SA#8 CO#11- NO COST TIME EXTENSION1. CO#12=L- WILL ADD ADDITIONAL LABOR HOURS TO REMOVE THE FRAMES DUE TO UNFORESEEN CONDITION OF GROUT FILLED FRAMES. THE COST FOR THIS ADDITIONAL WORK IS $22,508.22 AS A RESULT OF THE ABOVE CHANGES, THE CONTRACT PRICE IS CHANGED FROM $1,574,489.33 TO $1,596,997.55
Base award description: MATERIAL AND LABOR FOR TRAMWAY RENOVATION FOR FEDERAL HEALTH CARE CENTER, NORTH CHICAGO, IL
Modification chain · 9 transactions
Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.
- Base2011-09-01+$1,485,000= $1,485,000
- Mod 12012-03-13+$53,907= $1,538,907
- Mod 22012-03-23+$702= $1,539,609
- Mod 32012-05-11+$0= $1,539,609
- Mod 42012-05-30+$9,992= $1,549,601
- Mod 52012-07-02+$0= $1,549,601
- Mod A000062012-07-16+$24,889= $1,574,489
- Mod A000072012-08-23+$0= $1,574,489
- Mod A000082012-08-24+$22,508= $1,596,998
| Transaction | Action date | This action (delta) | Running total | Description on this transaction |
|---|---|---|---|---|
| Base | 2011-09-01 | +$1,485,000 | $1,485,000 | MATERIAL AND LABOR FOR TRAMWAY RENOVATION FOR FEDERAL HEALTH CARE CENTER, NORTH CHICAGO, IL |
| Mod 1· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-03-13 | +$53,907 | $1,538,907 | SA#1 FOR THE AMOUNT OF $53,906.61 CHANGE ORDER NO. 01 = A PROVIDE LABOR AND MATERIAL TO PATCH FAILING PAINT IN… |
| Mod 2· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-03-23 | +$702 | $1,539,609 | SA#2 CHANGE IN SCOPE FOR CHANGE ORDER NO. 07 = G PROVIDE LABOR AND MATERIAL TO REMOVE 3 ACM ELBOW AND 1 VIBRAT… |
| Mod 3· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-05-11 | +$0 | $1,539,609 | SA#3 EXTEND CONTRACT DATE TO JUNE 08,2012. |
| Mod 4· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-05-30 | +$9,992 | $1,549,601 | SA#4 1. CHANGE IN SCOPE FOR CHANGE ORDER NO. 08 = H WILL PROVIDE FOR OFF-HOURS WORK REQUIRED TO MINIMIZE THE D… |
| Mod 5· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-07-02 | +$0 | $1,549,601 | SA#5 NO COST TIME EXTENSION, |
| Mod A00006· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-07-16 | +$24,889 | $1,574,489 | SA#6 1. CO#10=J- WILL ADD ADDITIONAL FLOOR PATCHING. THE COST FOR THIS ADDITIONAL WORK IS $24,888.79 AS A… |
| Mod A00007· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-08-23 | +$0 | $1,574,489 | SA#7 CO#11- NO COST TIME EXTENSION |
| Mod A00008· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-08-24 | +$22,508 | $1,596,998 | SA#8 CO#11- NO COST TIME EXTENSION1. CO#12=L- WILL ADD ADDITIONAL LABOR HOURS TO REMOVE THE FRAMES DUE TO UN… |
Related awards · 11
Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.
Other VA awards to the same recipient (UEI PTSCYLWKCFK3)
| Award | Office · PSC / listing | Net obligations | FY |
|---|---|---|---|
| 36C77626C0072 | PCAC (36C776) · Y1BG · CONSTRUCTION OF ELECTRONIC AND COMMUNICATIONS FACILITIES | $7,244,850 | FY2026 |
| 36C25226C0032 | 252-NETWORK CONTRACT OFFICE 12 (36C252) · Z1DZ · MAINTENANCE OF OTHER HOSPITAL BUILDINGS | $5,868,000 | FY2026 |
| 36C25225C0056 | 252-NETWORK CONTRACT OFFICE 12 (36C252) · Y1DZ · CONSTRUCTION OF OTHER HOSPITAL BUILDINGS | $0 | FY2025 |
| 36S79725C0001 | NAC FACILITY PURCHASING SUPPORT (36S797) · Z2AA · REPAIR OR ALTERATION OF OFFICE BUILDINGS | $189,760 | FY2025 |
| 36C25225C0016 | 252-NETWORK CONTRACT OFFICE 12 (36C252) · Z1DA · MAINTENANCE OF HOSPITALS AND INFIRMARIES | $4,099,865 | FY2025 |
| 36S79724C0002 | NAC FACILITY PURCHASING SUPPORT (36S797) · Y1AA · CONSTRUCTION OF OFFICE BUILDINGS | $168,846 | FY2024 |
Other recipients under Z141 from 69D-NETWORK CONTRACT OFFICE 12 (most recent first)
| Award | Recipient | Office | Net obligations | FY |
|---|---|---|---|---|
| VA69D537C10505 | INDUSTRIA INC | 69D-NETWORK CONTRACT OFFICE 12 | $67,476 | FY2011 |
| VA69D537C10501 | JDM LLC | 69D-NETWORK CONTRACT OFFICE 12 | $70,934 | FY2011 |
| VA69D537C10446 | INDUSTRIA INC | 69D-NETWORK CONTRACT OFFICE 12 | $152,773 | FY2011 |
| VA69D537C10492 | JDM LLC | 69D-NETWORK CONTRACT OFFICE 12 | $0 | FY2011 |
| VA69D556C10391 | LEE & RYAN ENVIRONMENTAL CONSULTING, INCORPORATED | 69D-NETWORK CONTRACT OFFICE 12 | $29,911 | FY2011 |
Cite as: Glassbox VA record view · VA contract (USAspending / FPDS) · CONT_AWD_VA69DC0605_3600_-NONE-_-NONE- · retrieved 2026-09-26.