXISITNG SHAFT WALLS 003 CM-00198 UNKNOWN MH…
Mod P00446· DEFINITIZE CHANGE ORDER2014-07-30+$62,650$663,469,596SETTLEMENT BY DETERMINATION, DEFINITIZE BID PACKAGE 91, OPERABLE PARTICITIONS.
Mod P00539· CHANGE ORDER2014-07-31+$5,041$663,474,637001 CM-00124 RFI #230-FAN POWERED BOX CHANGE 002 CM-00161 RFI#299-EXISITNG SHAFT WALLS 003 CM-00198 UNKNOWN MH…
Mod P00680· EXERCISE AN OPTION2014-07-31+$3,976,523$667,451,160REA PKG#25A C&B PLUMBING
Mod P00693· DEFINITIZE CHANGE ORDER2014-07-31+$0$667,451,160NO COST SD TO DEFINITIZE P00550 (CHANGE ORDER) FOR DAT ROOM 03-02-E10-05 UTILITY SHELF MODIFICATIONS.
Mod P00460· CHANGE ORDER2014-08-01+$0$667,451,160001 CM-00124 RFI #230-FAN POWERED BOX CHANGE 002 CM-00161 RFI#299-EXISITNG SHAFT WALLS 003 CM-00198 UNKNOWN MH…
Mod P00588· CHANGE ORDER2014-08-01+$2,976$667,454,136SD FOR CM 0448, DEFINITIZE P00015 FOR OSI ADDITINOAL WATER VALVES.
Mod P00499· CHANGE ORDER2014-08-05+$1,326$667,455,462CM735 CON RETAIL SHOP FIRE PROTECTION
Mod P00774· OTHER ADMINISTRATIVE ACTION2014-08-15+$915$667,456,377SUPPLEMENTAL AGREEMENT, SETTLEMENT BY DETERMINATION - DENTAL CHAIRS
Mod P00551· CHANGE ORDER2014-08-20+$16,010$667,472,387001 CM-00124 RFI #230-FAN POWERED BOX CHANGE 002 CM-00161 RFI#299-EXISITNG SHAFT WALLS 003 CM-00198 UNKNOWN MH…
Mod P00592· CHANGE ORDER2014-08-20+$12,026$667,484,413001 CM-00124 RFI #230-FAN POWERED BOX CHANGE 002 CM-00161 RFI#299-EXISITNG SHAFT WALLS 003 CM-00198 UNKNOWN MH…
Mod P00780· CHANGE ORDER2014-08-20+$26,863$667,511,276SETTLEMENT BY DETERMINATION, DEFINITIZE CO P00057 AND SETTLE S-1285.
Mod P00483· DEFINITIZE CHANGE ORDER2014-08-22+$14,081$667,525,357SD CM00971 RFI 2266 RES SVC LVL FOUNDATION VENT
Mod P00487· DEFINITIZE CHANGE ORDER2014-08-22−$1,309$667,524,048P00487(SD) - ACM @ PVN NW CORNER NO. 7 - CM 0978
Mod P00488· DEFINITIZE CHANGE ORDER2014-08-25+$23,531$667,547,579TO DEFINITIZE P00085 WHEELING RELOCATION OSI.
Mod P00524· EXERCISE AN OPTION2014-08-26−$28,430$667,519,149BASED ON THE INFORMATION FROM STEAM TUNNEL REMOVAL, AND POT-HOLE INFORMATION. IT IS CLEAR THAT ASBESTOS WILL…
Mod P00468· CHANGE ORDER2014-08-27+$3,927$667,523,076001 CM-00124 RFI #230-FAN POWERED BOX CHANGE 002 CM-00161 RFI#299-EXISITNG SHAFT WALLS 003 CM-00198 UNKNOWN MH…
Mod P00541· CHANGE ORDER2014-08-27+$520$667,523,596001 CM-00124 RFI #230-FAN POWERED BOX CHANGE 002 CM-00161 RFI#299-EXISITNG SHAFT WALLS 003 CM-00198 UNKNOWN MH…
Mod P00314· CHANGE ORDER2014-08-28+$2,946$667,526,542CBS BLDG LEVEL 4 CHANGES, JSI#7
Mod P00291· OTHER ADMINISTRATIVE ACTION2014-08-29+$4,880$667,531,422SUPPLEMENTAL AGREEMENT, SETTLEMENT BY DETERMINATION - CENTURYLINK TELECOM PEDESTALS
Mod P00375· CHANGE ORDER2014-08-29+$25,695$667,557,117001 CM-00124 RFI #230-FAN POWERED BOX CHANGE 002 CM-00161 RFI#299-EXISITNG SHAFT WALLS 003 CM-00198 UNKNOWN MH…
Mod P00454· DEFINITIZE CHANGE ORDER2014-09-02+$12,175$667,569,293TO DEFINITIZE P00085 WHEELING RELOCATION OSI.
Mod P00425· CHANGE ORDER2014-09-03−$523$667,568,770001 CM-00124 RFI #230-FAN POWERED BOX CHANGE 002 CM-00161 RFI#299-EXISITNG SHAFT WALLS 003 CM-00198 UNKNOWN MH…
Mod P00498· CHANGE ORDER2014-09-03−$841$667,567,929001 CM-00124 RFI #230-FAN POWERED BOX CHANGE 002 CM-00161 RFI#299-EXISITNG SHAFT WALLS 003 CM-00198 UNKNOWN MH…
Mod P00716· DEFINITIZE CHANGE ORDER2014-09-03−$1$667,567,928BASED ON THE INFORMATION FROM STEAM TUNNEL REMOVAL, AND POT-HOLE INFORMATION. IT IS CLEAR THAT ASBESTOS WILL…
Mod P00772· CHANGE ORDER2014-09-08−$14,379,238$653,188,690DELETE CLC BUILDING FROM CONTRACT
Mod P00489· CHANGE ORDER2014-09-11+$10,232$653,198,922CHANGE ORDER FOR ACM - CENTERRE/DAROTECH
Mod P00408· CHANGE ORDER2014-09-17+$2,909$653,201,831WATERPROOFING CREDIT
Mod P00602· DEFINITIZE CHANGE ORDER2014-09-19+$8,390$653,210,221SD CM-01099/PCO-0569 - VA RFI-1510/K-T RFI-1666 PVS ADDITIONAL MANIFOLD
Mod P00649· DEFINITIZE CHANGE ORDER2014-09-19+$1,355$653,211,576CHANGE ORDER TO MODIFY POWER IN CBS LEVEL 4 DOD ROOM 10-04-B7-01.
Mod P00167· CHANGE ORDER2014-09-22+$70,000$653,281,576001 CM-00124 RFI #230-FAN POWERED BOX CHANGE 002 CM-00161 RFI#299-EXISITNG SHAFT WALLS 003 CM-00198 UNKNOWN MH…
Mod P00171· OTHER ADMINISTRATIVE ACTION2014-09-22+$2,000$653,283,576THIS ADMINISTRATIVE CHANGE IS TO CORRECT AN ERROR IN THE FUNDING SITE ON P00116 FROM "554CA2501H.13" TO "554CA…
Mod P00182· CHANGE ORDER2014-09-22+$30,000$653,313,576SEQUENTIAL KEY STAMPING OF NEW VA KEYCARDS
Mod P00233· CHANGE ORDER2014-09-22+$93,614$653,407,190OSI EXCEL SWITCH CABINET RELOCATION - EXCEL'S DESIGN AND CONSTURCTION FEE
Mod P00243· CHANGE ORDER2014-09-22+$9,780$653,416,970SEQUENTIAL KEY STAMPING OF NEW VA KEYCARDS
Mod P00258· CHANGE ORDER2014-09-22+$3,263$653,420,233BLDG 608 UNWARRANTED CLEARANCE
Mod P00263· CHANGE ORDER2014-09-22+$9,565$653,429,798CHANGE ORDER TO MODIFY POWER IN CBS LEVEL 4 DOD ROOM 10-04-B7-01.
Mod P00264· CHANGE ORDER2014-09-22+$26,952$653,456,750CHANGE ORDER TO MODIFY POWER IN CBS LEVEL 4 DOD ROOM 10-04-B7-01.
Mod P00280· CHANGE ORDER2014-09-22+$4,821$653,461,571OSI EXCEL SWITCH CABINET RELOCATION - EXCEL'S DESIGN AND CONSTURCTION FEE
Mod P00292· OTHER ADMINISTRATIVE ACTION2014-09-22+$5,000$653,466,571SUPPLEMENTAL AGREEMENT, SETTLEMENT BY DETERMINATION - CENTURYLINK TELECOM PEDESTALS
Mod P00308· OTHER ADMINISTRATIVE ACTION2014-09-22+$27,100$653,493,671FAR 52.216-17(H) BILLING PRICE CHANGE SCENAIRO 2.
Mod P00311· CHANGE ORDER2014-09-22+$18,000$653,511,671CHANGE ORDER TO MODIFY POWER IN CBS LEVEL 4 DOD ROOM 10-04-B7-01.
Mod P00313· CHANGE ORDER2014-09-22+$4,000$653,515,671BLDG 608 UNWARRANTED CLEARANCE
Mod P00316· CHANGE ORDER2014-09-22+$3,500$653,519,171SEQUENTIAL KEY STAMPING OF NEW VA KEYCARDS
Mod P00329· EXERCISE AN OPTION2014-09-22+$9,000$653,528,171BASED ON THE INFORMATION FROM STEAM TUNNEL REMOVAL, AND POT-HOLE INFORMATION. IT IS CLEAR THAT ASBESTOS WILL…
Mod P00333· CHANGE ORDER2014-09-22−$28,000$653,500,171CHANGE ORDER TO MODIFY POWER IN CBS LEVEL 4 DOD ROOM 10-04-B7-01.
Mod P00335· CHANGE ORDER2014-09-22+$43,850$653,544,021CHANGE ORDER TO MODIFY POWER IN CBS LEVEL 4 DOD ROOM 10-04-B7-01.
Mod P00336· CHANGE ORDER2014-09-22−$20,000$653,524,021CHANGE ORDER TO MODIFY POWER IN CBS LEVEL 4 DOD ROOM 10-04-B7-01.
Mod P00341· CHANGE ORDER2014-09-22+$35,000$653,559,021BLDG 608 UNWARRANTED CLEARANCE
Mod P00347· EXERCISE AN OPTION2014-09-22+$2,476$653,561,497BASED ON THE INFORMATION FROM STEAM TUNNEL REMOVAL, AND POT-HOLE INFORMATION. IT IS CLEAR THAT ASBESTOS WILL…
Mod P00349· EXERCISE AN OPTION2014-09-22+$6,200$653,567,697BASED ON THE INFORMATION FROM STEAM TUNNEL REMOVAL, AND POT-HOLE INFORMATION. IT IS CLEAR THAT ASBESTOS WILL…
Mod P00353· EXERCISE AN OPTION2014-09-22+$3,324$653,571,021BASED ON THE INFORMATION FROM STEAM TUNNEL REMOVAL, AND POT-HOLE INFORMATION. IT IS CLEAR THAT ASBESTOS WILL…
Mod P00354· EXERCISE AN OPTION2014-09-22+$7,000$653,578,021BASED ON THE INFORMATION FROM STEAM TUNNEL REMOVAL, AND POT-HOLE INFORMATION. IT IS CLEAR THAT ASBESTOS WILL…
Mod P00357· EXERCISE AN OPTION2014-09-22+$14,000$653,592,021BASED ON THE INFORMATION FROM STEAM TUNNEL REMOVAL, AND POT-HOLE INFORMATION. IT IS CLEAR THAT ASBESTOS WILL…
Mod P00360· OTHER ADMINISTRATIVE ACTION2014-09-22+$19,768$653,611,789THIS ADMINISTRATIVE CHANGE IS TO CORRECT AN ERROR IN THE FUNDING SITE ON P00116 FROM "554CA2501H.13" TO "554CA…
Mod P00363· OTHER ADMINISTRATIVE ACTION2014-09-22+$3,738$653,615,527OFFSITE STORED MATERIAL PAYMENT
Mod P00371· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2014-09-22+$3,000$653,618,527FAR 52.216-17(H) BILLING PRICE CHANGE SCENAIRO 2. BILLING PRICE ADJUSTMENT FOR OCTOBER 2013
Mod P00376· CHANGE ORDER2014-09-22+$2,998$653,621,525001 CM-00124 RFI #230-FAN POWERED BOX CHANGE 002 CM-00161 RFI#299-EXISITNG SHAFT WALLS 003 CM-00198 UNKNOWN MH…
Mod P00381· CHANGE ORDER2014-09-22+$7,739$653,629,264001 CM-00124 RFI #230-FAN POWERED BOX CHANGE 002 CM-00161 RFI#299-EXISITNG SHAFT WALLS 003 CM-00198 UNKNOWN MH…
Mod P00382· CHANGE ORDER2014-09-22+$1,950$653,631,214001 CM-00124 RFI #230-FAN POWERED BOX CHANGE 002 CM-00161 RFI#299-EXISITNG SHAFT WALLS 003 CM-00198 UNKNOWN MH…
Mod P00391· CHANGE ORDER2014-09-22−$1,200$653,630,014001 CM-00124 RFI #230-FAN POWERED BOX CHANGE 002 CM-00161 RFI#299-EXISITNG SHAFT WALLS 003 CM-00198 UNKNOWN MH…
Mod P00398· CHANGE ORDER2014-09-22+$13,199$653,643,213001 CM-00124 RFI #230-FAN POWERED BOX CHANGE 002 CM-00161 RFI#299-EXISITNG SHAFT WALLS 003 CM-00198 UNKNOWN MH…
Mod P00401· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2014-09-22+$36,200$653,679,413FAR 52.216-17(H) BILLING PRICE CHANGE SCENAIRO 2. BILLING PRICE ADJUSTMENT FOR OCTOBER 2013
Mod P00407· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2014-09-22+$6,000$653,685,413FAR 52.216-17(H) BILLING PRICE CHANGE SCENAIRO 2. BILLING PRICE ADJUSTMENT FOR OCTOBER 2013
Mod P00413· CHANGE ORDER2014-09-22−$28,960$653,656,453001 CM-00124 RFI #230-FAN POWERED BOX CHANGE 002 CM-00161 RFI#299-EXISITNG SHAFT WALLS 003 CM-00198 UNKNOWN MH…
Mod P00417· EXERCISE AN OPTION2014-09-22+$59,282$653,715,735BASED ON THE INFORMATION FROM STEAM TUNNEL REMOVAL, AND POT-HOLE INFORMATION. IT IS CLEAR THAT ASBESTOS WILL…
Mod P00428· EXERCISE AN OPTION2014-09-22+$17,000$653,732,735BASED ON THE INFORMATION FROM STEAM TUNNEL REMOVAL, AND POT-HOLE INFORMATION. IT IS CLEAR THAT ASBESTOS WILL…
Mod P00432· EXERCISE AN OPTION2014-09-22+$3,000$653,735,735BASED ON THE INFORMATION FROM STEAM TUNNEL REMOVAL, AND POT-HOLE INFORMATION. IT IS CLEAR THAT ASBESTOS WILL…
Mod P00441· CHANGE ORDER2014-09-22+$2,682$653,738,4171. 06.SS.000.A: REVISE TWO TOP OF PIER ELEVATIONS ALONG GRID 06-3 FROM 85 -0 TO 83 -8 PER SS.X044. 2. 06.SS.00…
Mod P00442· CHANGE ORDER2014-09-22+$34,612$653,773,0291. 06.SS.000.A: REVISE TWO TOP OF PIER ELEVATIONS ALONG GRID 06-3 FROM 85 -0 TO 83 -8 PER SS.X044. 2. 06.SS.00…
Mod P00443· CHANGE ORDER2014-09-22+$14,403$653,787,4321. 06.SS.000.A: REVISE TWO TOP OF PIER ELEVATIONS ALONG GRID 06-3 FROM 85 -0 TO 83 -8 PER SS.X044. 2. 06.SS.00…
Mod P00452· DEFINITIZE CHANGE ORDER2014-09-22+$0$653,787,432TO DEFINITIZE P00085 WHEELING RELOCATION OSI.
Mod P00453· DEFINITIZE CHANGE ORDER2014-09-22+$0$653,787,432TO DEFINITIZE P00085 WHEELING RELOCATION OSI.
Mod P00457· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2014-09-22+$27,400$653,814,832FAR 52.216-17(H) BILLING PRICE CHANGE SCENAIRO 2. BILLING PRICE ADJUSTMENT FOR OCTOBER 2013
Mod P00459· CHANGE ORDER2014-09-22+$614$653,815,446001 CM-00124 RFI #230-FAN POWERED BOX CHANGE 002 CM-00161 RFI#299-EXISITNG SHAFT WALLS 003 CM-00198 UNKNOWN MH…
Mod P00462· CHANGE ORDER2014-09-22+$20,000$653,835,446001 CM-00124 RFI #230-FAN POWERED BOX CHANGE 002 CM-00161 RFI#299-EXISITNG SHAFT WALLS 003 CM-00198 UNKNOWN MH…
Mod P00463· CHANGE ORDER2014-09-22+$33,580$653,869,026001 CM-00124 RFI #230-FAN POWERED BOX CHANGE 002 CM-00161 RFI#299-EXISITNG SHAFT WALLS 003 CM-00198 UNKNOWN MH…
Mod P00464· CHANGE ORDER2014-09-22−$6,937$653,862,089001 CM-00124 RFI #230-FAN POWERED BOX CHANGE 002 CM-00161 RFI#299-EXISITNG SHAFT WALLS 003 CM-00198 UNKNOWN MH…
Mod P00466· EXERCISE AN OPTION2014-09-22+$0$653,862,089BASED ON THE INFORMATION FROM STEAM TUNNEL REMOVAL, AND POT-HOLE INFORMATION. IT IS CLEAR THAT ASBESTOS WILL…
Mod P00469· CHANGE ORDER2014-09-22+$5,000$653,867,089001 CM-00124 RFI #230-FAN POWERED BOX CHANGE 002 CM-00161 RFI#299-EXISITNG SHAFT WALLS 003 CM-00198 UNKNOWN MH…
Mod P00477· CHANGE ORDER2014-09-22+$44,035$653,911,124CHANGE ORDER FOR ACM - CENTERRE/DAROTECH
Mod P00484· CHANGE ORDER2014-09-22+$77,844$653,988,968CHANGE ORDER FOR ACM - CENTERRE/DAROTECH
Mod P00491· CHANGE ORDER2014-09-22+$4,020$653,992,988CHANGE ORDER FOR ACM - CENTERRE/DAROTECH
Mod P00492· CHANGE ORDER2014-09-22+$5,718$653,998,706CHANGE ORDER FOR ACM - CENTERRE/DAROTECH
Mod P00496· CHANGE ORDER2014-09-22+$23,000$654,021,706001 CM-00124 RFI #230-FAN POWERED BOX CHANGE 002 CM-00161 RFI#299-EXISITNG SHAFT WALLS 003 CM-00198 UNKNOWN MH…
Mod P00572· CHANGE ORDER2014-09-22+$10,035$654,031,741001 CM-00124 RFI #230-FAN POWERED BOX CHANGE 002 CM-00161 RFI#299-EXISITNG SHAFT WALLS 003 CM-00198 UNKNOWN MH…
Mod P00574· CHANGE ORDER2014-09-22+$3,679$654,035,420001 CM-00124 RFI #230-FAN POWERED BOX CHANGE 002 CM-00161 RFI#299-EXISITNG SHAFT WALLS 003 CM-00198 UNKNOWN MH…
Mod P00386· EXERCISE AN OPTION2014-09-23+$56,852$654,092,272BASED ON THE INFORMATION FROM STEAM TUNNEL REMOVAL, AND POT-HOLE INFORMATION. IT IS CLEAR THAT ASBESTOS WILL…
Mod P00504· CHANGE ORDER2014-09-23+$0$654,092,272001 CM-00124 RFI #230-FAN POWERED BOX CHANGE 002 CM-00161 RFI#299-EXISITNG SHAFT WALLS 003 CM-00198 UNKNOWN MH…
Mod P00508· CHANGE ORDER2014-09-23+$24,342$654,116,614001 CM-00124 RFI #230-FAN POWERED BOX CHANGE 002 CM-00161 RFI#299-EXISITNG SHAFT WALLS 003 CM-00198 UNKNOWN MH…
Mod P00511· EXERCISE AN OPTION2014-09-23+$2,500$654,119,114BASED ON THE INFORMATION FROM STEAM TUNNEL REMOVAL, AND POT-HOLE INFORMATION. IT IS CLEAR THAT ASBESTOS WILL…
Mod P00519· EXERCISE AN OPTION2014-09-23+$1,720$654,120,834BASED ON THE INFORMATION FROM STEAM TUNNEL REMOVAL, AND POT-HOLE INFORMATION. IT IS CLEAR THAT ASBESTOS WILL…
Mod P00528· CHANGE ORDER2014-09-23+$10,000$654,130,834CHANGE ORDER TO MODIFY POWER IN CBS LEVEL 4 DOD ROOM 10-04-B7-01.
Mod P00536· EXERCISE AN OPTION2014-09-23+$1,500$654,132,334CM-00038 - ADD INLET PROTECTION
Mod P00538· CHANGE ORDER2014-09-23+$1,120$654,133,454SEQUENTIAL KEY STAMPING OF NEW VA KEYCARDS
Mod P00550· CHANGE ORDER2014-09-23+$862$654,134,316001 CM-00124 RFI #230-FAN POWERED BOX CHANGE 002 CM-00161 RFI#299-EXISITNG SHAFT WALLS 003 CM-00198 UNKNOWN MH…
Mod P00558· CHANGE ORDER2014-09-23+$1,356$654,135,672001 CM-00124 RFI #230-FAN POWERED BOX CHANGE 002 CM-00161 RFI#299-EXISITNG SHAFT WALLS 003 CM-00198 UNKNOWN MH…
Mod P00562· CHANGE ORDER2014-09-23+$0$654,135,672001 CM-00124 RFI #230-FAN POWERED BOX CHANGE 002 CM-00161 RFI#299-EXISITNG SHAFT WALLS 003 CM-00198 UNKNOWN MH…
Mod P00566· CHANGE ORDER2014-09-23+$0$654,135,672001 CM-00124 RFI #230-FAN POWERED BOX CHANGE 002 CM-00161 RFI#299-EXISITNG SHAFT WALLS 003 CM-00198 UNKNOWN MH…
Mod P00568· CHANGE ORDER2014-09-23+$0$654,135,672001 CM-00124 RFI #230-FAN POWERED BOX CHANGE 002 CM-00161 RFI#299-EXISITNG SHAFT WALLS 003 CM-00198 UNKNOWN MH…
Mod P00569· CHANGE ORDER2014-09-23+$0$654,135,672001 CM-00124 RFI #230-FAN POWERED BOX CHANGE 002 CM-00161 RFI#299-EXISITNG SHAFT WALLS 003 CM-00198 UNKNOWN MH…
Mod P00570· CHANGE ORDER2014-09-23+$0$654,135,672001 CM-00124 RFI #230-FAN POWERED BOX CHANGE 002 CM-00161 RFI#299-EXISITNG SHAFT WALLS 003 CM-00198 UNKNOWN MH…
Mod P00571· CHANGE ORDER2014-09-23+$750$654,136,422001 CM-00124 RFI #230-FAN POWERED BOX CHANGE 002 CM-00161 RFI#299-EXISITNG SHAFT WALLS 003 CM-00198 UNKNOWN MH…
Mod P00573· CHANGE ORDER2014-09-23+$550$654,136,972001 CM-00124 RFI #230-FAN POWERED BOX CHANGE 002 CM-00161 RFI#299-EXISITNG SHAFT WALLS 003 CM-00198 UNKNOWN MH…
Mod P00589· CHANGE ORDER2014-09-23+$0$654,136,972001 CM-00124 RFI #230-FAN POWERED BOX CHANGE 002 CM-00161 RFI#299-EXISITNG SHAFT WALLS 003 CM-00198 UNKNOWN MH…
Mod P00590· CHANGE ORDER2014-09-23+$12,579$654,149,551001 CM-00124 RFI #230-FAN POWERED BOX CHANGE 002 CM-00161 RFI#299-EXISITNG SHAFT WALLS 003 CM-00198 UNKNOWN MH…
Mod P00597· CHANGE ORDER2014-09-23+$900$654,150,451001 CM-00124 RFI #230-FAN POWERED BOX CHANGE 002 CM-00161 RFI#299-EXISITNG SHAFT WALLS 003 CM-00198 UNKNOWN MH…
Mod P00608· CHANGE ORDER2014-09-23+$4,977$654,155,4281. 06.SS.000.A: REVISE TWO TOP OF PIER ELEVATIONS ALONG GRID 06-3 FROM 85 -0 TO 83 -8 PER SS.X044. 2. 06.SS.00…
Mod P00612· CHANGE ORDER2014-09-23+$2,628$654,158,0561. 06.SS.000.A: REVISE TWO TOP OF PIER ELEVATIONS ALONG GRID 06-3 FROM 85 -0 TO 83 -8 PER SS.X044. 2. 06.SS.00…
Mod P00615· CHANGE ORDER2014-09-23+$2,974$654,161,030001 CM-00124 RFI #230-FAN POWERED BOX CHANGE 002 CM-00161 RFI#299-EXISITNG SHAFT WALLS 003 CM-00198 UNKNOWN MH…
Mod P00616· CHANGE ORDER2014-09-23+$10,000$654,171,030001 CM-00124 RFI #230-FAN POWERED BOX CHANGE 002 CM-00161 RFI#299-EXISITNG SHAFT WALLS 003 CM-00198 UNKNOWN MH…
Mod P00617· CHANGE ORDER2014-09-23−$77,787$654,093,243001 CM-00124 RFI #230-FAN POWERED BOX CHANGE 002 CM-00161 RFI#299-EXISITNG SHAFT WALLS 003 CM-00198 UNKNOWN MH…
Mod P00618· CHANGE ORDER2014-09-23+$800$654,094,043001 CM-00124 RFI #230-FAN POWERED BOX CHANGE 002 CM-00161 RFI#299-EXISITNG SHAFT WALLS 003 CM-00198 UNKNOWN MH…
Mod P00621· OTHER ADMINISTRATIVE ACTION2014-09-23+$74,220$654,168,263OFFSITE STORED MATERIAL PAYMENT
Mod P00622· CHANGE ORDER2014-09-23+$1,800$654,170,063001 CM-00124 RFI #230-FAN POWERED BOX CHANGE 002 CM-00161 RFI#299-EXISITNG SHAFT WALLS 003 CM-00198 UNKNOWN MH…
Mod P00623· CHANGE ORDER2014-09-23−$6,377$654,163,686001 CM-00124 RFI #230-FAN POWERED BOX CHANGE 002 CM-00161 RFI#299-EXISITNG SHAFT WALLS 003 CM-00198 UNKNOWN MH…
Mod P00626· CHANGE ORDER2014-09-23+$6,729$654,170,415001 CM-00124 RFI #230-FAN POWERED BOX CHANGE 002 CM-00161 RFI#299-EXISITNG SHAFT WALLS 003 CM-00198 UNKNOWN MH…
Mod P00627· CHANGE ORDER2014-09-23+$0$654,170,415001 CM-00124 RFI #230-FAN POWERED BOX CHANGE 002 CM-00161 RFI#299-EXISITNG SHAFT WALLS 003 CM-00198 UNKNOWN MH…
Mod P00629· CHANGE ORDER2014-09-23+$9,000$654,179,415001 CM-00124 RFI #230-FAN POWERED BOX CHANGE 002 CM-00161 RFI#299-EXISITNG SHAFT WALLS 003 CM-00198 UNKNOWN MH…
Mod P00632· CHANGE ORDER2014-09-23−$21,614$654,157,801001 CM-00124 RFI #230-FAN POWERED BOX CHANGE 002 CM-00161 RFI#299-EXISITNG SHAFT WALLS 003 CM-00198 UNKNOWN MH…
Mod P00633· CHANGE ORDER2014-09-23+$12,000$654,169,801001 CM-00124 RFI #230-FAN POWERED BOX CHANGE 002 CM-00161 RFI#299-EXISITNG SHAFT WALLS 003 CM-00198 UNKNOWN MH…
Mod P00634· CHANGE ORDER2014-09-23+$7,614$654,177,415001 CM-00124 RFI #230-FAN POWERED BOX CHANGE 002 CM-00161 RFI#299-EXISITNG SHAFT WALLS 003 CM-00198 UNKNOWN MH…
Mod P00635· CHANGE ORDER2014-09-23+$47,537$654,224,952001 CM-00124 RFI #230-FAN POWERED BOX CHANGE 002 CM-00161 RFI#299-EXISITNG SHAFT WALLS 003 CM-00198 UNKNOWN MH…
Mod P00636· CHANGE ORDER2014-09-23+$295$654,225,247001 CM-00124 RFI #230-FAN POWERED BOX CHANGE 002 CM-00161 RFI#299-EXISITNG SHAFT WALLS 003 CM-00198 UNKNOWN MH…
Mod P00637· CHANGE ORDER2014-09-23+$11,177$654,236,424001 CM-00124 RFI #230-FAN POWERED BOX CHANGE 002 CM-00161 RFI#299-EXISITNG SHAFT WALLS 003 CM-00198 UNKNOWN MH…
Mod P00639· CHANGE ORDER2014-09-23+$28,978$654,265,402001 CM-00124 RFI #230-FAN POWERED BOX CHANGE 002 CM-00161 RFI#299-EXISITNG SHAFT WALLS 003 CM-00198 UNKNOWN MH…
Mod P00640· CHANGE ORDER2014-09-23+$0$654,265,402001 CM-00124 RFI #230-FAN POWERED BOX CHANGE 002 CM-00161 RFI#299-EXISITNG SHAFT WALLS 003 CM-00198 UNKNOWN MH…
Mod P00643· CHANGE ORDER2014-09-24+$7,300$654,272,702001 CM-00124 RFI #230-FAN POWERED BOX CHANGE 002 CM-00161 RFI#299-EXISITNG SHAFT WALLS 003 CM-00198 UNKNOWN MH…
Mod P00648· DEFINITIZE CHANGE ORDER2014-09-24+$90,000$654,362,702TO DEFINITIZE P00085 WHEELING RELOCATION OSI.
Mod P00650· CHANGE ORDER2014-09-24−$6,010$654,356,692001 CM-00124 RFI #230-FAN POWERED BOX CHANGE 002 CM-00161 RFI#299-EXISITNG SHAFT WALLS 003 CM-00198 UNKNOWN MH…
Mod P00651· CHANGE ORDER2014-09-24+$30,835$654,387,527001 CM-00124 RFI #230-FAN POWERED BOX CHANGE 002 CM-00161 RFI#299-EXISITNG SHAFT WALLS 003 CM-00198 UNKNOWN MH…
Mod P00652· CHANGE ORDER2014-09-24−$3,211$654,384,316001 CM-00124 RFI #230-FAN POWERED BOX CHANGE 002 CM-00161 RFI#299-EXISITNG SHAFT WALLS 003 CM-00198 UNKNOWN MH…
Mod P00653· CHANGE ORDER2014-09-24+$39,724$654,424,040001 CM-00124 RFI #230-FAN POWERED BOX CHANGE 002 CM-00161 RFI#299-EXISITNG SHAFT WALLS 003 CM-00198 UNKNOWN MH…
Mod P00657· CHANGE ORDER2014-09-24−$39,818$654,384,222OSI EXCEL SWITCH CABINET RELOCATION - EXCEL'S DESIGN AND CONSTURCTION FEE
Mod P00658· DEFINITIZE CHANGE ORDER2014-09-24+$1,440$654,385,662TO DEFINITIZE P00085 WHEELING RELOCATION OSI.
Mod P00659· DEFINITIZE CHANGE ORDER2014-09-24−$1,395$654,384,267TO DEFINITIZE P00085 WHEELING RELOCATION OSI.
Mod P00661· CHANGE ORDER2014-09-24−$63,564$654,320,703001 CM-00124 RFI #230-FAN POWERED BOX CHANGE 002 CM-00161 RFI#299-EXISITNG SHAFT WALLS 003 CM-00198 UNKNOWN MH…
Mod P00665· CHANGE ORDER2014-09-24+$0$654,320,703001 CM-00124 RFI #230-FAN POWERED BOX CHANGE 002 CM-00161 RFI#299-EXISITNG SHAFT WALLS 003 CM-00198 UNKNOWN MH…
Mod P00669· CHANGE ORDER2014-09-24−$38,907$654,281,796001 CM-00124 RFI #230-FAN POWERED BOX CHANGE 002 CM-00161 RFI#299-EXISITNG SHAFT WALLS 003 CM-00198 UNKNOWN MH…
Mod P00671· DEFINITIZE CHANGE ORDER2014-09-24+$58,000$654,339,796TO DEFINITIZE P00085 WHEELING RELOCATION OSI.
Mod P00672· DEFINITIZE CHANGE ORDER2014-09-24−$39,375$654,300,421TO DEFINITIZE P00085 WHEELING RELOCATION OSI.
Mod P00676· CHANGE ORDER2014-09-24+$17,442$654,317,863001 CM-00124 RFI #230-FAN POWERED BOX CHANGE 002 CM-00161 RFI#299-EXISITNG SHAFT WALLS 003 CM-00198 UNKNOWN MH…
Mod P00679· CHANGE ORDER2014-09-24+$21,461$654,339,324CO-03G THERAPEUTIC POOLS AT IBN
Mod P00681· DEFINITIZE CHANGE ORDER2014-09-24+$3,300$654,342,624TO DEFINITIZE P00085 WHEELING RELOCATION OSI.
Mod P00682· DEFINITIZE CHANGE ORDER2014-09-24+$19,531$654,362,155TO DEFINITIZE P00085 WHEELING RELOCATION OSI.
Mod P00683· DEFINITIZE CHANGE ORDER2014-09-24+$6,000$654,368,155TO DEFINITIZE P00085 WHEELING RELOCATION OSI.
Mod P00687· DEFINITIZE CHANGE ORDER2014-09-24+$35,000$654,403,155TO DEFINITIZE P00085 WHEELING RELOCATION OSI.
Mod P00689· DEFINITIZE CHANGE ORDER2014-09-24+$11,865$654,415,020TO DEFINITIZE P00085 WHEELING RELOCATION OSI.
Mod P00692· DEFINITIZE CHANGE ORDER2014-09-24+$2,331$654,417,351TO DEFINITIZE P00085 WHEELING RELOCATION OSI.
Mod P00694· DEFINITIZE CHANGE ORDER2014-09-24+$9,000$654,426,351TO DEFINITIZE P00085 WHEELING RELOCATION OSI.
Mod P00695· DEFINITIZE CHANGE ORDER2014-09-24+$15,000$654,441,351TO DEFINITIZE P00085 WHEELING RELOCATION OSI.
Mod P00698· DEFINITIZE CHANGE ORDER2014-09-24+$1,200$654,442,551TO DEFINITIZE P00085 WHEELING RELOCATION OSI.
Mod P00701· DEFINITIZE CHANGE ORDER2014-09-24−$71,282$654,371,269TO DEFINITIZE P00085 WHEELING RELOCATION OSI.
Mod P00707· CHANGE ORDER2014-09-24+$0$654,371,269SEQUENTIAL KEY STAMPING OF NEW VA KEYCARDS
Mod P00710· EXERCISE AN OPTION2014-09-24+$41,783$654,413,052BASED ON THE INFORMATION FROM STEAM TUNNEL REMOVAL, AND POT-HOLE INFORMATION. IT IS CLEAR THAT ASBESTOS WILL…
Mod P00719· EXERCISE AN OPTION2014-09-24+$1,877$654,414,929BASED ON THE INFORMATION FROM STEAM TUNNEL REMOVAL, AND POT-HOLE INFORMATION. IT IS CLEAR THAT ASBESTOS WILL…
Mod P00720· EXERCISE AN OPTION2014-09-24+$1,743$654,416,672BASED ON THE INFORMATION FROM STEAM TUNNEL REMOVAL, AND POT-HOLE INFORMATION. IT IS CLEAR THAT ASBESTOS WILL…
Mod P00721· EXERCISE AN OPTION2014-09-24+$0$654,416,672BASED ON THE INFORMATION FROM STEAM TUNNEL REMOVAL, AND POT-HOLE INFORMATION. IT IS CLEAR THAT ASBESTOS WILL…
Mod P00722· EXERCISE AN OPTION2014-09-24+$28,863$654,445,535BASED ON THE INFORMATION FROM STEAM TUNNEL REMOVAL, AND POT-HOLE INFORMATION. IT IS CLEAR THAT ASBESTOS WILL…
Mod P00723· EXERCISE AN OPTION2014-09-24+$10,456$654,455,991BASED ON THE INFORMATION FROM STEAM TUNNEL REMOVAL, AND POT-HOLE INFORMATION. IT IS CLEAR THAT ASBESTOS WILL…
Mod P00724· EXERCISE AN OPTION2014-09-24+$0$654,455,991BASED ON THE INFORMATION FROM STEAM TUNNEL REMOVAL, AND POT-HOLE INFORMATION. IT IS CLEAR THAT ASBESTOS WILL…
Mod P00726· EXERCISE AN OPTION2014-09-24+$2,613$654,458,604BASED ON THE INFORMATION FROM STEAM TUNNEL REMOVAL, AND POT-HOLE INFORMATION. IT IS CLEAR THAT ASBESTOS WILL…
Mod P00727· CHANGE ORDER2014-09-24+$2,063$654,460,667001 CM-00124 RFI #230-FAN POWERED BOX CHANGE 002 CM-00161 RFI#299-EXISITNG SHAFT WALLS 003 CM-00198 UNKNOWN MH…
Mod P00728· CHANGE ORDER2014-09-24+$5,099$654,465,766001 CM-00124 RFI #230-FAN POWERED BOX CHANGE 002 CM-00161 RFI#299-EXISITNG SHAFT WALLS 003 CM-00198 UNKNOWN MH…
Mod P00730· CHANGE ORDER2014-09-24+$21,481$654,487,247001 CM-00124 RFI #230-FAN POWERED BOX CHANGE 002 CM-00161 RFI#299-EXISITNG SHAFT WALLS 003 CM-00198 UNKNOWN MH…
Mod P00731· CHANGE ORDER2014-09-24+$1,600$654,488,847001 CM-00124 RFI #230-FAN POWERED BOX CHANGE 002 CM-00161 RFI#299-EXISITNG SHAFT WALLS 003 CM-00198 UNKNOWN MH…
Mod P00732· CHANGE ORDER2014-09-24+$2,400$654,491,247001 CM-00124 RFI #230-FAN POWERED BOX CHANGE 002 CM-00161 RFI#299-EXISITNG SHAFT WALLS 003 CM-00198 UNKNOWN MH…
Mod P00734· CHANGE ORDER2014-09-24+$2,675$654,493,922001 CM-00124 RFI #230-FAN POWERED BOX CHANGE 002 CM-00161 RFI#299-EXISITNG SHAFT WALLS 003 CM-00198 UNKNOWN MH…
Mod P00735· CHANGE ORDER2014-09-24+$4,002$654,497,924001 CM-00124 RFI #230-FAN POWERED BOX CHANGE 002 CM-00161 RFI#299-EXISITNG SHAFT WALLS 003 CM-00198 UNKNOWN MH…
Mod P00739· EXERCISE AN OPTION2014-09-24+$5,118$654,503,042BASED ON THE INFORMATION FROM STEAM TUNNEL REMOVAL, AND POT-HOLE INFORMATION. IT IS CLEAR THAT ASBESTOS WILL…
Mod P00746· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2014-09-24+$8,600$654,511,642FAR 52.216-17(H) BILLING PRICE CHANGE SCENAIRO 2. BILLING PRICE ADJUSTMENT FOR OCTOBER 2013
Mod P00748· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2014-09-24+$29,000$654,540,642FAR 52.216-17(H) BILLING PRICE CHANGE SCENAIRO 2. BILLING PRICE ADJUSTMENT FOR OCTOBER 2013
Mod P00750· CHANGE ORDER2014-09-24−$12,821$654,527,821001 CM-00124 RFI #230-FAN POWERED BOX CHANGE 002 CM-00161 RFI#299-EXISITNG SHAFT WALLS 003 CM-00198 UNKNOWN MH…
Mod P00755· CHANGE ORDER2014-09-24+$1,190$654,529,011001 CM-00124 RFI #230-FAN POWERED BOX CHANGE 002 CM-00161 RFI#299-EXISITNG SHAFT WALLS 003 CM-00198 UNKNOWN MH…
Mod P00775· OTHER ADMINISTRATIVE ACTION2014-09-24+$2,000$654,531,011SUPPLEMENTAL AGREEMENT, SETTLEMENT BY DETERMINATION - CENTURYLINK TELECOM PEDESTALS
Mod P00779· DEFINITIZE CHANGE ORDER2014-09-24+$13,000$654,544,011TO DEFINITIZE P00085 WHEELING RELOCATION OSI.
Mod P00781· CHANGE ORDER2014-09-24−$2,869$654,541,142OSI EXCEL SWITCH CABINET RELOCATION - EXCEL'S DESIGN AND CONSTURCTION FEE
Mod P00782· DEFINITIZE CHANGE ORDER2014-09-24+$25,375$654,566,517TO DEFINITIZE P00085 WHEELING RELOCATION OSI.
Mod P00787· DEFINITIZE CHANGE ORDER2014-09-24+$455$654,566,972TO DEFINITIZE P00085 WHEELING RELOCATION OSI.
Mod P00809· DEFINITIZE CHANGE ORDER2014-09-24+$50,990$654,617,962TO DEFINITIZE P00085 WHEELING RELOCATION OSI.
Mod P00812· DEFINITIZE CHANGE ORDER2014-09-24+$6,000$654,623,962TO DEFINITIZE P00085 WHEELING RELOCATION OSI.
Mod P00816· DEFINITIZE CHANGE ORDER2014-09-24+$4,350$654,628,312TO DEFINITIZE P00085 WHEELING RELOCATION OSI.
Mod P00532· DEFINITIZE CHANGE ORDER2014-09-25+$13,502$654,641,814SD CM00910 RFI 2408 RES ELEVATOR SUMP PUMP
Mod P00581· OTHER ADMINISTRATIVE ACTION2014-10-16+$7,922$654,649,736DEFINITIZE P0026 - JSI 65; MODIFY PVS FLOOR ELEVATION TO DRAIN.
Mod P00713· EXERCISE AN OPTION2014-10-31−$523,317$654,126,419REA PKG #111, GENERAL TRADES
Mod P00851· CHANGE ORDER2014-11-05+$269,000$654,395,419CHANGE ORDER TO PROVIDE LABOR AND MATERIAL TO PERFORM WORK AS LISTED IN JSI 104.
Mod P00910· DEFINITIZE CHANGE ORDER2014-11-21+$235$654,395,654SD TO INCORPORATE JSI 79 FOR THE INSTALLATION OF AN AREA DRAIN AT LEVEL 1 OF PVS NEAR THE BOTTOM OF THE RAMP.
Mod P01052· CHANGE ORDER2016-04-19+$20,000,000$674,395,654INCORPORATE CORRECT WD
Mod P01053· CHANGE ORDER2016-05-18+$3,000,000$677,395,654INCORPORATE CORRECT WD
Mod P01054· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2016-11-30+$1,100,000$678,495,654INCORPORATE CORRECT WD
Mod P01055· CHANGE ORDER2017-06-27−$33,305$678,462,349INCORPORATE CORRECT WD

Related awards · 6

Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.

Other VA awards to the same recipient (UEI W8F9CKD8QJQ6)

AwardOffice · PSC / listingNet obligationsFY
VA101F15C0005OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F) · Y1DA · CONSTRUCTION OF HOSPITALS AND INFIRMARIES$225,606,735FY2015

Other recipients under Y141 from OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F) (most recent first)

AwardRecipientOfficeNet obligationsFY
VA101CFMC0168WALSH'DEMARIA JOINT VENTURE VOFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F)$126,493,873FY2011
VA101CFMC0206BRASFIELD & GORRIE LLCOFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F)$318,479,500FY2010
VA101CFMC0205JAMES A. CUMMINGS, INC.OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F)$41,922,305FY2010
VA101183B4C0007WALSH DEMARIA JOINT VENTURE IVOFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F)$4,033,647FY2008
VA101CFMC0003CLARK/HUNT, A JOINT VENTURE-NEVADAOFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F)$398,932,679FY2008

Cite as: Glassbox VA record view · VA contract (USAspending / FPDS) · CONT_AWD_VA101CFMC0100_3600_-NONE-_-NONE- · retrieved 2026-09-25.