Description
S/A #7 RENOVATE PSYCH WARDS AT NORTH CHICAGO VA CHANGES U AND Z.
Base award description: RENOVATE PSYCH WARDS AT NORTH CHICAGO VA
Modification chain · 11 transactions
Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.
- Base2009-06-15+$3,004,500= $3,004,500
- Mod 12009-12-18+$34,866= $3,039,366
- Mod 22010-03-17+$3,880= $3,043,246
- Mod 32010-05-07+$49,057= $3,092,303
- Mod 42010-05-24+$63,544= $3,155,847
- Mod 52010-10-08+$11,998= $3,167,845
- Mod 62011-02-14+$13,837= $3,181,683
- Mod 82011-09-08+$148,532= $3,330,215
- Mod 92011-09-14+$4,014= $3,334,228
- Mod 102012-02-22+$98,929= $3,433,157
- Mod 72012-02-22+$13,775= $3,446,932
| Transaction | Action date | This action (delta) | Running total | Description on this transaction |
|---|---|---|---|---|
| Base | 2009-06-15 | +$3,004,500 | $3,004,500 | RENOVATE PSYCH WARDS AT NORTH CHICAGO VA |
| Mod 1· CHANGE ORDER | 2009-12-18 | +$34,866 | $3,039,366 | THIS IS FOR 5 CHANGE ORDER REQUEST THAT HAVE BEEN APPROVED AS WITHIN SCOPE CHANGES A-E. RENOVATE PSYCH WARDS A… |
| Mod 2· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2010-03-17 | +$3,880 | $3,043,246 | S/A #2 RENOVATE PSYCH WARDS AT NORTH CHICAGO VA |
| Mod 3· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2010-05-07 | +$49,057 | $3,092,303 | S/A #3 RENOVATE PSYCH WARDS AT NORTH CHICAGO VA CHANGES FGJANDK |
| Mod 4· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2010-05-24 | +$63,544 | $3,155,847 | S/A #4 RENOVATE PSYCH WARDS AT NORTH CHICAGO VA CHANGES L,M,N |
| Mod 5· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2010-10-08 | +$11,998 | $3,167,845 | S/A #5RENOVATE PSYCH WARDS AT NORTH CHICAGO VA CHANGES P, Q, S AND T. |
| Mod 6· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-02-14 | +$13,837 | $3,181,683 | S/A #6 RENOVATE PSYCH WARDS AT NORTH CHICAGO VA CHANGES O,V X AND Y. |
| Mod 8· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-09-08 | +$148,532 | $3,330,215 | CO# AF , NOT TO EXCEED ORDER FOR $148,532.00 |
| Mod 9· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-09-14 | +$4,014 | $3,334,228 | ADDITIONS: 1. PROVIDE LABOR AND MATERIAL FOR PCO#AC TO FURNISH AND INSTALL (10) SOLID SURFACE SHOWER THRESH… |
| Mod 10· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-02-22 | +$98,929 | $3,433,157 | ADDITIONS: 1. PROVIDES FOR EXTENDED OVERHEAD AND LABOR RATE INCREASES DUE TO UNFORESEEN DELAYS. THE COST FO… |
| Mod 7· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-02-22 | +$13,775 | $3,446,932 | S/A #7 RENOVATE PSYCH WARDS AT NORTH CHICAGO VA CHANGES U AND Z. |
Related awards · 5
Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.
Other recipients under Y149 from 69D-NETWORK CONTRACT OFFICE 12 (most recent first)
| Award | Recipient | Office | Net obligations | FY |
|---|---|---|---|---|
| VA69DC1825 | NAGEL-REICHL JV 1 | 69D-NETWORK CONTRACT OFFICE 12 | $5,781,593 | FY2011 |
| VA69DC1908 | INDUSTRIAL MAINTENANCE SERVICES INC | 69D-NETWORK CONTRACT OFFICE 12 | $1,245,768 | FY2011 |
| VA69DC1628 | BLUE YONDER INC | 69D-NETWORK CONTRACT OFFICE 12 | $5,805,052 | FY2010 |
| VA69D578C00118 | INDUSTRIA VETERAN GROUP | 69D-NETWORK CONTRACT OFFICE 12 | $33,457 | FY2010 |
| VA69D578C00271 | INDUSTRIA VETERAN GROUP | 69D-NETWORK CONTRACT OFFICE 12 | $10,032 | FY2010 |
Cite as: Glassbox VA record view · VA contract (USAspending / FPDS) · CONT_AWD_VA69DC1024_3600_-NONE-_-NONE- · retrieved 2026-09-26.