THE CONTRACTOR SHALL PLACEN AN ADDITIONAL 2" OF GENERAL FILL COVER OVER THE CRYPT FIELD. DELETED WORK: 745 TONS OF PEA STONE OVER THE CRYPT FIELD. CREDIT TO GOVERNMENT: ELEMINATION OF PEDESTAL SUPPORT BOXES AT FORT CUSTER NATIONAL CEMETERY.
Base award description: CONTRACTOR SHALL DEMO AND REMOVE EXISTING STRUCTURES AND PAVEMENTS, GRADING, GENERAL CONSTRUCTION, VEHICULAR AND PEDESTRIAN PAVING, DRAINAGE, LANDSCAPE PLANTING AND TURF, SITE FURNISHING, IRRIGATION AND CERTAIN OTHER ITEMS AS INDICATED IN THE SPECIFICATIOSN AND DRAWINGS. CONTRACTOR SHALL ALSO INSTALL CRYPTS AND CRYPT LIDS. CONTRACTOR SHALL MANUFACTURE AND DELIVER TO THE SITE 3,101 DOUBLE-DEPTH PRE-CAST CONCRETE CRYPTS, PLUS TWENTY EXTRA CRYPT LIDS, AND THREE CRYPT LID LIFTING DEVICES. CONTRACTOR SHALL MANUFACTURE AND DELIVER 3,101 REMOVABLE FLAT MARKER SUPPORTS TO THE SITE PLUS TWENTY EXTRA SUPPORTS. CONTRACTOR SHALL PROVIDE ALL LABOR, TOOLS, MATERIALS, AND EQUIPMENT NECESSARY TO ENCLOSE THE OPEN SIDED MAINTENANCE STRUCTURE IN THE MAINTENANCE COMPLEX AT FORT CUSTER NATIONAL CEMETERY.
Modification chain · 8 transactions
Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.
- Base2011-10-18+$2,853,000= $2,853,000
- Mod SA0012011-11-03+$0= $2,853,000
- Mod SA0022012-09-12+$1,430= $2,854,430
- Mod SA0032012-09-12+$0= $2,854,430
- Mod SA0042012-09-12+$16,980= $2,871,410
- Mod SA0052013-01-03+$74,814= $2,946,224
- Mod SA0062013-01-04+$15,170= $2,961,394
- Mod SA72013-01-15-$114,613= $2,846,780
| Transaction | Action date | This action (delta) | Running total | Description on this transaction |
|---|---|---|---|---|
| Base | 2011-10-18 | +$2,853,000 | $2,853,000 | CONTRACTOR SHALL DEMO AND REMOVE EXISTING STRUCTURES AND PAVEMENTS, GRADING, GENERAL CONSTRUCTION, VEHICULAR A… |
| Mod SA001· OTHER ADMINISTRATIVE ACTION | 2011-11-03 | +$0 | $2,853,000 | TO CHANGE THE CONTRACT DURATION OF THE PROJECT TO 365 CALENDAR DAYS AT FORT CUSTER NATIONAL CEMETERY. |
| Mod SA002· OTHER ADMINISTRATIVE ACTION | 2012-09-12 | +$1,430 | $2,854,430 | CONTRACTOR SHALL INSTALL APPROX. 12' X 85' LONG SOD ALONG THE NEW SIDEWALK AT THE NORTH EAST SIDE OF CORTEGE R… |
| Mod SA003· OTHER ADMINISTRATIVE ACTION | 2012-09-12 | +$0 | $2,854,430 | TO CEASE BACKFILL FOR CRYPT FIELD 4A AT FORT CUSTER NATIONAL CEMETERY. |
| Mod SA004· OTHER ADMINISTRATIVE ACTION | 2012-09-12 | +$16,980 | $2,871,410 | THE CONTRACTOR SHALL SUPPLY THE FOLLOWING AT FORT CUSTER NATIONAL CEMETERY: A. SUPPLY AND INSTALL EXPANSION JO… |
| Mod SA005· OTHER ADMINISTRATIVE ACTION | 2013-01-03 | +$74,814 | $2,946,224 | CONTRACTOR SHALL REMOVE THE EXISTING PAVEMENT UNDERNEATH THE MAINTENANCE STORAGE BUILDING AND CONSTRUCT A NEW… |
| Mod SA006· OTHER ADMINISTRATIVE ACTION | 2013-01-04 | +$15,170 | $2,961,394 | CONTRACTOR SHALL RELOCATE THE LOW AREA AT CORTEGE LANE AND RAISE THE GRADES AT THE MANHOLE AND WATER STATION A… |
| Mod SA7· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2013-01-15 | −$114,613 | $2,846,780 | THE CONTRACTOR SHALL PLACEN AN ADDITIONAL 2" OF GENERAL FILL COVER OVER THE CRYPT FIELD. DELETED WORK: 745 TO… |
Related awards · 7
Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.
Other VA awards to the same recipient (UEI KNHQKE9VHTP5)
| Award | Office · PSC / listing | Net obligations | FY |
|---|---|---|---|
| VA25112C0074 | 553-DETROIT · Z1DA · MAINTENANCE OF HOSPITALS AND INFIRMARIES | $2,572,132 | FY2012 |
| VA25512C0190 | 255-NETWORK CONTRACT OFFICE 15 · T006 · PHOTO/MAP/PRINT/PUBLICATION- FILM/VIDEO TAPE PRODUCTION | $164,185 | FY2012 |
Other recipients under Y1PZ from NATIONAL CEMETERY ADMINISTRATION (most recent first)
| Award | Recipient | Office | Net obligations | FY |
|---|---|---|---|---|
| VA786A15C0026 | DECATUR CONSTRUCTION, INC | NATIONAL CEMETERY ADMINISTRATION | $654,877 | FY2015 |
| VA786A15C0018 | WSP USA ENVIRONMENT & INFRASTRUCTURE INC. | NATIONAL CEMETERY ADMINISTRATION | $54,784 | FY2015 |
| VA78615P1059 | H L SERVICES INC | NATIONAL CEMETERY ADMINISTRATION | $4,950 | FY2015 |
| VA786A15C0010 | C & C CONTRACTORS LLC | NATIONAL CEMETERY ADMINISTRATION | $5,306,326 | FY2015 |
| VA786A14C0024 | G&C FAB-CON, LLC | NATIONAL CEMETERY ADMINISTRATION | $0 | FY2014 |