Description
A00040.SA-24 - DEFINITIZE OPEN COS
Base award description: CONSTRUCTION OF RESEARCH OFFICE BUILDING (ROB) BRIDGE, VA PITTSBURGH PA
Modification chain · 47 transactions
Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.
- Base2019-08-26+$2,180,000= $2,180,000
- Mod A000022020-06-29+$2,672= $2,182,672
- Mod A000032020-06-29+$12,861= $2,195,533
- Mod A000042020-06-29+$12,252= $2,207,785
- Mod P000012020-06-29+$6,700= $2,214,485
- Mod P000052020-10-20+$0= $2,214,485
- Mod P000062020-11-18+$0= $2,214,485
- Mod P000072020-12-02+$23,660= $2,238,145
- Mod P000082021-01-21+$0= $2,238,145
- Mod A000052021-02-14+$1,351= $2,239,496
- Mod A000062021-02-14+$2,445= $2,241,941
- Mod A000072021-02-14+$32,570= $2,274,511
- Mod A000082021-02-14+$11,776= $2,286,287
- Mod A000092021-02-14+$0= $2,286,287
- Mod A000102021-11-30+$96,894= $2,383,181
- Mod A000112021-11-30+$49,610= $2,432,791
- Mod A000122021-11-30+$4,010= $2,436,801
- Mod A000142021-11-30+$3,400= $2,440,201
- Mod A000152021-11-30+$0= $2,440,201
- Mod A000162021-11-30+$6,237= $2,446,438
- Mod A000172021-11-30+$7,629= $2,454,067
- Mod A000182021-11-30+$0= $2,454,067
- Mod A000192021-11-30+$86,787= $2,540,854
- Mod A000202021-11-30+$0= $2,540,854
- Mod A000212021-11-30+$32,844= $2,573,698
- Mod A000222021-11-30+$9,390= $2,583,088
- Mod A000232021-11-30+$8,176= $2,591,264
- Mod A000242021-11-30+$27,146= $2,618,410
- Mod A000252021-11-30+$4,785= $2,623,195
- Mod A000262021-11-30+$47,200= $2,670,395
- Mod A000272021-11-30+$94,174= $2,764,569
- Mod A000282021-11-30+$0= $2,764,569
- Mod A000292021-11-30+$0= $2,764,569
- Mod A000302021-11-30+$0= $2,764,569
- Mod A000332021-12-10+$0= $2,764,569
- Mod A000342022-01-02+$0= $2,764,569
- Mod A000012022-09-13+$6,700= $2,771,269
- Mod A000132022-09-13+$3,041= $2,774,310
- Mod A000312022-09-13+$38,677= $2,812,987
- Mod A000322022-09-13+$21,608= $2,834,595
- Mod A000352022-09-13+$4,556= $2,839,151
- Mod A000362022-09-13+$7,481= $2,846,632
- Mod A000372022-09-13+$59,802= $2,906,434
- Mod A000382022-09-13+$37,303= $2,943,737
- Mod A000392022-09-13+$21,131= $2,964,868
- Mod A000402022-09-13+$0= $2,964,868
- Mod P000412023-03-28-$11,800= $2,953,068
| Transaction | Action date | This action (delta) | Running total | Description on this transaction |
|---|---|---|---|---|
| Base | 2019-08-26 | +$2,180,000 | $2,180,000 | CONSTRUCTION OF RESEARCH OFFICE BUILDING (ROB) BRIDGE, VA PITTSBURGH PA |
| Mod A00002· OTHER ADMINISTRATIVE ACTION | 2020-06-29 | +$2,672 | $2,182,672 | CONSTRUCTION OF RESEARCH OFFICE BUILDING (ROB) BRIDGE, VA PITTSBURGH PA - A00002.SA#01 - REMOVE EXISTING ELECT… |
| Mod A00003· OTHER ADMINISTRATIVE ACTION | 2020-06-29 | +$12,861 | $2,195,533 | CONSTRUCTION OF RESEARCH OFFICE BUILDING (ROB) BRIDGE, VA PITTSBURGH PA - A00003.SA#012 ~ DIFFERING SITE CONDI… |
| Mod A00004· DEFINITIZE CHANGE ORDER | 2020-06-29 | +$12,252 | $2,207,785 | A00004.SA#03 - EXTEND CAISSON PER CPR #01R1 DATED 2-10-2020 (DEFINITIZE P00001.CO-01A) |
| Mod P00001· CHANGE ORDER | 2020-06-29 | +$6,700 | $2,214,485 | CONSTRUCTION OF RESEARCH OFFICE BUILDING (ROB) BRIDGE, VA PITTSBURGH PA - P00001.CO-01A ~ EXTEND THE DEPTH OF… |
| Mod P00005· CHANGE ORDER | 2020-10-20 | +$0 | $2,214,485 | CONSTRUCTION OF RESEARCH OFFICE BUILDING (ROB) BRIDGE, VA PITTSBURGH PA - P00005 CHANGE ORDER TO EXTEND CONTRA… |
| Mod P00006· CHANGE ORDER | 2020-11-18 | +$0 | $2,214,485 | CONSTRUCTION OF RESEARCH OFFICE BUILDING (ROB) BRIDGE, VA PITTSBURGH PA - P00006 MODIFICATION TO EXTEND CONTRA… |
| Mod P00007· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2020-12-02 | +$23,660 | $2,238,145 | CONSTRUCTION OF RESEARCH OFFICE BUILDING (ROB) BRIDGE, VA PITTSBURGH PA - P00007 TO DEFINITIZE P00005 FOR THE… |
| Mod P00008· OTHER ADMINISTRATIVE ACTION | 2021-01-21 | +$0 | $2,238,145 | CONSTRUCTION OF RESEARCH OFFICE BUILDING (ROB) BRIDGE, VA PITTSBURGH PA - P00008 FOR ADDITIONAL TIME DUE TO CO… |
| Mod A00005· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2021-02-14 | +$1,351 | $2,239,496 | A00005.SA-04 - REROUTE LIGHTNING PROTECTION AT B#01. |
| Mod A00006· CHANGE ORDER | 2021-02-14 | +$2,445 | $2,241,941 | A00006.CO-01D - INCREASED IN SIZE OF CONCRETE DUMPSTER PAD IN THE ALLEY. |
| Mod A00007· CHANGE ORDER | 2021-02-14 | +$32,570 | $2,274,511 | A00007.CO-01E - COSTS FOR STEEL REVISIONS AT THE B#30 WINDOWS (RFCO #05) |
| Mod A00008· CHANGE ORDER | 2021-02-14 | +$11,776 | $2,286,287 | A00008.CO-01F - COSTS TO CUT THE SOG AT B#01 2W AND ROOF FOR RELOCATED DUCTWORK. |
| Mod A00009· CHANGE ORDER | 2021-02-14 | +$0 | $2,286,287 | A00009.CO-01G - ISSUED FOR 65 CALENDAR DAYS FOR RFCO #05 STEEL AT B#30 WINDOWS (A00007.CO-01E WAS FOR COSTS). |
| Mod A00010· CHANGE ORDER | 2021-11-30 | +$96,894 | $2,383,181 | A00010.CO-01H - CPR#04 & #05 (RFCOS #08 & #13) |
| Mod A00011· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2021-11-30 | +$49,610 | $2,432,791 | A00011.SA-05 - EXTENDED OH COSTS 65 DAYS (RFCO #05 STEEL) |
| Mod A00012· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2021-11-30 | +$4,010 | $2,436,801 | A00012.SA-06 CPR #05 (RFCO #19 CRASH RAIL) |
| Mod A00014· CHANGE ORDER | 2021-11-30 | +$3,400 | $2,440,201 | A00014.CO-01K CPR #05 (RFCO #11) - WALL 5A |
| Mod A00015· CHANGE ORDER | 2021-11-30 | +$0 | $2,440,201 | A00015.CO-01J - EXTEND CC 31 DAYS TO 5.08.2021 |
| Mod A00016· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2021-11-30 | +$6,237 | $2,446,438 | A00016.SA-08 - RFCO #15 INT. FRAMING |
| Mod A00017· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2021-11-30 | +$7,629 | $2,454,067 | A00017.SA-09 - CPR #04 (RFCO #10 - RAMP + WALL TYPES |
| Mod A00018· CHANGE ORDER | 2021-11-30 | +$0 | $2,454,067 | A00018.CO-01K - EXTEND CC 47 DAYS TO 6.24.2021 |
| Mod A00019· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2021-11-30 | +$86,787 | $2,540,854 | A00019.SA-10 - EXTEND CC 36 DAYS TO 7.31.2021 |
| Mod A00020· CHANGE ORDER | 2021-11-30 | +$0 | $2,540,854 | A00020.CO-01L - EXTEND CC 35 DAYS TO 9.03.2021 |
| Mod A00021· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2021-11-30 | +$32,844 | $2,573,698 | A00021.SA-11 - RFCO #16 LIGHTING CONTROLS |
| Mod A00022· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2021-11-30 | +$9,390 | $2,583,088 | A00022.SA-12 - RFCO #25 & #30 FP |
| Mod A00023· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2021-11-30 | +$8,176 | $2,591,264 | A00023.SA-13 CPR #04 & #05 ADD ICRA WALL (RFCO#20) |
| Mod A00024· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2021-11-30 | +$27,146 | $2,618,410 | A00024.SA-14 - CPR#06 & RFI #27 (RFCOS #26 & #31) |
| Mod A00025· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2021-11-30 | +$4,785 | $2,623,195 | A00025.SA-15 - RFCO #27 ADD LIGHTNING PROTECTION |
| Mod A00026· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2021-11-30 | +$47,200 | $2,670,395 | A00026.SA-26 EXTEND CC 62 DAYS WITH OH $ |
| Mod A00027· CHANGE ORDER | 2021-11-30 | +$94,174 | $2,764,569 | A00027.CO-01M - CPR #06 (RFCO #22 - HVAC) |
| Mod A00028· CHANGE ORDER | 2021-11-30 | +$0 | $2,764,569 | A00028.CO-01L - EXTEND CC 20 DAYS TO 10.20.2021 |
| Mod A00029· CHANGE ORDER | 2021-11-30 | +$0 | $2,764,569 | A00029.CO-01N - EXTEND CC 29 DAYS TO 11.19.2021 |
| Mod A00030· CHANGE ORDER | 2021-11-30 | +$0 | $2,764,569 | A00030.CO-01O - EXTEND CC 21 DAYS TO 12.10.2021 |
| Mod A00033· CHANGE ORDER | 2021-12-10 | +$0 | $2,764,569 | A00033.CO-01P - EXTEND CC TO 12.31.2021 |
| Mod A00034· CHANGE ORDER | 2022-01-02 | +$0 | $2,764,569 | A00033.CO-01P - EXTEND CC TO 12.31.2021 |
| Mod A00001· CHANGE ORDER | 2022-09-13 | +$6,700 | $2,771,269 | A00001.CO-01A EXTEND CAISSON DEPTH 15FT |
| Mod A00013· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2022-09-13 | +$3,041 | $2,774,310 | A00013.SA-07 |
| Mod A00031· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2022-09-13 | +$38,677 | $2,812,987 | A00031.SA-17 - RFCO #32 (CPR #04) |
| Mod A00032· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2022-09-13 | +$21,608 | $2,834,595 | A00032.SA-18 - RFCO #29 EXTERIOR METAL PANELS |
| Mod A00035· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2022-09-13 | +$4,556 | $2,839,151 | A00035.SA-19 - RFCO #39 - SPRINKLER CALCS AND TWO HEADS |
| Mod A00036· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2022-09-13 | +$7,481 | $2,846,632 | A00036.SA-20 - RFCO #37 RA 2W DUCT |
| Mod A00037· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2022-09-13 | +$59,802 | $2,906,434 | A00037.SA-21 - RFCO #38 BALANCE OF HEN DUCT |
| Mod A00038· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2022-09-13 | +$37,303 | $2,943,737 | A00038.SA-22 - EXTENDED OH COSTS TO NOV 2021 |
| Mod A00039· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2022-09-13 | +$21,131 | $2,964,868 | A00039.SA-23 - RFCO 317 MISC ELEC CHANGES |
| Mod A00040· DEFINITIZE CHANGE ORDER | 2022-09-13 | +$0 | $2,964,868 | A00040.SA-24 - DEFINITIZE OPEN COS |
| Mod P00041· OTHER ADMINISTRATIVE ACTION | 2023-03-28 | −$11,800 | $2,953,068 | A00040.SA-24 - DEFINITIZE OPEN COS |
Related awards · 11
Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.
Other VA awards to the same recipient (UEI GH24ZFQWHST9)
| Award | Office · PSC / listing | Net obligations | FY |
|---|---|---|---|
| 36C78626P0055 | NATIONAL CEMETERY ADMIN (36C786) · Y1PZ · CONSTRUCTION OF OTHER NON-BUILDING FACILITIES | $34,653 | FY2026 |
| 36C78626C0008 | NATIONAL CEMETERY ADMIN (36C786) · Y1EB · CONSTRUCTION OF MAINTENANCE BUILDINGS | $3,400,000 | FY2026 |
| 36C24426N0368 | 244-NETWORK CONTRACT OFFICE 4 (36C244) · Z1DA · MAINTENANCE OF HOSPITALS AND INFIRMARIES | $5,000 | FY2026 |
| 36C24426D0034 | 244-NETWORK CONTRACT OFFICE 4 (36C244) · Z1DA · MAINTENANCE OF HOSPITALS AND INFIRMARIES | $0 | FY2026 |
| 36C24426N0064 | 244-NETWORK CONTRACT OFFICE 4 (36C244) · Z1DA · MAINTENANCE OF HOSPITALS AND INFIRMARIES | $376,054 | FY2026 |
| 36C24425N1329 | 244-NETWORK CONTRACT OFFICE 4 (36C244) · Z1DA · MAINTENANCE OF HOSPITALS AND INFIRMARIES | $182,175 | FY2025 |
Other recipients under Y1DA from OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F) (most recent first)
| Award | Recipient | Office | Net obligations | FY |
|---|---|---|---|---|
| 36C10F26C0014 | PROJECT MANAGEMENT SOLUTIONS LLC | OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F) | $2,229,000 | FY2026 |
| 36C10F26C0013 | V&C GENERAL CONTRACTOR LLC | OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F) | $2,518,650 | FY2026 |
| 36C10F23C0007 | WALSH CONSTRUCTION COMPANY II, LLC | OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F) | $215,172,226 | FY2023 |
| 36C10F23N0064 | SSPC LLC | OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F) | $421,407 | FY2023 |
| 36C10F23C0003 | DAV ENERGY SOLUTIONS, INC. | OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F) | $175,181 | FY2023 |
Cite as: Glassbox VA record view · VA contract (USAspending / FPDS) · CONT_AWD_36C10F19C0016_3600_-NONE-_-NONE- · retrieved 2026-09-26.