Description
NHCU MODIFICATIONS 9A AT VAMC MILWAUKEE S/A#22 - RFP 142 MIXING VALVES,RFP-143 PATIENT BED LIGHTING AND RFP-144 MURFEE BED REPAIR
Base award description: NHCU MODIFICATIONS 9A AT CLEMENT J. ZABLOCKI VA MEDICAL CENTER, MILWAUKEE, WI
Modification chain · 23 transactions
Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.
- Base2009-08-20+$3,490,943= $3,490,943
- Mod 12010-07-15+$56,901= $3,547,844
- Mod 22010-08-18+$816= $3,548,660
- Mod 32010-08-24+$15,890= $3,564,549
- Mod 42010-09-21+$43,054= $3,607,603
- Mod 52010-10-19+$75,624= $3,683,227
- Mod 62010-11-17+$5,637= $3,688,864
- Mod 72010-12-09+$10,840= $3,699,704
- Mod 82010-12-20+$1,807= $3,701,511
- Mod 92010-12-28+$8,061= $3,709,572
- Mod 102011-02-17+$1,853= $3,711,425
- Mod 112011-05-19+$12,045= $3,723,470
- Mod 122011-05-19+$3,034= $3,726,504
- Mod 132011-05-31+$23,704= $3,750,208
- Mod 142011-06-17+$19,478= $3,769,686
- Mod 152011-06-20+$2,864= $3,772,550
- Mod 162011-08-10+$5,594= $3,778,144
- Mod 172011-09-15+$5,264= $3,783,408
- Mod 182011-10-19+$2,093= $3,785,501
- Mod 192011-11-29+$12,011= $3,797,512
- Mod 202011-11-29+$0= $3,797,512
- Mod 212012-03-21+$9,945= $3,807,458
- Mod 222012-05-23+$6,834= $3,814,292
| Transaction | Action date | This action (delta) | Running total | Description on this transaction |
|---|---|---|---|---|
| Base | 2009-08-20 | +$3,490,943 | $3,490,943 | NHCU MODIFICATIONS 9A AT CLEMENT J. ZABLOCKI VA MEDICAL CENTER, MILWAUKEE, WI |
| Mod 1· FUNDING ONLY ACTION | 2010-07-15 | +$56,901 | $3,547,844 | NHCU MODIFICATIONS 9A AT CLEMENT J. ZABLOCKI VA MEDICAL CENTER, MILWAUKEE, WI S/A#01 - INCREASE IN COSTS DUE T… |
| Mod 2· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2010-08-18 | +$816 | $3,548,660 | NHCU MODIFICATIONS 9A AT CLEMENT J. ZABLOCKI VA MEDICAL CENTER, MILWAUKEE, WI S/A#02 - PIPING REROUTES |
| Mod 3· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2010-08-24 | +$15,890 | $3,564,549 | NHCU MODIFICATIONS 9A AT CLEMENT J. ZABLOCKI VA MEDICAL CENTER, MILWAUKEE, WI S/A#03 - HVAC DUCTWORK AND PIPIN… |
| Mod 4· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2010-09-21 | +$43,054 | $3,607,603 | NHCU MODIFICATIONS 9A AT CLEMENT J. ZABLOCKI VA MEDICAL CENTER, MILWAUKEE, WI S/A#04 - INSTALL SANITARY SEWER… |
| Mod 5· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2010-10-19 | +$75,624 | $3,683,227 | NHCU MODIFICATIONS 9A AT CLEMENT J. ZABLOCKI VA MEDICAL CENTER, MILWAUKEE, WI S/A#05 - DELAYS AND MATERIAL CHA… |
| Mod 6· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2010-11-17 | +$5,637 | $3,688,864 | NHCU MODIFICATIONS 9A AT CLEMENT J. ZABLOCKI VA MEDICAL CENTER, MILWAUKEE, WI S/A#06 - PATIENT LIFTS ADDITION |
| Mod 7· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2010-12-09 | +$10,840 | $3,699,704 | NHCU MODIFICATIONS 9A AT CLEMENT J. ZABLOCKI VA MEDICAL CENTER, MILWAUKEE, WI S/A#07 - PROVIDE AND INSTALL WAT… |
| Mod 8· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2010-12-20 | +$1,807 | $3,701,511 | NHCU MODIFICATIONS 9A AT CLEMENT J. ZABLOCKI VA MEDICAL CENTER, MILWAUKEE, WI S/A#07 - PROVIDE AND INSTALL WAT… |
| Mod 9· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2010-12-28 | +$8,061 | $3,709,572 | NHCU MODIFICATIONS 9A AT CLEMENT J. ZABLOCKI VA MEDICAL CENTER, MILWAUKEE, WI S/A#09 - RECEPTION AREA LIGHTING… |
| Mod 10· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-02-17 | +$1,853 | $3,711,425 | NHCU MODIFICATIONS 9A AT CLEMENT J. ZABLOCKI VA MEDICAL CENTER, MILWAUKEE, WI S/A#10 - ADDITIONAL ELECTRICAL O… |
| Mod 11· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-05-19 | +$12,045 | $3,723,470 | NHCU MODIFICATIONS 9A AT VAMC MILWAUKEE PROJECT #695-CA-3233 S/A#11 - SOUTH MAINS INSTALLATION |
| Mod 12· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-05-19 | +$3,034 | $3,726,504 | NHCU MODIFICATIONS 9A AT VAMC MILWAUKEE S/A#12 - RFP'S 119&120 CEILING AND SIGNAGE CHANGES |
| Mod 13· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-05-31 | +$23,704 | $3,750,208 | NHCU MODIFICATIONS 9A AT VAMC MILWAUKEE S/A#13 FOR RFP 123 - PIPING RELOCATIONS |
| Mod 14· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-06-17 | +$19,478 | $3,769,686 | NHCU MODIFICATIONS 9A AT VAMC MILWAUKEE S/A#14 FOR RFP 124, 125, 126&130 |
| Mod 15· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-06-20 | +$2,864 | $3,772,550 | NHCU MODIFICATIONS 9A AT VAMC MILWAUKEE S/A#15 - RFPS 129&130 |
| Mod 16· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-08-10 | +$5,594 | $3,778,144 | NHCU MODIFICATIONS 9A AT VAMC MILWAUKEE S/A#16 - RFP'S 131, 132, 133 |
| Mod 17· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-09-15 | +$5,264 | $3,783,408 | NHCU MODIFICATIONS 9A AT VAMC MILWAUKEE S/A#17 - RFP 134 AND 136 |
| Mod 18· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-10-19 | +$2,093 | $3,785,501 | NHCU MODIFICATIONS 9A AT VAMC MILWAUKEE S/A#18 - RFP 128 EC DOOR ADD / SAFETY |
| Mod 19· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-11-29 | +$12,011 | $3,797,512 | NHCU MODIFICATIONS 9A AT VAMC MILWAUKEE S/A#19-INCORPORATES RFPS 137 AND 138 |
| Mod 20· CHANGE ORDER | 2011-11-29 | +$0 | $3,797,512 | NHCU MODIFICATIONS 9A AT VAMC MILWAUKEE S/A#18 - RFP 128 EC DOOR ADD / SAFETY |
| Mod 21· CHANGE ORDER | 2012-03-21 | +$9,945 | $3,807,458 | NHCU MODIFICATIONS 9A AT VAMC MILWAUKEE S/A#21 - RFP 139 DEFINITIZE CO-AM OF SA-20, AND RFP-141 SMOKE WALLS MO… |
| Mod 22· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-05-23 | +$6,834 | $3,814,292 | NHCU MODIFICATIONS 9A AT VAMC MILWAUKEE S/A#22 - RFP 142 MIXING VALVES,RFP-143 PATIENT BED LIGHTING AND RFP-1… |
Related awards · 11
Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.
Other VA awards to the same recipient (UEI ZJE3GTWE6D36)
| Award | Office · PSC / listing | Net obligations | FY |
|---|---|---|---|
| VA69D16J6000 | 252-NETWORK CONTRACT OFFICE 12 (36C252) · Z1DZ · MAINTENANCE OF OTHER HOSPITAL BUILDINGS | $104,449 | FY2016 |
| VA69D16C0293 | 252-NETWORK CONTRACT OFFICE 12 (36C252) · Z1DA · MAINTENANCE OF HOSPITALS AND INFIRMARIES | $510,740 | FY2016 |
| VA69D16J5225 | 252-NETWORK CONTRACT OFFICE 12 (36C252) · Z1DZ · MAINTENANCE OF OTHER HOSPITAL BUILDINGS | $533,186 | FY2016 |
| VA69D16J4507 | 252-NETWORK CONTRACT OFFICE 12 (36C252) · Z1DA · MAINTENANCE OF HOSPITALS AND INFIRMARIES | $920,504 | FY2016 |
| VA69D16J3602 | 252-NETWORK CONTRACT OFFICE 12 (36C252) · Z1DZ · MAINTENANCE OF OTHER HOSPITAL BUILDINGS | $339,641 | FY2016 |
| VA69D16D0157 | 252-NETWORK CONTRACT OFFICE 12 (36C252) · Z1DZ · MAINTENANCE OF OTHER HOSPITAL BUILDINGS | $0 | FY2016 |
Other recipients under Z141 from 69D-NETWORK CONTRACT OFFICE 12 (most recent first)
| Award | Recipient | Office | Net obligations | FY |
|---|---|---|---|---|
| VA69D537C10505 | INDUSTRIA INC | 69D-NETWORK CONTRACT OFFICE 12 | $67,476 | FY2011 |
| VA69D537C10501 | JDM LLC | 69D-NETWORK CONTRACT OFFICE 12 | $70,934 | FY2011 |
| VA69D537C10446 | INDUSTRIA INC | 69D-NETWORK CONTRACT OFFICE 12 | $152,773 | FY2011 |
| VA69D537C10492 | JDM LLC | 69D-NETWORK CONTRACT OFFICE 12 | $0 | FY2011 |
| VA69D556C10391 | LEE & RYAN ENVIRONMENTAL CONSULTING, INCORPORATED | 69D-NETWORK CONTRACT OFFICE 12 | $29,911 | FY2011 |
Cite as: Glassbox VA record view · VA contract (USAspending / FPDS) · CONT_AWD_VA69DC1113_3600_-NONE-_-NONE- · retrieved 2026-09-26.