Award recordCONTRACT

DWG & ASSOCIATES, INC.

PIID VARA531C09244· VHA· 260-NETWORK CONTRACT OFFICE 20· Y249 · CONSTRUCTION OF OTHER UTILITIES· FY2010· $1,924,607 net obligations· UEI JX8HZ5S2L396· CO

Description

TAS::36 0158::TAS CONSTRUCT GENERATOR BUILDING AND INSTALL EQUIPMENT

First action · last action
2010-03-25 · 2014-10-03
Transactions
21
First transaction's obligation
$1,614,703
Base + all options value (sum of deltas)
$1,924,607
Extent competed
FULL AND OPEN COMPETITION AFTER EXCLUSION OF SOURCES
Other than full & open authority
—
Set-aside
VETERAN SET ASIDE
Offers received
6
SDVOSB flag on record
Yes (self-representation)
Parent IDV
VA260C0585
NAICS
236220 · COMMERCIAL AND INSTITUTIONAL BUILDING CONSTRUCTION

Modification chain · 21 transactions

Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.

$1,924,607$0Base award · 2010-03-25 · this action $1,614,703 · running total $1,614,703Modification 2 · 2010-09-30 · this action $0 · running total $1,614,703Modification 4 · 2011-02-10 · this action $0 · running total $1,614,703Modification 6 · 2011-02-15 · this action $38,625 · running total $1,653,328Modification 1 · 2011-04-26 · this action $9,180 · running total $1,662,508Modification 5 · 2011-04-26 · this action $0 · running total $1,662,508Modification 7 · 2011-06-10 · this action $56,372 · running total $1,718,880Modification 8 · 2011-07-28 · this action $3,037 · running total $1,721,917Modification 3 · 2011-09-08 · this action $14,481 · running total $1,736,398Modification 9 · 2011-10-13 · this action $74,085 · running total $1,810,483Modification 11 · 2011-11-09 · this action $0 · running total $1,810,483Modification 10 · 2011-11-18 · this action $5,818 · running total $1,816,301Modification 12 · 2012-01-04 · this action $0 · running total $1,816,301Modification 13 · 2012-01-04 · this action $0 · running total $1,816,301Modification 15 · 2012-06-06 · this action $5,873 · running total $1,822,174Modification P00017 · 2012-11-13 · this action $35,003 · running total $1,857,176Modification P00016 · 2012-11-20 · this action $30,563 · running total $1,887,740Modification P00018 · 2012-11-20 · this action $20,356 · running total $1,908,096Modification P00019 · 2013-01-22 · this action $9,352 · running total $1,917,447Modification P00020 · 2013-01-30 · this action $0 · running total $1,917,447Modification P00021 · 2014-10-03 · this action $7,160 · running total $1,924,607
  • Base2010-03-25+$1,614,703= $1,614,703
  • Mod 22010-09-30+$0= $1,614,703
  • Mod 42011-02-10+$0= $1,614,703
  • Mod 62011-02-15+$38,625= $1,653,328
  • Mod 12011-04-26+$9,180= $1,662,508
  • Mod 52011-04-26+$0= $1,662,508
  • Mod 72011-06-10+$56,372= $1,718,880
  • Mod 82011-07-28+$3,037= $1,721,917
  • Mod 32011-09-08+$14,481= $1,736,398
  • Mod 92011-10-13+$74,085= $1,810,483
  • Mod 112011-11-09+$0= $1,810,483
  • Mod 102011-11-18+$5,818= $1,816,301
  • Mod 122012-01-04+$0= $1,816,301
  • Mod 132012-01-04+$0= $1,816,301
  • Mod 152012-06-06+$5,873= $1,822,174
  • Mod P000172012-11-13+$35,003= $1,857,176
  • Mod P000162012-11-20+$30,563= $1,887,740
  • Mod P000182012-11-20+$20,356= $1,908,096
  • Mod P000192013-01-22+$9,352= $1,917,447
  • Mod P000202013-01-30+$0= $1,917,447
  • Mod P000212014-10-03+$7,160= $1,924,607
TransactionAction dateThis action (delta)Running totalDescription on this transaction
Base2010-03-25+$1,614,703$1,614,703TAS::36 0158::TAS CONSTRUCT GENERATOR BUILDING AND INSTALL EQUIPMENT
Mod 2· CHANGE ORDER2010-09-30+$0$1,614,703TAS::36 0158::TAS CONSTRUCT GENERATOR BUILDING AND INSTALL EQUIPMENT
Mod 4· CHANGE ORDER2011-02-10+$0$1,614,703TAS::36 0158::TAS CONSTRUCT GENERATOR BUILDING AND INSTALL EQUIPMENT
Mod 6· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-02-15+$38,625$1,653,328TAS::36 0158::TAS CONSTRUCT GENERATOR BUILDING AND INSTALL EQUIPMENT
Mod 1· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-04-26+$9,180$1,662,508TAS::36 0158::TAS CONSTRUCT GENERATOR BUILDING AND INSTALL EQUIPMENT
Mod 5· CHANGE ORDER2011-04-26+$0$1,662,508TAS::36 0158::TAS CONSTRUCT GENERATOR BUILDING AND INSTALL EQUIPMENT
Mod 7· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-06-10+$56,372$1,718,880TAS::36 0158::TAS CONSTRUCT GENERATOR BUILDING AND INSTALL EQUIPMENT
Mod 8· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-07-28+$3,037$1,721,917TAS::36 0158::TAS CONSTRUCT GENERATOR BUILDING AND INSTALL EQUIPMENT
Mod 3· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-09-08+$14,481$1,736,398TAS::36 0158::TAS CONSTRUCT GENERATOR BUILDING AND INSTALL EQUIPMENT
Mod 9· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-10-13+$74,085$1,810,483TAS::36 0158::TAS CONSTRUCT GENERATOR BUILDING AND INSTALL EQUIPMENT
Mod 11· CHANGE ORDER2011-11-09+$0$1,810,483TAS::36 0158::TAS CONSTRUCT GENERATOR BUILDING AND INSTALL EQUIPMENT
Mod 10· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-11-18+$5,818$1,816,301TAS::36 0158::TAS CONSTRUCT GENERATOR BUILDING AND INSTALL EQUIPMENT
Mod 12· CHANGE ORDER2012-01-04+$0$1,816,301TAS::36 0158::TAS CONSTRUCT GENERATOR BUILDING AND INSTALL EQUIPMENT
Mod 13· CHANGE ORDER2012-01-04+$0$1,816,301TAS::36 0158::TAS CONSTRUCT GENERATOR BUILDING AND INSTALL EQUIPMENT
Mod 15· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2012-06-06+$5,873$1,822,174TAS::36 0158::TAS CONSTRUCT GENERATOR BUILDING AND INSTALL EQUIPMENT
Mod P00017· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2012-11-13+$35,003$1,857,176TAS::36 0158::TAS CONSTRUCT GENERATOR BUILDING AND INSTALL EQUIPMENT
Mod P00016· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2012-11-20+$30,563$1,887,740TAS::36 0158::TAS CONSTRUCT GENERATOR BUILDING AND INSTALL EQUIPMENT
Mod P00018· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2012-11-20+$20,356$1,908,096TAS::36 0158::TAS CONSTRUCT GENERATOR BUILDING AND INSTALL EQUIPMENT
Mod P00019· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2013-01-22+$9,352$1,917,447TAS::36 0158::TAS CONSTRUCT GENERATOR BUILDING AND INSTALL EQUIPMENT
Mod P00020· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2013-01-30+$0$1,917,447TAS::36 0158::TAS CONSTRUCT GENERATOR BUILDING AND INSTALL EQUIPMENT
Mod P00021· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2014-10-03+$7,160$1,924,607TAS::36 0158::TAS CONSTRUCT GENERATOR BUILDING AND INSTALL EQUIPMENT

Related awards · 11

Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.

Other VA awards to the same recipient (UEI JX8HZ5S2L396)

AwardOffice · PSC / listingNet obligationsFY
VA531C15113260-NETWORK CONTRACT OFFICE 20 · Z111 · MAINT-REP-ALT/OFFICE BLDGS$559,269FY2011
VA668C15056260-NETWORK CONTRACT OFFICE 20 · Y141 · CONSTRUCT/HOSPITALS & INFIRMARIES$137,594FY2011
VA531C14328260-NETWORK CONTRACT OFFICE 20 · Z111 · MAINT-REP-ALT/OFFICE BLDGS$118,157FY2011
VA531C15112260-NETWORK CONTRACT OFFICE 20 · Y149 · CONSTRUCT/OTHER HOSPITAL BLDGS$819,872FY2011
VA531C15116260-NETWORK CONTRACT OFFICE 20 · Z142 · MAINT-REP-ALT/LABS & CLINICS$474,731FY2011
VA668C15059260-NETWORK CONTRACT OFFICE 20 · Y149 · CONSTRUCT/OTHER HOSPITAL BLDGS$1,992,181FY2011

Other recipients under Y249 from 260-NETWORK CONTRACT OFFICE 20 (most recent first)

AwardRecipientOfficeNet obligationsFY
VA260RA0817CMEC, ARC ELECTRIC, JV, LLC260-NETWORK CONTRACT OFFICE 20$5,175,963FY2010
VARA531C09259NORTHWEST TECHNOLOGIES INC260-NETWORK CONTRACT OFFICE 20$449,419FY2010
VA260C0663VET INDUSTRIAL INC260-NETWORK CONTRACT OFFICE 20$2,007,115FY2009
VA531C99258ATS INLAND NW LLC260-NETWORK CONTRACT OFFICE 20$13,496FY2009
VA531C99255CONTRACTORS SERVICES LLC260-NETWORK CONTRACT OFFICE 20$35,341FY2009

Cite as: Glassbox VA record view · VA contract (USAspending / FPDS) · CONT_AWD_VARA531C09244_3600_VA260C0585_3600 · retrieved 2026-09-26.