Description
P00083 DEFINITIZE CHANGE ORDER
Base award description: DESIGN BUILD SEISMIC RENOVATE, ASBESTOS AND LEAD BASED PAINT ABATEMENT BLDG. 86 OPC WALLA WALLA, WA
Modification chain · 122 transactions
Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.
- Base2018-09-26+$22,994,144= $22,994,144
- Mod P000012019-01-03+$0= $22,994,144
- Mod P000022019-01-08+$0= $22,994,144
- Mod A000012019-04-10+$0= $22,994,144
- Mod A000022020-01-06+$7,903= $23,002,047
- Mod A000032020-04-03+$77,125= $23,079,172
- Mod A000042020-04-24+$5,437= $23,084,609
- Mod A000052020-05-14+$36,459= $23,121,068
- Mod A000082020-05-29+$106,027= $23,227,095
- Mod A000072020-06-01+$67,722= $23,294,817
- Mod A000062020-06-19+$10,007= $23,304,824
- Mod A000092020-06-19+$23,083= $23,327,907
- Mod A000102020-06-24+$33,011= $23,360,918
- Mod A000112020-07-31+$137,659= $23,498,577
- Mod A000132020-08-04+$71,705= $23,570,282
- Mod A000142020-08-26+$29,576= $23,599,858
- Mod A000122020-09-04+$17,348= $23,617,206
- Mod A000152020-10-01+$3,310= $23,620,516
- Mod A000172020-11-03+$11,986= $23,632,502
- Mod A000162020-11-12+$7,505= $23,640,007
- Mod A000202020-11-17+$50,000= $23,690,007
- Mod A000212020-11-17+$170,000= $23,860,007
- Mod A000192020-11-19+$120,417= $23,980,424
- Mod A000222020-12-14+$4,438= $23,984,862
- Mod A000242021-01-22+$19,887= $24,004,749
- Mod A000252021-01-22+$164,000= $24,168,749
- Mod A000182021-01-29+$183,181= $24,351,930
- Mod A000262021-02-01+$37,764= $24,389,694
- Mod A000282021-03-15+$130,970= $24,520,664
- Mod A000312021-03-17+$7,198= $24,527,862
- Mod P000032021-03-22+$241,269= $24,769,130
- Mod P000042021-03-23+$0= $24,769,130
- Mod A000302021-03-30+$93,764= $24,862,894
- Mod A000232021-03-31+$35,045= $24,897,939
- Mod A000292021-03-31+$10,681= $24,908,620
- Mod A000272021-04-02+$38,163= $24,946,783
- Mod P000052021-04-29+$1,750,000= $26,696,783
- Mod A000322021-06-01+$36,377= $26,733,160
- Mod P000062021-06-14+$0= $26,733,160
- Mod A000332021-06-15+$4,241= $26,737,401
- Mod A000392021-06-17+$247,076= $26,984,477
- Mod A000402021-06-23+$62,375= $27,046,852
- Mod A000342021-06-24+$0= $27,046,852
- Mod A000412021-06-24+$56,219= $27,103,071
- Mod A000382021-07-08+$16,049= $27,119,120
- Mod A000422021-07-16-$128,672= $26,990,448
- Mod A000442021-07-26-$15,568= $26,974,880
- Mod A000432021-08-10+$8,816= $26,983,696
- Mod P000072021-11-08+$358,973= $27,342,669
- Mod P000092022-01-18+$425,936= $27,768,605
- Mod A000452022-01-27+$11,760= $27,780,365
- Mod P000112022-02-08+$0= $27,780,365
- Mod P000082022-03-08+$1,282,871= $29,063,236
- Mod P000102022-03-18+$43,024= $29,106,260
- Mod P000132022-03-21-$19,266= $29,086,994
- Mod P000142022-03-21+$109,530= $29,196,524
- Mod P000152022-03-22-$22,542= $29,173,982
- Mod P000162022-04-21+$100,000= $29,273,982
- Mod P000122022-05-13+$96,200= $29,370,182
- Mod P000182022-07-05+$11,124= $29,381,307
- Mod P000222022-08-25+$61,034= $29,442,340
- Mod P000242022-09-29+$11,357= $29,453,698
- Mod P000252022-11-02+$2,917= $29,456,615
- Mod P000232022-11-30+$3,583,800= $33,040,415
- Mod P000262022-12-07+$2,231,970= $35,272,384
- Mod P000282023-01-19+$16,872= $35,289,256
- Mod P000302023-02-15+$111,821= $35,401,077
- Mod P000272023-02-23+$42,689= $35,443,766
- Mod P000312023-03-09+$19,372= $35,463,138
- Mod P000292023-03-13+$59,434= $35,522,572
- Mod P000322023-04-11+$3,265= $35,525,837
- Mod P000342023-07-24+$81,450= $35,607,287
- Mod P000362023-08-07+$27,131= $35,634,418
- Mod P000352023-08-11+$86,957= $35,721,375
- Mod P000412023-09-15+$385,022= $36,106,397
- Mod P000372023-09-18+$108,768= $36,215,165
- Mod P000392023-09-27+$887,276= $37,102,441
- Mod P000432023-10-25-$3,497= $37,098,944
- Mod P000482023-11-30+$83,560= $37,182,503
- Mod P000462023-12-19+$151,229= $37,333,732
- Mod P000382024-01-02+$1,272,310= $38,606,042
- Mod P000402024-01-08+$115,380= $38,721,422
- Mod P000502024-01-08+$0= $38,721,422
- Mod P000472024-01-10+$34,193= $38,755,615
- Mod P000452024-01-12+$87,695= $38,843,310
- Mod P000512024-01-12+$168,051= $39,011,361
- Mod P000492024-01-18+$536,117= $39,547,478
- Mod P000422024-02-08+$19,357= $39,566,835
- Mod P000522024-02-08-$16,448= $39,550,387
- Mod P000572024-04-29+$183,473= $39,733,860
- Mod P000442024-05-01+$108,611= $39,842,471
- Mod P000562024-05-01+$547,079= $40,389,550
- Mod P000582024-06-04+$8,039= $40,397,589
- Mod P000602024-06-04+$12,853= $40,410,442
- Mod P000542024-06-13+$61,667= $40,472,110
- Mod P000552024-06-13+$0= $40,472,110
- Mod P000612024-06-13+$1,945= $40,474,055
- Mod P000622024-08-01+$651,273= $41,125,328
- Mod P000592024-09-19+$63,113= $41,188,441
- Mod P000532024-09-23+$362,884= $41,551,326
- Mod P000632024-10-21+$0= $41,551,326
- Mod P000652024-10-31+$161,528= $41,712,853
- Mod P000662024-11-13+$81,484= $41,794,337
- Mod P000642024-11-14+$1,179,762= $42,974,099
- Mod P000702024-11-18-$13,823= $42,960,276
- Mod P000672024-11-25+$101,224= $43,061,501
- Mod P000682024-11-25+$206,221= $43,267,721
- Mod P000692025-01-29+$240,797= $43,508,518
- Mod P000712025-02-24+$164,467= $43,672,985
- Mod P000722025-02-26+$16,054= $43,689,039
- Mod P000742025-04-01+$6,856= $43,695,895
- Mod P000762025-04-10+$0= $43,695,895
- Mod P000752025-04-15+$31,581= $43,727,476
- Mod P000772025-07-23-$17,826= $43,709,650
- Mod P000782025-07-23+$9,498= $43,719,148
- Mod P000792025-07-23+$47,435= $43,766,583
- Mod P000802025-07-23-$23,383= $43,743,200
- Mod P000842025-08-04-$20= $43,743,181
- Mod P000812025-08-11+$62,172= $43,805,353
- Mod P000822025-08-18+$1,054,619= $44,859,971
- Mod P000832025-08-18+$139,539= $44,999,511
- Mod P000852025-09-11+$106,000= $45,105,511
| Transaction | Action date | This action (delta) | Running total | Description on this transaction |
|---|---|---|---|---|
| Base | 2018-09-26 | +$22,994,144 | $22,994,144 | DESIGN BUILD SEISMIC RENOVATE, ASBESTOS AND LEAD BASED PAINT ABATEMENT BLDG. 86 OPC WALLA WALLA, WA |
| Mod P00001· OTHER ADMINISTRATIVE ACTION | 2019-01-03 | +$0 | $22,994,144 | DESIGN BUILD SEISMIC RENOVATE, ASBESTOS AND LEAD BASED PAINT ABATEMENT BLDG. 86 OPC WALLA WALLA, WA |
| Mod P00002· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2019-01-08 | +$0 | $22,994,144 | DESIGN BUILD SEISMIC RENOVATE, ASBESTOS AND LEAD BASED PAINT ABATEMENT BLDG. 86 OPC WALLA WALLA, WA |
| Mod A00001· CHANGE ORDER | 2019-04-10 | +$0 | $22,994,144 | DESIGN BUILD SEISMIC RENOVATE, ASBESTOS AND LEAD BASED PAINT ABATEMENT BLDG. 86 OPC WALLA WALLA, WA |
| Mod A00002· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2020-01-06 | +$7,903 | $23,002,047 | DESIGN BUILD SEISMIC RENOVATE, ASBESTOS AND LEAD BASED PAINT ABATEMENT BLDG. 86 OPC WALLA WALLA, WA |
| Mod A00003· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2020-04-03 | +$77,125 | $23,079,172 | DESIGN BUILD SEISMIC RENOVATE, ASBESTOS AND LEAD BASED PAINT ABATEMENT BLDG. 86 OPC WALLA WALLA, WA |
| Mod A00004· CHANGE ORDER | 2020-04-24 | +$5,437 | $23,084,609 | DESIGN BUILD SEISMIC RENOVATE, ASBESTOS AND LEAD BASED PAINT ABATEMENT BLDG. 86 OPC WALLA WALLA, WA |
| Mod A00005· DEFINITIZE CHANGE ORDER | 2020-05-14 | +$36,459 | $23,121,068 | MODIFICATION A00005 ENGINEER SERVICES FOR CONCRETE REPAIR (DEFINITIZED) |
| Mod A00008· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2020-05-29 | +$106,027 | $23,227,095 | MODIFICATION A00008 CRAWL SPACE ABATEMENT |
| Mod A00007· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2020-06-01 | +$67,722 | $23,294,817 | MODIFICATION A00007 ROOF REPLACEMENT |
| Mod A00006· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2020-06-19 | +$10,007 | $23,304,824 | MODIFICATION A00006 3-PART DEMOLITION/CONSTRUCTION |
| Mod A00009· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2020-06-19 | +$23,083 | $23,327,907 | MODIFICATION A00009 4-PART DEMOLITION/ABATEMENT |
| Mod A00010· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2020-06-24 | +$33,011 | $23,360,918 | MODIFICATION A00010 LEAD PAINT IN MECHANICAL ROOM |
| Mod A00011· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2020-07-31 | +$137,659 | $23,498,577 | SUPPLEMENTAL AGREEMENT A00011 (CAT 6A AND ROOF LADDER FOR B86) |
| Mod A00013· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2020-08-04 | +$71,705 | $23,570,282 | SUPPLEMENTAL AGREEMENT A00013 (2-PART DEMOLITION/CONSTRUCTION) |
| Mod A00014· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2020-08-26 | +$29,576 | $23,599,858 | SUPPLEMENTAL AGREEMENT A00014 PARADE LOOP DESIGN MODIFICATION |
| Mod A00012· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2020-09-04 | +$17,348 | $23,617,206 | SUPPLEMENTAL AGREEMENT A00012 PLASTER AND LATHE CEILING REMOVAL |
| Mod A00015· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2020-10-01 | +$3,310 | $23,620,516 | SUPPLEMENTAL AGREEMENT A00015 FOUNDATION CRACK REPAIR |
| Mod A00017· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2020-11-03 | +$11,986 | $23,632,502 | SUPPLEMENTAL AGREEMENT A00017 TEMPORARY SPS SITE SURVEY |
| Mod A00016· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2020-11-12 | +$7,505 | $23,640,007 | SUPPLEMENTAL AGREEMENT A00016 MISCELLANEOUS BASEMENT AND 3RD FLOOR ACM ABATEMENT |
| Mod A00020· CHANGE ORDER | 2020-11-17 | +$50,000 | $23,690,007 | CHANGE ORDER A00020 CONCRETE REPAIR AREA 2A |
| Mod A00021· CHANGE ORDER | 2020-11-17 | +$170,000 | $23,860,007 | CHANGE ORDER A00021 CONCRETE REPAIR AREA 2B |
| Mod A00019· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2020-11-19 | +$120,417 | $23,980,424 | SUPPLEMENTAL AGREEMENT A00019 SPS RELOCATION DESIGN |
| Mod A00022· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2020-12-14 | +$4,438 | $23,984,862 | SUPPLEMENTAL AGREEMENT A00022 POWER DEMAND METERING |
| Mod A00024· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2021-01-22 | +$19,887 | $24,004,749 | SUPPLEMENTAL AGREEMENT A00024 RELOCATE STEAM TO BLDG. 143 |
| Mod A00025· CHANGE ORDER | 2021-01-22 | +$164,000 | $24,168,749 | CHANGE ORDER A00025 CONCRETE REPAIRS - 3RD FLOOR NON-SPS AREAS |
| Mod A00018· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2021-01-29 | +$183,181 | $24,351,930 | SUPPLEMENTAL AGREEMENT A00018 PARADE LOOP MODIFICATIONS |
| Mod A00026· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2021-02-01 | +$37,764 | $24,389,694 | SUPPLEMENTAL AGREEMENT A00026 RADIOLOGY DESIGN CHANGES |
| Mod A00028· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2021-03-15 | +$130,970 | $24,520,664 | SUPPLEMENTAL AGREEMENT A00028 BUILDING 143 TEMPORARY SPS (AHU UNIT ONLY) |
| Mod A00031· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2021-03-17 | +$7,198 | $24,527,862 | SUPPLEMENTAL AGREEMENT A00031 VERMICULITE REMOVAL |
| Mod P00003· CHANGE ORDER | 2021-03-22 | +$241,269 | $24,769,130 | SUPPLEMENTAL AGREEMENT A00022 POWER DEMAND METERING |
| Mod P00004· OTHER ADMINISTRATIVE ACTION | 2021-03-23 | +$0 | $24,769,130 | SUPPLEMENTAL AGREEMENT A00022 POWER DEMAND METERING |
| Mod A00030· CHANGE ORDER | 2021-03-30 | +$93,764 | $24,862,894 | CHANGE ORDER A00030 DEMO 3RD FLOOR TOPPING SLAB AND ABATE ACM |
| Mod A00023· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2021-03-31 | +$35,045 | $24,897,939 | SUPPLEMENTAL AGREEMENT A00023 LEAD ABATEMENT ROOMS 240 AND 242 |
| Mod A00029· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2021-03-31 | +$10,681 | $24,908,620 | SUPPLEMENTAL AGREEMENT A00029 FINISH ALTERATIONS |
| Mod A00027· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2021-04-02 | +$38,163 | $24,946,783 | SUPPLEMENTAL AGREEMENT A00027 GROUPED MOD #2 |
| Mod P00005· CHANGE ORDER | 2021-04-29 | +$1,750,000 | $26,696,783 | SUPPLEMENTAL AGREEMENT A00027 GROUPED MOD #2 |
| Mod A00032· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2021-06-01 | +$36,377 | $26,733,160 | SUPPLEMENTAL AGREEMENT A00032 DOOR ACTUATOR INSTALLATION |
| Mod P00006· DEFINITIZE CHANGE ORDER | 2021-06-14 | +$0 | $26,733,160 | SUPPLEMENTAL AGREEMENT A00027 GROUPED MOD #2 |
| Mod A00033· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2021-06-15 | +$4,241 | $26,737,401 | SUPPLEMENTAL AGREEMENT A00033 ISOLATION VALVE AND BOLLARDS |
| Mod A00039· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2021-06-17 | +$247,076 | $26,984,477 | SUPPLEMENTAL AGREEMENT A00039 CFM TRAILER |
| Mod A00040· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2021-06-23 | +$62,375 | $27,046,852 | SUPPLEMENTAL AGREEMENT A00040 PATIENT LIFTS |
| Mod A00034· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2021-06-24 | +$0 | $27,046,852 | SUPPLEMENTAL AGREEMENT A00034 REVISION (TIME) FOR A00012 AND A00016 |
| Mod A00041· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2021-06-24 | +$56,219 | $27,103,071 | SUPPLEMENTAL AGREEMENT A00041 TEMP ADA RAMP FRONT ENTRANCE |
| Mod A00038· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2021-07-08 | +$16,049 | $27,119,120 | SUPPLEMENTAL AGREEMENT A00038 AFTER HOURS WORK |
| Mod A00042· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2021-07-16 | −$128,672 | $26,990,448 | SUPPLEMENTAL AGREEMENT A00042 UNSUITABLE SOIL CONDITION AND CANCEL TEMP. SPS AHU |
| Mod A00044· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2021-07-26 | −$15,568 | $26,974,880 | SUPPLEMENTAL AGREEMENT A00044 DEDUCT IPADS AND ALLOWANCE |
| Mod A00043· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2021-08-10 | +$8,816 | $26,983,696 | SUPPLEMENTAL AGREEMENT A00043 ANTENNA REMOVAL AND REINSTALLATION |
| Mod P00007· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2021-11-08 | +$358,973 | $27,342,669 | SUPPLEMENTAL AGREEMENT A00043 ANTENNA REMOVAL AND REINSTALLATION |
| Mod P00009· CHANGE ORDER | 2022-01-18 | +$425,936 | $27,768,605 | CHANGE ORDER P00009 - 1ST FLOOR CONCRETE REPAIRS |
| Mod A00045· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2022-01-27 | +$11,760 | $27,780,365 | SUPPLEMENTAL AGREEMENT A00045 - GENERATOR TESTING |
| Mod P00011· OTHER ADMINISTRATIVE ACTION | 2022-02-08 | +$0 | $27,780,365 | CHANGE ORDER P00009 - 1ST FLOOR CONCRETE REPAIRS |
| Mod P00008· CHANGE ORDER | 2022-03-08 | +$1,282,871 | $29,063,236 | CHANGE ORDER P00009 - 1ST FLOOR CONCRETE REPAIRS |
| Mod P00010· CHANGE ORDER | 2022-03-18 | +$43,024 | $29,106,260 | SUPPLEMENTAL AGREEMENT A00043 ANTENNA REMOVAL AND REINSTALLATION |
| Mod P00013· CHANGE ORDER | 2022-03-21 | −$19,266 | $29,086,994 | CHANGE ORDER P00009 - 1ST FLOOR CONCRETE REPAIRS |
| Mod P00014· CHANGE ORDER | 2022-03-21 | +$109,530 | $29,196,524 | CHANGE ORDER P00009 - 1ST FLOOR CONCRETE REPAIRS |
| Mod P00015· CHANGE ORDER | 2022-03-22 | −$22,542 | $29,173,982 | CHANGE ORDER P00009 - 1ST FLOOR CONCRETE REPAIRS |
| Mod P00016· CHANGE ORDER | 2022-04-21 | +$100,000 | $29,273,982 | CHANGE ORDER P00009 - 1ST FLOOR CONCRETE REPAIRS |
| Mod P00012· CHANGE ORDER | 2022-05-13 | +$96,200 | $29,370,182 | SUPPLEMENTAL AGREEMENT A00043 ANTENNA REMOVAL AND REINSTALLATION |
| Mod P00018· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2022-07-05 | +$11,124 | $29,381,307 | CHANGE ORDER P00009 - 1ST FLOOR CONCRETE REPAIRS |
| Mod P00022· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2022-08-25 | +$61,034 | $29,442,340 | RADIOLOGY TRAILER 3 ANTENNA REMOVAL AND REINSTALLATION |
| Mod P00024· CHANGE ORDER | 2022-09-29 | +$11,357 | $29,453,698 | RADIOLOGY TRAILER 3 ANTENNA REMOVAL AND REINSTALLATION |
| Mod P00025· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2022-11-02 | +$2,917 | $29,456,615 | REVISE DESIGN BASIS FOR NON-STRUCTURAL SEISMIC |
| Mod P00023· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2022-11-30 | +$3,583,800 | $33,040,415 | P000023 SETTLEMENT MODIFICATION |
| Mod P00026· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2022-12-07 | +$2,231,970 | $35,272,384 | REVISE DESIGN BASIS FOR NON-STRUCTURAL SEISMIC |
| Mod P00028· CHANGE ORDER | 2023-01-19 | +$16,872 | $35,289,256 | P00028 ASI 023 INSTALLATION |
| Mod P00030· CHANGE ORDER | 2023-02-15 | +$111,821 | $35,401,077 | P000023 SETTLEMENT MODIFICATION |
| Mod P00027· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2023-02-23 | +$42,689 | $35,443,766 | P000023 SETTLEMENT MODIFICATION |
| Mod P00031· CHANGE ORDER | 2023-03-09 | +$19,372 | $35,463,138 | P000023 SETTLEMENT MODIFICATION |
| Mod P00029· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2023-03-13 | +$59,434 | $35,522,572 | P000023 SETTLEMENT MODIFICATION |
| Mod P00032· CHANGE ORDER | 2023-04-11 | +$3,265 | $35,525,837 | P00032 CHANGE ORDER MODIFICATION SPS ADDED DATA AND POWER |
| Mod P00034· CHANGE ORDER | 2023-07-24 | +$81,450 | $35,607,287 | P00032 CHANGE ORDER MODIFICATION SPS ADDED DATA AND POWER |
| Mod P00036· CHANGE ORDER | 2023-08-07 | +$27,131 | $35,634,418 | P00032 CHANGE ORDER MODIFICATION SPS ADDED DATA AND POWER |
| Mod P00035· CHANGE ORDER | 2023-08-11 | +$86,957 | $35,721,375 | P00032 CHANGE ORDER MODIFICATION SPS ADDED DATA AND POWER |
| Mod P00041· CHANGE ORDER | 2023-09-15 | +$385,022 | $36,106,397 | P00032 CHANGE ORDER MODIFICATION ELEVATOR MODERNIZATION USER REQUESTED CHANGE |
| Mod P00037· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2023-09-18 | +$108,768 | $36,215,165 | P00032 SUPPLEMENTAL AGREEMENT 1ST AND 2ND FLOOR CONCRETE REPAIRS |
| Mod P00039· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2023-09-27 | +$887,276 | $37,102,441 | P00032 CHANGE ORDER MODIFICATION SPS ADDED DATA AND POWER |
| Mod P00043· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2023-10-25 | −$3,497 | $37,098,944 | P00032 CHANGE ORDER MODIFICATION SPS ADDED DATA AND POWER |
| Mod P00048· CHANGE ORDER | 2023-11-30 | +$83,560 | $37,182,503 | P00048 CHANGE ORDER ADDITIONAL WATER TESTING |
| Mod P00046· CHANGE ORDER | 2023-12-19 | +$151,229 | $37,333,732 | P00046 CHANGE ORDER MODIFICATION SPS STEAM INSTALLATION |
| Mod P00038· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2024-01-02 | +$1,272,310 | $38,606,042 | P00032 CHANGE ORDER MODIFICATION SPS ADDED DATA AND POWER |
| Mod P00040· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2024-01-08 | +$115,380 | $38,721,422 | P00032 CHANGE ORDER MODIFICATION SPS ADDED DATA AND POWER |
| Mod P00050· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2024-01-08 | +$0 | $38,721,422 | P00032 CHANGE ORDER MODIFICATION SPS ADDED DATA AND POWER |
| Mod P00047· CHANGE ORDER | 2024-01-10 | +$34,193 | $38,755,615 | P00032 CHANGE ORDER MODIFICATION SPS ADDED DATA AND POWER |
| Mod P00045· CHANGE ORDER | 2024-01-12 | +$87,695 | $38,843,310 | P00032 CHANGE ORDER SPS MOVE IN MODIFICATIONS |
| Mod P00051· CHANGE ORDER | 2024-01-12 | +$168,051 | $39,011,361 | P00032 CHANGE ORDER MODIFICATION SPS ADDED DATA AND POWER |
| Mod P00049· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2024-01-18 | +$536,117 | $39,547,478 | P00032 CHANGE ORDER MODIFICATION SPS ADDED DATA AND POWER |
| Mod P00042· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2024-02-08 | +$19,357 | $39,566,835 | P00042 FIRE EXIT DOOR MODIFICATION |
| Mod P00052· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2024-02-08 | −$16,448 | $39,550,387 | P00052 STERIS PIPE RELOCATION |
| Mod P00057· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2024-04-29 | +$183,473 | $39,733,860 | P00057 - 3RD FLOOR STRUCTURAL REPAIRS SUPPLEMENTAL AGREEMENT TO DEFINITIZE P00051 |
| Mod P00044· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2024-05-01 | +$108,611 | $39,842,471 | P00044 SUPPLEMENTAL AGREEMENT ASI 17 |
| Mod P00056· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2024-05-01 | +$547,079 | $40,389,550 | P00056 CHANGE ORDER ADDITIONAL R/O DESIGN AND INSTALLATION |
| Mod P00058· CHANGE ORDER | 2024-06-04 | +$8,039 | $40,397,589 | P00052 STERIS PIPE RELOCATION |
| Mod P00060· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2024-06-04 | +$12,853 | $40,410,442 | P00056 CHANGE ORDER ADDITIONAL R/O DESIGN AND INSTALLATION |
| Mod P00054· CHANGE ORDER | 2024-06-13 | +$61,667 | $40,472,110 | P00052 STERIS PIPE RELOCATION |
| Mod P00055· OTHER ADMINISTRATIVE ACTION | 2024-06-13 | +$0 | $40,472,110 | P00055 SPS MOVE IN MODIFICATIONS DEFINITIZATION MODIFICATION |
| Mod P00061· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2024-06-13 | +$1,945 | $40,474,055 | P00061 SA DCVA VALVE REPLACEMENT |
| Mod P00062· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2024-08-01 | +$651,273 | $41,125,328 | P00062 SA ADDITIONAL RO WATER DESIGN AND WATER MODIFICATION |
| Mod P00059· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2024-09-19 | +$63,113 | $41,188,441 | P00056 CHANGE ORDER ADDITIONAL R/O DESIGN AND INSTALLATION |
| Mod P00053· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2024-09-23 | +$362,884 | $41,551,326 | P00053 SUBCONTRACTOR ESCALATION MODIFICATION 2 |
| Mod P00063· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2024-10-21 | +$0 | $41,551,326 | P00063 RADIOLOGY TRAILER EXTENSION MODIFICATION |
| Mod P00065· CHANGE ORDER | 2024-10-31 | +$161,528 | $41,712,853 | P00065 UPS UPDATE CHANGE ORDER |
| Mod P00066· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2024-11-13 | +$81,484 | $41,794,337 | P00066 REPLACE ATTIC FIRE SUPPRESSION SYSTEM |
| Mod P00064· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2024-11-14 | +$1,179,762 | $42,974,099 | P00064 CREM SUBCONTRACTOR ESCALATION MODIFICATION |
| Mod P00070· CHANGE ORDER | 2024-11-18 | −$13,823 | $42,960,276 | P00070 CHANGE ORDER - ELEVATOR MODERNIZATION MODIFICATION P00054 SUPPLEMENT |
| Mod P00067· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2024-11-25 | +$101,224 | $43,061,501 | P00067 HISTORICAL PRESERVATION |
| Mod P00068· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2024-11-25 | +$206,221 | $43,267,721 | P00068 FLOOR INFILL |
| Mod P00069· CHANGE ORDER | 2025-01-29 | +$240,797 | $43,508,518 | P00069 RO CHANGES FINALIZATION CHANGE ORDER |
| Mod P00071· CHANGE ORDER | 2025-02-24 | +$164,467 | $43,672,985 | P00069 COMPLETION ITEMS CHANGE ORDER |
| Mod P00072· CHANGE ORDER | 2025-02-26 | +$16,054 | $43,689,039 | P00072 ACCESS CONTROL COORDINATION CHANGE ORDER |
| Mod P00074· CHANGE ORDER | 2025-04-01 | +$6,856 | $43,695,895 | P00072 ACCESS CONTROL COORDINATION CHANGE ORDER |
| Mod P00076· OTHER ADMINISTRATIVE ACTION | 2025-04-10 | +$0 | $43,695,895 | P00076 ADMIN MOD - EXTEND POP |
| Mod P00075· CHANGE ORDER | 2025-04-15 | +$31,581 | $43,727,476 | P00075 HVAC RELOCATION CHANGE ORDER |
| Mod P00077· DEFINITIZE CHANGE ORDER | 2025-07-23 | −$17,826 | $43,709,650 | P00077 DEFINITIZE CHANGE ORDER P00065 INSTALL UPS AND PDU |
| Mod P00078· DEFINITIZE CHANGE ORDER | 2025-07-23 | +$9,498 | $43,719,148 | P00078 DEFINITIZE CHANGE ORDER P00072 |
| Mod P00079· DEFINITIZE CHANGE ORDER | 2025-07-23 | +$47,435 | $43,766,583 | P00075 HVAC RELOCATION CHANGE ORDER |
| Mod P00080· DEFINITIZE CHANGE ORDER | 2025-07-23 | −$23,383 | $43,743,200 | P00080 DEFINITIZE CHANGE ORDER P00075 |
| Mod P00084· DEFINITIZE CHANGE ORDER | 2025-08-04 | −$20 | $43,743,181 | P00084 DEFINITIZE P00058 |
| Mod P00081· DEFINITIZE CHANGE ORDER | 2025-08-11 | +$62,172 | $43,805,353 | P00081 DEFINITIZE P00074 CHANGE ORDER |
| Mod P00082· DEFINITIZE CHANGE ORDER | 2025-08-18 | +$1,054,619 | $44,859,971 | P00082 DEFINITIZE CHANGE ORDER |
| Mod P00083· DEFINITIZE CHANGE ORDER | 2025-08-18 | +$139,539 | $44,999,511 | P00083 DEFINITIZE CHANGE ORDER |
| Mod P00085· CHANGE ORDER | 2025-09-11 | +$106,000 | $45,105,511 | P00083 DEFINITIZE CHANGE ORDER |
Related awards · 5
Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.
Other recipients under Y1DA from OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F) (most recent first)
| Award | Recipient | Office | Net obligations | FY |
|---|---|---|---|---|
| 36C10F26C0014 | PROJECT MANAGEMENT SOLUTIONS LLC | OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F) | $2,229,000 | FY2026 |
| 36C10F26C0013 | V&C GENERAL CONTRACTOR LLC | OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F) | $2,518,650 | FY2026 |
| 36C10F23C0007 | WALSH CONSTRUCTION COMPANY II, LLC | OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F) | $215,172,226 | FY2023 |
| 36C10F23N0064 | SSPC LLC | OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F) | $421,407 | FY2023 |
| 36C10F23C0003 | DAV ENERGY SOLUTIONS, INC. | OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F) | $175,181 | FY2023 |
Cite as: Glassbox VA record view · VA contract (USAspending / FPDS) · CONT_AWD_36C10F18C3377_3600_-NONE-_-NONE- · retrieved 2026-09-26.