Award recordCONTRACT

CBAY, LLC

PIID VA69DC1253· VHA· 69D-NETWORK CONTRACT OFFICE 12· Y141 · CONSTRUCT/HOSPITALS & INFIRMARIES· FY2010· $10,431,999 net obligations· UEI L6MMBNK832K3· WI

Description

SA-16 INCORPORATES CHANGE ORDERS 71, 72, AND 73 FOR THE REPLACE BOILERS AT CLEMENT J. ZABLOCKI VAMC, MILWAUKEE, WISCONSIN

Base award description: REPLACE BOILERS AT CLEMENT J. ZABLOCKI VAMC, MILWAUKEE, WISCONSIN REMOVE 3 HTHW BOILERS AND ASSOCIATED EQUIPMENT AND REPLACE WITH TWO HIGH EFFICIENCY BOILERS. CONVERT AND UPGRADE BOILER CONTROLS FOR COMPLIANCE WITH NEW STANDARDS. REMOVE OLD STEAM TRESTLE, ASBESTOS ABATEMENT IN DESIGNATED AREAS, PROVIDE NEW EMERGENCY RESERVOIR TANK FOR BOILERS. ADDITIONAL REQUIREMENTS PER CONTRACT DOCUMENTS.

First action · last action
2009-11-30 · 2013-02-08
Transactions
22
First transaction's obligation
$9,057,000
Base + all options value (sum of deltas)
$10,431,999
Extent competed
FULL AND OPEN COMPETITION AFTER EXCLUSION OF SOURCES
Other than full & open authority
—
Set-aside
SERVICE DISABLED VETERAN OWNED SMALL BUSINESS SET-ASIDE
Offers received
7
SDVOSB flag on record
Yes (self-representation)
NAICS
238220 · PLUMBING, HEATING, AND AIR-CONDITIONING CONTRACTORS

Modification chain · 22 transactions

Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.

$10,431,999$0Base award · 2009-11-30 · this action $9,057,000 · running total $9,057,000Modification 1 · 2010-06-15 · this action $1,973 · running total $9,058,973Modification SA2 · 2010-08-12 · this action $0 · running total $9,058,973Modification SA4 · 2010-08-12 · this action $165,200 · running total $9,224,173Modification COAB · 2010-08-26 · this action $0 · running total $9,224,173Modification COTU · 2010-08-26 · this action $0 · running total $9,224,173Modification SA3 · 2010-08-26 · this action $1,040 · running total $9,225,214Modification SA5 · 2010-08-26 · this action $76,493 · running total $9,301,707Modification SA6 · 2010-09-10 · this action -$957 · running total $9,300,749Modification COAT · 2010-09-24 · this action $0 · running total $9,300,749Modification SA7 · 2010-09-24 · this action $20,596 · running total $9,321,345Modification COBB · 2010-12-04 · this action $800,000 · running total $10,121,345Modification SA10 · 2011-12-08 · this action $39,914 · running total $10,161,259Modification SA11 · 2011-12-08 · this action $51,114 · running total $10,212,373Modification SA12 · 2011-12-08 · this action $0 · running total $10,212,373Modification SA13 · 2011-12-08 · this action $111,097 · running total $10,323,470Modification SA14 · 2011-12-08 · this action $21,215 · running total $10,344,685Modification SA15 · 2011-12-08 · this action $33,897 · running total $10,378,582Modification SA8 · 2011-12-08 · this action -$7 · running total $10,378,575Modification SA9 · 2011-12-08 · this action $17,342 · running total $10,395,917Modification SA16 · 2012-04-27 · this action $31,259 · running total $10,427,176Modification SA17 · 2013-02-08 · this action $4,823 · running total $10,431,999
  • Base2009-11-30+$9,057,000= $9,057,000
  • Mod 12010-06-15+$1,973= $9,058,973
  • Mod SA22010-08-12+$0= $9,058,973
  • Mod SA42010-08-12+$165,200= $9,224,173
  • Mod COAB2010-08-26+$0= $9,224,173
  • Mod COTU2010-08-26+$0= $9,224,173
  • Mod SA32010-08-26+$1,040= $9,225,214
  • Mod SA52010-08-26+$76,493= $9,301,707
  • Mod SA62010-09-10-$957= $9,300,749
  • Mod COAT2010-09-24+$0= $9,300,749
  • Mod SA72010-09-24+$20,596= $9,321,345
  • Mod COBB2010-12-04+$800,000= $10,121,345
  • Mod SA102011-12-08+$39,914= $10,161,259
  • Mod SA112011-12-08+$51,114= $10,212,373
  • Mod SA122011-12-08+$0= $10,212,373
  • Mod SA132011-12-08+$111,097= $10,323,470
  • Mod SA142011-12-08+$21,215= $10,344,685
  • Mod SA152011-12-08+$33,897= $10,378,582
  • Mod SA82011-12-08-$7= $10,378,575
  • Mod SA92011-12-08+$17,342= $10,395,917
  • Mod SA162012-04-27+$31,259= $10,427,176
  • Mod SA172013-02-08+$4,823= $10,431,999
TransactionAction dateThis action (delta)Running totalDescription on this transaction
Base2009-11-30+$9,057,000$9,057,000REPLACE BOILERS AT CLEMENT J. ZABLOCKI VAMC, MILWAUKEE, WISCONSIN REMOVE 3 HTHW BOILERS AND ASSOCIATED EQUIPME…
Mod 1· CHANGE ORDER2010-06-15+$1,973$9,058,973SA-1 INCORPORATE CHANGE ORDERS 1-8, 9-19 FOR THE REPLACE BOILERS AT CLEMENT J. ZABLOCKI VAMC, MILWAUKEE, WISCO…
Mod SA2· OTHER ADMINISTRATIVE ACTION2010-08-12+$0$9,058,973SA-2 ADMINISTRATIVE CHANGE. CHANGING DESIGNATION OF CHANGE ORDERS 1-8, 9-19 FROM NUMERICAL SEQUENCING TO SEQUE…
Mod SA4· CHANGE ORDER2010-08-12+$165,200$9,224,173SA-4 DEFINITIZES CHANGE ORDER AB (REFERENCE CO 26)FOR THE REPLACE BOILERS AT CLEMENT J. ZABLOCKI VAMC, MILWAUK…
Mod COAB· CHANGE ORDER2010-08-26+$0$9,224,173CHANGE ORDER AB NOT TO EXCEED $65,000 FOR MATERIAL PURCHASES(NO LABOR) FOR FUEL RETURN LINES REFERENCE CONTRAC…
Mod COTU· CHANGE ORDER2010-08-26+$0$9,224,173CHANGE ORDER T-U NOT TO EXCEED. INSTALL 14-INCH DRAIN LINE FOR STORM WATER TO PREVENT FURTHER FLOODING&REPAIR…
Mod SA3· CHANGE ORDER2010-08-26+$1,040$9,225,214SA-3 INCORPORATE CHANGE ORDERS V, X, Y, AC, AD,AE,AF, AH, AND AJ. ALSO DEFINITIZES CHANGE ORDERS Z, T, AND UFO…
Mod SA5· CHANGE ORDER2010-08-26+$76,493$9,301,707SA-5 INCORPORATES CHANGE ORDER AK (REFERENCE CO 37)FOR THE REPLACE BOILERS AT CLEMENT J. ZABLOCKI VAMC, MILWAU…
Mod SA6· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-09-10−$957$9,300,749SA-6 INCORPORATES CHANGE ORDERS W, AA, AL, AM, AO, AP, AQ, AR, AND AS FOR THE REPLACE BOILERS AT CLEMENT J. ZA…
Mod COAT· CHANGE ORDER2010-09-24+$0$9,300,749NOT TO EXCEED CHANGE ORDER AT (REFERENCE CO # 46)REROUTE LIGHT POLE ELECTRICAL&CONDUIT ON HANK AARON DNR BIKE…
Mod SA7· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-09-24+$20,596$9,321,345SA-7 INCORPORATES CHANGE ORDERS AN, AT,AND AU FOR THE REPLACE BOILERS AT CLEMENT J. ZABLOCKI VAMC, MILWAUKEE,…
Mod COBB· CHANGE ORDER2010-12-04+$800,000$10,121,345CHANGE ORDER BB (REFERENCE CO # 54) NOT TO EXCEED $800,000.00 FOR THE BLDG 70 - 123 STEAM CONDENSATE REPLACEME…
Mod SA10· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-12-08+$39,914$10,161,259CHANGE ORDERS BC, BD, BE, BF, BG, AND BH: (REFERENCE CO # 55, 56, 57, 58, 59, AND 60)FOR THE REPLACE BOILERS A…
Mod SA11· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-12-08+$51,114$10,212,373CHANGE ORDER BK (REFERENCE CO # 62) CRITICAL ITEMS ON CB 8 FOR THE REPLACE BOILERS AT CLEMENT J. ZABLOCKI VAM…
Mod SA12· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-12-08+$0$10,212,373CHANGE ORDER BI: 135 CALENDAR DAY TIME EXTENSION FOR THE REPLACE BOILERS AT CLEMENT J. ZABLOCKI VAMC, MILWAUK…
Mod SA13· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-12-08+$111,097$10,323,470CHANGE ORDER BL, BM, BN, BO, BP, AND BQ FOR THE REPLACE BOILERS AT CLEMENT J. ZABLOCKI VAMC, MILWAUKEE, WISCON…
Mod SA14· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-12-08+$21,215$10,344,685CHANGE ORDER BR, BS, FOR THE REPLACE BOILERS AT CLEMENT J. ZABLOCKI VAMC, MILWAUKEE, WISCONSIN
Mod SA15· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-12-08+$33,897$10,378,582CHANGE ORDER BB (REFERENCE CO # 54) THIS ACTION DEFINITIZES THE NOT TO EXCEED $800,000.00 TO $833,,896.54 FOR…
Mod SA8· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-12-08−$7$10,378,575SA-8 INCORPORATES CHANGE ORDERS AV, AW, AX, AND AY FOR THE REPLACE BOILERS AT CLEMENT J. ZABLOCKI VAMC, MILWAU…
Mod SA9· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-12-08+$17,342$10,395,917SA-9 INCORPORATES CHANGE ORDERS AZ&BA FOR THE REPLACE BOILERS AT CLEMENT J. ZABLOCKI VAMC, MILWAUKEE, WISCONSI…
Mod SA16· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2012-04-27+$31,259$10,427,176SA-16 INCORPORATES CHANGE ORDERS 71, 72, AND 73 FOR THE REPLACE BOILERS AT CLEMENT J. ZABLOCKI VAMC, MILWAUKEE…
Mod SA17· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2013-02-08+$4,823$10,431,999SA-16 INCORPORATES CHANGE ORDERS 71, 72, AND 73 FOR THE REPLACE BOILERS AT CLEMENT J. ZABLOCKI VAMC, MILWAUKEE…

Related awards · 11

Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.

Other VA awards to the same recipient (UEI L6MMBNK832K3)

AwardOffice · PSC / listingNet obligationsFY
VA69D12J144969D-NETWORK CONTRACT OFFICE 12 · Z1DZ · MAINTENANCE OF OTHER HOSPITAL BUILDINGS$48,857FY2012
VA69D12J133669D-NETWORK CONTRACT OFFICE 12 · Z1DZ · MAINTENANCE OF OTHER HOSPITAL BUILDINGS$60,761FY2012
VA69DC2015269D-NETWORK CONTRACT OFFICE 12 · Z1DA · MAINTENANCE OF HOSPITALS AND INFIRMARIES$132,848FY2012
VA69DC2012269D-NETWORK CONTRACT OFFICE 12 · Z1DA · MAINTENANCE OF HOSPITALS AND INFIRMARIES$44,991FY2012
VA69D676C1032069D-NETWORK CONTRACT OFFICE 12 · Z141 · MAINT-REP-ALT/HOSPITALS & INFIRMARY$42,558FY2011
VA69DC1027969D-NETWORK CONTRACT OFFICE 12 · Z141 · MAINT-REP-ALT/HOSPITALS & INFIRMARY$382,660FY2011

Other recipients under Y141 from 69D-NETWORK CONTRACT OFFICE 12 (most recent first)

AwardRecipientOfficeNet obligationsFY
VA69DC1958C3T, INC.69D-NETWORK CONTRACT OFFICE 12$406,369FY2011
VA69D676C10312C3T, INC.69D-NETWORK CONTRACT OFFICE 12$55,780FY2011
VA69D676C10311COMPLETE COMFORT HEATING & A/C SERVICE, INC.69D-NETWORK CONTRACT OFFICE 12$56,514FY2011
VA69D676C10310C3T, INC.69D-NETWORK CONTRACT OFFICE 12$121,948FY2011
VA69D676C10313PLATT CONSTRUCTION, INC.69D-NETWORK CONTRACT OFFICE 12$32,321FY2011

Cite as: Glassbox VA record view · VA contract (USAspending / FPDS) · CONT_AWD_VA69DC1253_3600_-NONE-_-NONE- · retrieved 2026-09-26.