Award recordCONTRACT

ALLIANCE ROOFING LLC

PIID VARA549C01073· VHA· 257-NETWORK CONTRACT OFFICE 17 (36C257)· Z141 · MAINT-REP-ALT/HOSPITALS & INFIRMARY· FY2010· $1,405,846 net obligations· UEI D1KEQ3HNMCK7· CT

Description

RECOVERY ACT PROJECT - R549-09-900 PATIENT CARE AREA ROOF REPLACEMENT MOD 11 - EXTEND THE POP

Base award description: PROJECT 549-09-900 PATIENT CARE AREA ROOF REPLACEMENT

First action · last action
2010-03-30 · 2018-11-09
Transactions
13
First transaction's obligation
$1,149,551
Base + all options value (sum of deltas)
$1,405,846
Extent competed
FULL AND OPEN COMPETITION
Other than full & open authority
—
Set-aside
—
Offers received
2
SDVOSB flag on record
No
Parent IDV
GS07F0224N
NAICS
324122 · ASPHALT SHINGLE AND COATING MATERIALS MANUFACTURING

Modification chain · 13 transactions

Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.

$1,405,847$0Base award · 2010-03-30 · this action $1,149,551 · running total $1,149,551Modification 1 · 2010-05-13 · this action $135,654 · running total $1,285,205Modification 2 · 2011-03-18 · this action $90,164 · running total $1,375,369Modification 3 · 2011-06-30 · this action $0 · running total $1,375,369Modification 4 · 2011-09-30 · this action $0 · running total $1,375,369Modification 5 · 2011-11-30 · this action $15,875 · running total $1,391,244Modification 6 · 2012-01-11 · this action $0 · running total $1,391,244Modification P00007 · 2012-03-13 · this action $0 · running total $1,391,244Modification P00008 · 2012-05-04 · this action $0 · running total $1,391,244Modification P00009 · 2012-05-17 · this action $14,603 · running total $1,405,847Modification P00010 · 2012-09-14 · this action $0 · running total $1,405,847Modification P00011 · 2012-11-06 · this action $0 · running total $1,405,847Modification P00012 · 2018-11-09 · this action -$1 · running total $1,405,846
  • Base2010-03-30+$1,149,551= $1,149,551
  • Mod 12010-05-13+$135,654= $1,285,205
  • Mod 22011-03-18+$90,164= $1,375,369
  • Mod 32011-06-30+$0= $1,375,369
  • Mod 42011-09-30+$0= $1,375,369
  • Mod 52011-11-30+$15,875= $1,391,244
  • Mod 62012-01-11+$0= $1,391,244
  • Mod P000072012-03-13+$0= $1,391,244
  • Mod P000082012-05-04+$0= $1,391,244
  • Mod P000092012-05-17+$14,603= $1,405,847
  • Mod P000102012-09-14+$0= $1,405,847
  • Mod P000112012-11-06+$0= $1,405,847
  • Mod P000122018-11-09-$1= $1,405,846
TransactionAction dateThis action (delta)Running totalDescription on this transaction
Base2010-03-30+$1,149,551$1,149,551PROJECT 549-09-900 PATIENT CARE AREA ROOF REPLACEMENT
Mod 1· CHANGE ORDER2010-05-13+$135,654$1,285,205PROJECT 549-09-900, MOD ONE PATIENT CARE AREA ROOF REPLACEMENT ADDING ADD ALT ONE TO THE CONTRACT
Mod 2· CHANGE ORDER2011-03-18+$90,164$1,375,369PROJECT 549-09-900, MOD TWO PATIENT CARE AREA ROOF REPLACEMENT PRIOR YEAR FUNDS REQUEST APPROVED
Mod 3· CHANGE ORDER2011-06-30+$0$1,375,369RECOVERY ACT PROJECT - R549-09-900 PATIENT CARE AREA ROOF REPLACEMENT MOD THREE EXTEND THE PERIOD OF PERFOR…
Mod 4· CHANGE ORDER2011-09-30+$0$1,375,369RECOVERY ACT PROJECT - R549-09-900 PATIENT CARE AREA ROOF REPLACEMENT MOD FOUR EXTEND THE PERIOD OF PERFORM…
Mod 5· CHANGE ORDER2011-11-30+$15,875$1,391,244RECOVERY ACT PROJECT - R549-09-900 PATIENT CARE AREA ROOF REPLACEMENT MOD FIVE PRIOR YEAR FUNDS REQUEST
Mod 6· CHANGE ORDER2012-01-11+$0$1,391,244RECOVERY ACT PROJECT - R549-09-900 PATIENT CARE AREA ROOF REPLACEMENT MOD SIX EXTEND THE POP
Mod P00007· CHANGE ORDER2012-03-13+$0$1,391,244RECOVERY ACT PROJECT - R549-09-900 PATIENT CARE AREA ROOF REPLACEMENT MOD 7 - EXTEND THE POP
Mod P00008· CHANGE ORDER2012-05-04+$0$1,391,244RECOVERY ACT PROJECT - R549-09-900 PATIENT CARE AREA ROOF REPLACEMENT MOD 8 - EXTEND THE POP
Mod P00009· CHANGE ORDER2012-05-17+$14,603$1,405,847RECOVERY ACT PROJECT - R549-09-900 PATIENT CARE AREA ROOF REPLACEMENT MOD 9 - EXTEND THE POP ADDING 3 PRIOR…
Mod P00010· CHANGE ORDER2012-09-14+$0$1,405,847RECOVERY ACT PROJECT - R549-09-900 PATIENT CARE AREA ROOF REPLACEMENT MOD 10 - EXTEND THE POP
Mod P00011· CHANGE ORDER2012-11-06+$0$1,405,847RECOVERY ACT PROJECT - R549-09-900 PATIENT CARE AREA ROOF REPLACEMENT MOD 11 - EXTEND THE POP
Mod P00012· FUNDING ONLY ACTION2018-11-09−$1$1,405,846RECOVERY ACT PROJECT - R549-09-900 PATIENT CARE AREA ROOF REPLACEMENT MOD 11 - EXTEND THE POP

Related awards · 6

Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.

Other VA awards to the same recipient (UEI D1KEQ3HNMCK7)

AwardOffice · PSC / listingNet obligationsFY
V689C10380241-NETWORK CONTRACT OFFICE 01 · Z111 · MAINT-REP-ALT/OFFICE BLDGS$137,175FY2011
VA515C10275515-BATTLE CREEK · N062 · INSTALL OF LIGHTING FIXTURES$0FY2011
V689C10315241-NETWORK CONTRACT OFFICE 01 · Z141 · MAINT-REP-ALT/HOSPITALS & INFIRMARY$97,789FY2011
VA5490P3337549S-DALLAS SMALL PURCHASE · 5510 · LUMBER & RELATED WOOD MATERIALS$3,674FY2010
V689C00309241-NETWORK CONTRACT OFFICE 01 · 5650 · ROOFING AND SIDING MATERIALS$970,996FY2010
VA241C1452689-WEST HAVEN · Z141 · MAINT-REP-ALT/HOSPITALS & INFIRMARY$1,508,000FY2009

Cite as: Glassbox VA record view · VA contract (USAspending / FPDS) · CONT_AWD_VARA549C01073_3600_GS07F0224N_4730 · retrieved 2026-09-26.