Description
THIS MODIFICATION IS TO PROVIDE GREEN GLOBES CERTIFICATION AND CONSTRUCTION INSPECTION AND MATERIAL TESTING, AND TO REMOVE COMMISSIONING SERVICES FROM THE DESIGN FOR THE ATLANTA COMBINED HEAT AND POWER DESIGN PROJECT AT THE ATLANTA VA MEDICAL CENTER.
Base award description: IGF::OT::IGF - THIS TASK ORDER IS AGAINST THE VISN 07 A/E IDIQ WITH URS GROUP, INC. FOR THE DESIGN OF A COMBINED HEAT AND POWER PLANT AT THE ATLANTA VA MEDICAL CENTER. THE PROJECT WILL INCLUDE ALL DESIGN , ENGINEERING, AND CONSTRUCTION ADMINISTRATION SERVICES.
Modification chain · 21 transactions
Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.
- Base2013-05-03+$909,421= $909,421
- Mod P000012013-09-26+$448,763= $1,358,184
- Mod P000022014-03-06+$0= $1,358,184
- Mod P000032014-06-05+$560,129= $1,918,313
- Mod P000042014-07-24+$117,127= $2,035,440
- Mod P000052015-11-05+$58,959= $2,094,399
- Mod P000062016-01-20+$420,580= $2,514,978
- Mod P000072016-03-16+$425,812= $2,940,790
- Mod P000082017-02-13+$141,084= $3,081,874
- Mod P000092017-05-24+$729,701= $3,811,575
- Mod P000102018-01-10+$197,587= $4,009,163
- Mod P000112018-07-16+$796,981= $4,806,144
- Mod P000122019-09-09+$127,764= $4,933,908
- Mod P000132020-03-10+$103,129= $5,037,036
- Mod P000142020-07-22+$106,340= $5,143,376
- Mod P000152020-09-30+$89,762= $5,233,138
- Mod P000162021-04-07+$71,687= $5,304,825
- Mod P000172022-02-09+$158,930= $5,463,756
- Mod P000182022-08-30+$112,613= $5,576,369
- Mod P000192022-09-26+$184,690= $5,761,059
- Mod P000212024-06-13+$122,504= $5,883,563
| Transaction | Action date | This action (delta) | Running total | Description on this transaction |
|---|---|---|---|---|
| Base | 2013-05-03 | +$909,421 | $909,421 | IGF::OT::IGF - THIS TASK ORDER IS AGAINST THE VISN 07 A/E IDIQ WITH URS GROUP, INC. FOR THE DESIGN OF A COMBIN… |
| Mod P00001· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2013-09-26 | +$448,763 | $1,358,184 | IGF::OT::IGF - THIS MODIFICATIO IS TO PROVIDE ADDITIONAL DESIGN SERVICES AND TO PROVIDE A TIME EXTENSION OF 12… |
| Mod P00002· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2014-03-06 | +$0 | $1,358,184 | IGF::OT::IGF - THIS MODIFICATIO IS TO PROVIDE A TIME EXTENSION OF 14 CALENDAR DAYS TO ALLOW FOR THE FINAL SUBM… |
| Mod P00003· EXERCISE AN OPTION | 2014-06-05 | +$560,129 | $1,918,313 | IGF::OT::IGF - THIS MODIFICATIO IS TO EXERCISE THE OPTION FOR CONSTRUCTION PERIOD SERVICES FOR THE ATLANTA COM… |
| Mod P00004· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2014-07-24 | +$117,127 | $2,035,440 | IGF::OT::IGF - THIS MODIFICATION IS TO PROVIDE GREEN GLOBES CERTIFICATION AND CONSTRUCTION INSPECTION AND MATE… |
| Mod P00005· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2015-11-05 | +$58,959 | $2,094,399 | IGF::OT::IGF - THIS MODIFICATION IS TO PROVIDE GREEN GLOBES CERTIFICATION AND CONSTRUCTION INSPECTION AND MATE… |
| Mod P00006· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2016-01-20 | +$420,580 | $2,514,978 | IGF::OT::IGF - THIS MODIFICATION IS TO PROVIDE GREEN GLOBES CERTIFICATION AND CONSTRUCTION INSPECTION AND MATE… |
| Mod P00007· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2016-03-16 | +$425,812 | $2,940,790 | IGF::OT::IGF - THIS MODIFICATION IS TO PROVIDE GREEN GLOBES CERTIFICATION AND CONSTRUCTION INSPECTION AND MATE… |
| Mod P00008· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2017-02-13 | +$141,084 | $3,081,874 | IGF::OT::IGF - THIS MODIFICATION IS TO PROVIDE GREEN GLOBES CERTIFICATION AND CONSTRUCTION INSPECTION AND MATE… |
| Mod P00009· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2017-05-24 | +$729,701 | $3,811,575 | IGF::OT::IGF - THIS MODIFICATION IS TO PROVIDE GREEN GLOBES CERTIFICATION AND CONSTRUCTION INSPECTION AND MATE… |
| Mod P00010· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2018-01-10 | +$197,587 | $4,009,163 | IGF::OT::IGF - THIS MODIFICATION IS TO PROVIDE GREEN GLOBES CERTIFICATION AND CONSTRUCTION INSPECTION AND MATE… |
| Mod P00011· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2018-07-16 | +$796,981 | $4,806,144 | IGF::OT::IGF - THIS MODIFICATION IS TO PROVIDE GREEN GLOBES CERTIFICATION AND CONSTRUCTION INSPECTION AND MATE… |
| Mod P00012· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2019-09-09 | +$127,764 | $4,933,908 | THIS MODIFICATION IS TO PROVIDE GREEN GLOBES CERTIFICATION AND CONSTRUCTION INSPECTION AND MATERIAL TESTING, A… |
| Mod P00013· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2020-03-10 | +$103,129 | $5,037,036 | THIS MODIFICATION IS TO PROVIDE GREEN GLOBES CERTIFICATION AND CONSTRUCTION INSPECTION AND MATERIAL TESTING, A… |
| Mod P00014· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2020-07-22 | +$106,340 | $5,143,376 | THIS MODIFICATION IS TO PROVIDE GREEN GLOBES CERTIFICATION AND CONSTRUCTION INSPECTION AND MATERIAL TESTING, A… |
| Mod P00015· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2020-09-30 | +$89,762 | $5,233,138 | THIS MODIFICATION IS TO PROVIDE GREEN GLOBES CERTIFICATION AND CONSTRUCTION INSPECTION AND MATERIAL TESTING, A… |
| Mod P00016· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2021-04-07 | +$71,687 | $5,304,825 | THIS MODIFICATION IS TO PROVIDE GREEN GLOBES CERTIFICATION AND CONSTRUCTION INSPECTION AND MATERIAL TESTING, A… |
| Mod P00017· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2022-02-09 | +$158,930 | $5,463,756 | THIS MODIFICATION IS TO PROVIDE GREEN GLOBES CERTIFICATION AND CONSTRUCTION INSPECTION AND MATERIAL TESTING, A… |
| Mod P00018· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2022-08-30 | +$112,613 | $5,576,369 | THIS MODIFICATION IS TO PROVIDE GREEN GLOBES CERTIFICATION AND CONSTRUCTION INSPECTION AND MATERIAL TESTING, A… |
| Mod P00019· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2022-09-26 | +$184,690 | $5,761,059 | THIS MODIFICATION IS TO PROVIDE GREEN GLOBES CERTIFICATION AND CONSTRUCTION INSPECTION AND MATERIAL TESTING, A… |
| Mod P00021· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2024-06-13 | +$122,504 | $5,883,563 | THIS MODIFICATION IS TO PROVIDE GREEN GLOBES CERTIFICATION AND CONSTRUCTION INSPECTION AND MATERIAL TESTING, A… |
Related awards · 4
Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.
Other VA awards to the same recipient (UEI DBH8KZZJZ1Z6)
| Award | Office · PSC / listing | Net obligations | FY |
|---|---|---|---|
| VA70114J0111 | PCAC NATIONAL ENERGY BUSINESS CENTER · C1MZ · ARCHITECT AND ENGINEERING- CONSTRUCTION: EPG FACILITIES - OTHER, INCLUDING TRANSMISSION | $1,339,521 | FY2014 |
| VA70114J0118 | PCAC NATIONAL ENERGY BUSINESS CENTER · C1MZ · ARCHITECT AND ENGINEERING- CONSTRUCTION: EPG FACILITIES - OTHER, INCLUDING TRANSMISSION | $1,289,812 | FY2014 |
| VA70112J0091 | PCAC NATIONAL ENERGY BUSINESS CENTER · C211 · ARCHITECT AND ENGINEERING- GENERAL: LANDSCAPING, INTERIOR LAYOUT, AND DESIGNING | $2,500 | FY2012 |
| VA70112D0022 | PCAC NATIONAL ENERGY BUSINESS CENTER · C211 · ARCHITECT AND ENGINEERING- GENERAL: LANDSCAPING, INTERIOR LAYOUT, AND DESIGNING | $0 | FY2012 |
Cite as: Glassbox VA record view · VA contract (USAspending / FPDS) · CONT_AWD_VA70113J0086_3600_VA70112D0022_3600 · retrieved 2026-09-26.