Description
SA #3 DECREASE FOR AE TASKS NO LONGER REQUIRED UNDER THE CONTRACT - REPLACE ROOF, BUILDING 217, EDWARD HINES JR. VA HOSPITAL, HINES, ILLINOIS.
Base award description: TAS::36 0158::TAS A/E FOR DESIGN AND REPLACE ROOF, BUILDING 217, EDWARD HINES JR. VA HOSPITAL, HINES, ILLINOIS.
Modification chain · 4 transactions
Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.
- Base2009-09-25+$288,749= $288,749
- Mod 12010-09-30+$28,750= $317,499
- Mod 22012-04-24+$2,500= $319,999
- Mod P000032012-08-21-$2,500= $317,499
| Transaction | Action date | This action (delta) | Running total | Description on this transaction |
|---|---|---|---|---|
| Base | 2009-09-25 | +$288,749 | $288,749 | TAS::36 0158::TAS A/E FOR DESIGN AND REPLACE ROOF, BUILDING 217, EDWARD HINES JR. VA HOSPITAL, HINES, ILLINO… |
| Mod 1· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2010-09-30 | +$28,750 | $317,499 | TAS::36 0162::TAS SA #1 FOR ADDITIONAL A/E DESIGN SERVICES TO REPLACE ROOF, BUILDING 217, EDWARD HINES JR. VA… |
| Mod 2· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-04-24 | +$2,500 | $319,999 | SA #2 FOR ADDITIONAL A/E DESIGN SERVICES TO REPLACE ROOF, BUILDING 217, EDWARD HINES JR. VA HOSPITAL, HINES, I… |
| Mod P00003· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-08-21 | −$2,500 | $317,499 | SA #3 DECREASE FOR AE TASKS NO LONGER REQUIRED UNDER THE CONTRACT - REPLACE ROOF, BUILDING 217, EDWARD HINES J… |
Related awards · 11
Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.
Other VA awards to the same recipient (UEI PL6GRLGM62D6)
| Award | Office · PSC / listing | Net obligations | FY |
|---|---|---|---|
| VA69D13J2748 | 252-NETWORK CONTRACT OFFICE 12 (36C252) · C219 · ARCHITECT AND ENGINEERING- GENERAL: OTHER | $45,777 | FY2013 |
| VA69D13J1963 | 252-NETWORK CONTRACT OFFICE 12 (36C252) · C219 · ARCHITECT AND ENGINEERING- GENERAL: OTHER | $54,396 | FY2013 |
| VA69D12J2300 | 252-NETWORK CONTRACT OFFICE 12 (36C252) · C219 · ARCHITECT AND ENGINEERING- GENERAL: OTHER | $168,222 | FY2012 |
| VA69D12J1155 | 69D-NETWORK CONTRACT OFFICE 12 · C219 · ARCHITECT AND ENGINEERING- GENERAL: OTHER | $35,283 | FY2012 |
| VA69D12J0899 | 252-NETWORK CONTRACT OFFICE 12 (36C252) · C219 · ARCHITECT AND ENGINEERING- GENERAL: OTHER | $86,025 | FY2012 |
| VA69D12J0900 | 69D-NETWORK CONTRACT OFFICE 12 · C219 · ARCHITECT AND ENGINEERING- GENERAL: OTHER | $52,323 | FY2012 |
Other recipients under C214 from 69D-NETWORK CONTRACT OFFICE 12 (most recent first)
| Award | Recipient | Office | Net obligations | FY |
|---|---|---|---|---|
| VA69D15J2910 | T & M ASSOCIATES, INCORPORATED | 69D-NETWORK CONTRACT OFFICE 12 | $20,000 | FY2015 |
| VA69D14J5159 | T & M ASSOCIATES, INCORPORATED | 69D-NETWORK CONTRACT OFFICE 12 | $30,000 | FY2014 |
| VA69D14J4884 | CHEQUAMEGON BAY GROUP INC | 69D-NETWORK CONTRACT OFFICE 12 | $23,910 | FY2014 |
| VA69D14J3033 | ANDERSON ENGINEERING OF MINNESOTA, LLC | 69D-NETWORK CONTRACT OFFICE 12 | $49,873 | FY2014 |
| VA69D14J2281 | CHEQUAMEGON BAY GROUP INC | 69D-NETWORK CONTRACT OFFICE 12 | $16,196 | FY2014 |
Cite as: Glassbox VA record view · VA contract (USAspending / FPDS) · CONT_AWD_VA69DP1164_3600_-NONE-_-NONE- · retrieved 2026-09-26.