Award recordCONTRACT

VETERANS ELECTRIC LLC

PIID VA69DC1834· VHA· 69D-NETWORK CONTRACT OFFICE 12· Z141 · MAINT-REP-ALT/HOSPITALS & INFIRMARY· FY2011· $4,823,050 net obligations· UEI V5VNBYRVAKJ8· WI

Description

IGF::OT::IGE MODIFICATION P00025 INCORPORATES RFP 143, LOUVER MODIFICATION, UNDER CONTRACT VA69D-C-1834, 111 UPGRADE FCA EMERGENCY GENERATOR CONTROLS AT MILWAUKEE VAMC, MILWAUKEE, WISCONSIN.

Base award description: VA PROJECT #695-11-106 UPGRADE FCA EMERGENCY GENERATOR CONTROLS AND SYNCHRONIZATION CLEMENT J. ZABLOCKI VA MEDICAL CENTER MILWAUKEE, WISCONSIN

First action · last action
2011-08-01 · 2015-04-02
Transactions
26
First transaction's obligation
$4,438,209
Base + all options value (sum of deltas)
$4,823,050
Extent competed
FULL AND OPEN COMPETITION AFTER EXCLUSION OF SOURCES
Other than full & open authority
—
Set-aside
SERVICE DISABLED VETERAN OWNED SMALL BUSINESS SET-ASIDE
Offers received
3
SDVOSB flag on record
Yes (self-representation)
NAICS
238210 · ELECTRICAL CONTRACTORS AND OTHER WIRING INSTALLATION CONTRACTORS

Modification chain · 26 transactions

Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.

$4,823,050$0Base award · 2011-08-01 · this action $4,438,209 · running total $4,438,209Modification 1 · 2011-09-20 · this action $57,612 · running total $4,495,821Modification 2 · 2011-09-20 · this action $0 · running total $4,495,821Modification 3 · 2011-12-14 · this action $23,501 · running total $4,519,322Modification 4 · 2011-12-29 · this action $5,843 · running total $4,525,165Modification 5 · 2012-03-07 · this action $0 · running total $4,525,165Modification 6 · 2012-04-24 · this action $4,045 · running total $4,529,210Modification 7 · 2012-06-05 · this action $0 · running total $4,529,210Modification P0008 · 2012-08-18 · this action $0 · running total $4,529,210Modification P0009 · 2012-09-14 · this action $9,080 · running total $4,538,290Modification P00010 · 2012-10-18 · this action $0 · running total $4,538,290Modification P00011 · 2012-12-04 · this action $0 · running total $4,538,290Modification P00012 · 2013-02-21 · this action $0 · running total $4,538,290Modification P00013 · 2013-03-25 · this action $0 · running total $4,538,290Modification P00014 · 2013-04-10 · this action $0 · running total $4,538,290Modification P00015 · 2013-05-10 · this action -$3,955 · running total $4,534,335Modification P00016 · 2013-05-30 · this action $0 · running total $4,534,335Modification P00017 · 2013-06-28 · this action $0 · running total $4,534,335Modification P00018 · 2013-07-25 · this action $16,961 · running total $4,551,296Modification P00019 · 2013-09-18 · this action $0 · running total $4,551,296Modification P00021 · 2013-09-20 · this action $0 · running total $4,551,296Modification P00020 · 2013-11-08 · this action $0 · running total $4,551,296Modification P00022 · 2014-09-18 · this action $77,609 · running total $4,628,905Modification P00023 · 2014-11-06 · this action $97,292 · running total $4,726,198Modification P00024 · 2014-12-03 · this action $68,069 · running total $4,794,267Modification P00025 · 2015-04-02 · this action $28,783 · running total $4,823,050
  • Base2011-08-01+$4,438,209= $4,438,209
  • Mod 12011-09-20+$57,612= $4,495,821
  • Mod 22011-09-20+$0= $4,495,821
  • Mod 32011-12-14+$23,501= $4,519,322
  • Mod 42011-12-29+$5,843= $4,525,165
  • Mod 52012-03-07+$0= $4,525,165
  • Mod 62012-04-24+$4,045= $4,529,210
  • Mod 72012-06-05+$0= $4,529,210
  • Mod P00082012-08-18+$0= $4,529,210
  • Mod P00092012-09-14+$9,080= $4,538,290
  • Mod P000102012-10-18+$0= $4,538,290
  • Mod P000112012-12-04+$0= $4,538,290
  • Mod P000122013-02-21+$0= $4,538,290
  • Mod P000132013-03-25+$0= $4,538,290
  • Mod P000142013-04-10+$0= $4,538,290
  • Mod P000152013-05-10-$3,955= $4,534,335
  • Mod P000162013-05-30+$0= $4,534,335
  • Mod P000172013-06-28+$0= $4,534,335
  • Mod P000182013-07-25+$16,961= $4,551,296
  • Mod P000192013-09-18+$0= $4,551,296
  • Mod P000212013-09-20+$0= $4,551,296
  • Mod P000202013-11-08+$0= $4,551,296
  • Mod P000222014-09-18+$77,609= $4,628,905
  • Mod P000232014-11-06+$97,292= $4,726,198
  • Mod P000242014-12-03+$68,069= $4,794,267
  • Mod P000252015-04-02+$28,783= $4,823,050
TransactionAction dateThis action (delta)Running totalDescription on this transaction
Base2011-08-01+$4,438,209$4,438,209VA PROJECT #695-11-106 UPGRADE FCA EMERGENCY GENERATOR CONTROLS AND SYNCHRONIZATION CLEMENT J. ZABLOCKI VA ME…
Mod 1· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-09-20+$57,612$4,495,821VA PROJECT #695-11-106 UPGRADE FCA EMERGENCY GENERATOR CONTROLS AND SYNCHRONIZATION CLEMENT J. ZABLOCKI VA ME…
Mod 2· CHANGE ORDER2011-09-20+$0$4,495,821UPGRADE FCA EMERGENCY GENERATOR CONTROLS AND SYNCHRONIZATION, BLDG. 111 VETERANS ELECTRIC CHANGE ORDER "A"
Mod 3· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-12-14+$23,501$4,519,322UPGRADE FCA EMERGENCY GENERATOR CONTROLS AND SYNCHRONIZATION, BLDG. 111 VETERANS ELECTRIC SA0003 REPAIR TO BLD…
Mod 4· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-12-29+$5,843$4,525,165UPGRADE FCA EMERGENCY GENERATOR CONTROLS AND SYNCHRONIZATION, BLDG. 111, VETERANS ELECTRIC SA-0004 DEMO. OIL I…
Mod 5· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2012-03-07+$0$4,525,165SA-5 RFP-108&113 - CREDIT/CHANGES - UPGRADE FCA EMERGENCY GENERATOR CONTROLS AND SYNCHRONIZATION, BLDG. 111, V…
Mod 6· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2012-04-24+$4,045$4,529,210SA-6 RFPS 103, 112R1, 115, 117, 120, AND 121- CREDIT/CHANGES - UPGRADE FCA EMERGENCY GENERATOR CONTROLS AND SY…
Mod 7· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2012-06-05+$0$4,529,210OTHER FUNCTION - SA-7 RFP-124, 59 DAY T.E. FOR AUTO-SYNCH INSTALL - UPGRADE FCA EMERGENCY GENERATOR CONTROLS A…
Mod P0008· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2012-08-18+$0$4,529,210OTHER FUNCTION - SA-09 59 DAY T.E.- UPGRADE FCA EMERGENCY GENERATOR CONTROLS AND SYNCHRONIZATION, BLDG. 111, V…
Mod P0009· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2012-09-14+$9,080$4,538,290OTHER FUNCTION - SA-09 RFPS 118, 122, AND 125-UPGRADE FCA EMERGENCY GENERATOR CONTROLS AND SYNCHRONIZATION, BL…
Mod P00010· CHANGE ORDER2012-10-18+$0$4,538,290OTHER FUNCTION - CHANGE ORDER "S" - RFP-119 - EXHAUST DUCT MATERIAL CHANGE - UPGRADE FCA EMERGENCY GENERATOR C…
Mod P00011· CHANGE ORDER2012-12-04+$0$4,538,290OTHER FUNCTIONS: TIME EXTENSION OF 45 CALENDAR DAYS FOR THE UPGRADE EMERGENCY GENERATORS AT MILWAUKEE VAMC, MI…
Mod P00012· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2013-02-21+$0$4,538,290OTHER FUNCTIONS: TIME EXTENSION OF 59 CALENDAR DAYS FOR THE UPGRADE EMERGENCY GENERATORS AT MILWAUKEE VAMC, MI…
Mod P00013· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2013-03-25+$0$4,538,290OTHER FUNCTIONS: TIME EXTENSION OF 24 CALENDAR DAYS FOR THE UPGRADE EMERGENCY GENERATORS AT MILWAUKEE VAMC, MI…
Mod P00014· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2013-04-10+$0$4,538,290OTHER FUNCTIONS: TIME EXTENSION OF 30 CALENDAR DAYS FOR THE UPGRADE EMERGENCY GENERATORS AT MILWAUKEE VAMC, MI…
Mod P00015· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2013-05-10−$3,955$4,534,335OTHER FUNCTIONS: RFP 119 (TEMPORARY GENERATOR EXHAUST DUCT MATERIAL CHANGE), RFP 123 (RELOCATION OF MOTOR STAR…
Mod P00016· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2013-05-30+$0$4,534,335OTHER FUNCTIONS: 30 DAY NO COST TIME EXTENSION UPGRADE EMERGENCY GENERATORS AT MILWAUKEE VAMC, MILWAUKEE, WIS…
Mod P00017· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2013-06-28+$0$4,534,335OTHER FUNCTIONS: 59 DAY NO COST TIME EXTENSION UPGRADE EMERGENCY GENERATORS AT MILWAUKEE VAMC, MILWAUKEE, WIS…
Mod P00018· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2013-07-25+$16,961$4,551,296OTHER FUNCTIONS: P00018 INCORPORATES RFP'S 130 AND 133, UPGRADE EMERGENCY GENERATORS AT MILWAUKEE VAMC, MILWAU…
Mod P00019· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2013-09-18+$0$4,551,296OTHER FUNCTIONS: P00019 55 DAY TIME EXTENSION - REMAINING WORK TO CLOSE OUT PROJECT, - 111 UPGRADE EMERGENCY G…
Mod P00021· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2013-09-20+$0$4,551,296OTHER FUNCTION: P00021 START GPS (GUARANTEED PERIOD SVC'S.) - RFP-140 / CO #AP - 111 UPGRADE EMERGENCY GENERAT…
Mod P00020· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2013-11-08+$0$4,551,296OTHER FUNCTION: P00020 59 DAY TIME EXTENSION - RFP-102 DEFINITIZE W/RFP-107, 126, 130, - 111 UPGRADE EMERGENCY…
Mod P00022· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2014-09-18+$77,609$4,628,905OTHER FUNCTION- P00022 - RFPS-129R,131R,134,136,137,138, AND 139 - 111 UPGRADE EMERGENCY GENERATORS AT MILWAUK…
Mod P00023· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2014-11-06+$97,292$4,726,198OTHER FUNCTION- P00023 - RFP-141R1 - TEMP GEN RENTALS&MISC RFI'S - 111 UPGRADE EMERGENCY GENERATORS AT MILWAUK…
Mod P00024· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2014-12-03+$68,069$4,794,267OTHER FUNCTION- P00024 - RFP-142 - TEMP GEN RENTALS&MISC RFI'S - 111 UPGRADE EMERGENCY GENERATORS AT MILWAUKEE…
Mod P00025· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2015-04-02+$28,783$4,823,050IGF::OT::IGE MODIFICATION P00025 INCORPORATES RFP 143, LOUVER MODIFICATION, UNDER CONTRACT VA69D-C-1834, 111 U…

Related awards · 11

Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.

Other VA awards to the same recipient (UEI V5VNBYRVAKJ8)

AwardOffice · PSC / listingNet obligationsFY
36C25225P1272252-NETWORK CONTRACT OFFICE 12 (36C252) · Z1DA · MAINTENANCE OF HOSPITALS AND INFIRMARIES$19,970FY2025
36C25224P1144252-NETWORK CONTRACT OFFICE 12 (36C252) · J031 · MAINT/REPAIR/REBUILD OF EQUIPMENT- BEARINGS$55,054FY2024
36C25224P1020252-NETWORK CONTRACT OFFICE 12 (36C252) · Z1DA · MAINTENANCE OF HOSPITALS AND INFIRMARIES$6,566FY2024
36C25224P0866252-NETWORK CONTRACT OFFICE 12 (36C252) · J049 · MAINT/REPAIR/REBUILD OF EQUIPMENT- MAINTENANCE AND REPAIR SHOP EQUIPMENT$14,906FY2024
36C25224P1073252-NETWORK CONTRACT OFFICE 12 (36C252) · J061 · MAINT/REPAIR/REBUILD OF EQUIPMENT- ELECTRIC WIRE AND POWER DISTRIBUTION EQUIPMENT$4,700FY2024
36C25223C0051252-NETWORK CONTRACT OFFICE 12 (36C252) · Z1DA · MAINTENANCE OF HOSPITALS AND INFIRMARIES$3,559FY2023

Other recipients under Z141 from 69D-NETWORK CONTRACT OFFICE 12 (most recent first)

AwardRecipientOfficeNet obligationsFY
VA69D537C10505INDUSTRIA INC69D-NETWORK CONTRACT OFFICE 12$67,476FY2011
VA69D537C10501JDM LLC69D-NETWORK CONTRACT OFFICE 12$70,934FY2011
VA69D537C10446INDUSTRIA INC69D-NETWORK CONTRACT OFFICE 12$152,773FY2011
VA69D537C10492JDM LLC69D-NETWORK CONTRACT OFFICE 12$0FY2011
VA69D556C10391LEE & RYAN ENVIRONMENTAL CONSULTING, INCORPORATED69D-NETWORK CONTRACT OFFICE 12$29,911FY2011

Cite as: Glassbox VA record view · VA contract (USAspending / FPDS) · CONT_AWD_VA69DC1834_3600_-NONE-_-NONE- · retrieved 2026-09-26.