Award recordCONTRACT

SDV & RASCH JOINT VENTURE

PIID VA69DC1024· VHA· 69D-NETWORK CONTRACT OFFICE 12· Y149 · CONSTRUCT/OTHER HOSPITAL BLDGS· FY2009· $3,446,932 net obligations· UEI LY65DNZLT6X1· WI

Description

S/A #7 RENOVATE PSYCH WARDS AT NORTH CHICAGO VA CHANGES U AND Z.

Base award description: RENOVATE PSYCH WARDS AT NORTH CHICAGO VA

First action · last action
2009-06-15 · 2012-02-22
Transactions
11
First transaction's obligation
$3,004,500
Base + all options value (sum of deltas)
$3,446,932
Extent competed
FULL AND OPEN COMPETITION
Other than full & open authority
—
Set-aside
NO SET ASIDE USED.
Offers received
17
SDVOSB flag on record
Yes (self-representation)
NAICS
236220 · COMMERCIAL AND INSTITUTIONAL BUILDING CONSTRUCTION

Modification chain · 11 transactions

Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.

$3,446,932$0Base award · 2009-06-15 · this action $3,004,500 · running total $3,004,500Modification 1 · 2009-12-18 · this action $34,866 · running total $3,039,366Modification 2 · 2010-03-17 · this action $3,880 · running total $3,043,246Modification 3 · 2010-05-07 · this action $49,057 · running total $3,092,303Modification 4 · 2010-05-24 · this action $63,544 · running total $3,155,847Modification 5 · 2010-10-08 · this action $11,998 · running total $3,167,845Modification 6 · 2011-02-14 · this action $13,837 · running total $3,181,683Modification 8 · 2011-09-08 · this action $148,532 · running total $3,330,215Modification 9 · 2011-09-14 · this action $4,014 · running total $3,334,228Modification 10 · 2012-02-22 · this action $98,929 · running total $3,433,157Modification 7 · 2012-02-22 · this action $13,775 · running total $3,446,932
  • Base2009-06-15+$3,004,500= $3,004,500
  • Mod 12009-12-18+$34,866= $3,039,366
  • Mod 22010-03-17+$3,880= $3,043,246
  • Mod 32010-05-07+$49,057= $3,092,303
  • Mod 42010-05-24+$63,544= $3,155,847
  • Mod 52010-10-08+$11,998= $3,167,845
  • Mod 62011-02-14+$13,837= $3,181,683
  • Mod 82011-09-08+$148,532= $3,330,215
  • Mod 92011-09-14+$4,014= $3,334,228
  • Mod 102012-02-22+$98,929= $3,433,157
  • Mod 72012-02-22+$13,775= $3,446,932
TransactionAction dateThis action (delta)Running totalDescription on this transaction
Base2009-06-15+$3,004,500$3,004,500RENOVATE PSYCH WARDS AT NORTH CHICAGO VA
Mod 1· CHANGE ORDER2009-12-18+$34,866$3,039,366THIS IS FOR 5 CHANGE ORDER REQUEST THAT HAVE BEEN APPROVED AS WITHIN SCOPE CHANGES A-E. RENOVATE PSYCH WARDS A…
Mod 2· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-03-17+$3,880$3,043,246S/A #2 RENOVATE PSYCH WARDS AT NORTH CHICAGO VA
Mod 3· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-05-07+$49,057$3,092,303S/A #3 RENOVATE PSYCH WARDS AT NORTH CHICAGO VA CHANGES FGJANDK
Mod 4· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-05-24+$63,544$3,155,847S/A #4 RENOVATE PSYCH WARDS AT NORTH CHICAGO VA CHANGES L,M,N
Mod 5· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-10-08+$11,998$3,167,845S/A #5RENOVATE PSYCH WARDS AT NORTH CHICAGO VA CHANGES P, Q, S AND T.
Mod 6· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-02-14+$13,837$3,181,683S/A #6 RENOVATE PSYCH WARDS AT NORTH CHICAGO VA CHANGES O,V X AND Y.
Mod 8· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-09-08+$148,532$3,330,215CO# AF , NOT TO EXCEED ORDER FOR $148,532.00
Mod 9· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2011-09-14+$4,014$3,334,228ADDITIONS: 1. PROVIDE LABOR AND MATERIAL FOR PCO#AC TO FURNISH AND INSTALL (10) SOLID SURFACE SHOWER THRESH…
Mod 10· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2012-02-22+$98,929$3,433,157ADDITIONS: 1. PROVIDES FOR EXTENDED OVERHEAD AND LABOR RATE INCREASES DUE TO UNFORESEEN DELAYS. THE COST FO…
Mod 7· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2012-02-22+$13,775$3,446,932S/A #7 RENOVATE PSYCH WARDS AT NORTH CHICAGO VA CHANGES U AND Z.

Related awards · 5

Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.

Other recipients under Y149 from 69D-NETWORK CONTRACT OFFICE 12 (most recent first)

AwardRecipientOfficeNet obligationsFY
VA69DC1825NAGEL-REICHL JV 169D-NETWORK CONTRACT OFFICE 12$5,781,593FY2011
VA69DC1908INDUSTRIAL MAINTENANCE SERVICES INC69D-NETWORK CONTRACT OFFICE 12$1,245,768FY2011
VA69DC1628BLUE YONDER INC69D-NETWORK CONTRACT OFFICE 12$5,805,052FY2010
VA69D578C00118INDUSTRIA VETERAN GROUP69D-NETWORK CONTRACT OFFICE 12$33,457FY2010
VA69D578C00271INDUSTRIA VETERAN GROUP69D-NETWORK CONTRACT OFFICE 12$10,032FY2010

Cite as: Glassbox VA record view · VA contract (USAspending / FPDS) · CONT_AWD_VA69DC1024_3600_-NONE-_-NONE- · retrieved 2026-09-26.