OTHER FUNCTION - MOD P00003: DESCOPE CONSTRUCTION PERIOD SERVICES, CONSTRUCTION SITE VISITS, AND COMMISSIONING SERVICES DUE TO LACK OF FUNDING FOR THE CONSTRUCTION PORTION OF THE PROJECT FOR PATIENT LIFTS FEASIBILITY STUDY AT IRON MOUNTAIN VAMC, IRON MOUNTAIN, MICHIGAN
Base award description: INSTALL PATIENT LIFTS FEASIBILITY STUDY AT IRON MOUNTAIN VAMC
Modification chain · 4 transactions
Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.
- Base2011-06-03+$65,075= $65,075
- Mod P000012013-02-01+$36,656= $101,731
- Mod P000032013-05-20+$0= $101,731
- Mod P000042016-02-23-$18,017= $83,714
| Transaction | Action date | This action (delta) | Running total | Description on this transaction |
|---|---|---|---|---|
| Base | 2011-06-03 | +$65,075 | $65,075 | INSTALL PATIENT LIFTS FEASIBILITY STUDY AT IRON MOUNTAIN VAMC |
| Mod P00001· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2013-02-01 | +$36,656 | $101,731 | OTHER FUNCTION - CONDUCT AE PATIENT LIFTS FEASIBILITY STUDY AT IRON MOUNTAIN VAMC, MOD-P000001 FOR ADDITIONAL… |
| Mod P00003· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2013-05-20 | +$0 | $101,731 | OTHER FUNCTION - CONDUCT AE PATIENT LIFTS FEASIBILITY STUDY AT IRON MOUNTAIN VAMC, MOD-P000002 FOR DESIGN TIME… |
| Mod P00004· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2016-02-23 | −$18,017 | $83,714 | OTHER FUNCTION - MOD P00003: DESCOPE CONSTRUCTION PERIOD SERVICES, CONSTRUCTION SITE VISITS, AND COMMISSIONING… |
Related awards · 11
Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.
Other VA awards to the same recipient (UEI UVM9J88SQXY6)
| Award | Office · PSC / listing | Net obligations | FY |
|---|---|---|---|
| VA69D13J4225 | 252-NETWORK CONTRACT OFFICE 12 (36C252) · C1DZ · ARCHITECT AND ENGINEERING- CONSTRUCTION: OTHER HOSPITAL BUILDINGS | $7,059 | FY2013 |
| VA69D13J2968 | 69D-NETWORK CONTRACT OFFICE 12 · C1DA · ARCHITECT AND ENGINEERING- CONSTRUCTION: HOSPITALS AND INFIRMARIES | $17,235 | FY2013 |
| VA69D13J3278 | 69D-NETWORK CONTRACT OFFICE 12 · C1DZ · ARCHITECT AND ENGINEERING- CONSTRUCTION: OTHER HOSPITAL BUILDINGS | $25,190 | FY2013 |
| VA69D13J2083 | 69D-NETWORK CONTRACT OFFICE 12 · C1DA · ARCHITECT AND ENGINEERING- CONSTRUCTION: HOSPITALS AND INFIRMARIES | $19,811 | FY2013 |
| VA69D12J1528 | 69D-NETWORK CONTRACT OFFICE 12 · C1DA · ARCHITECT AND ENGINEERING- CONSTRUCTION: HOSPITALS AND INFIRMARIES | $142,001 | FY2012 |
| VA69D585C10108 | 69D-NETWORK CONTRACT OFFICE 12 · C211 · A/E SVCS. (INCL LANDSCAPING INTERIO | $23,986 | FY2011 |
Other recipients under C114 from 69D-NETWORK CONTRACT OFFICE 12 (most recent first)
| Award | Recipient | Office | Net obligations | FY |
|---|---|---|---|---|
| VA69D585C10196 | NORTHERN DESIGN WORKS PLLC | 69D-NETWORK CONTRACT OFFICE 12 | $245,636 | FY2011 |
| VA69DP0602 | NORTHERN DESIGN WORKS PLLC | 69D-NETWORK CONTRACT OFFICE 12 | $0 | FY2011 |
| VA69D585C10167 | NORTHERN DESIGN WORKS PLLC | 69D-NETWORK CONTRACT OFFICE 12 | $4,194 | FY2011 |
| VA69D537C10375 | CT MECHANICAL LLC | 69D-NETWORK CONTRACT OFFICE 12 | $7,160 | FY2011 |
| VA69D282J16152 | CHICAGO COOLING TOWER | 69D-NETWORK CONTRACT OFFICE 12 | $9,845 | FY2011 |
Cite as: Glassbox VA record view · VA contract (USAspending / FPDS) · CONT_AWD_VA69D585C10136_3600_VA69DP1516_3600 · retrieved 2026-09-26.