Description
TIME EXTENSION OF 30 DAYS.
Base award description: EAST ENTRANCE CANOPY REPLACEMENT AT THE VA MILWAUKEE, WI.
Modification chain · 15 transactions
Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.
- Base2008-11-17+$1,347,268= $1,347,268
- Mod 22009-06-22+$0= $1,347,268
- Mod 32009-07-22+$2,046= $1,349,314
- Mod 42009-07-30+$10,752= $1,360,066
- Mod 52009-08-06+$8,028= $1,368,094
- Mod 62009-08-26+$46,947= $1,415,041
- Mod 72009-11-20+$213,185= $1,628,226
- Mod 82009-11-23+$35,948= $1,664,174
- Mod COG2009-12-01+$0= $1,664,174
- Mod 102009-12-10+$0= $1,664,174
- Mod 92009-12-14+$2,636= $1,666,810
- Mod 112010-03-08+$6,016= $1,672,826
- Mod 122010-05-07+$10,654= $1,683,480
- Mod 132010-09-28+$7,450= $1,690,930
- Mod 142010-10-12+$0= $1,690,930
| Transaction | Action date | This action (delta) | Running total | Description on this transaction |
|---|---|---|---|---|
| Base | 2008-11-17 | +$1,347,268 | $1,347,268 | EAST ENTRANCE CANOPY REPLACEMENT AT THE VA MILWAUKEE, WI. |
| Mod 2· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2009-06-22 | +$0 | $1,347,268 | S/A#2, ARCHITECTURAL PANEL CHANGES. |
| Mod 3· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2009-07-22 | +$2,046 | $1,349,314 | VA69D-C-0972, S/A#3. REMOVE SMOKE STAINS. |
| Mod 4· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2009-07-30 | +$10,752 | $1,360,066 | VA69D-C-0972, S/A#3. REMOVE SMOKE STAINS. |
| Mod 5· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2009-08-06 | +$8,028 | $1,368,094 | S/A#5, RFP 111. |
| Mod 6· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2009-08-26 | +$46,947 | $1,415,041 | S/A #6, RFP 111 |
| Mod 7· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2009-11-20 | +$213,185 | $1,628,226 | S/A #7. THIS SUPPLEMENTAL AGREEMENT IS ISSUED TO DEFINITIZE CHANGE ORDER "E" FOR CONTRACT # VA69D-C-0792. |
| Mod 8· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2009-11-23 | +$35,948 | $1,664,174 | S/A #8. THIS SUPPLEMENTAL AGREEMENT IS ISSUED TO DEFINITIZE CHANGE ORDER "F" FOR CONTRACT # VA69D-C-0792. |
| Mod COG· CHANGE ORDER | 2009-12-01 | +$0 | $1,664,174 | CHANGE ORDER "G" |
| Mod 10· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2009-12-10 | +$0 | $1,664,174 | S/A #10 - SUSPEND WORK DUE TO INCLEMENT WAETHER. |
| Mod 9· DEFINITIZE CHANGE ORDER | 2009-12-14 | +$2,636 | $1,666,810 | THIS S/A IS ISSUED TO DEFINITIZE CHANGE ORDER "G". |
| Mod 11· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2010-03-08 | +$6,016 | $1,672,826 | S/A #11 - SUSPEND WORK DUE TO INCLEMENT WEATHER. |
| Mod 12· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2010-05-07 | +$10,654 | $1,683,480 | EAST ENTRANCE CANOPY REPLACEMENT AT THE VA MILWAUKEE, WI, SUPPLEMENTAL AGREEMENT #12. 1. PROVIDE REMOVAL OF 12… |
| Mod 13· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2010-09-28 | +$7,450 | $1,690,930 | EAST ENTRANCE CANOPY REPLACEMENT AT THE VA MILWAUKEE, WI, SUPPLEMENTAL AGREEMENT #13. REPAIR FLOORING. |
| Mod 14· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2010-10-12 | +$0 | $1,690,930 | TIME EXTENSION OF 30 DAYS. |
Related awards · 11
Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.
Other VA awards to the same recipient (UEI ZJE3GTWE6D36)
| Award | Office · PSC / listing | Net obligations | FY |
|---|---|---|---|
| VA69D16J6000 | 252-NETWORK CONTRACT OFFICE 12 (36C252) · Z1DZ · MAINTENANCE OF OTHER HOSPITAL BUILDINGS | $104,449 | FY2016 |
| VA69D16C0293 | 252-NETWORK CONTRACT OFFICE 12 (36C252) · Z1DA · MAINTENANCE OF HOSPITALS AND INFIRMARIES | $510,740 | FY2016 |
| VA69D16J5225 | 252-NETWORK CONTRACT OFFICE 12 (36C252) · Z1DZ · MAINTENANCE OF OTHER HOSPITAL BUILDINGS | $533,186 | FY2016 |
| VA69D16J4507 | 252-NETWORK CONTRACT OFFICE 12 (36C252) · Z1DA · MAINTENANCE OF HOSPITALS AND INFIRMARIES | $920,504 | FY2016 |
| VA69D16J3602 | 252-NETWORK CONTRACT OFFICE 12 (36C252) · Z1DZ · MAINTENANCE OF OTHER HOSPITAL BUILDINGS | $339,641 | FY2016 |
| VA69D16D0157 | 252-NETWORK CONTRACT OFFICE 12 (36C252) · Z1DZ · MAINTENANCE OF OTHER HOSPITAL BUILDINGS | $0 | FY2016 |
Other recipients under Z142 from 69D-NETWORK CONTRACT OFFICE 12 (most recent first)
| Award | Recipient | Office | Net obligations | FY |
|---|---|---|---|---|
| VA69D556C00385 | GREAT REALTY ADVISORS | 69D-NETWORK CONTRACT OFFICE 12 | $1,700 | FY2010 |
| V695C00846 | API HVAC SERVICES, INC. | 69D-NETWORK CONTRACT OFFICE 12 | $9,769 | FY2010 |
| VA69D556C00350 | CIC CORP | 69D-NETWORK CONTRACT OFFICE 12 | $15,400 | FY2010 |
| VA69D578C00296 | BEAR MECHANICAL INC. | 69D-NETWORK CONTRACT OFFICE 12 | $27,300 | FY2010 |
| VA69D53700243 | JDM LLC | 69D-NETWORK CONTRACT OFFICE 12 | $173,391 | FY2010 |