CEMETERY SITE AND HISTORIC BUILDING IMPROVEMENT PROJECT AT MARION NC
Modification chain · 8 transactions
Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.
- Base2009-07-31+$3,325,007= $3,325,007
- Mod 12009-11-16+$6,298= $3,331,305
- Mod SA22010-01-29+$5,252= $3,336,557
- Mod SA32010-03-03+$17,614= $3,354,171
- Mod SA42010-04-20+$14,574= $3,368,745
- Mod SA52010-05-14+$79,618= $3,448,363
- Mod SA62010-08-02+$10,321= $3,458,684
- Mod SA72010-08-27+$21,415= $3,480,099
| Transaction | Action date | This action (delta) | Running total | Description on this transaction |
|---|---|---|---|---|
| Base | 2009-07-31 | +$3,325,007 | $3,325,007 | CEMETERY SITE AND HISTORIC BUILDING IMPROVEMENT PROJECT AT MARION NC |
| Mod 1· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2009-11-16 | +$6,298 | $3,331,305 | CEMETERY SITE AND HISTORIC BUILDING IMPROVEMENT PROJECT AT MARION NC |
| Mod SA2· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2010-01-29 | +$5,252 | $3,336,557 | CEMETERY SITE AND HISTORIC BUILDING IMPROVEMENT PROJECT AT MARION NC |
| Mod SA3· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2010-03-03 | +$17,614 | $3,354,171 | CEMETERY SITE AND HISTORIC BUILDING IMPROVEMENT PROJECT AT MARION NC |
| Mod SA4· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2010-04-20 | +$14,574 | $3,368,745 | CEMETERY SITE AND HISTORIC BUILDING IMPROVEMENT PROJECT AT MARION NC |
| Mod SA5· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2010-05-14 | +$79,618 | $3,448,363 | CEMETERY SITE AND HISTORIC BUILDING IMPROVEMENT PROJECT AT MARION NC |
| Mod SA6· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2010-08-02 | +$10,321 | $3,458,684 | CEMETERY SITE AND HISTORIC BUILDING IMPROVEMENT PROJECT AT MARION NC |
| Mod SA7· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2010-08-27 | +$21,415 | $3,480,099 | CEMETERY SITE AND HISTORIC BUILDING IMPROVEMENT PROJECT AT MARION NC |
Related awards · 11
Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.
Other VA awards to the same recipient (UEI GFUMJUGHUSZ7)
| Award | Office · PSC / listing | Net obligations | FY |
|---|---|---|---|
| 36C24423N1031 | 244-NETWORK CONTRACT OFFICE 4 (36C244) · H399 · INSPECTION- MISCELLANEOUS | $29,000 | FY2023 |
| 36C24423N0970 | 244-NETWORK CONTRACT OFFICE 4 (36C244) · H399 · INSPECTION- MISCELLANEOUS | $3,878 | FY2023 |
| 36C24423N0246 | 244-NETWORK CONTRACT OFFICE 4 (36C244) · H399 · INSPECTION- MISCELLANEOUS | $5,029 | FY2023 |
| 36C24423N0104 | 244-NETWORK CONTRACT OFFICE 4 (36C244) · H399 · INSPECTION- MISCELLANEOUS | $3,878 | FY2023 |
| 36C24423N0085 | 244-NETWORK CONTRACT OFFICE 4 (36C244) · H399 · INSPECTION- MISCELLANEOUS | $10,766 | FY2023 |
| 36C24522F0543 | 245-NETWORK CONTRACT OFFICE 5 (36C245) · F115 · ENVIRONMENTAL SYSTEMS PROTECTION- ENVIRONMENTAL CONSULTING AND LEGAL SUPPORT | $4,691 | FY2022 |
Other recipients under Y299 from NATIONAL CEMETERY ADMINISTRATION (most recent first)
| Award | Recipient | Office | Net obligations | FY |
|---|---|---|---|---|
| VA786AC0454 | AMERICAN ARTISANS GROUP LLC | NATIONAL CEMETERY ADMINISTRATION | $212,000 | FY2011 |
| VA786AC0457 | MARE SOLUTIONS INC | NATIONAL CEMETERY ADMINISTRATION | $370,000 | FY2011 |
| VA786AC0455 | DANIELS BUILDING CO INC | NATIONAL CEMETERY ADMINISTRATION | $649,540 | FY2011 |
| VA786AC0440 | PARADIGM CONSTRUCTION, L.L.C | NATIONAL CEMETERY ADMINISTRATION | $3,544,801 | FY2011 |
| VA786AC0453 | 3 D CONTRACTING INC. | NATIONAL CEMETERY ADMINISTRATION | $23,870 | FY2011 |