Description
ADDITION OF CLAUSE FAR 52.222-90 PER EXECUTIVE ORDER 14398.
Base award description: AE DESIGN TO RELOCATE AND EXPAND CANTEEN
Modification chain · 8 transactions
Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.
- Base2024-07-23+$805,008= $805,008
- Mod P000012024-09-16+$0= $805,008
- Mod P000022025-03-17+$129,814= $934,822
- Mod P000032025-09-06+$0= $934,822
- Mod P000042025-10-16+$0= $934,822
- Mod P000052025-11-18+$0= $934,822
- Mod P000062026-04-07+$0= $934,822
- Mod P000072026-06-30+$0= $934,822
| Transaction | Action date | This action (delta) | Running total | Description on this transaction |
|---|---|---|---|---|
| Base | 2024-07-23 | +$805,008 | $805,008 | AE DESIGN TO RELOCATE AND EXPAND CANTEEN |
| Mod P00001· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2024-09-16 | +$0 | $805,008 | REMOVED "ATTACHMENT 01 - ARCHITECTURAL AND ENGINEERING CPM SCHEDULES" |
| Mod P00002· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2025-03-17 | +$129,814 | $934,822 | INCORPORATE GSFT INCREASE AND INCREASE POP WITH 135 CALENDAR DAYS. |
| Mod P00003· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2025-09-06 | +$0 | $934,822 | NO COST TIME EXTENSION OF POP WITH 46 CALENDAR DAYS. |
| Mod P00004· CHANGE ORDER | 2025-10-16 | +$0 | $934,822 | NO COST TIME EXTENSION OF POP WITH 30 CALENDAR DAYS. |
| Mod P00005· CHANGE ORDER | 2025-11-18 | +$0 | $934,822 | NO COST TIME EXTENSION OF POP WITH 365 CALENDAR DAYS DUE TO GOVERNMENT-CAUSED DELAYS. |
| Mod P00006· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2026-04-07 | +$0 | $934,822 | NO COST TIME EXTENSION OF POP WITH 134 CALENDAR DAYS DUE TO GOVERNMENT-CAUSED DELAYS, AS WELL AS DEFINITIZATIO… |
| Mod P00007· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2026-06-30 | +$0 | $934,822 | ADDITION OF CLAUSE FAR 52.222-90 PER EXECUTIVE ORDER 14398. |
Related awards · 11
Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.
Other VA awards to the same recipient (UEI TBDQJRW48CK4)
| Award | Office · PSC / listing | Net obligations | FY |
|---|---|---|---|
| 36C26225D0163 | 262-NETWORK CONTRACT OFFICE 22 (36C262) · C1DA · ARCHITECT AND ENGINEERING- CONSTRUCTION: HOSPITALS AND INFIRMARIES | $0 | FY2025 |
| 36C24725C0035 | 247-NETWORK CONTRACT OFFICE 7 (36C247) · C1DA · ARCHITECT AND ENGINEERING- CONSTRUCTION: HOSPITALS AND INFIRMARIES | $19,035 | FY2025 |
| 36C25925N0131 | NETWORK CONTRACT OFFICE 19 (36C259) · C1DA · ARCHITECT AND ENGINEERING- CONSTRUCTION: HOSPITALS AND INFIRMARIES | $1,176,824 | FY2025 |
| 36C25924N0432 | NETWORK CONTRACT OFFICE 19 (36C259) · C1DA · ARCHITECT AND ENGINEERING- CONSTRUCTION: HOSPITALS AND INFIRMARIES | $486,831 | FY2024 |
| 36C25924N0400 | NETWORK CONTRACT OFFICE 19 (36C259) · C1DA · ARCHITECT AND ENGINEERING- CONSTRUCTION: HOSPITALS AND INFIRMARIES | $48,212 | FY2024 |
| 36C26024C0047 | 260-NETWORK CONTRACT OFFICE 20 (36C260) · C1DA · ARCHITECT AND ENGINEERING- CONSTRUCTION: HOSPITALS AND INFIRMARIES | $37,443 | FY2024 |
Other recipients under C1DA from PCAC (36C776) (most recent first)
| Award | Recipient | Office | Net obligations | FY |
|---|---|---|---|---|
| 36C77626N0546 | ENVIROS LLC | PCAC (36C776) | $314,770 | FY2026 |
| 36C77626N0790 | ABOVE GROUP INC. | PCAC (36C776) | $1,540,190 | FY2026 |
| 36C77626N0730 | ATRIAX/DLR GROUP JV LLC | PCAC (36C776) | $4,255,339 | FY2026 |
| 36C77626N0786 | FOURFRONT DESIGN INC | PCAC (36C776) | $1,305,596 | FY2026 |
| 36C77626C0030 | HEALTH FACILITY SOLUTIONS COMPANY | PCAC (36C776) | $1,535,617 | FY2026 |
Cite as: Glassbox VA record view · VA contract (USAspending / FPDS) · CONT_AWD_36C77624C0073_3600_-NONE-_-NONE- · retrieved 2026-09-26.