Description
DE-OBLIGATE REMAINING FUNDS FOR OPTION YEAR 2 (CALENDAR YEAR 2013).
Base award description: CONSTRUCTION MANAGEMENT SERVICES FOR REPLACEMENT MEDICAL CENTER FACILITY, ECHCS
Modification chain · 50 transactions
Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.
- Base2011-03-09+$792,334= $792,334
- Mod SA0012011-07-11+$57,104= $849,438
- Mod SA0022011-07-29+$59,321= $908,759
- Mod SA0032011-08-26+$80,083= $988,843
- Mod SA0042011-12-06+$60,540= $1,049,383
- Mod 12012-01-02+$1,943,216= $2,992,598
- Mod SA0052012-04-24+$515,992= $3,508,591
- Mod P000072012-10-05+$52,586= $3,561,176
- Mod P000082012-10-31+$47,656= $3,608,832
- Mod P000102012-11-20+$20,424= $3,629,256
- Mod P000112012-12-31+$2,812,514= $6,441,770
- Mod P000092013-01-18+$508,501= $6,950,271
- Mod A000022013-01-30+$0= $6,950,271
- Mod P000132013-03-06+$0= $6,950,271
- Mod P000162013-05-15+$0= $6,950,271
- Mod P000142013-05-29+$117,541= $7,067,812
- Mod P000152013-05-29+$55,564= $7,123,376
- Mod P000172013-06-05-$221,150= $6,902,226
- Mod P000122013-06-06+$0= $6,902,226
- Mod P000182013-07-26+$130,936= $7,033,162
- Mod P000192013-07-26+$130,936= $7,164,098
- Mod P000202013-07-31+$71,516= $7,235,615
- Mod P000212013-08-23+$78,640= $7,314,255
- Mod P000222013-08-23+$201,440= $7,515,695
- Mod P000232013-09-04+$153,094= $7,668,789
- Mod P000242013-09-04+$163,166= $7,831,955
- Mod P000252013-09-11+$231,656= $8,063,611
- Mod P000262013-09-11+$0= $8,063,611
- Mod P000272013-11-01+$100,575= $8,164,186
- Mod P000282013-11-01+$134,859= $8,299,046
- Mod P000292013-11-01+$51,116= $8,350,162
- Mod P000302013-11-01+$90,648= $8,440,810
- Mod P000312013-11-13+$70,504= $8,511,314
- Mod P000322013-11-13+$126,038= $8,637,352
- Mod P000332013-11-14+$134,454= $8,771,806
- Mod P000342013-12-13+$35,404= $8,807,210
- Mod P000352013-12-19+$16,311= $8,823,521
- Mod P000362013-12-19+$40,962= $8,864,483
- Mod P000372013-12-19+$42,714= $8,907,197
- Mod P000382013-12-23+$5,235= $8,912,432
- Mod P000392013-12-23+$26,505= $8,938,937
- Mod P000402013-12-23+$108,971= $9,047,908
- Mod P000412013-12-31+$4,768,311= $13,816,219
- Mod P000422014-02-28+$26,666= $13,842,885
- Mod P000432014-02-28+$28,660= $13,871,545
- Mod P000442014-04-24+$112,962= $13,984,507
- Mod P000452014-06-02+$63,513= $14,048,020
- Mod P000462014-06-02-$819,428= $13,228,592
- Mod P000472014-06-24+$155,740= $13,384,332
- Mod P000482016-03-15-$1,200,278= $12,184,054
| Transaction | Action date | This action (delta) | Running total | Description on this transaction |
|---|---|---|---|---|
| Base | 2011-03-09 | +$792,334 | $792,334 | CONSTRUCTION MANAGEMENT SERVICES FOR REPLACEMENT MEDICAL CENTER FACILITY, ECHCS |
| Mod SA001· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-07-11 | +$57,104 | $849,438 | CONSTRUCTION MANAGEMENT SERVICES FOR REPLACEMENT MEDICAL CENTER FACILITY, ECHCS |
| Mod SA002· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-07-29 | +$59,321 | $908,759 | CONSTRUCTION MANAGEMENT SERVICES FOR REPLACEMENT MEDICAL CENTER FACILITY, ECHCS |
| Mod SA003· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-08-26 | +$80,083 | $988,843 | CONSTRUCTION MANAGEMENT SERVICES FOR REPLACEMENT MEDICAL CENTER FACILITY, ECHCS |
| Mod SA004· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-12-06 | +$60,540 | $1,049,383 | CONSTRUCTION MANAGEMENT SERVICES FOR REPLACEMENT MEDICAL CENTER FACILITY, ECHCS, THREE COST ESTIMATORS |
| Mod 1· EXERCISE AN OPTION | 2012-01-02 | +$1,943,216 | $2,992,598 | CONSTRUCTION MANAGEMENT SERVICES FOR REPLACEMENT MEDICAL CENTER FACILITY, ECHCS OPTION PERIOD ONE |
| Mod SA005· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-04-24 | +$515,992 | $3,508,591 | CONSTRUCTION MANAGEMENT SERVICES FOR REPLACEMENT MEDICAL CENTER FACILITY, ECHCS, TWO COST ESTIMATES |
| Mod P00007· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-10-05 | +$52,586 | $3,561,176 | CONSTRUCTION MANAGEMENT SERVICES FOR REPLACEMENT MEDICAL CENTER FACILITY, ECHCS THE REMAINING BALANCE FROM SA-… |
| Mod P00008· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-10-31 | +$47,656 | $3,608,832 | CONSTRUCTION MANAGEMENT SERVICES FOR REPLACEMENT MEDICAL CENTER FACILITY, ECHCS OPTION PERIOD ONE. ADDED STRUC… |
| Mod P00010· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-11-20 | +$20,424 | $3,629,256 | CONSTRUCTION MANAGEMENT SERVICES FOR REPLACEMENT MEDICAL CENTER FACILITY, ADDITIONAL CIVIL INSPECTOR |
| Mod P00011· EXERCISE AN OPTION | 2012-12-31 | +$2,812,514 | $6,441,770 | CONSTRUCTION MANAGEMENT SERVICES FOR REPLACEMENT MEDICAL CENTER FACILITY, ECHCS OPTION PERIOD TWO |
| Mod P00009· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2013-01-18 | +$508,501 | $6,950,271 | CONSTRUCTION MANAGEMENT SERVICES FOR REPLACEMENT MEDICAL CENTER FACILITY, ECHCS OPTION PERIOD ONE. ADDITIONAL… |
| Mod A00002· OTHER ADMINISTRATIVE ACTION | 2013-01-30 | +$0 | $6,950,271 | CONSTRUCTION MANAGEMENT SERVICES FOR REPLACEMENT MEDICAL CENTER FACILITY, ECHCS ADDING 52.232-99. |
| Mod P00013· OTHER ADMINISTRATIVE ACTION | 2013-03-06 | +$0 | $6,950,271 | CONSTRUCTION MANAGEMENT SERVICES FOR REPLACEMENT MEDICAL CENTER FACILITY, ECHCS CORRECT FUNDING ACCOUNTING LIN… |
| Mod P00016· EXERCISE AN OPTION | 2013-05-15 | +$0 | $6,950,271 | CONSTRUCTION MANAGEMENT SERVICES FOR REPLACEMENT MEDICAL CENTER FACILITY, ECHCS OPTION PERIOD TWO |
| Mod P00014· EXERCISE AN OPTION | 2013-05-29 | +$117,541 | $7,067,812 | CONSTRUCTION MANAGEMENT SERVICES FOR REPLACEMENT MEDICAL CENTER FACILITY, ECHCS OPTION PERIOD TWO |
| Mod P00015· EXERCISE AN OPTION | 2013-05-29 | +$55,564 | $7,123,376 | CONSTRUCTION MANAGEMENT SERVICES FOR REPLACEMENT MEDICAL CENTER FACILITY, ECHCS OPTION PERIOD TWO |
| Mod P00017· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2013-06-05 | −$221,150 | $6,902,226 | CONSTRUCTION MANAGEMENT SERVICES FOR REPLACEMENT MEDICAL CENTER FACILITY, ECHCS |
| Mod P00012· OTHER ADMINISTRATIVE ACTION | 2013-06-06 | +$0 | $6,902,226 | CONSTRUCTION MANAGEMENT SERVICES FOR REPLACEMENT MEDICAL CENTER FACILITY, ECHCS ADMINISTRATIVE CHANGE OF THE M… |
| Mod P00018· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2013-07-26 | +$130,936 | $7,033,162 | CONSTRUCTION MANAGEMENT SERVICES FOR REPLACEMENT MEDICAL CENTER FACILITY, ECHCS ADMINISTRATIVE CHANGE OF THE M… |
| Mod P00019· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2013-07-26 | +$130,936 | $7,164,098 | CONSTRUCTION MANAGEMENT SERVICES FOR REPLACEMENT MEDICAL CENTER FACILITY, ECHCS ADMINISTRATIVE CHANGE OF THE M… |
| Mod P00020· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2013-07-31 | +$71,516 | $7,235,615 | CONSTRUCTION MANAGEMENT SERVICES FOR REPLACEMENT MEDICAL CENTER FACILITY, ADDITIONAL STRUCTUAL INSPECTOR |
| Mod P00021· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2013-08-23 | +$78,640 | $7,314,255 | CONSTRUCTION MANAGEMENT SERVICES FOR REPLACEMENT MEDICAL CENTER FACILITY, ECHCS SENIOR COST ESTIMATER FOR FINA… |
| Mod P00022· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2013-08-23 | +$201,440 | $7,515,695 | CONSTRUCTION MANAGEMENT SERVICES FOR REPLACEMENT MEDICAL CENTER FACILITY, ECHCS MECH ESTIMATORS (2). LAST MINU… |
| Mod P00023· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2013-09-04 | +$153,094 | $7,668,789 | CONSTRUCTION MANAGEMENT SERVICES FOR REPLACEMENT MEDICAL CENTER FACILITY, ECHCS SR. ELECTRICAL ESTIMATORS FOR… |
| Mod P00024· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2013-09-04 | +$163,166 | $7,831,955 | CONSTRUCTION MANAGEMENT SERVICES FOR REPLACEMENT MEDICAL CENTER FACILITY, ECHCS ADMINISTRATIVE EXTEND CURRENT… |
| Mod P00025· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2013-09-11 | +$231,656 | $8,063,611 | CONSTRUCTION MANAGEMENT SERVICES FOR REPLACEMENT MEDICAL CENTER FACILITY, ECHCS SR. ELECTRICAL ESTIMATORS FOR… |
| Mod P00026· OTHER ADMINISTRATIVE ACTION | 2013-09-11 | +$0 | $8,063,611 | CONSTRUCTION MANAGEMENT SERVICES FOR REPLACEMENT MEDICAL CENTER FACILITY, ECHCS ADMINISTRATIVE CHANGE TO CORRE… |
| Mod P00027· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2013-11-01 | +$100,575 | $8,164,186 | CONTRACTOR IS TO PROVIDE A COST COORDINATOR AND A SECOND SCHEDULER FOR THE PERIOD ENDING 12/31/2013. |
| Mod P00028· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2013-11-01 | +$134,859 | $8,299,046 | CONTRACTOR IS TO PROVIDE A SR. PROJECT DIRECTOR/FINAL PRICE MGR. FOR THE PERIOD ENDING 12/31/2013. |
| Mod P00029· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2013-11-01 | +$51,116 | $8,350,162 | CONTRACTOR IS TO PROVIDE A CURRENT SCHEDUL/EVMS COORDINATOR IN SUPPORT OF THE DEVELOPMENT OF A PROJECT CONTROL… |
| Mod P00030· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2013-11-01 | +$90,648 | $8,440,810 | CONTRACTOR IS TO PROVIDE FOUR PART TIME ADDITIONAL SR. ESTIMATORS FOR THE FINAL PRICE TEAM AS NEEDED. |
| Mod P00031· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2013-11-13 | +$70,504 | $8,511,314 | SA TO ADD ONE SENIOR COST ESTIMATOR. |
| Mod P00032· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2013-11-13 | +$126,038 | $8,637,352 | SA TO ADD A CHIEF ESTIMATOR, ARCHITECTURAL DD ESTIMATOR, AND A TIMBERLINE DATA ENTRY PERSON. |
| Mod P00033· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2013-11-14 | +$134,454 | $8,771,806 | SA TO BRING FIVE PEOPLE ON FOR THE ENHANCED BID PACKAGES. |
| Mod P00034· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2013-12-13 | +$35,404 | $8,807,210 | SA TO ADD ONE ARCHITECTURAL INSPECTOR AND ONE PLUMBING INSPECTOR |
| Mod P00035· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2013-12-19 | +$16,311 | $8,823,521 | TO ADD ONE SENIOR LEVEL ADMINISTRATOR |
| Mod P00036· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2013-12-19 | +$40,962 | $8,864,483 | TO CHANGE THE ROLE OF LOREE BRUNO FROM DOCUMENT CONTROL CLERK TP PCMS MANAGER. |
| Mod P00037· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2013-12-19 | +$42,714 | $8,907,197 | TO ADD: TWO EACH OF - ELECTRICAL, MECHANICAL, AND PLUMBING ENGINEERS. 2 SRCHITECTS, 1 CIVIL ENGINEER AND 1 DO… |
| Mod P00038· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2013-12-23 | +$5,235 | $8,912,432 | CONTRACTOR IS TO PROVIDE FOUR PART TIME ADDITIONAL SR. ESTIMATORS FOR THE FINAL PRICE TEAM AS NEEDED. |
| Mod P00039· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2013-12-23 | +$26,505 | $8,938,937 | CONTRACTOR IS TO PROVIDE FOUR PART TIME ADDITIONAL SR. ESTIMATORS FOR THE FINAL PRICE TEAM AS NEEDED. |
| Mod P00040· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2013-12-23 | +$108,971 | $9,047,908 | REIMBURSABLE EXPENSES; 07/26/13 - 12/31/13. |
| Mod P00041· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2013-12-31 | +$4,768,311 | $13,816,219 | CM SERVICES FOR SIX MONTHS IAW FAR 52.217-8; POP 01/01/14 - 06/30/14. |
| Mod P00042· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2014-02-28 | +$26,666 | $13,842,885 | PROVIDE A DETAILED QUANTITY TAKE OFF OF STR-2 "IN PROGRESS 75%". SERVICES INCLUDE A REPORT THAT IDENTIFIES QU… |
| Mod P00043· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2014-02-28 | +$28,660 | $13,871,545 | PROLOG IMPLEMENTATION. |
| Mod P00044· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2014-04-24 | +$112,962 | $13,984,507 | REIMBURSABLE EXPENSES FOR 6 MONTH EXTENSION - 01/01/14 - 06/30/14. |
| Mod P00045· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2014-06-02 | +$63,513 | $14,048,020 | PROLOG - PHASE III: CUSTOMIZATION, USER MANUAL&TRAINING, AND SUPPORT. |
| Mod P00046· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2014-06-02 | −$819,428 | $13,228,592 | DE-OBLIGATE REMAINING FUNDS FOR OPTION YEAR 2 (CALENDAR YEAR 2013). |
| Mod P00047· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2014-06-24 | +$155,740 | $13,384,332 | SA TO IMPLEMENT PROLOG PHASE 4 WHICH INCLUDES: DISCOVERY AND ANALYSIS; CONFIGURATION, DOCUMENTATION, AND DATA… |
| Mod P00048· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2016-03-15 | −$1,200,278 | $12,184,054 | DE-OBLIGATE REMAINING FUNDS FOR OPTION YEAR 2 (CALENDAR YEAR 2013). |
Related awards · 11
Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.
Other VA awards to the same recipient (UEI H2RGSKWXKHQ5)
| Award | Office · PSC / listing | Net obligations | FY |
|---|---|---|---|
| 36C10F20N0010 | OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F) · C214 · ARCHITECT AND ENGINEERING- GENERAL: MANAGEMENT ENGINEERING | $36,243 | FY2020 |
| VA101F16J2721 | OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F) · C214 · ARCHITECT AND ENGINEERING- GENERAL: MANAGEMENT ENGINEERING | $94,845 | FY2016 |
| VA101F15J0360 | OFFICE OF CONSTRUCTION & FACILITIES MANAGEMENT · R425 · SUPPORT- PROFESSIONAL: ENGINEERING/TECHNICAL | $16,292 | FY2015 |
| VA101F15J0361 | OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F) · C214 · ARCHITECT AND ENGINEERING- GENERAL: MANAGEMENT ENGINEERING | $28,079 | FY2015 |
| VA101F15F0169 | OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F) · R425 · SUPPORT- PROFESSIONAL: ENGINEERING/TECHNICAL | $423,939 | FY2015 |
| VA101F14A0006A | OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F) · C214 · ARCHITECT AND ENGINEERING- GENERAL: MANAGEMENT ENGINEERING | $0 | FY2015 |
Other recipients under R499 from OFFICE OF CONSTRUCTION & FACILITIES MANAGEMENT (most recent first)
| Award | Recipient | Office | Net obligations | FY |
|---|---|---|---|---|
| VA101F15J0393 | NATIONAL INSTITUTE OF BUILDING SCIENCES | OFFICE OF CONSTRUCTION & FACILITIES MANAGEMENT | $74,890 | FY2015 |
| VA101F15F0145 | ALARES LLC | OFFICE OF CONSTRUCTION & FACILITIES MANAGEMENT | $86,915 | FY2015 |
| VA101F15F0146 | DAV ENERGY SOLUTIONS, INC. | OFFICE OF CONSTRUCTION & FACILITIES MANAGEMENT | $82,752 | FY2015 |
| VA101F15F0147 | DAV ENERGY SOLUTIONS, INC. | OFFICE OF CONSTRUCTION & FACILITIES MANAGEMENT | $49,696 | FY2015 |
| VA101F14F0319 | DAV ENERGY SOLUTIONS, INC. | OFFICE OF CONSTRUCTION & FACILITIES MANAGEMENT | $159,633 | FY2014 |