Description
TAS::36 0158::TAS TAS:36 0158 000::TAS TO UPGRADE BOILER PLANT.
Modification chain · 1 transaction
Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.
- Base2009-06-11+$67,969= $67,969
| Transaction | Action date | This action (delta) | Running total | Description on this transaction |
|---|---|---|---|---|
| Base | 2009-06-11 | +$67,969 | $67,969 | TAS::36 0158::TAS TAS:36 0158 000::TAS TO UPGRADE BOILER PLANT. |
Related awards · 10
Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.
Other VA awards to the same recipient (UEI GKPVANP9V6P8)
| Award | Office · PSC / listing | Net obligations | FY |
|---|---|---|---|
| VA25714J0742 | 257-NETWORK CONTRACT OFFICE 17 · Y1DA · CONSTRUCTION OF HOSPITALS AND INFIRMARIES | $176,054 | FY2014 |
| VA25713J1036 | 674-TEMPLE · C219 · ARCHITECT AND ENGINEERING- GENERAL: OTHER | $620,867 | FY2013 |
| VA25712J1183 | 257-NETWORK CONTRACT OFFICE 17 · C219 · ARCHITECT AND ENGINEERING- GENERAL: OTHER | $115,234 | FY2012 |
| VA25712J0457 | 671-SAN ANTONIO · C219 · ARCHITECT AND ENGINEERING- GENERAL: OTHER | $65,970 | FY2012 |
| VA25712F0126 | 257-NETWORK CONTRACT OFFICE 17 · C214 · ARCHITECT AND ENGINEERING- GENERAL: MANAGEMENT ENGINEERING | $70,971 | FY2012 |
| V671C11150 | 257-NETWORK CONTRACT OFFICE 17 (36C257) · C219 · ARCHITECT AND ENGINEERING- GENERAL: OTHER | $337,497 | FY2011 |
Other recipients under C212 from 671-SAN ANTONIO (most recent first)
| Award | Recipient | Office | Net obligations | FY |
|---|---|---|---|---|
| V671C00893 | MCCALL & ASSOCIATES - AIA - ARCHITECTS | 671-SAN ANTONIO | $15,041 | FY2010 |
| VA257C0210 | M E P CONSULTING ENGINEERS | 671-SAN ANTONIO | $21,810 | FY2008 |
| V671C81211 | WESTEAST DESIGN GROUP, LLC | 671-SAN ANTONIO | $141,842 | FY2008 |
| V671C81178 | M E P CONSULTING ENGINEERS | 671-SAN ANTONIO | $96,867 | FY2008 |
Cite as: Glassbox VA record view · VA contract (USAspending / FPDS) · CONT_AWD_VARA671C91294_3600_VA257P0247_3600 · retrieved 2026-09-26.