Description
CONTRACTOR TO PROVIDE TOTAL CEMETERY MAINTENANCE AS REQUIRED IN ACCORDANCE WITH STATEMENT OF WORK AT MARIETTA NC. P00032 DATA CLEANSE ACTION
Base award description: CONTRACTOR TO PROVIDE TOTAL CEMETERY MAINTENANCE AS REQUIRED IN ACCORDANCE WITH STATEMENT OF WORK AT MARIETTA NC. IGF::CL::IGF
Modification chain · 36 transactions
Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.
- Base2014-03-31+$217,607= $217,607
- Mod P000012014-04-30+$0= $217,607
- Mod P000022014-06-25+$128,020= $345,627
- Mod P000032014-10-01+$91,094= $436,721
- Mod P000042015-01-29+$370,609= $807,330
- Mod P000052015-02-12-$128,021= $679,309
- Mod P000062015-03-30+$7,245= $686,554
- Mod P000072015-05-20+$90,000= $776,554
- Mod P000082015-07-16+$500= $777,054
- Mod P000092015-08-13+$15,177= $792,231
- Mod P000102015-10-14+$67,780= $860,011
- Mod P000112016-01-27+$64,262= $924,273
- Mod P000122016-03-28+$212,476= $1,136,749
- Mod P000132016-06-20+$90,000= $1,226,749
- Mod P000142016-08-29+$9,401= $1,236,150
- Mod P000152016-09-26+$7,935= $1,244,085
- Mod P000172016-11-08+$28,802= $1,272,888
- Mod P000182016-12-09+$331,228= $1,604,116
- Mod P000192017-04-28+$90,000= $1,694,116
- Mod P000202017-10-04+$63,344= $1,757,460
- Mod P000212017-10-13+$0= $1,757,460
- Mod P000222018-01-07+$48,440= $1,805,900
- Mod P000232018-03-13+$63,344= $1,869,244
- Mod P000242018-04-11+$40,986= $1,910,230
- Mod P000252018-05-01+$156,499= $2,066,729
- Mod P000262018-05-23+$90,000= $2,156,729
- Mod P000272018-05-29+$12,600= $2,169,329
- Mod P000282018-10-01+$101,720= $2,271,049
- Mod P000292018-10-21-$2,865= $2,268,184
- Mod P000302018-10-30+$4,900= $2,273,084
- Mod P000312018-11-23+$832= $2,273,916
- Mod P000322018-12-17+$3,160= $2,277,076
- Mod P000332018-12-26+$77,605= $2,354,680
- Mod P000342020-01-30-$2,511= $2,352,169
- Mod P000352020-06-22-$1,609= $2,350,560
- Mod P000362022-02-09+$0= $2,350,560
| Transaction | Action date | This action (delta) | Running total | Description on this transaction |
|---|---|---|---|---|
| Base | 2014-03-31 | +$217,607 | $217,607 | CONTRACTOR TO PROVIDE TOTAL CEMETERY MAINTENANCE AS REQUIRED IN ACCORDANCE WITH STATEMENT OF WORK AT MARIETTA… |
| Mod P00001· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2014-04-30 | +$0 | $217,607 | CONTRACTOR TO PROVIDE TOTAL CEMETERY MAINTENANCE AS REQUIRED IN ACCORDANCE WITH STATEMENT OF WORK AT MARIETTA… |
| Mod P00002· CHANGE ORDER | 2014-06-25 | +$128,020 | $345,627 | CONTRACTOR TO PROVIDE TOTAL CEMETERY MAINTENANCE AS REQUIRED IN ACCORDANCE WITH STATEMENT OF WORK AT MARIETTA… |
| Mod P00003· EXERCISE AN OPTION | 2014-10-01 | +$91,094 | $436,721 | CONTRACTOR TO PROVIDE TOTAL CEMETERY MAINTENANCE AS REQUIRED IN ACCORDANCE WITH STATEMENT OF WORK AT MARIETTA… |
| Mod P00004· FUNDING ONLY ACTION | 2015-01-29 | +$370,609 | $807,330 | CONTRACTOR TO PROVIDE TOTAL CEMETERY MAINTENANCE AS REQUIRED IN ACCORDANCE WITH STATEMENT OF WORK AT MARIETTA… |
| Mod P00005· FUNDING ONLY ACTION | 2015-02-12 | −$128,021 | $679,309 | CONTRACTOR TO PROVIDE TOTAL CEMETERY MAINTENANCE AS REQUIRED IN ACCORDANCE WITH STATEMENT OF WORK AT MARIETTA… |
| Mod P00006· CHANGE ORDER | 2015-03-30 | +$7,245 | $686,554 | CONTRACTOR TO PROVIDE TOTAL CEMETERY MAINTENANCE AS REQUIRED IN ACCORDANCE WITH STATEMENT OF WORK AT MARIETTA… |
| Mod P00007· CHANGE ORDER | 2015-05-20 | +$90,000 | $776,554 | CONTRACTOR TO PROVIDE TOTAL CEMETERY MAINTENANCE AS REQUIRED IN ACCORDANCE WITH STATEMENT OF WORK AT MARIETTA… |
| Mod P00008· CHANGE ORDER | 2015-07-16 | +$500 | $777,054 | CONTRACTOR TO PROVIDE TOTAL CEMETERY MAINTENANCE AS REQUIRED IN ACCORDANCE WITH STATEMENT OF WORK AT MARIETTA… |
| Mod P00009· CHANGE ORDER | 2015-08-13 | +$15,177 | $792,231 | CONTRACTOR TO PROVIDE TOTAL CEMETERY MAINTENANCE AS REQUIRED IN ACCORDANCE WITH STATEMENT OF WORK AT MARIETTA… |
| Mod P00010· EXERCISE AN OPTION | 2015-10-14 | +$67,780 | $860,011 | CONTRACTOR TO PROVIDE TOTAL CEMETERY MAINTENANCE AS REQUIRED IN ACCORDANCE WITH STATEMENT OF WORK AT MARIETTA… |
| Mod P00011· FUNDING ONLY ACTION | 2016-01-27 | +$64,262 | $924,273 | CONTRACTOR TO PROVIDE TOTAL CEMETERY MAINTENANCE AS REQUIRED IN ACCORDANCE WITH STATEMENT OF WORK AT MARIETTA… |
| Mod P00012· FUNDING ONLY ACTION | 2016-03-28 | +$212,476 | $1,136,749 | CONTRACTOR TO PROVIDE TOTAL CEMETERY MAINTENANCE AS REQUIRED IN ACCORDANCE WITH STATEMENT OF WORK AT MARIETTA… |
| Mod P00013· CHANGE ORDER | 2016-06-20 | +$90,000 | $1,226,749 | CONTRACTOR TO PROVIDE TOTAL CEMETERY MAINTENANCE AS REQUIRED IN ACCORDANCE WITH STATEMENT OF WORK AT MARIETTA… |
| Mod P00014· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2016-08-29 | +$9,401 | $1,236,150 | CONTRACTOR TO PROVIDE TOTAL CEMETERY MAINTENANCE AS REQUIRED IN ACCORDANCE WITH STATEMENT OF WORK AT MARIETTA… |
| Mod P00015· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2016-09-26 | +$7,935 | $1,244,085 | CONTRACTOR TO PROVIDE TOTAL CEMETERY MAINTENANCE AS REQUIRED IN ACCORDANCE WITH STATEMENT OF WORK AT MARIETTA… |
| Mod P00017· EXERCISE AN OPTION | 2016-11-08 | +$28,802 | $1,272,888 | CONTRACTOR TO PROVIDE TOTAL CEMETERY MAINTENANCE AS REQUIRED IN ACCORDANCE WITH STATEMENT OF WORK AT MARIETTA… |
| Mod P00018· FUNDING ONLY ACTION | 2016-12-09 | +$331,228 | $1,604,116 | CONTRACTOR TO PROVIDE TOTAL CEMETERY MAINTENANCE AS REQUIRED IN ACCORDANCE WITH STATEMENT OF WORK AT MARIETTA… |
| Mod P00019· CHANGE ORDER | 2017-04-28 | +$90,000 | $1,694,116 | CONTRACTOR TO PROVIDE TOTAL CEMETERY MAINTENANCE AS REQUIRED IN ACCORDANCE WITH STATEMENT OF WORK AT MARIETTA… |
| Mod P00020· EXERCISE AN OPTION | 2017-10-04 | +$63,344 | $1,757,460 | CONTRACTOR TO PROVIDE TOTAL CEMETERY MAINTENANCE AS REQUIRED IN ACCORDANCE WITH STATEMENT OF WORK AT MARIETTA… |
| Mod P00021· OTHER ADMINISTRATIVE ACTION | 2017-10-13 | +$0 | $1,757,460 | CONTRACTOR TO PROVIDE TOTAL CEMETERY MAINTENANCE AS REQUIRED IN ACCORDANCE WITH STATEMENT OF WORK AT MARIETTA… |
| Mod P00022· FUNDING ONLY ACTION | 2018-01-07 | +$48,440 | $1,805,900 | CONTRACTOR TO PROVIDE TOTAL CEMETERY MAINTENANCE AS REQUIRED IN ACCORDANCE WITH STATEMENT OF WORK AT MARIETTA… |
| Mod P00023· FUNDING ONLY ACTION | 2018-03-13 | +$63,344 | $1,869,244 | CONTRACTOR TO PROVIDE TOTAL CEMETERY MAINTENANCE AS REQUIRED IN ACCORDANCE WITH STATEMENT OF WORK AT MARIETTA… |
| Mod P00024· FUNDING ONLY ACTION | 2018-04-11 | +$40,986 | $1,910,230 | CONTRACTOR TO PROVIDE TOTAL CEMETERY MAINTENANCE AS REQUIRED IN ACCORDANCE WITH STATEMENT OF WORK AT MARIETTA… |
| Mod P00025· FUNDING ONLY ACTION | 2018-05-01 | +$156,499 | $2,066,729 | CONTRACTOR TO PROVIDE TOTAL CEMETERY MAINTENANCE AS REQUIRED IN ACCORDANCE WITH STATEMENT OF WORK AT MARIETTA… |
| Mod P00026· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2018-05-23 | +$90,000 | $2,156,729 | CONTRACTOR TO PROVIDE TOTAL CEMETERY MAINTENANCE AS REQUIRED IN ACCORDANCE WITH STATEMENT OF WORK AT MARIETTA… |
| Mod P00027· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2018-05-29 | +$12,600 | $2,169,329 | CONTRACTOR TO PROVIDE TOTAL CEMETERY MAINTENANCE AS REQUIRED IN ACCORDANCE WITH STATEMENT OF WORK AT MARIETTA… |
| Mod P00028· OTHER ADMINISTRATIVE ACTION | 2018-10-01 | +$101,720 | $2,271,049 | CONTRACTOR TO PROVIDE TOTAL CEMETERY MAINTENANCE AS REQUIRED IN ACCORDANCE WITH STATEMENT OF WORK AT MARIETTA… |
| Mod P00029· FUNDING ONLY ACTION | 2018-10-21 | −$2,865 | $2,268,184 | CONTRACTOR TO PROVIDE TOTAL CEMETERY MAINTENANCE AS REQUIRED IN ACCORDANCE WITH STATEMENT OF WORK AT MARIETTA… |
| Mod P00030· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2018-10-30 | +$4,900 | $2,273,084 | CONTRACTOR TO PROVIDE TOTAL CEMETERY MAINTENANCE AS REQUIRED IN ACCORDANCE WITH STATEMENT OF WORK AT MARIETTA… |
| Mod P00031· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2018-11-23 | +$832 | $2,273,916 | CONTRACTOR TO PROVIDE TOTAL CEMETERY MAINTENANCE AS REQUIRED IN ACCORDANCE WITH STATEMENT OF WORK AT MARIETTA… |
| Mod P00032· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2018-12-17 | +$3,160 | $2,277,076 | CONTRACTOR TO PROVIDE TOTAL CEMETERY MAINTENANCE AS REQUIRED IN ACCORDANCE WITH STATEMENT OF WORK AT MARIETTA… |
| Mod P00033· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2018-12-26 | +$77,605 | $2,354,680 | CONTRACTOR TO PROVIDE TOTAL CEMETERY MAINTENANCE AS REQUIRED IN ACCORDANCE WITH STATEMENT OF WORK AT MARIETTA… |
| Mod P00034· FUNDING ONLY ACTION | 2020-01-30 | −$2,511 | $2,352,169 | CONTRACTOR TO PROVIDE TOTAL CEMETERY MAINTENANCE AS REQUIRED IN ACCORDANCE WITH STATEMENT OF WORK AT MARIETTA… |
| Mod P00035· OTHER ADMINISTRATIVE ACTION | 2020-06-22 | −$1,609 | $2,350,560 | CONTRACTOR TO PROVIDE TOTAL CEMETERY MAINTENANCE AS REQUIRED IN ACCORDANCE WITH STATEMENT OF WORK AT MARIETTA… |
| Mod P00036· CLOSE OUT | 2022-02-09 | +$0 | $2,350,560 | CONTRACTOR TO PROVIDE TOTAL CEMETERY MAINTENANCE AS REQUIRED IN ACCORDANCE WITH STATEMENT OF WORK AT MARIETTA… |
Related awards · 11
Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.
Other VA awards to the same recipient (UEI CVHHMTMPDAE9)
| Award | Office · PSC / listing | Net obligations | FY |
|---|---|---|---|
| 36C78626P0088 | NATIONAL CEMETERY ADMIN (36C786) · S208 · HOUSEKEEPING- LANDSCAPING/GROUNDSKEEPING | $212,164 | FY2026 |
| 36C78626N50889 | NATIONAL CEMETERY ADMIN (36C786) · S208 · HOUSEKEEPING- LANDSCAPING/GROUNDSKEEPING | $5,312 | FY2026 |
| 36C78626P50319 | NATIONAL CEMETERY ADMIN (36C786) · S208 · HOUSEKEEPING- LANDSCAPING/GROUNDSKEEPING | $4,876 | FY2026 |
| 36C78626N50841 | NATIONAL CEMETERY ADMIN (36C786) · S208 · HOUSEKEEPING- LANDSCAPING/GROUNDSKEEPING | $4,320 | FY2026 |
| 36C78626N50833 | NATIONAL CEMETERY ADMIN (36C786) · S208 · HOUSEKEEPING- LANDSCAPING/GROUNDSKEEPING | $1,190,849 | FY2026 |
| 36C78626N50795 | NATIONAL CEMETERY ADMIN (36C786) · S208 · HOUSEKEEPING- LANDSCAPING/GROUNDSKEEPING | $680,560 | FY2026 |
Other recipients under S208 from NATIONAL CEMETERY ADMIN (36C786) (most recent first)
| Award | Recipient | Office | Net obligations | FY |
|---|---|---|---|---|
| 36C78626N50946 | BOCO CONTRACTING & CONSTRUCTION LLC | NATIONAL CEMETERY ADMIN (36C786) | $29,713 | FY2026 |
| 36C78626N50957 | MANUEL HUERTA JR. | NATIONAL CEMETERY ADMIN (36C786) | $36,000 | FY2026 |
| 36C78626N50958 | BYRD ENTERPRISES UNLIMITED INC | NATIONAL CEMETERY ADMIN (36C786) | $29,751 | FY2026 |
| 36C78626N0465 | BYRD ENTERPRISES UNLIMITED INC | NATIONAL CEMETERY ADMIN (36C786) | $89,729 | FY2026 |
| 36C78626N50959 | GREAT LAKES INVESTMENT PROPERTY LLC | NATIONAL CEMETERY ADMIN (36C786) | $19,238 | FY2026 |
Cite as: Glassbox VA record view · VA contract (USAspending / FPDS) · CONT_AWD_VA78614C0094_3600_-NONE-_-NONE- · retrieved 2026-09-26.