IGF: :OT: :IGF SA-4 CO#5=E-INSTALL A SLOPED SILL ON THE EXISTING INTERIOR WINDOW LEDGE IN ROOM 417. THE SLOPED SILL SHOULD BE OF HEAVY DUTY CONSTRUCTION, SECURELY FASTENED TO THE SUBSTRATE, AND HAVE SECURITY SEALANT AROUND THE PERIMETER. THE COST FOR THIS ADDITIONAL WORK IS $247.50 AS A RESULT OF THE ABOVE CHANGES, THE CONTRACT PRICE IS CHANGED FROM $1,670,614.31 TO $1,670,861.81
Base award description: PROJECT 556-10-101 REPLACE WINDOWS IN BLDG 131
Modification chain · 5 transactions
Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.
- Base2010-09-17+$1,579,000= $1,579,000
- Mod 12012-01-30+$84,659= $1,663,659
- Mod P00022012-07-25+$5,033= $1,668,692
- Mod P00032012-08-09+$1,923= $1,670,614
- Mod P000042012-12-18+$248= $1,670,862
| Transaction | Action date | This action (delta) | Running total | Description on this transaction |
|---|---|---|---|---|
| Base | 2010-09-17 | +$1,579,000 | $1,579,000 | PROJECT 556-10-101 REPLACE WINDOWS IN BLDG 131 |
| Mod 1· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-01-30 | +$84,659 | $1,663,659 | SA-1: REINSTALLATION OF SECURITY WINDOWS. PROJECT 556-10-101 REPLACE WINDOWS IN BLDG 131 |
| Mod P0002· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-07-25 | +$5,033 | $1,668,692 | SA-2 CO#3=C WILL PROVIDE FOR RAISE PRIMARY (EXTERIOR) BLINDS AND PLACE IN FIXED FULLY OPEN POSITION. B131, 4T… |
| Mod P0003· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-08-09 | +$1,923 | $1,670,614 | SA-3 1. CO#4=D-WILL PROVIDE LABOR AND MATERIALS TO INSTALL SECURITY SEALANT (PECORA DYNAFLEX OR EQUAL) AROUND… |
| Mod P00004· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-12-18 | +$248 | $1,670,862 | IGF: :OT: :IGF SA-4 CO#5=E-INSTALL A SLOPED SILL ON THE EXISTING INTERIOR WINDOW LEDGE IN ROOM 417. THE SLOPED… |
Related awards · 11
Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.
Other VA awards to the same recipient (UEI ZHN5JLVRSX99)
| Award | Office · PSC / listing | Net obligations | FY |
|---|---|---|---|
| VA69D14C0306 | 69D-NETWORK CONTRACT OFFICE 12 · Z1DA · MAINTENANCE OF HOSPITALS AND INFIRMARIES | $395,425 | FY2014 |
| VA78614C0173 | NATIONAL CEMETERY ADMINISTRATION · Y1PZ · CONSTRUCTION OF OTHER NON-BUILDING FACILITIES | $172,437 | FY2014 |
| VA69D14C0332 | 69D-NETWORK CONTRACT OFFICE 12 · Z1DA · MAINTENANCE OF HOSPITALS AND INFIRMARIES | $104,500 | FY2014 |
| VA69D14J1650 | 69D-NETWORK CONTRACT OFFICE 12 · Z1DA · MAINTENANCE OF HOSPITALS AND INFIRMARIES | $488,364 | FY2014 |
| VA69D14J1467 | 69D-NETWORK CONTRACT OFFICE 12 · Z1DA · MAINTENANCE OF HOSPITALS AND INFIRMARIES | $5,496 | FY2014 |
| 695C40179 | 69D-NETWORK CONTRACT OFFICE 12 · Z1AZ · MAINTENANCE OF OTHER ADMINISTRATIVE FACILITIES AND SERVICE BUILDINGS | $0 | FY2014 |
Other recipients under Z141 from 69D-NETWORK CONTRACT OFFICE 12 (most recent first)
| Award | Recipient | Office | Net obligations | FY |
|---|---|---|---|---|
| VA69D537C10505 | INDUSTRIA INC | 69D-NETWORK CONTRACT OFFICE 12 | $67,476 | FY2011 |
| VA69D537C10501 | JDM LLC | 69D-NETWORK CONTRACT OFFICE 12 | $70,934 | FY2011 |
| VA69D537C10446 | INDUSTRIA INC | 69D-NETWORK CONTRACT OFFICE 12 | $152,773 | FY2011 |
| VA69D537C10492 | JDM LLC | 69D-NETWORK CONTRACT OFFICE 12 | $0 | FY2011 |
| VA69D556C10391 | LEE & RYAN ENVIRONMENTAL CONSULTING, INCORPORATED | 69D-NETWORK CONTRACT OFFICE 12 | $29,911 | FY2011 |