CONSTRUCTION MANAGEMENT SERVICES NATIONWIDE. DEOBLIGATION OF EXCESS FUNDS.
Base award description: CONSTRUCTION MANAGEMENT SERVICES NATIONWIDE
Modification chain · 30 transactions
Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.
- Base2010-03-03+$0= $0
- Mod SATO082010-03-18+$321,113= $321,113
- Mod SATO092010-05-03+$334,603= $655,716
- Mod SATO072010-06-15+$984,521= $1,640,237
- Mod SATO102010-11-03+$252,071= $1,892,308
- Mod SATO012010-12-17+$30,000= $1,922,308
- Mod SATO022010-12-17+$8,346= $1,930,654
- Mod SATO042010-12-17+$3,151= $1,933,805
- Mod SATO052010-12-17+$100,000= $2,033,805
- Mod SATO062010-12-17+$160,613= $2,194,418
- Mod SATO112011-04-12+$56,655= $2,251,073
- Mod SATO132012-01-05+$99,346= $2,350,419
- Mod SATO142012-01-05+$99,911= $2,450,330
- Mod SATO152012-01-05+$99,704= $2,550,034
- Mod SATO162012-05-23+$99,296= $2,649,330
- Mod SATO172012-05-23+$0= $2,649,330
- Mod SATO182012-06-08+$99,936= $2,749,266
- Mod SATO192012-11-14+$98,556= $2,847,822
- Mod SATO202012-11-14+$99,486= $2,947,308
- Mod SATO212013-01-04+$0= $2,947,308
- Mod P000012013-03-13+$99,683= $3,046,991
- Mod P000022013-03-13+$99,696= $3,146,687
- Mod P000032013-03-13+$99,684= $3,246,371
- Mod P000042013-05-01+$0= $3,246,371
- Mod P000052013-09-17+$94,446= $3,340,817
- Mod P000062013-09-17+$95,767= $3,436,584
- Mod P000072013-09-17+$92,769= $3,529,353
- Mod P000082014-06-27-$16,653= $3,512,700
- Mod P000092014-07-08+$0= $3,512,700
- Mod P000102018-06-22-$23,081= $3,489,619
| Transaction | Action date | This action (delta) | Running total | Description on this transaction |
|---|---|---|---|---|
| Base | 2010-03-03 | +$0 | $0 | CONSTRUCTION MANAGEMENT SERVICES NATIONWIDE |
| Mod SATO08· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2010-03-18 | +$321,113 | $321,113 | CONSTRUCTION MANAGEMENT SERVICES LAS VEGAS, ARCHITECT, MECHANICAL AND ELECTRICAL ENGINEERS |
| Mod SATO09· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2010-05-03 | +$334,603 | $655,716 | CONSTRUCTION MANAGEMENT OPTIONED SERVICES LAS VEGAS, |
| Mod SATO07· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2010-06-15 | +$984,521 | $1,640,237 | CONSTRUCTION MANAGEMENT SERVICES LAS VEGAS, |
| Mod SATO10· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2010-11-03 | +$252,071 | $1,892,308 | CONSTRUCTION MANAGEMENT OPTIONED SERVICES LAS VEGAS, |
| Mod SATO01· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2010-12-17 | +$30,000 | $1,922,308 | ADDITIONAL ESTIMATING REQUIRED FOR THE PROJECT NOT IDENTIFIED IN THE ORIGINAL CONTRACT. |
| Mod SATO02· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2010-12-17 | +$8,346 | $1,930,654 | ADDITIONAL ESTIMATING REQUIRED FOR THE PROJECT NOT IDENTIFIED IN THE ORIGINAL CONTRACT. |
| Mod SATO04· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2010-12-17 | +$3,151 | $1,933,805 | THE MODIFICATION MODIFIES AND FINALIZES MODIFICATION #3 ISSUED SEPTEMBER 25, 2007 IN THE AMOUNT OF $60,000.00 |
| Mod SATO05· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2010-12-17 | +$100,000 | $2,033,805 | A COMPLETE ITEMIZED COST BREAKDOWN IS NECESSARY TO ESTABLISH A COST BASELINE FOR THE PHASE IV PROJECT. |
| Mod SATO06· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2010-12-17 | +$160,613 | $2,194,418 | A COMPLETE ITEMIZED COST BREAKDOWN IS NECESSARY TO ESTABLISH A COST BASELINE FOR THE PHASE IV PROJECT. |
| Mod SATO11· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-04-12 | +$56,655 | $2,251,073 | TO PROVIDE FUNDS FOR ADDITIONAL HOURS OF WORK INCLUDING OVERTIME. |
| Mod SATO13· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-01-05 | +$99,346 | $2,350,419 | CONSTRUCTION MANAGEMENT OPTIONED SERVICES LAS VEGAS,NV |
| Mod SATO14· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-01-05 | +$99,911 | $2,450,330 | CONSTRUCTION MANAGEMENT OPTIONED SERVICES LAS VEGAS,NV |
| Mod SATO15· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-01-05 | +$99,704 | $2,550,034 | CONSTRUCTION MANAGEMENT OPTIONED SERVICES LAS VEGAS,NV |
| Mod SATO16· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-05-23 | +$99,296 | $2,649,330 | CONSTRUCTION MANAGEMENT OPTIONED SERVICES VAMC LAS VEGAS,NV |
| Mod SATO17· OTHER ADMINISTRATIVE ACTION | 2012-05-23 | +$0 | $2,649,330 | CONSTRUCTION MANAGEMENT OPTIONED SERVICES LAS VEGAS, |
| Mod SATO18· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-06-08 | +$99,936 | $2,749,266 | CONSTRUCTION MANAGEMENT OPTIONED SERVICES LAS VEGAS,NV |
| Mod SATO19· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-11-14 | +$98,556 | $2,847,822 | CRITICAL FUNCTION: EXTENSION OF CONSTRUCTION MANAGEMENT OPTIONED SERVICES LAS VEGAS,NV |
| Mod SATO20· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-11-14 | +$99,486 | $2,947,308 | CRITICAL FUNCTION: EXTEND CONSTRUCTION MANAGEMENT OPTIONED SERVICES LAS VEGAS,NV |
| Mod SATO21· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2013-01-04 | +$0 | $2,947,308 | CRITICAL FUNCTION: REFLECT NOVATION EXECUTED APRIL 13, 2012. |
| Mod P00001· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2013-03-13 | +$99,683 | $3,046,991 | CRITICAL FUNCTION: EXTEND THE PERIOD OF PERFORMANCE FOR THE MECHANICAL CONSTRUCTION MANAGER FROM 5/11/2013 TO… |
| Mod P00002· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2013-03-13 | +$99,696 | $3,146,687 | CRITICAL FUNCTION: EXTEND THE PERIOD OF PERFORMANCE OF THE ELECTRICAL CONSTRUCTION MANAGER FROM 4/22/2013 TO 9… |
| Mod P00003· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2013-03-13 | +$99,684 | $3,246,371 | CRITICAL FUNCTION: EXTEND THE PERIOD OF PERFORMANCE OF THE ARCHITECTURAL CONSTRUCTION MANAGER FROM 3/18/2013 T… |
| Mod P00004· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2013-05-01 | +$0 | $3,246,371 | CRITICAL FUNCTION: EXTEND PERIOD OF PERFORMANCE TO 5/30/2013 TO PROVIDE OVERTIME FOR THE VAMC LAS VEGAS MAJOR… |
| Mod P00005· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2013-09-17 | +$94,446 | $3,340,817 | CRITICAL FUNCTION: EXTEND THE PERIOD OF PERFORMANCE FOR THE MECHANICAL CONSTRUCTION MANAGER FROM 11/13/13 TO 4… |
| Mod P00006· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2013-09-17 | +$95,767 | $3,436,584 | CRITICAL FUNCTION: EXTEND THE PERIOD OF PERFORMANCE OF THE ARCHITECTURAL CONSTRUCTION MANAGER FROM 9/17/2013 T… |
| Mod P00007· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2013-09-17 | +$92,769 | $3,529,353 | CRITICAL FUNCTION: EXTEND THE PERIOD OF PERFORMANCE OF THE ELECTRICAL CONSTRUCTION MANAGER FROM 9/23/2013 TO 2… |
| Mod P00008· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2014-06-27 | −$16,653 | $3,512,700 | CRITICAL FUNCTION: DECREASE THE ARCHITECTURAL CM HOURS AS A RESULT OF AN INJURY IN 2012. |
| Mod P00009· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2014-07-08 | +$0 | $3,512,700 | CRITICAL FUNCTION: EXTEND PERIOD OF PERFORMANCE TO 5/30/2015 TO PROVIDE OVERTIME FOR THE VAMC LAS VEGAS MAJOR… |
| Mod P00010· OTHER ADMINISTRATIVE ACTION | 2018-06-22 | −$23,081 | $3,489,619 | CONSTRUCTION MANAGEMENT SERVICES NATIONWIDE. DEOBLIGATION OF EXCESS FUNDS. |
Related awards · 11
Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.
Other VA awards to the same recipient (UEI NMBCAG1JBKL7)
| Award | Office · PSC / listing | Net obligations | FY |
|---|---|---|---|
| 36C10F18N3340 | OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F) · AD66 · R&D- DEFENSE OTHER: CONSTRUCTION (MANAGEMENT/SUPPORT) | $1,000 | FY2018 |
| VA101F17J2866 | OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F) · C214 · ARCHITECT AND ENGINEERING- GENERAL: MANAGEMENT ENGINEERING | $283,177 | FY2017 |
| VA101F16J2599 | OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F) · C214 · ARCHITECT AND ENGINEERING- GENERAL: MANAGEMENT ENGINEERING | $138,580 | FY2016 |
| VA101F15J0243 | OFFICE OF CONSTRUCTION & FACILITIES MANAGEMENT · C214 · ARCHITECT AND ENGINEERING- GENERAL: MANAGEMENT ENGINEERING | $326,286 | FY2015 |
| VA101F15J0093 | OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F) · C214 · ARCHITECT AND ENGINEERING- GENERAL: MANAGEMENT ENGINEERING | $2,621,114 | FY2015 |
| VA101F15J0091 | OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F) · C214 · ARCHITECT AND ENGINEERING- GENERAL: MANAGEMENT ENGINEERING | $1,535,820 | FY2015 |
Other recipients under R425 from OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F) (most recent first)
| Award | Recipient | Office | Net obligations | FY |
|---|---|---|---|---|
| 36C10F26F0009 | VALI COOPER INTERNATIONAL LLC | OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F) | $658,396 | FY2026 |
| 36C10F26N0018 | SA3 CONSTRUCTION MANAGEMENT LLC | OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F) | $473,328 | FY2026 |
| 36C10F26N0017 | SSPC LLC | OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F) | $1,915,692 | FY2026 |
| 36C10F25C0009 | GOLDEN WOLF, LLC | OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F) | $5,332,064 | FY2025 |
| 36C10F25C0010 | GUIDON DESIGN INC | OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F) | $5,964,155 | FY2025 |
Cite as: Glassbox VA record view · VA contract (USAspending / FPDS) · CONT_AWD_VACFM050783_3600_VA101CFMBP0007_3600 · retrieved 2026-09-26.