Description
SETTLEMENT BY DETERMINATION P00036 (SD-P00036) SECTION 1SS UNSUITABLE SOILS OVER-EXCAVATE SECTIONS OF CRYPT SECTION 1SS TO REMEDIATE UNSUITABLE MATERIAL IDENTIFIED BY PROOF ROLL.
Base award description: JEFFERSON BARRACKS NATIONAL CEMETERY PH 5 EXPANSION ADDS INTERMENT SITES
Modification chain · 39 transactions
Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.
- Base2020-04-02+$12,811,000= $12,811,000
- Mod P000012020-07-23+$45,000= $12,856,000
- Mod P000042020-08-25+$7,500= $12,863,500
- Mod P000052020-09-10+$18,500= $12,882,000
- Mod P000062020-10-16+$8,000= $12,890,000
- Mod P000072020-10-16+$13,500= $12,903,500
- Mod P000082020-10-16+$2,500= $12,906,000
- Mod P000092020-10-16+$0= $12,906,000
- Mod P000102020-11-20+$9,064= $12,915,064
- Mod P000112021-01-06+$0= $12,915,064
- Mod P000122021-01-25+$20,000= $12,935,064
- Mod P000132021-01-26+$70,000= $13,005,064
- Mod P000142021-01-26+$6,000= $13,011,064
- Mod P000152021-03-11+$25,000= $13,036,064
- Mod P000172021-03-17+$2,808= $13,038,872
- Mod P000032021-03-19-$66,984= $12,971,888
- Mod P000182021-03-19+$18,962= $12,990,850
- Mod P000162021-03-24+$55,859= $13,046,709
- Mod P000192021-03-26+$0= $13,046,709
- Mod P000202021-03-29+$16,877= $13,063,586
- Mod P000212021-03-31+$40,000= $13,103,586
- Mod P000222021-04-05+$19,834= $13,123,420
- Mod P000232021-04-05+$9,257= $13,132,677
- Mod P000242021-04-05+$4,915= $13,137,592
- Mod P000022021-04-06-$9,602= $13,127,990
- Mod P000252021-07-28+$8,915= $13,136,905
- Mod P000262021-07-28+$8,323= $13,145,228
- Mod P000272021-07-28+$702= $13,145,930
- Mod P000282021-07-28+$832= $13,146,762
- Mod P000292021-07-28-$864= $13,145,898
- Mod P000312021-08-11+$9,624= $13,155,522
- Mod P000322021-08-11+$1,108= $13,156,630
- Mod P000332021-08-11+$2,133= $13,158,763
- Mod P000352021-08-25+$12,667= $13,171,430
- Mod P000342021-09-08+$0= $13,171,430
- Mod P000362021-09-08+$41,939= $13,213,369
- Mod P000372021-09-21+$97,557= $13,310,926
- Mod A000382021-09-24+$92,015= $13,402,941
- Mod A000392021-11-30+$1,379= $13,404,320
| Transaction | Action date | This action (delta) | Running total | Description on this transaction |
|---|---|---|---|---|
| Base | 2020-04-02 | +$12,811,000 | $12,811,000 | JEFFERSON BARRACKS NATIONAL CEMETERY PH 5 EXPANSION ADDS INTERMENT SITES |
| Mod P00001· CHANGE ORDER | 2020-07-23 | +$45,000 | $12,856,000 | UNFORESEEN SITE CONDITION, REMOVAL&ABATEMENT OF OLD, IN GROUND, STEAM LINE - APPROXIMATELY 390LF. LINE COATED… |
| Mod P00004· CHANGE ORDER | 2020-08-25 | +$7,500 | $12,863,500 | CO-P00004, INSTALL CHANNEL DRAIN AT RETAINING WALL 2 |
| Mod P00005· CHANGE ORDER | 2020-09-10 | +$18,500 | $12,882,000 | CO-P00005, RELOCATE IRRIGATION MAIN AT 1QQ |
| Mod P00006· CHANGE ORDER | 2020-10-16 | +$8,000 | $12,890,000 | CO-P00006, RFI 60&62, SECTION 1TT CHANGES |
| Mod P00007· CHANGE ORDER | 2020-10-16 | +$13,500 | $12,903,500 | CO-P00007, RFI 41&57 IRRIGATION CHANGES |
| Mod P00008· CHANGE ORDER | 2020-10-16 | +$2,500 | $12,906,000 | CO-P00008, RFI-41 RETAINING WALL 2 CHANGES |
| Mod P00009· CHANGE ORDER | 2020-10-16 | +$0 | $12,906,000 | CO-P00009, ETO CHANGE |
| Mod P00010· CHANGE ORDER | 2020-11-20 | +$9,064 | $12,915,064 | CO-P00010, RETAINING WALLS UNFORESEEN CONDITIONS |
| Mod P00011· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2021-01-06 | +$0 | $12,915,064 | CO-P00011, EXCUSABLE DELAYS FOR WEATHER |
| Mod P00012· CHANGE ORDER | 2021-01-25 | +$20,000 | $12,935,064 | CO-P00012, RETAINING WALL #1 UNSUITABLE SOILS |
| Mod P00013· CHANGE ORDER | 2021-01-26 | +$70,000 | $13,005,064 | CO-P00013, 1UU UNSUITABLE SOILS |
| Mod P00014· CHANGE ORDER | 2021-01-26 | +$6,000 | $13,011,064 | CO-P00014, ROADWAY C REALIGNMENT |
| Mod P00015· CHANGE ORDER | 2021-03-11 | +$25,000 | $13,036,064 | CO-P00015, 1RR UNSUITABLE SOILS |
| Mod P00017· CHANGE ORDER | 2021-03-17 | +$2,808 | $13,038,872 | SA-P00017, LT BLASSIE DRIVE INLET CHANGE |
| Mod P00003· CHANGE ORDER | 2021-03-19 | −$66,984 | $12,971,888 | SA-P00003 - RE TRAILER AND SUPPLIES |
| Mod P00018· DEFINITIZE CHANGE ORDER | 2021-03-19 | +$18,962 | $12,990,850 | SA-P00018, 1UU UNSUITABLE SOILS |
| Mod P00016· DEFINITIZE CHANGE ORDER | 2021-03-24 | +$55,859 | $13,046,709 | SA-P00016, EARLY TURNOVER AREA CHANGE FROM 1RR TO 1TT/1VV |
| Mod P00019· CHANGE ORDER | 2021-03-26 | +$0 | $13,046,709 | SA-P00019, WEATHER IMPACTS FOR 11/2020 - 2/2021 |
| Mod P00020· DEFINITIZE CHANGE ORDER | 2021-03-29 | +$16,877 | $13,063,586 | SA-P00020, 1RR UNSUITABLE SOILS |
| Mod P00021· CHANGE ORDER | 2021-03-31 | +$40,000 | $13,103,586 | SA-P00021, ADDITIONAL ETO CHANGES |
| Mod P00022· DEFINITIZE CHANGE ORDER | 2021-04-05 | +$19,834 | $13,123,420 | SA-P00022 TO DEFINITIZE CHANGE ORDER P00012 - OVER EXCAVATE THE FOOTING SUBGRADE AT RETAINING WALL #1 AND INST… |
| Mod P00023· DEFINITIZE CHANGE ORDER | 2021-04-05 | +$9,257 | $13,132,677 | P00019 SETTLEMENT BY DETERMINATION TO DEFINITIZE CHANGE ORDER P00005 - INSTALL 125 LF OF IRRIGATION MAIN AT 1P… |
| Mod P00024· DEFINITIZE CHANGE ORDER | 2021-04-05 | +$4,915 | $13,137,592 | SA-P00024, SETTLEMENT BY DETERMINATION TO DEFINITIZE CHANGE ORDER P00006-REMOVE ITEMS DISCOVERED DURING THE EX… |
| Mod P00002· DEFINITIZE CHANGE ORDER | 2021-04-06 | −$9,602 | $13,127,990 | DEFINITIZE CHANGE ORDER P00001 - UNFORESEEN SITE CONDITION, REMOVAL&ABATEMENT OF OLD, IN GROUND, STEAM LINE -… |
| Mod P00025· DEFINITIZE CHANGE ORDER | 2021-07-28 | +$8,915 | $13,136,905 | SD-P00025, SETTLEMENT BY DETERMINATION TO DEFINITIZE CHANGE ORDER P00014-EXISTING IRRIGATION COMPONENTS WERE D… |
| Mod P00026· DEFINITIZE CHANGE ORDER | 2021-07-28 | +$8,323 | $13,145,228 | SD-P00026, SETTLEMENT BY DETERMINATION TO DEFINITIZE CHANGE ORDER P00007-IRRIGATION CONFLICTS RESOLVED |
| Mod P00027· DEFINITIZE CHANGE ORDER | 2021-07-28 | +$702 | $13,145,930 | SA-P00027, SETTLEMENT BY DETERMINATION TO DEFINITIZE CHANGE ORDER P00010-RETAINING WALL 1 AND 2 UNFORESEEN CON… |
| Mod P00028· DEFINITIZE CHANGE ORDER | 2021-07-28 | +$832 | $13,146,762 | SD-P00028, SETTLEMENT BY DETERMINATION TO DEFINITIZE CHANGE ORDER P00004-CHANNEL DRAIN AT RETAINING WALL 2 |
| Mod P00029· DEFINITIZE CHANGE ORDER | 2021-07-28 | −$864 | $13,145,898 | SA-P00029, SETTLEMENT BY DETERMINATION TO DEFINITIZE CHANGE ORDER P00008-RFI 041 RETAINING WALL 2 CHANGES |
| Mod P00031· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2021-08-11 | +$9,624 | $13,155,522 | SA-P00031, RFP D-0005 RETAINING WALL 1 SWALES |
| Mod P00032· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2021-08-11 | +$1,108 | $13,156,630 | SA-P00032, RFI 0094 ELECTRICAL CONDUIT WATER BLOCKOUT KIT |
| Mod P00033· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2021-08-11 | +$2,133 | $13,158,763 | SA-P00033, RFI 0098 RESTROOM SLOPE SEED TO SOD CHANGE |
| Mod P00035· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2021-08-25 | +$12,667 | $13,171,430 | SA-P00035 - RFI 102 SECTION 1RR CURB REPLACEMENT |
| Mod P00034· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2021-09-08 | +$0 | $13,171,430 | SA-P00034, WEATHER IMPACTS FOR MARCH 2021 THROUGH JUNE 2021 |
| Mod P00036· DEFINITIZE CHANGE ORDER | 2021-09-08 | +$41,939 | $13,213,369 | SETTLEMENT BY DETERMINATION P00036 (SD-P00036) SECTION 1SS UNSUITABLE SOILS OVER-EXCAVATE SECTIONS OF CRYPT S… |
| Mod P00037· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2021-09-21 | +$97,557 | $13,310,926 | SA-00038, SUPPLY TOPSOIL |
| Mod A00038· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2021-09-24 | +$92,015 | $13,402,941 | A00038 SUPPLY TOPSOIL $92,015.00 |
| Mod A00039· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2021-11-30 | +$1,379 | $13,404,320 | SETTLEMENT BY DETERMINATION P00036 (SD-P00036) SECTION 1SS UNSUITABLE SOILS OVER-EXCAVATE SECTIONS OF CRYPT S… |
Related awards · 11
Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.
Other VA awards to the same recipient (UEI XMKUEVF3NMB5)
| Award | Office · PSC / listing | Net obligations | FY |
|---|---|---|---|
| 36C25926C0030 | NETWORK CONTRACT OFFICE 19 (36C259) · Z1DA · MAINTENANCE OF HOSPITALS AND INFIRMARIES | $8,570,100 | FY2026 |
| 36C10F25C0005 | OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F) · Z2JZ · REPAIR OR ALTERATION OF MISCELLANEOUS BUILDINGS | $3,677,824 | FY2025 |
| 36C78624C0035 | NATIONAL CEMETERY ADMIN (36C786) · Y1PZ · CONSTRUCTION OF OTHER NON-BUILDING FACILITIES | $3,595,875 | FY2024 |
| 36C10F22C0016 | OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F) · Y1PC · CONSTRUCTION OF UNIMPROVED REAL PROPERTY (LAND) | $20,321,493 | FY2022 |
| 36C10F22C0007 | OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F) · Y1AZ · CONSTRUCTION OF OTHER ADMINISTRATIVE FACILITIES AND SERVICE BUILDINGS | $1,663,765 | FY2022 |
| 36C10F21C0014 | OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F) · Y1PC · CONSTRUCTION OF UNIMPROVED REAL PROPERTY (LAND) | $54,096,194 | FY2021 |
Other recipients under Y1PC from OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F) (most recent first)
| Award | Recipient | Office | Net obligations | FY |
|---|---|---|---|---|
| 36C10F26C0005 | GC & V CONSTRUCTION LLC | OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F) | $59,890,000 | FY2026 |
| 36C10F25C0007 | HAMILTON PACIFIC CHAMBERLAIN LLC | OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F) | $637,437 | FY2025 |
| 36C10F24C0007 | SEABEE CONSTRUCTION, INC. | OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F) | $79,106,191 | FY2024 |
| 36C10F24C0001 | RBVETCO, LLC | OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F) | $38,940,668 | FY2024 |
| 36C10F23C0008 | SGC SERVICES 2, LLC | OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F) | $42,010,850 | FY2023 |
Cite as: Glassbox VA record view · VA contract (USAspending / FPDS) · CONT_AWD_36C10F20C0008_3600_-NONE-_-NONE- · retrieved 2026-09-26.