Award recordCONTRACT

BLUEFORGE, LLC

PIID VA786AC0398· NCA· NATIONAL CEMETERY ADMINISTRATION· Y119 · CONSTRUCT/OTHER ADMIN & SVCS BLDGS· FY2011· $4,420,467 net obligations· UEI LKKDLGFN9H13· FL

Description

COST FOR TRAILERS; DESCREASE FOR PLANTS MATERIAL AT BAY PINES NATIONAL CEMETERY.

Base award description: REMOVE AND REPLACE ADMIN/PIC BUILDING AT BAY PINES NATIONAL CEMETERY

First action · last action
2011-04-29 · 2013-06-13
Transactions
21
First transaction's obligation
$3,753,000
Base + all options value (sum of deltas)
$4,420,467
Extent competed
FULL AND OPEN COMPETITION AFTER EXCLUSION OF SOURCES
Other than full & open authority
—
Set-aside
SERVICE DISABLED VETERAN OWNED SMALL BUSINESS SET-ASIDE
Offers received
8
SDVOSB flag on record
Yes (self-representation)
NAICS
236220 · COMMERCIAL AND INSTITUTIONAL BUILDING CONSTRUCTION

Modification chain · 21 transactions

Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.

$4,420,467$0Base award · 2011-04-29 · this action $3,753,000 · running total $3,753,000Modification SA1 · 2011-08-30 · this action $45,296 · running total $3,798,296Modification SA2 · 2011-11-03 · this action $20,309 · running total $3,818,605Modification CO1 · 2011-12-29 · this action $20,000 · running total $3,838,605Modification SA3 · 2012-01-18 · this action $36,550 · running total $3,875,155Modification SA4 · 2012-01-26 · this action $17,946 · running total $3,893,101Modification SA5 · 2012-02-10 · this action $68,766 · running total $3,961,867Modification SA6 · 2012-02-27 · this action $22,540 · running total $3,984,407Modification SA7 · 2012-04-13 · this action $8,903 · running total $3,993,310Modification SA8 · 2012-05-02 · this action $78,263 · running total $4,071,573Modification SA9 · 2012-06-15 · this action $9,077 · running total $4,080,650Modification SA10 · 2012-09-04 · this action $68,242 · running total $4,148,892Modification SA11 · 2012-09-04 · this action $17,475 · running total $4,166,367Modification SA12 · 2012-10-05 · this action $64,999 · running total $4,231,366Modification SA13 · 2012-10-31 · this action $46,493 · running total $4,277,859Modification SA14 · 2012-10-31 · this action $52,560 · running total $4,330,420Modification SA15 · 2012-11-21 · this action $0 · running total $4,330,420Modification SA16 · 2012-12-10 · this action $12,121 · running total $4,342,541Modification SA17 · 2013-01-15 · this action $19,296 · running total $4,361,837Modification SA18 · 2013-04-03 · this action $49,033 · running total $4,410,869Modification SA19 · 2013-06-13 · this action $9,597 · running total $4,420,467
  • Base2011-04-29+$3,753,000= $3,753,000
  • Mod SA12011-08-30+$45,296= $3,798,296
  • Mod SA22011-11-03+$20,309= $3,818,605
  • Mod CO12011-12-29+$20,000= $3,838,605
  • Mod SA32012-01-18+$36,550= $3,875,155
  • Mod SA42012-01-26+$17,946= $3,893,101
  • Mod SA52012-02-10+$68,766= $3,961,867
  • Mod SA62012-02-27+$22,540= $3,984,407
  • Mod SA72012-04-13+$8,903= $3,993,310
  • Mod SA82012-05-02+$78,263= $4,071,573
  • Mod SA92012-06-15+$9,077= $4,080,650
  • Mod SA102012-09-04+$68,242= $4,148,892
  • Mod SA112012-09-04+$17,475= $4,166,367
  • Mod SA122012-10-05+$64,999= $4,231,366
  • Mod SA132012-10-31+$46,493= $4,277,859
  • Mod SA142012-10-31+$52,560= $4,330,420
  • Mod SA152012-11-21+$0= $4,330,420
  • Mod SA162012-12-10+$12,121= $4,342,541
  • Mod SA172013-01-15+$19,296= $4,361,837
  • Mod SA182013-04-03+$49,033= $4,410,869
  • Mod SA192013-06-13+$9,597= $4,420,467
TransactionAction dateThis action (delta)Running totalDescription on this transaction
Base2011-04-29+$3,753,000$3,753,000REMOVE AND REPLACE ADMIN/PIC BUILDING AT BAY PINES NATIONAL CEMETERY
Mod SA1· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-08-30+$45,296$3,798,296REMOVE AND REPLACE ADMIN/PIC BUILDING AT BAY PINES NATIONAL CEMETERY
Mod SA2· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-11-03+$20,309$3,818,605REMOVE AND REPLACE ADMIN/PIC BUILDING AT BAY PINES NATIONAL CEMETERY
Mod CO1· CHANGE ORDER2011-12-29+$20,000$3,838,605CHANGE ORDER FOR EMERGENCY REPAIRS OF AN ELECTRICAL LINE THAT WAS CUT BY THE CONTRACTOR AT BAY PINES NATIONAL…
Mod SA3· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2012-01-18+$36,550$3,875,155REMOVE AND REPLACE ADMIN/PIC BUILDING AT BAY PINES NATIONAL CEMETERY
Mod SA4· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2012-01-26+$17,946$3,893,101REMOVE AND REPLACE ADMIN/PIC BUILDING AT BAY PINES NATIONAL CEMETERY
Mod SA5· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2012-02-10+$68,766$3,961,867REMOVE AND REPLACE ADMIN/PIC BUILDING AT BAY PINES NATIONAL CEMETERY
Mod SA6· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2012-02-27+$22,540$3,984,407REMOVE AND REPLACE ADMIN/PIC BUILDING AT BAY PINES NATIONAL CEMETERY
Mod SA7· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2012-04-13+$8,903$3,993,310REMOVE AND REPLACE ADMIN/PIC BUILDING AT BAY PINES NATIONAL CEMETERY
Mod SA8· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2012-05-02+$78,263$4,071,573REMOVE AND REPLACE ADMIN/PIC BUILDING AT BAY PINES NATIONAL CEMETERY
Mod SA9· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2012-06-15+$9,077$4,080,650INSTALL ADDITIONAL DRAINAGE STONE AROUND INLET DW-100 AND ADDITIONAL DRAINAGE AT TEH ENTRY ROAD TO BAY PINES N…
Mod SA10· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2012-09-04+$68,242$4,148,892INSTALL WINDOW TREATMENT, ADD DOOR, AND RELOCATEE THE OUT-FALL OF THE CEMETERY'S STORM-WATER LINE AT BAY PINES…
Mod SA11· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2012-09-04+$17,475$4,166,367INSTALL THE FRAMING REVISION, REVISE THE CASEWORK, PROVIDE PLATFORM FOR AC UNITS, ELECTRICAL FEED FROM TRANSFO…
Mod SA12· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2012-10-05+$64,999$4,231,366INSTALL THE FRAMING REVISION, REVISE THE CASEWORK, PROVIDE PLATFORM FOR AC UNITS, ELECTRICAL FEED FROM TRANSFO…
Mod SA13· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2012-10-31+$46,493$4,277,859CONTRACTOR SHALL PROVIDE THE FOLLOWING AT BAY PINES NATIONAL CEMETERY: INSTALL ADDITIONAL SECURITY EQUIPMENT;…
Mod SA14· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2012-10-31+$52,560$4,330,420CONTRACTOR SHALL PROVIDE THE FOLLOWING CHANGES AT AT BAY PINES NATIONAL CEMETERY: CHANGE FRAMING AT PIC WINDO…
Mod SA15· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2012-11-21+$0$4,330,420A TIME EXTENSION OF 10 CALENDAR DAYS IS PROVIDED FOR THE CURRENT CONTRACT AT BAY PINES NATIONAL CEMETERY.
Mod SA16· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2012-12-10+$12,121$4,342,541CONTRACTOR SHALL PROVIDE THE FOLLOWING AT BAY PINES NATIONAL CEMETERY: ADD STEEL SUPPORT; PROVIDE ELECTRICAL…
Mod SA17· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2013-01-15+$19,296$4,361,837CONTRACTOR SHALL ADD ROOF/WALL AIR BARRIER TRANSITIONS, LOW ROOF PARAPET WALL ANCHORING, AND ADD BLUESKIN ABOV…
Mod SA18· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2013-04-03+$49,033$4,410,869CONTRACTOR SHALL PROVIDE THE FOLLOWING AT BAY PINES NATIONAL CEMETERY: INSTALL LIGHT GAUGE SUPPORT&GWB SOFFIT…
Mod SA19· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2013-06-13+$9,597$4,420,467COST FOR TRAILERS; DESCREASE FOR PLANTS MATERIAL AT BAY PINES NATIONAL CEMETERY.

Related awards · 11

Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.

Other VA awards to the same recipient (UEI LKKDLGFN9H13)

AwardOffice · PSC / listingNet obligationsFY
36C24719D0019247-NETWORK CONTRACT OFFICE 7 (36C247) · Y1DA · CONSTRUCTION OF HOSPITALS AND INFIRMARIES$0FY2019
36C24719N0532247-NETWORK CONTRACT OFFICE 7 (36C247) · Y1DA · CONSTRUCTION OF HOSPITALS AND INFIRMARIES$1,000FY2019
36C24818N4730248-NETWORK CONTRACT OFFICE 8 (36C248) · Y1DA · CONSTRUCTION OF HOSPITALS AND INFIRMARIES$0FY2018
36C24818D0091248-NETWORK CONTRACT OFFICE 8 (36C248) · Y1DA · CONSTRUCTION OF HOSPITALS AND INFIRMARIES$0FY2018
VA24815J5028248-NETWORK CONTRACT OFFICE 8 (36C248) · Z2DB · REPAIR OR ALTERATION OF LABORATORIES AND CLINICS$928,315FY2015
VA24814J4583248-NETWORK CONTRACT OFFICE 8 (36C248) · Y1LZ · CONSTRUCTION OF PARKING FACILITIES$9,111,427FY2014

Other recipients under Y119 from NATIONAL CEMETERY ADMINISTRATION (most recent first)

AwardRecipientOfficeNet obligationsFY
VA786AC0441ATHENA CONSTRUCTION GROUP, INC.NATIONAL CEMETERY ADMINISTRATION$10,565FY2011
VA786AC0443FACILITY DEFENSE CONSULTANTS INCNATIONAL CEMETERY ADMINISTRATION$2,837,836FY2011
VA786AC0418SIRIUS FEDERAL LLCNATIONAL CEMETERY ADMINISTRATION$52,800FY2011
VA786AC0348DESECO CORPNATIONAL CEMETERY ADMINISTRATION$199,052FY2010
VA786ARA0215MURPHY'S HOME IMPROVEMENTS, INC.NATIONAL CEMETERY ADMINISTRATION$49,544FY2010

Cite as: Glassbox VA record view · VA contract (USAspending / FPDS) · CONT_AWD_VA786AC0398_3600_-NONE-_-NONE- · retrieved 2026-09-26.