Award recordCONTRACT

TRAFFIC ANALYSIS & DESIGN, INC.

PIID VA69DP1300· VHA· 69D-NETWORK CONTRACT OFFICE 12· C214 · A&E MANAGEMENT ENGINEERING SERVICES· FY2010· $389,575 net obligations· UEI RL91MZJ7LCA9· IL

Description

S/A #4 FOR ADDITIONAL AE SERVICES ON CAMPUS TRAFFIC AND PARKING STUDY AT THE EDWARD HINES JR. VA HOSPITAL, HINES IL.

Base award description: TAS::36 0158::TAS AE DESIGN SERVICES TO PERFORM A CAMPUS TRAFFIC STUDY AT THE EDWARD HINES JR. VA HOSPITAL, HINES ILLINOIS.

First action · last action
2010-01-14 · 2011-07-26
Transactions
5
First transaction's obligation
$224,183
Base + all options value (sum of deltas)
$389,575
Extent competed
FULL AND OPEN COMPETITION
Other than full & open authority
—
Set-aside
NO SET ASIDE USED.
Offers received
5
SDVOSB flag on record
No
NAICS
541330 · ENGINEERING SERVICES

Modification chain · 5 transactions

Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.

$389,575$0Base award · 2010-01-14 · this action $224,183 · running total $224,183Modification 1 · 2010-07-01 · this action $12,568 · running total $236,751Modification 2 · 2010-09-30 · this action $75,077 · running total $311,827Modification 3 · 2011-03-30 · this action $44,259 · running total $356,087Modification 4 · 2011-07-26 · this action $33,488 · running total $389,575
  • Base2010-01-14+$224,183= $224,183
  • Mod 12010-07-01+$12,568= $236,751
  • Mod 22010-09-30+$75,077= $311,827
  • Mod 32011-03-30+$44,259= $356,087
  • Mod 42011-07-26+$33,488= $389,575
TransactionAction dateThis action (delta)Running totalDescription on this transaction
Base2010-01-14+$224,183$224,183TAS::36 0158::TAS AE DESIGN SERVICES TO PERFORM A CAMPUS TRAFFIC STUDY AT THE EDWARD HINES JR. VA HOSPITAL, H…
Mod 1· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-07-01+$12,568$236,751TAS::36 0158::TAS AE DESIGN SERVICES TO PERFORM A CAMPUS TRAFFIC STUDY AT THE EDWARD HINES JR. VA HOSPITAL, H…
Mod 2· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-09-30+$75,077$311,827TAS::36 0162::TAS S/A #1 AE DESIGN SERVICES TO PERFORM A CAMPUS TRAFFIC STUDY AT THE EDWARD HINES JR. VA HOSP…
Mod 3· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-03-30+$44,259$356,087S/A #3 FOR ADDITIONAL AE SERVICES ON CAMPUS TRAFFIC AND PARKING STUDY AT THE EDWARD HINES JR. VA HOSPITAL, HIN…
Mod 4· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-07-26+$33,488$389,575S/A #4 FOR ADDITIONAL AE SERVICES ON CAMPUS TRAFFIC AND PARKING STUDY AT THE EDWARD HINES JR. VA HOSPITAL, HIN…

Related awards · 7

Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.

Other VA awards to the same recipient (UEI RL91MZJ7LCA9)

AwardOffice · PSC / listingNet obligationsFY
VA24413C0319244-NETWORK CONTRACT OFFICE 4 (36C244) · C1LZ · ARCHITECT AND ENGINEERING- CONSTRUCTION: PARKING FACILITIES$395,772FY2013
VA69D12C002269D-NETWORK CONTRACT OFFICE 12 · C1DZ · ARCHITECT AND ENGINEERING- CONSTRUCTION: OTHER HOSPITAL BUILDINGS$1,095,972FY2012

Other recipients under C214 from 69D-NETWORK CONTRACT OFFICE 12 (most recent first)

AwardRecipientOfficeNet obligationsFY
VA69D15J2910T & M ASSOCIATES, INCORPORATED69D-NETWORK CONTRACT OFFICE 12$20,000FY2015
VA69D14J5159T & M ASSOCIATES, INCORPORATED69D-NETWORK CONTRACT OFFICE 12$30,000FY2014
VA69D14J4884CHEQUAMEGON BAY GROUP INC69D-NETWORK CONTRACT OFFICE 12$23,910FY2014
VA69D14J3033ANDERSON ENGINEERING OF MINNESOTA, LLC69D-NETWORK CONTRACT OFFICE 12$49,873FY2014
VA69D14J2281CHEQUAMEGON BAY GROUP INC69D-NETWORK CONTRACT OFFICE 12$16,196FY2014

Cite as: Glassbox VA record view · VA contract (USAspending / FPDS) · CONT_AWD_VA69DP1300_3600_-NONE-_-NONE- · retrieved 2026-09-26.